← Späť na vyhľadávanie
Súdny dvor Európskej únie·Rozsudok·28.10.1981

C-275/80

ECLI:EU:C:1981:247

Súd
Súdny dvor Európskej únie
IČS
61980CJ0275

KRUPP ν COMMISSION

In Joined Cases 275/80 and 24/81

KRUPP STAHL AG, whose registered office is at 165 Alleestraße, Bochum 4630, represented by A. Gödde and F. Stemmer, members of its Board of Directors, assisted by K. Pfeiffer, H. Biedenkopf, P. Ossenbach, Advocates, with an address for service in Luxembourg at the Chambers of J.-C. Wolter, Advocate, 2 Rue Goethe,

v

COMMISSION OF THE EUROPEAN COMMUNITIES, represented by H. Matthies, Legal Adviser, assisted by E. Grabitz, Professor at the Free University of Berlin, with an address for service in Luxembourg at the office of O. Montako, a member of the Legal Department, Jean Monnet Building, Kirchberg,

APPLICATION for a declaration that certain provisions of the notifications of the Commission of 1 November 1980 and 19 December 1980 determining, pursuant to the general Commission Decision of 31 October 1980 (Official Journal L 291, p. 1), the production quotas for the applicant for the last quarter of 1980 and the first quarter of 1981 are void,

THE COURT

composed of: J. Mertens de Wilmars, President, A. Touffait and O. Due, (Presidents of Chambers), Lord Mackenzie Stuart, A. O'Keeffe, T. Koopmans, and U. Everling, Judges,

Advocate General: G. Reischl Registrar: A. Van Houtte

gives the following

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

JUDGMENT

Facts and Issues

The facts of the case, the course of the the same month during the period procedure, the conclusions, submissions from July 1977 to June 1980 during and arguments of the parties may be which the total production of the summarized as follows: four groups of rolled products was the highest. The three months thus chosen, which will not necessarily be consecutive, shall constitute the I — Facts and p r o c e d u r e reference period.

1. Background to the Case (2) The reference production figures shall be the same, for crude steel and for each of the other groups of By Decision 2794/80/ECSC the Com- rolled products, as the production mission established a system of steel of the corresponding items during production quotas for undertakings in the reference period." the iron and steel industry (Official Journal L 291, p. 1). Article 4, points 3, 4 and 5, describes the According to Article 2 of that decision special cases in which the reference the Commission was to fix quarterly production and consequently the quotas production quotas for crude steel for the are increased. Article 4, point 4, provides four groups of rolled products defined for adaptation of the reference therein and more particularly described production of an undertaking which, in Annex 1 to the decision. following an investment programme duly reported and not the subject of According to Article 3 of the general an unfavourable opinion from the decision the Commission was to fix Commission, activates a new plant after quarterly production quotas "for each 1 July 1980 bringing the total production undertaking" on the basis of the possibilities for the four groups of reference production figures, as referred products to a level exceeding by at least to in Article 3, of that undertaking and 15 % the total production possibilities by application of abatement rates to existing for 1979. those reference production figures as referred to in Article 5. Article 4, point 5, provides that to take Article 4, points 1 and 2, of the decision account of restructuring, the Com- lays down the general rules for calcu- mission must increase the reference lating the quarterly reference production production figures: figures both for rolled products and crude steel. That provision reads as "— Where an undertaking's total follows : production of the four groups of products during a reference period "(1) For each month of the relevant falls short of production in the same quarter, reference shall be made to quarter of 1974, and

KRUPP ν COMMISSION

— Where this undertaking has 2. Course of the procedure achieved for the year ending in 1979 a profit which is shown in its annual report or reported to the national By application received at the Court official agency responsible for the Registry on 11 December 1980 the filing of the annual accounts of applicant brought an action for a companies." declaration that the Commission's notification of 1 November 1980 was in part void. In that case the reference production figures have to be increased "so as to By a second application received at the reach the total equivalent to the Court Registry on 9 February 1981 the production of the corresponding quota applicant brought an action for a of 1974". declaration that the Commission's notification of 19 December 1980 was in part void. After the Commission had, by Article 7 (2) of Commission Decision letter dated 9 February 1980, informed 2794/80/ECSC also imposes restrictions the applicant of its decision to amend the with regard to the delivery of products notification of 19 December 1980, the subject to the quota system. Under­ applicant pursued its action in modified takings "may not exceed, by group form by lodging a supplementary of products, for deliveries within application at the Court Registry on the Common Market, the ratio of 10 March 1981. Community deliveries to total deliveries in the twelve months of the period from July 1977 to June 1980 in which the total By order of 8 April 1981 the Court production of the four groups of rolled ordered the cases to be joined for the products was the highest". purpose of the oral procedure.

By notification dated 1 November 1980 the Commission determined the pro­ Upon hearing the report of the Judge- Rapporteur and the views of the duction quotas for Krupp Stahl AG for Advocate General the Court decided to the fourth quarter of 1980. open the oral procedure without any preparatory inquiry. By notification dated 19 December 1980 the Commission determined the pro­ duction quotas for Krupp Stahl AG for the first quarter of 1981. II — C o n c l u s i o n s of t h e p a r t i e s

By letter dated 9 February 1981 the Commission recognized that it was Krupp Stahl AG claims that the Court necessary to apply Article 4, point 4, of should: Decision 2794/80/ECSC to Krupp Stahl AG as regards the products in Group I. In consequence it altered the company's 1. Declare void the notification of the reference production and quotas in defendant of 1 November 1980 in so respect of Group I and crude steel for far as it determines production quotas the first quarter of 1980. for hot-rolled wide and narrow strip

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

within the meaning of Group I of position in Case 275/80 and points out Article 1 of Decision 2794/80/ECSC that in the order of the President of the and for crude steel; Court of 16 December 1980 (Case 258/80 Rumi ν Commission) it was also in principle thought that the notification 2. Order the defendant to pay the costs. of the quotas of 1 November 1980 constituted an "individual decision".

The Commission contends that the Court should: Β — Substance

1. Declare that the actions in Cases 1. Infringement of essential procedural 275/80 and 24/81 are unfounded; requirements and defective statement of reasons. 2. Order the applicant to pay the costs. The applicant maintains that in so far as the contested notifications are individual decisions addressed to it they have to be Ill — Submissions and argu­ in the form provided for by Decision m e n t s of t h e p a r t i e s 22/60 of the High Authority of 7 September 1960 on the Implementation of Article 15 of the ECSC Treaty A — Admissibility (Official Journal, English Special Edition, Second Series VIII, p. 13). According to that decision, decisions In its application in Case 275/80 the relating to the ECSC must be described applicant devotes lengthy argument to as such in their titles; show the date on the question of the admissibility of its which the High Authority, now the action. It argues that although the Commission, adopted them, be signed by contested measure is described as a the President, Vice-President or a notification it is in fact an individual member of the High Authority (now the decision within the meaning of Article 14 Commission), be preceded by a reference of the ECSC Treaty capable according to the provisions of the Treaty or the to the second paragraph of Article 33 decisions which form their legal basis thereof of being the subject of an action and contain a statement of reasons and before the Court of Justice. be set out in articles. Notification may be by "registered post with receipted delivery". None of these formal According to the Commission the requirements was observed by the notifications in question in conjunction contested notifications. The applicant with the application therein of the points out that the notifications are not provisions or the General Decision described as decisions in their title and 2794/80 constitute individual decisions addressed to the applicant. Consequently do not appear to have been signed by a the Commission does not challenge the member of the Commission since there is admissibility of the actions for a only a mention of the name of a declaration that the notifications are Commissioner. Nor do the notifications void. show the date of the Commission's decision, which indicates, in the applicant's view, that contrary to the In its application in Case 24/71 Krupp rules of the ECSC Treaty the Stahl AG refers to the Commission's notification is not based upon a decision

