← Späť na vyhľadávanie
Súdny dvor Európskej únie·Rozsudok·16.2.1982

C-39/81

ECLI:EU:C:1982:59

Súd
Súdny dvor Európskej únie
IČS
61981CJ0039

HALYVOURGIKI v COMMISSION

means that the link established by conjectural, such as production Article 58 (1) between the intro- capacity; secondly, it enables total duction of production quotas and the production to be reduced without imposition of restrictions on imports altering the positions of the under- of competing products cannot be in takings on the market as between any way automatic. each other. 5. Article 58 (2) of the ECSC Treaty 6. Under the scheme of Decision N o does not restrict the Commission's 2794/80 the aim of paragraphs (3) freedom to choose the basis upon and (4) of Article 4 thereof is to help which the quotas may be equitably some undertakings by rectifying the determined in a given economic results obtained by taking into situation. There are no reasonable account the reference production grounds for denying that the figures defined by Article 4 (1) and Commission's choice of the criterion (2). The aim of those provisions is, based on undertakings' actual pro- more precisely, to adapt the reference duction may constitute an "equitable production figures of some under- basis" within the meaning of Article takings, having regard to their par- 58 (2). Indeed that criterion, as ticipation during the period under adjusted by Article 4 of Decision N o consideration in voluntary reduction 2794/80, constitutes, in the first place, programmes and to the restrictions an objective basis of assessment which placed upon them as a result of the avoids the uncertainties inherent in control exercised by the Commission determining a factor which is partly over new investment.

In J o i n e d Cases 39, 4 3 , 85 a n d 8 8 / 8 1

HALYVOURGIKI I N C . , a c o m p a n y i n c o r p o r a t e d u n d e r t h e laws of Greece having its registered office in Athens (Cases 39 a n d 8 5 / 8 1 ) ,

and

HELLENIKI HALYVOURGIA SA, a c o m p a n y i n c o r p o r a t e d u n d e r t h e laws of G r e e c e having its registered office at Piraeus a n d its h e a d q u a r t e r s in A t h e n s (Cases 43 a n d 8 8 / 8 1 ) ,

represented b y A n d r é Elvinger, of t h e L u x e m b o u r g Bar, with an address for service in L u x e m b o u r g a t t h e C h a m b e r s of A n d r é Elvinger, 15 C ô t e d ' E i c h ,

applicants, v

COMMISSION O F THE E U R O P E A N C O M M U N I T I E S , r e p r e s e n t e d by its Legal Adviser, Michel van A c k e r e , acting as A g e n t , assisted by F r a n k Benyon, a m e m b e r of

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

its Legal Department, with an address for service in Luxembourg at the office of Oreste Montalto, a member of its Legal Department, Jean Monnet Building, Kirchberg, defendant,

APPLICATIONS for a declaration that individual decisions by which the Commission fixed the applicants' production quotas for crude steel and rolled products for the first quarter of 1981 are void,

THE COURT

composed of: J. Mertens de Wilmars, President, G. Bosco, A. Touffait and O. Due (Presidents of Chambers), P. Pescatore, Lord Mackenzie Stuart, A. O'Keeffe, T. Koopmans, U. Everling, A. Chloros and F. Grévisse, Judges,

Advocate General : P. VerLoren van Themaat Registrar: A. Van Houtte

gives the following

JUDGMENT

Facts and issues

The facts of the case, the course of market and on the world market, total the procedure, and the conclusions, orders falling suddenly by 20% submissions and arguments of the parties compared with the third quarter of 1979, may be summarized as follows : a quarter in which orders were already at a low level. Orders from the Community market fell by 25%. I — Summary of the facts and the course of the procedure The utilization rate of Community steel undertakings, which was approximately In the third quarter of 1980 demand for 70% in the second quarter of 1980, fell steel slumped both on the Community to 58% in September, the lowest rate

HALYVOURGIKI v COMMISSION

ever recorded in the Community. The mill plate and wide flats; heavy sections undertakings' forecasts indicated that the (sheet piling, wide flanged beams, other rate would fall again in the fourth beams and other