KRUPP ν COMMISSION

of the Commission as a collegiate body July 1963 in Case 24/62 [1963] ECR 85 but simply on the decision of Mr and judgment of 1 December 1965 in Commissioner Davignon who was Case 16/65 [1965] ECR 877). In the specially authorized for that purpose in present case, however, the deficiency of the present case. Finally there is no the statement of reasons is so extensive statement of reasons, the drafting is not that it is impossible for the undertakings set out in articles and notification was to check either the law or the facts in not effected by registered post with relation to the notifications. More par­ receipted delivery. ticularly the notifications do not show either the reference figures on which they are based or the provisions which were applied when the necessary adap­ tation under Article 4 of Decision 2794/80 was made. The supplementary The fact that the decision in question explanations given orally to the applicant may be regarded as an individual cannot in any event compensate for the measure confined to bringing particular insufficient statement of reasons since facts within one of the cases provided for that statement must be part of the by a general decision cannot, in the decision itself so as to enable the Court applicant's view, justify infringement of of Justice to carry out an effective review the formal requirements provided for by of it. Decision 22/60 since the rules referred to therein apply to every decision whatever its subject-matter.

In the Commission's view the notifications must be considered in conjunction with Decision 2794/80 Apart from infringement of the essential which states the general criteria which procedural requirements provided for by the individual decisions sent in the form Decision 22/60 of the High Authority, of notifications to the undertakings Decision 2794/80 of the Commission simply apply. That state of affairs was also infringes the requirement to state recognized by the Court in its order of the reasons upon which it is based and 16 December 1980 (Case 258/80 R that requirement, as the Court of Justice Rumi v Commission). Since the noti­ has frequently stated, does not derive fication is confined to applying math­ from formal considerations but is ematically the criteria contained in the intended to enable the parties to defend general Decision 2794/80 to the their rights, the Court to exercise its production figures supplied by the review of legality and the Member States applicant itself it was not necessary to and any national concerned to know the state the reasons on which those circumstances in which the Commission notifications were leased, each time has applied the Treaty. The applicant repeating a large part of Decision recognizes that the reasons may even be 2794/80. Moreover the applicant is stated summarily provided that they are wrong in claiming that it was prevented clear and relevant; the requirements from checking the notification from the regarding the statement of reasons may point of view of law and of fact since it vary according to the circumstances and does not challenge the calculations as in certain conditions reference to the such and its only complaint is that the statement of reasons in a basic general Commission did not apply Article 4, decision may be sufficient (judgment of 4 points 4 and 5, of Decision 2794/80

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

cumulatively: their non-application is not "Subject to the principle of collegiate denied. At the most the Commission responsibility being respected in full the admits that it might have added to the Commission may empower its members words "adapted pursuant to Article 4" in to take, in its name and subject to its the notifications in question the number control, clearly defined measures of of the paragraph applied in each management or administration." particular case but that is not a fundamental condition. The applicant itself moreover easily found which paragraph of Article 4 had been applied and the Commission gave all the necessary explanation to the under- It is on that basis that the Commission takings which asked for them. empowered one of its members, Viscount Davignon, to ensure implementation of Decision 1794/80 by working out quotas for each undertaking according to an arithmetical process leaving no discretion to the Commission. In those circum- As to the question of the infringement of stances, since the determination of the essential procedural requirements quotas is simply an administrative provided for in Decision 22/60 of the measure, the principle of collegiate High Authority the Commission observes responsibility of the Commission was first of all that in its view these formal respected in full. provisions are not mandatory. Only the Treaty contains such provisions and in so far as Decision 22/60 is not simply repeating those provisions it contains rules relating to an administrative practice of the Commission from which it may deviate where as in the present 2. Infringement of Article 4 of Decision case it is justified by particular circum- 2794/80 stances. Moreover the majority of the rules of Decision 22/60, which the applicant alleges to be infringed, do not constitute essential procedural require- ments. That is so as regards the description "decision", the written In Case 275/80 the applicant complains signature, the date and the division into that the Commission gave it only the articles. As regards the applicant's benefit of Article 4, point 5, of Decision objection that the notifications are not 2794/80. In its view the Commission based on a decision taken by the ought also, pursuant to Article 4, point Commission as a collegiate body, the 4, of that decision, to have adapted the Commission states that the notification is applicant's reference production figures based on a decision taken by the since it had activated new plant after Commission following the procedure laid 1 July 1980, so bringing the production down for such cases as the present by the possibilities to a level exceeding by more first paragraph of Article 27 of the pro- than 15% the total production visional Rules of Procedure of the possibilities existing for 1979. In its Commission of 6 July 1967 (Journal application in Case 24/81, as amended Officiel 147, p. 1, 179, p. 1) as amended after the Commission's decision granting on ,23 July 1975 (Official Journal L 199, it the benefit of Article 4, point 4, the p. 43) which provide as follows: applicant challenges the Commission's

KRUPP ν COMMISSION

right then to withdraw the benefit of "possibility" being here understood as Article 4, point 5. In the applicant's view, the largest quantity that an undertaking as it already stressed in Case 275/80, can produce assuming that the Article 4, points 4 and 5, are capable of production possibilities existing at the simultaneous application. time of the estimate remain invariable for the unit of time, namely a year, taken as a reference) are compared with the maximum production in fact possible in 1979, the result is an increase in In Case 275/80 the Commission denies possibilities of 18.7%. In the applicant's that the conditions for applying Article view it is that criterion, implying the 4, point 4, are satisfied and also application of two distinct concepts of maintains that the application of Article 4, point 4, rules out the application of "production possibility" which is Article 4, point 5. In Case 24/81 the referred to in Article 4, point 4, when it Commission recognizes that the is stated that the new production conditions for applying Article 4, point possibility must bring the total 4, are satisfied and it has consequently production possibilities to a level amended its decision. It maintains exceeding by at least 1 5 % the total however that the application of that production possibilities existing for 1979. paragraph rules out the simultaneous Such an interpretation is the only one application of Article 4, point 5. consistent with the wording of Article 4 and the aim of Decision 2794/80.

On the one hand it is determinant that (a) Conditions for applying Article 4, Article 4, point 4, simply speaks of an point 4 increase in "production possibilities" without referring to a specific calendar year. If that were not so it would be necessary in the applicant's view to According to the terms of this provision apply, for the first two quarters of 1981, adaptation of the reference production is criteria which could not be definitely possible where new plant is activated in assessed until the end of the year, that is, so far as "the new production possibility six months after the expiry of the system thus established brings the total brought into force by Decision 2794/80. production possibilities for the four Before then there would be only groups of products to a level exceeding estimated figures which might prove to by at least 1 5 % the total production be inaccurate. possibilities existing for 1979". The Commission, relying on the Ques­ tionnaire 2-61 on investments which was supplied by the applicant for 1980, On the other hand if the increase in maintains that the production capacity of production were assessed taking into Krupp Stahl AG increased by · only account the possible production for the 9.35% between 1979 and 1980. The whole of 1980, that, in the applicant's applicant recognizes that the changes in view, would lead undertakings which, capacity give rise to a maximum possible activating new plant, could close down increase in production of 9.35% for the outdated plant, to postpone such whole of 1980. On the other hand if the reduction in their production, otherwise total production possibilities when the desirable because of the situation of new plant is activated (the term excess production, for unless they did so

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

they must expect not to obtain the in that sector must be accompanied by benefit of Article 4, point 4. On the the shutting-down of old plant. In that other hand undertakings whose reference connection and on the assumption that production is calculated solely on the the applicant would show understanding basis of Article 4, points 1 and 2, could for this point of view the Commission reduce their production possibilities did not give an unfavourable opinion on without having to expect a reduction in the investments of Krupp Stahl AG. their reference production figures.

A further condition is that the increase In addition for yet another reason the in capacity must be significant. The Commission's interpretation is incompat- Commission in that respect stresses that ible both with the wording and the aim the applicant is the only integrated of the rules adopted. To assess the undertaking in respect of which, at least production increase in terms of the for 1981, application of Article 4, point maximum possible production increase 4, comes into question. As regards calcu- for 1980 in relation to that of 1979 lation of the growth in production would amount to requiring a more or capacity the Commission considers that less large increase in those possibilities it had to use for that purpose the infor- according to whether the activation of mation taken from the annual inquiry the new plant takes place earlier or later into investments made by means of in the course of the year. The wording Questionnaire 2-61 in which the concept of Article 4, point 4, does not justify of "maximum possible production" is such a result. Nor is there any reasonable that which the Commission has always ground which does so. used. It has nothing in common with the concept of a technical production capacity used by the applicant: such an abstract and technical concept is of no use to those wishing to obtain as realistic In the Commission's view Article 4, point as possible a view of the market. 4, must be interpreted in the general context of the system of production quotas. The object of the provision in question is to take into account, in the quota system, new production capacities That the application of these criteria created after the expiry of the reference results in not taking the new plant into period. But this is subject to certain account immediately, but only for 1981, preconditions and is not to take place is the result intended by the provision, immediately and not to the full extent. which is aimed at a gradual introduction of the new production possibilities. The new production possibilities are moreover never fully taken into account. Thus the Commission must not have given an unfavourable opinion on the investment programme in question. In the applicant's case the Commission On the basis of those explanations the states that although the surplus capacity Commission considers that it was not in the hot wide-strip sector does not necessary to state expressly in Article 4, prevent modernization of the existing point 4, of Decision 2794/80 that plant, it does mean that new investments the increase in production possibilities

KRUPP ν COMMISSION

referred to a whole year since it is clear (b) The simultaneous application of that such increase must be compared Article 4, points 4 ana 5 with the total production possibilities existing for 1979 and that it is not possible, as the applicant would like to compare data based on different concepts. The applicant admits that the wording of Article 4 is not felicitous and that it may be concluded from the reference both at point 4 and point 5 of Article 4 to an increase in the reference production that the two systems allow only one increase The applicant is also mistaken in in the reference production and that only thinking that the Commission's view the provision most favourable to the would lead to worthless results since the undertaking concerned applies to it. Such production capacity for 1981 cannot be an interpretation however would in its assessed. The questionnaire which under­ view conflict with the purpose and takings had to send to the Commission general scheme of Decision 2794/80. in the spring of 1980 contains figures for 1979, 1980 and 1981 which are the only ones which could conceivably be taken into account in a uniform manner. In that respect it observes first of all that the term "production" is not always used in the same sense in Decision 2794/80. For example, whereas in Article 4, points 1 and 2, the reference production is As regards the impact of Article 4, point the volume of production calculated 4, on the possibilities for undetakings, according to Article 4, points 1 and 2, in which have undertaken new investment, Article 5, points 1, the same term to shut down plant, the Commission obviously refers to the production observes that the absence of an unfavour­ resulting from the application of the able opinion on an investment shows that adaptation rules in Article 4, points 3 to after consideration there is no cause in 5, that is, to the production as already the Commission's view to shut down increased. The fact that the term certain old plant. In those circumstances "reference production" is to be found in the undertaking has no ground for Article 4, point 4, does not therefore shutting down the plant on its own mean that that provision cannot be initiative. The Commission also observes applied to the reference production as that although, under Article 4, points 1 and 2, closure is irrelevant in a case of already increased pursuant to Article 4, normal reference production, that is point 5. because there it is not a question of considering capacity but of production actually achieved. Finally the Commission admits that in requiring a Further the aim of the provisions of production increase of 15 % for the Article 4 with the exception of point 4 is whole of 1980 it is imposing a condition to ensure that past circumstances are which will not be fulfilled save in very taken into account in calculating the rare cases, but that is fully justified by reference production figures. Point 4 is the objective pursued which is to take intended to deal with the effects of account of large, new plant only bringing into operation new capacity. It gradually and to a limited extent. follows that to take account or point 4

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

only as an alternative to the other — Calculation of the normal reference provisions of Article 4 of Decision production figures (points 1 and 2). 2794/80 would withdraw a benefit granted because of one particular situation simply because the undertaking in question may enjoy another benefit by — In so far as point 3, 4 or 5 is virtue of a completely different situation. applicable, amendment of those That would mean treating different normal reference production figures situations similarly which is discrimi- by virtue of one of those provisions. nation prohibited by Article 4 of the ECSC Treaty and is a misuse of law. — In other cases the normal reference production figures are unchanged. In conclusion, in the applicant's view, neither a literal interpretation of Article 4 nor an interpretation based upon the connections between points 4 and 5 or their objectives justifies applying them in Article 5 is then applied to the result the alternative. Point 5 simply comes obtained to calculate the production after point 4 in Decisions 2794/80 quotas. The existence of that systematic without being presented as an alterna- connection therefore excludes the possi- tive; the points relate to completely bility of applying several corrections to different circumstances and have the "normal" reference production different objectives intended to take figures cumulatively. account of those circumstances.

The Commission also rejects the In both cases, even if it does not consider applicant's argument to the effect that the question to be decisive in Case Article 4, points 3 and 5, refer to the 275/80, the Commission denies that it is past whereas point 4 refers to the period possible to apply points 4 and 5 of subsequent to June 1980. In the Article 4 of Decision 2794/80 simul- Commission's view the decisive factor is taneously. the reference period taken into account. That is 1974 in point 5 and the period 1977-80 in point 4. It is therefore wrong In the first place, in the Commission's to take as basis the higher production of 1974 (applying point 5) and to apply to view, the applicant is wrong in thinking it a further upwards correction provided that the concept of reference production only for the period 1977-80. A double is not used in the same sense in Articles 4 increase of that kind could, in the and 5 on the ground that, unlike Article Commission's view, lead to unreal 4, Article 5, point 1, obviously refers to reference production figures, depriving production as already increased. The the rate of abatement of any practical applicant is not in fact taking account of effect. the first sentence of Article 4 stating "the quarterly reference production figures for each undertaking shall be calculated as follows:" The Commission also observes that cumulative application of points 4 and 5 could involve discrimination between The calculation is made in two stages: undertakings in the same position

KRUPP ν COMMISSION

according to whether they have activated period (point 1) neither point 4 nor point new plant before or after 1 July 1980. 5 applies; if the new plant is not activated until after 1 July 1980 point 4 applies. Finally the Commission finds confir­ mation of the alternative nature of Article 4, points 4 and 5, of Decision The applicant considers that in the latter 2794/80 in their aims. Point 5 is aimed case " B " must be allocated first 100 at taking account of a reduction in pursuant to point 5 and then, and in production by an undertaking in relation addition, 30 pursuant to point 4, that is to its production in 1974. Point 4 is 130 in all, whereas the production intended to take account of the capacity amounts only to 110. The activation of new plant and thus the applicant should explain why it considers introduction of new capacity after 30 point 5 should be applied before point 4. June 1980. The Commission admits that If in the example point 4 is applied first, new plant may constitute rationalization 80 + 30 gives 110. In that case and even or modernization which must be if the cumulative principle is adopted, welcomed, but it stresses that such new point 4 no longer applies, for 110 is plant counterbalances (in whole or in more than 100, that is to say that during part) a reduction in production which the reference period the production has took place before the plant was not been less than that in 1974 as activated. It follows that it would be required by point 5." manifestly contrary to the aim of the two provisions to take the two processes into consideration separately, that is to say, In the Commission's view points 4 and 5 first to reward the reduction in can therefore apply only in the alter­ production (point 5) and secondly to native, the undertaking in question being correct the reference production figures entitled to have applied to it the on the basis of an increase in pro­ paragraph most favourable to it for each duction compensating for that reduction group of products. (point 4).

That is why for the first quarter of 1981 The Commission illustrates its argument it amended by letter dated 9 February with the following example: 1981 the applicant's reference production figures for Group I by applying Article 4, point 4, and maintained the reference production figures for Groups II to "Before July 1977 (beginning of the IV calculated on the basis of Article 4, reference period) two undertakings, " A " point 5. and " B " , both reduced their production, which as 100 in 1974 to 80. Subsequently " B " activated new plant of a capacity The applicant rejects the Commission's of 30. analysis. In its view Article 4 provides three systems of increase of the reference production without stating that there can " A " is given a reference production of be only one increase and there is no 100 (point 5) and " B " 110, whether the general principle of interpretation of new plant is activated before or after Community law according to which 1 July 1980, for if the production of the several provisions granting different new plant takes place during a reference benefits in different circumstances are

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

applicable in the alternative. As regards In the same way the allegation that, if the Commission's argument to the effect the applicant's legal argument was that "the existence of that systematic followed, the quota would be higher connection therefore excludes the possi- than the actual capacity if Article 4, bility of applying serveral corrections to points 4 and 5, were applied cumu- the 'normal' reference production figures latively, is shown on examination to be cumulatively", the applicant considers untenable. It is based on the one hand on that analysis of the different possibilities confusion between actual production and of increase shows that each of them is capacity and on the other hand on the related to completely different circum- wrong assumption that the new capacity stances; there is no possible systematic is fully taken into account in the quota; connection between them and it is only taken into account to the extent accordingly nothing to prevent the simul- of approximately 65 % , as provided for taneous application of the rules in Article 4, point 4. Finally it is also contained in Article 4, points 3 to 5. The wrong to contend that after applying fact that the objectives pursued by Article 4, point 4, "even if the cumu- Article 4, points 3 to 5, are completely lative principle is adopted" point 5 no different, as the Commission recognizes, longer applies because the reference also excludes their application in the production is less than the production in alternative. Finally the Commission is 1974. As the Commission itself rightly wrong in objecting that the cumulative stated, the adaptation rules of points 3 to application of Articles 4 and 5 could 5 must always be related solely to the involve discrimination between under- normal reference production figures takings. If there is discrimination because within the meaning of points 1 and 2 and capacity activated before 1 July 1980 can not to the reference production already be taken into account in calculating the increased pursuant to the systems of reference production figures only if the adaptation. date when it was activated is sufficiently remote, that discrimination results not from the interpretation advocated by the applicant but from the system constructed by the Commission.

More fundamentally however the applicant criticizes the Commission for not having compared two undertakings only one of which had effected the re- structuring measures taken into account The applicant also challenges the pursuant to Article 4, point 5, whereas example put forward by the Commission. both have new plant in operation after In this respect it first of all points out 1 July 1980. Such a comparison would, what it considers to be errors of law and in the applicant's view, give the following fact in the example. Thus in its view it is result: wrong to assume that " B " is granted a reference production of 110 whether the new plant was activated before or after 1 July 1980. T o take new plant activated before 1 July 1980 into account in calcu- lating the reference production pursuant to Article 4, point 1, is possible only "— Undertaking A reduced its 1974 subject to strictly limited conditions and production of 100 to 80 before July quite impossible in certain circumstances. 1977 and after 1 July 1980 activated

KRUPP ν COMMISSION

new plant with a capacity of 30. If these three examples are compared Since according to point 4 two- then it is apparent that the Commission's thirds of that capacity may be taken interpretation of Article 4 of Decision into account in calculating the 2794/80 leads to discrimination. The reference production, A is given a facts in the first and third examples are reference production of 100. treated similarly although they are quite Application of point 5 gives the different. Only undertakings which have same result. If the two systems of not engaged in restructuring measures adaptation were applied together may benefit from Article 4, point 4. the reference production would be 120, but since the defendant considers that would not be permissible the reference production In answer to those arguments the remains at 100. Commission maintains that neither a literal analysis nor the internal logic of Article 4 nor an analysis of the objectives pursued by that provision justifies the cumulative rather than alternative application of points 4 and 5 of that — Undertaking Β did not engage article. in restructuring measures and therefore did not produce less from 1977 to 1980 than in 1974. For all those years its reference production The Commission observes that, in its was 100 and consequently it is fixed view, since points 4 and 5 of Article 4 at that amount pursuant to points 1 represent exceptions to the system and 2. After 1 July 1980 B, just like provided for in points 1 and 2 of that A, activated new plant which even article, such exceptions may be taken in the defendant's opinion involves simultaneously into account only if an increase in the reference Article 4 provides so expressly. It also production to 120. Β is therefore in remarks that, in its opinion, the two a better position than A." provisions in question have the same aim, namely the restructuring of the European steel industry. Such restructuring may be achieved either by reduction in capacity (point 5) or increase in capacity and modernization of the undertaking (point 4). It would not however be possible, as Since the defendant did not apply Article the cumulative application of point 4 and 4, point 5, in the present case, the two point 5 would assume, for a particular examples given need to be supplemented undertaking simultaneously to increase by a third variant: and reduce its production.

As regards the discrimination which, " — Undertaking C, like undertaking A, according to the Commission, would reduced its 1974 production of 100 ensue from a cumulative application of to 80 before July 1977 but did not points 4 and 5, the Commission remarks subsequently instai new plant. that, in its view, the applicant has not Application of Article 4, point 5, denied the possibility of such discrimi­ leads in this case to a reference nation. It has simply maintained that production of 100." discrimination could come about

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

independently of the application of point Thus in example A it is not the capacity 5 because of the defective drafting of but the adaptation resulting from the point 4. In that respect the Commission activation of the new plant which must contends that point 4 might be capable be taken as 30. Undertaking A must of causing discrimination if interpreted therefore receive 110 and not 130 as the strictly and literally to purely applicant contends. hypothetical cases, but that had not been the case. Moreover, in a case where a reasonable interpretation did not enable In example Β it is assumed that an the question to be settled satisfactorily, it undertaking which carried out no re­ would always have been possible to structuring measures could have main­ examine the problem from the point of tained its production at the same level view of Article 14 of the decision. without interruption from 1974 to 1980. The Commission considers that possible only if the undertaking were particularly The Commission then calculates the competitive, which means that it had various possible reference production already modernized its structures and figures for the applicant. had adapted itself to the market. It would be quite fair to treat such an undertaking more favourably than others — Effective reference production figures which had only begun their restructuring (Article 4, points 1 and 2); operations later; the assumption that these undertakings could have main­ tained their production at the level of — 1974 reference production figures 1974 in spite of the crisis is absurd. Their (Article 4, point 5); production would have diminished not because of restructuring but because of unprofitability which it would be fair to — Adaptation following the activation take into account. of new plant after 1 July 1980 (Article 4, point 4). The example C put forward by the applicant corresponds to the Com­ In the Commission's view the applicant mission's case A. The undertaking wishes the basis to be not the effective receives 100 and thus is not treated reference production figures but the the same way as in the applicant's 1974 reference production figures example A. adapted following the activation of new plant after 1 July 1980. That would lead to a much higher total than the 1974 production which in the system 3. Illegality of Decision 2794/80 introduced by the Commission could be taken only in exceptional cases as a basis instead of the normal reference In Case 275/80 the applicant raises the production, and which according to the objection that Decision 2794/80 is Commission's case (effective reference illegal. Article 4, point 4, constitutes a production figures and adaptation) breach of the Commission's duty under would in spite of everything be exceeded. Article 58 (2) of the ECSC Treaty to determine quotas on an equitable basis. In making the benefit of Article 4, point The examples put forward by the 4, dependent on the absence of an un­ applicant contain a number of errors. favourable opinion by the Commission

KRUPP ν COMMISSION

on the investment programme the reference production. The condition laid Commission in fact gave to the unfavour­ down in Article 4, point 4, is thus only able opinion within the meaning of the the expression of the general objectives fourth paragraph of Article 54, which by which the Commission pursues in its its very nature is not binding, as is clear decision and cannot therefore be relied from the fourth paragraph of Article 14 upon to support an objection of of the Treaty, legal effects which that illegality. opinion could not have.

In its rejoinder in Case 275/80 the The Commission considers that the Commission states that since the objection of illegality is inadmissible. applicant has not replied to those There must be a connection between the objections it assumes that the objection general decision which is alleged to be of illegality is no longer being pursued. illegal and the individual decision which it is sought to have declared void. There is no such connection where the general provision or at least the article of a general provision, the illegality of which is being alleged, was not applied in the particular case and therefore its In Case 24/81 the applicant raises an defectiveness could have had no effect upon the particular decision. That is so objection of illegality in regard to the in the present case where the objection system of delivery quotas provided for by of illegality is directed against an article Article 7 (2) of Decision 2794/80. In so of the decision which was not applied to doing it does not comment on the merits the applicant. In support of its view the of the legal argument on which the Commission cites the judgments of the Commission founds its view that the Court in Joined Cases 41 and 50/59, objection of illegality in Case 275/80 is Case 18/62 and Case 32/65. inadmissible. So far as the applicant is concerned, even assuming this argument to be well-founded the condition stated therein, for the admissibility of an objection of illegality, namely "a connection between the general decision and the individual decision to the effect In regard to the substance of the that the individual decision is based on objection, the Commission, after the general decision" is fulfilled as far stressing that it did not give an un­ as Article 7 of Decision 2794/80 is favourable opinion on the applicant's concerned. That follows from the fact investment programme, states that that Article 7 of Decision 2794/80 refers although the unfavourable opinion is not for the determination of the delivery a legally binding measure it is quotas to the production quotas fixed nevertheless a fact. It means that the pursuant to Article 3. Thus the total of Commission considers the proposed the delivery quotas for the Community investments undesirable. For the purposes market and for non-Community markets of the system of production quotas there is equal to the production quotas defined is no reason for rewarding such by the defendant. The fixing of undesirable new plant by fixing a higher production quotas thus amounts to fixing

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

delivery quotas and the "connection" expressly conferred in relation to required by the Commission exists. production quotas do not enable in any circumstances the aims of the Treaty to be achieved. There can be no question of that, as is shown by the practice in the matter of cartels. In addition, if the Commission really has an implied right As to the substance of its submission, the to take all necessary measures to re- applicant maintains first that Article 58 of the ECSC Treaty only authorizes the establish a balance between supply and Commission to establish a system of demand on the Community market it production quotas and not a system of ought, in the applicant's view, to have

delivery quotas. The doctrine of implied imposed import quotas. In that respect, powers cannot justify the establishment however, Article 74 of the ECSC Treaty of a system of delivery quotas. That allows the Commission only to make doctrine, which moreover is rejected by recommendations to the governments of the great majority of the governments of the Member States. Since the doctrine of the Member States, is also rejected by implied powers is thus not applicable in legal writers having regard to specific relation to imports, the same rules must articles of the Treaties (Article 95 of the also apply to delivery quotas. ECSC Treaty, Article 235 of the EEC Treaty and Article 203 of the EAEC Treaty) providing detailed rules for the case where the powers given by the Treaties are not sufficient to achieve Legal writers consider the introduction

their aims. The Court itself has not of delivery quotas under Article 58 of the recognized any general principle ECSC Treaty as contrary to the Treaty. according to which the Commission has all the requisite legislative powers to achieve the aims of the Treaty without regard to the rules contained in the Treaty for each particular factual The applicant also considers that the situation. It has simply accepted, in wording of Article 7 (2) of Decision particular in Case 8/55 ([1954 to 1956] 2794/80 is not clear.

It allows a whole ECR 292 at p. 299) the application to series of interpretations and thus makes Community law of a rule of interpret- it impossible for the undertakings ation "generally accepted in both inter- concerned to calculate their delivery national and national law, according to quotas. It might even lead to a certain which the rules laid down by an inter- discrimination between manufacturers. national treaty or a law presupposes the More particularly, the applicant states rules without which that treaty or law that it is not clear whether the duty would have no meaning or could not be which Article 7 imposes on undertakings reasonably and usefully applied." not to exceed, as regards deliveries of products subject to the quota system in the common market, the ratio between

Community deliveries and total deliveries during a particular period, concerns all products including those from stock, The application of those principles to imports or other sources of supply or this case compel the conclusion that refers only to deliveries of products powers in relation to delivery quotas may manufactured by the undertaking during not be inferred from Article 58 of the the period of validity of the quota ECSC Treaty unless the powers system. The first paragraph of Article 9

KRUPP ν COMMISSION

of Decision 2794/80 seems however to Thirdly, the reference period prescribed indicate that Article 7 applies only to the by Article 7 (2) of Decision 2794/80 is deliveries of products manufactured by quite inappropriate. The reference period the undertaking during the period of in question is one of twelve months validity of the quota system. In that case whereas the system of delivery quotas, as however there would be discrimination may be inferred from the first paragraph in favour of undertakings which are able of Article 9, is related to the production to compensate for the restriction on their quotas determined on a quarterly basis. possibilities of delivery in the common Therefore in the applicant's view it market by deliveries from stock or other would have been more appropriate to sources. Such discrimination would establish reference periods on a quarterly favour the least competitive undertakings basis rather than a reference period of if they possessed extensive stocks and a whole year. The reference period would not be justified by the purpose of adopted makes it objectively impossible the quota system. The applicant adds for undertakings to determine their that the system introduced by Article quotas. Moreover the applicant fails to 7 (2) of Decision 2794/80 also discrimi­ see why delivery quotas had to be nates against undertakings which during determined on the basis of a reference the reference period fixed by that period in which "the total production of provision reduced their stocks by exports the four groups of rolled products was to markets outside the Community. That the highest". In contrast to the amount means that undertakings affected by the of deliveries the volume of production is delivery quota system could, while it irrelevant in this context, all the more so applies, sell only part of their current since there is classification according to production on the Community market the type of product. although during that reference period they have delivered the whole or their production in the common market.

Accordingly the applicant maintains that Decision N o 2794/80 does not deter­ mine delivery quotas with the precision and reliability required of a body of rules the contravention of which is punishable by a fine.

Secondly, the applicant considers that, as regards products of Group I, under the delivery quota system it is uncertain whether the delivery quotas cover that part of the production quotas which are In conclusion the applicant contends that not sold to third parties but processed even assuming delivery quotas for the within the undertaking. There is no common market were admissible, the doubt that according to the wording of fact remains that the combined effect of Article 7 (2) such processed products do the fixing in Decision 2794/80, total not come within the system of delivery production quotas, on the one hand, and quotas. This favours undertakings with delivery quotas for the common market an integrated production system. In this on the other amounts to fixing export respect too, there is discrimination quotas which institutions of the contrary to the objective of Decision Community have in any event no power 2794/80. to do.

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

As in Case 275/80 the Commission takes non-member countries from affecting the the view that the objective illegality is supplies in the common market. That inadmissible. There is no connection provision remains within the limits of the between Articles 4 and 7 of Decision powers which the Commission has under 2794/80. Article 7 is intended to prevent, Article 58 of the Treaty according to the in the event of exports declining, case-law of the Court cited by the products which have not been sold applicant, without there being any outside the Community from being necessity of establishing whether the offered on the Community market. For Community has general implied powers. that purpose it is provided that the ratio Without these rules the purpose of the of Community deliveries to total grant of powers which is to re-establish a deliveries as existing in the reference balance between supply and demand, period should not be exceeded. The ratio could not be achieved or could be is not identical with the total of the achieved only by means of rules production quotas but is a statistical ratio restricting to a far greater extent the for each undertaking and is defined freedom of decision of undertakings. independently of the production quotas for the undertakings.

The Commission considers the applicant's observations regarding the difficulties of interpreting Article 7 as an attempt to obtain an abstract interpret- ation of the content of that article. N o Only after a fine has been imposed under such claim may be made in an the first paragraph of Article 9 on an application for a declaration that a undertaking which has infringed Article measure is void. Furthermore, the first 7 (2) may that undertaking raise an paragraph of Article 9 in conjunction objection of illegality in relation to that with Article 7 (2) is clear because after article. determining the production quotas on the basis of the ratio, laid down by Article 7 (2) and known to the under- takings, between sales in the common market and exports, each undertaking knows when liability to a fine under the In the alternative the Commission first paragraph of Article 9 arises. contends that the objection of illegality is in any event unfounded. The power which the Commission has under Article 58 of the ECSC Treaty to fix production quotas by implication includes the power to adopt the rules laid down in Article IV — O r a l p r o c e d u r e 7 (2) which fixes neither delivery quotas nor export quotas. The purpose of the grant of the powers provided for in Article 58 of the ECSC Treaty is to deal At the sitting on 27 May 1981 the parties with a decline in demand amounting to a presented oral argument. crisis and to re-establish the balance between supply and demand on the market. The purpose of Article 7 (2) is simply to introduce a system to prevent a The Advocate General delivered his decline in demand on the markets of opinion at the sitting on 25 June 1981.

KRUPP ν COMMISSION

Decision

1 By applications registered at the Court Registry on 11 December 1980 and 9 February 1981 Krupp Stahl AG brought pursuant to the second paragraph of Article 33 of the ECSC Treaty two actions for a declaration that the notifications of 1 November (Case 275/80) and 19 December 1980, the latter as amended by letter dated 9 February 1981 (Case 24/81), are void in so far as they determine production quotas for crude steel and for hot-rolled wide and narrow strip under Group I of Article 2 of Decision 2794/80/ECSC of 31 October 1980 establishing a system of steel production quotas for under­ takings in the iron and steel industry (Official Journal L 291, p. 1).

2 Article 3 of Decision 2794/80 provides that the Commission is to fix quarterly production quotas for each undertaking " o n the basis of the reference production figures as referred to in Article 4 of that undertaking" and "by application of abatement rates to those reference production figures as referred to in Article 5". Article 4, points 1 and 2, determines the method for calculating the reference production. Article 4, points 3 to 5, defines three exceptional situations justifying an increase in the reference production figures calculated pursuant to points 1 and 2.

3 Article 4, points 4 and 5, read as follows:

"(4) Where, further to an investment programme duly reported and not the subject of an unfavourable opinion, the undertaking activates a new plant after 1 July 1980, the Commission shall adapt appropriately the reference production of this undertaking, provided it finds that the new production possibility thus established brings the total production possibilities for the four groups of products to a level exceeding by at least 15 % the total production possibilities existing for 1979.

In this case, the reference production shall be increased by a quantity derived from application to the new production possibilities of a rate corresponding to the highest annual average rate of utilization of the same plant in the Community during the years 1977, 1978 and 1979, less five percentage points. The reference production for crude steel shall be adapted accordingly.

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

(5) T o take account of restructuring, the Commission shall increase the reference production figures:

— Where an undertaking's total production of the four groups of products during a reference period falls short of production in the same quarter of 1974, and

— Where this undertaking has achieved for the year ending in 1979 a profit which is shown in its annual report or reported to the national official agency responsible for the filing of the annual accounts of companies.

In this case, the Commission shall increase the reference production figures so as to reach the total equivalent to the production of the corresponding quarter of 1974."

4 By notification of 1 November 1980 the Commission determined the production quotas for the applicant for the fourth quarter of 1980. In doing so it applied Article 4, point 5, of Decision 2794/80. The applicant however took the view that it satisfied not only the conditions of Article 4, point 5, but also of Article 4, point 4. It therefore sought the benefit of the cumu- lative application of these two provisions. It made the same request in regard to the production quotas which the Commission had determined by notification of 19 December 1980 for the first quarter of 1981.

5 Both requests were rejected by the Commission. As regards the production quotas for the fourth quarter of 1980 the Commission contends that the conditions for the application of Article 4, point 4, were not satisfied, but even if they had been it would not have been possible, as the applicant desires, to apply Article 4, points 4 and 5, cumulatively. As regards the production quotas for the first quarter of 1981 the Commission admitted in a letter dated 9 February 1981 addressed to the applicant that the conditions for applying Article 4, points 4 and 5, were satisfied. It nevertheless adhered to its contention that the paragraphs could not be applied cumulatively. After finding that the application of Article 4, point 4, was more advantageous to the applicant than the application of Article 4, point 5, it amended, in the above-mentioned letter, the notification of 19 December 1980 by applying Article 4, point 4, instead of Article 4, point 5.

KRUPP ν COMMISSION

Infringement of essential procedural requirements and insufficient statement of reasons

6 Although the applicant claims a declaration that the notifications addressed to it are void only in so far as they determine the production quotas for Group I products referred to in Article 2 of Decision 2794/80, it nevertheless contends that those notifications were, taken as a whole, issued in breach of the essential procedural requirements prescribed by Decision 22/60 of the High Authority of 7 September 1960 on the implementation of Article 15 of the ECSC Treaty (Official Journal, Special Edition, Second Series VIII p. 13) and in breach of the general duty to state reasons which is intended to enable the parties to defend their rights and the court to exercise its review of legality.

7 The form of decisions recommendations and opinions of the High Authority is determined in detail by Decision 22/60. Thus it is provided that the measure is to be expressely described in its title, that it must show the date of its adoption, the form of signature, contain reference to relevant legislation and to opinions obtained, be furnished with a statement of the reasons on which it is based and be set out in the form of articles. In addition it pre­ scribes the procedure for notifying measures of the High Authority.

8 It is not denied that the notifications sent to the applicants do not comply with these formal requirements. The Commission however denies that they are essential requirements non-compliance with which makes the contested notifications void.

9 Decision 22/60 prescribes in such a detailed manner the formal presentation of measures of the High Authority in order clearly to distinguish the nature of measures by using standard forms. Failure to comply with that requirement nevertheless does not entail the nullity of measures when they are unquestionably individual decisions taken on the implementation of a scheme previously established by means of a general decision adopted in accordance with the formal requirements prescribed by Decision 22/60. That is precisely the case with the contested notifications which constitute no more than the application of Article 3 of Decision 2794/80 under which the

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

Commission fixes quarterly production quotas for each undertaking and notifies them of it. The submission that the contested notifications did not comply with the formal requirements laid down by Decision 22/60 must therefore be rejected.

10 It does not follow however that such notifications may be exempted from stating the reasons on which they are based. In that respect the applicant objects that the Commission did not state which of the points of Article 4 of Decision 2794/80 it was applying or indicate the grounds on which it relied.

1 1 In the Commission's view the notifications sent to the applicant must be considered in conjunction with Decision 2794/80 of which they constitute a mathematical application on the basis of production figures supplied by the applicant itself. The applicant moreover had no trouble in determining by reference to that decision which provisions thereof had been applied to it.

12 The applicant's submission in relation to the notification relating to the first quarter of 1981 is manifestly unfounded. As amended by letter dated 9 February 1981 the notification refers not only to the point of Article 4 which was applied but to the reasons which led the Commission to apply it. In those circumstances there can be no question of there being no statement of reasons.

1 3 As regards the notification of 1 November 1980, it is to be regretted that the Commission did not consider it necessary to state the provisions which it was applying and to explain the interpretation which it was thus giving to Decision 2794/80. It is however true that it was possible for the applicant, by examining the figures in the notification in the light of the methods of calcu- lation defined in the decision, to determine which provisions had been applied to take account of its own economic position. The Commission's summary statement of reasons was therefore not such as to deprive the applicant of the opportunity of checking the correct application, in regard to

KRUPP ν COMMISSION

itself, of the rules laid down by Decision 2794/80 or to prevent the Court from exercising its task of review and therefore cannot adversely affect the validity of the notification of 1 November 1980.

T h e c o n d i t i o n s for applying Article 4, p o i n t 4, of Decision 2794/80

14 Article 4, point 4, provides for adaptation of the reference production when the new production capacities bring "the total production possibilities for the four groups of products to a level exceeding by at least 15 % the total production possibilities existing for 1979". It is not denied that the applicant activated on 1 July 1980 an additional pre-heating oven, the construction of which was not the subject of an unfavourable opinion on the part of the Commission. In the applicant's view the effect of that new plant was immediately to increase the production capacity of its undertaking by at least 15 % for the four groups of rolled products covered by the quota system and it concludes from this that it is entitled to the increase in the reference quota provided for by Article 4, point 4. The Commission denies that the conditions for applying that provision are satisfied. In its view the total production possibilities for the four groups of products in question was increased, as a result of the investment in question, by only 9.5 % in relation to the total production possibilities existing for 1979.

15 That discrepancy arises from a difference of interpretation of Article 4, point 4. The applicant maintains that it suffices that the new plant should, on the day on which it is activated, increase the production capacity by 15 % in relation to that for 1979. It bases that argument essentially on the wording of the provision which does not specify the annual nature of the increase in production possibilities and the fact that the interpretation proposed by the Commission would make taking into consideration new production capacities depend on the date on which they became operative.

16 In the Commission's view on the other hand it is necessary to compare the maximum production possibility for the whole of 1980 as estimated in the Questionnaire N o 2-61 ECSC completed by the applicant itself in the spring of 1980 with the maximum production possibility for the whole of 1979 as stated in the same questionnaire. The particulars supplied by the applicant

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

itself show that by applying those criteria the maximum total production possibility for 1980 is only 9.5 % higher than those existing for 1979.

17 The Commission justifies its position by arguing that it needs to establish a comparison between identical information already available, namely the production possibilities existing for the whole of each of the years 1979 and 1980. If that leads to taking account of new plant only as from 1981 it is in accord with the objective of point 4 which is intended to ensure that new capacity is gradually taken into account.

18 The Commission is not to be criticized for the concern which prompts it to have recourse, in its interpretation of Article 4, point 4, to facts which are known, easily comparable and which enable the effectiveness of the quota system to be maintained by strictly limiting the possibility of exceptions. Further it is necessary that the interpretation adopted should not be such as to make the application of Article 4, point 4, subject to conditions which are not justified by the objectives of the rules in question and which are a source of discrimination.

19 The interpretation proposed by the Commission finds support neither in the wording nor in the objectives of the provisions in question. They provide for a comparison between the total production possibilities existing for 1979 and the new production capacity arising from the activation of new plant. The difference between the two production capacities must be at least 15%. In thus comparing the production capacity existing for 1979 with that existing when new capacity is brought into operation the benefit of Article 4, point 4, is granted to every undertaking which increased its production capacity by more than 15% at any time during the second half of 1980. On the other hand in comparing, as does the Commission, the annual production capacities for 1979 and 1980 the increase in the quota is made to depend on an increase in production capacities which must be proportionately larger according to how late in the second half of 1980 new plant is activated and the result is to favour or place at a disadvantage undertakings on the basis of a factor alien to the system.

KRUPP ν COMMISSION

20 It follows that the interpretation and application by the Commission of Article 4, point 4, in its notification to the applicant of 1 November 1980 are not well-founded and that accordingly the notification must be declared to be void.

T h e c u m u l a t i v e a p p l i c a t i o n of A r t i c l e 4, p o i n t s 4 a n d 5, of Decision 2794/80

21 The restructuring policy of Krupp Stahl AG obliged it to reduce its production until July 1980. At that time it activated new plant which sub­ stantially increased its production possibilities. It follows that the applicant satisfies the conditions of both points 4 and 5 of Article 4. It therefore asks that it be granted the cumulative benefit of the increases in the reference production provided for by both provisions. The Commission considers that in a situation such as that of the applicant there is no ground for cumu­ latively applying Article 4, points 4 and 5, and that only the provision which is most advantageous to the undertaking in question should be applied.

22 Both the Commission and the applicant rely on the wording of Article 4 in support of their argument. In the Commission's view the structure of the article indicates that only one correction to the reference production calculated on the basis of points 1 and 2 may be made. In the applicant's view the fact that the various possibilities of adapting the normal reference production are given in sequence in points 3, 4 and 5 of Article 4, without its being stated that the application of one excludes the application of the others, is decisive and implies the possibility of cumulative application.

23 Neither the wording nor the structure of the provision enables the matter to be settled one way or the other. It is therefore by considering the objectives pursued by Decision 2794/80 and more particularly in Article 4, points 4 and 5, that it must be decided whether or not those points are capable of cumu­ lative application.

24 The Commission justifies its refusal to apply those two provisions cumu­ latively by the necessity to preserve the general objectives of the decision which are to re-establish a balance between supply and demand by means of

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

strict control of production. A double increase in the reference production might, in the Commission's view, jeopardize the whole system. It would put the applicant undertaking in an excessively advantageous position in relation to its competitors and would create a discriminatory system with regard to undertakings which had first reduced their production and then brought into operation new production capacities but before July 1980.

25 The applicant finds justification for the cumulative application to which it considers itself entitled in the fact that points 4 and 5 of the provision at issue are concerned with different cases and have different objectives. Point 4 takes account of a growth in capacity in respect of which the Commission has not given an unfavourable opinion whereas point 5 takes account of previous restructuring efforts which have led to the elimination of non- competitive capacities. Every undertaking which, like the applicant, has undertaken both forms of restructuring is entitled to the two increases cumu- latively, each taking account of a particular kind of restructuring.

26 It is clear, as the Commission stresses, that extensive application of the exceptions to the reference production system provided for in Article 4, points 3 to 5, of Decision 2794/80 would imperil the fundamental objective of the decision, namely to re-establish a balance between supply and demand in the steel market. It follows that a restrictive interpretation is consistent with the general objective of the decision. That is therefore the interpretation which must be adopted unless it prevents certain special objectives of the provisions at issue of Decision 2794/80 from being taken into account.

27 As regards the specific objectives of Article 4, points 4 and 5, it is true, as the applicant points out, that they take account of two different kinds of re- structuring. It does not however follow that the two provisions must therefore be applied cumulatively.

KRUPP ν COMMISSION

28 On the contrary it follows from the nature and the objectives of the two different restructuring measures referred to in Article 4, points 4 and 5, that from the economic point of view their effects are in normal cases intended to compensate one another and not to be cumulative. That economic connection in turn necessitates the rejection of an interpretation which would result in the two quota increases being cumulated and give rise to abnormal production possibilities clearly exceeding the objectives of the provision in question.

29 Finally it must be pointed out in support of the Commission's argument that if the applicant's reference quotas were to be increased twice it would result in favouring the applicant to the detriment of undertakings which had also reduced and then increased their production capacity but had done all this before 1 July 1980. Such a difference in treatment cannot be justified in regard to the objectives of the decision. It would mean severer treatment of undertakings which had been speedier in implementing their restructuring programme.

30 It follows from the foregoing that the Commission rightly refused to apply Article 4, points 4 and 5, of Decision 2794/80 cumulatively. The applicant's submission must therefore be rejected.

O b j e c t i o n s of i l l e g a l i t y r a i s e d in r e g a r d t o A r t i c l e 4, p o i n t 4 a n d A r t i c l e 7 of D e c i s i o n 2 7 9 4 / 8 0

31 The applicant raises two objections of illegality in regard to Decision 2794/80. The first of those objections related to the requirement that there should not be an unfavourable opinion of the Commission and is the means whereby the applicant contests the legality of the consequences attached by the decision to the existence of an unfavourable opinion. The second objection relates to Article 7 of the decision and involves a denial that the Commission has power to lay down delivery quotas.

32 With regard to those two objections it should be pointed out that although in an action for a declaration that an individual decision is void the applicant may allege that certain provisions of the general decisions which the

JUDGMENT OF 28. 10. 1981 — JOINED CASES 275/80 AND 24/81

contested decision implements are illegal, the applicant may do so only if the individual decision is based on the rules alleged to be illegal.

33 In this case the contested notifications do not apply the consequences attached to an unfavourable opinion since no such opinion was given in respect of the applicant's new investments. Nor do they fix delivery quotas and are not therefore based on Article 7 of Decision 2794/80. Accordingly the objections of illegality raised by the applicant are inadmissible.

Costs

34 The Commission has failed in its submissions in Case 275/80 and the applicant in Case 24/81.

35 However since the two cases have been formally joined for the purposes of the oral procedure and the parties have treated them as such during the written procedure, it is impossible to determine the costs attributable to each of the cases. It is therefore right for the purposes of the proper administration of justice to apply Article 69 (3) of the Rules of Procedure according to which the Court may where the circumstances are exceptional order that the parties bear their own costs.

On those grounds,

THE COURT

hereby:

1. Declares that the Commission's notification of 1 November 1980 relating to the applicant in the reference production and production quotas for the fourth quarter of 1980 is void in so far as it relates to Group I of rolled products and crude steel;

KRUPP ν COMMISSION

2. For the rest, dismisses the application;

3. Orders the parties to bear their own costs.

Menens de Wilmars Touffait Due

Mackenzie Stuart O'Keeffe Koopmans Everling

Delivered in open court in Luxembourg on 28 October 1981.

For the Registrar

H. A. Rühi J. Mertens de Wilmars Principal Administrator President

OPINION OF MR ADVOCATE GENERAL REISCHL DELIVERED ON 25 JUNE 1981 1

Mr President, European steel industry was confronted Members of the Court, with a period of "manifest crisis". Since the Commission was convinced that the In autumn 1980 the Commission noted indirect means of action provided for in that in the course of the third quarter of Article 57 of the ECSC Treaty were not that year there had been a sudden and adequate, and that it was necessary to considerable drop in the demand for take direct and binding measures in the steel, that the rate of utilization of the sphere of production in order to restore steel undertakings of the Community equilibrium between supply and demand, had fallen sharply and that in the it decided to apply Article 58 of the Community there had been a marked fall ECSC Treaty and to introduce a system in steel prices which had coincided with of production quotas. This was done by an increase in manufacturing costs. This Decision No 2794/80/ECSC of 31 led the Commission to assume that the October 1980 which was published in the

1 — Translated from the German.

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Rozsudok C-275/80 – Súdny dvor Európskej únie | AI Pravnik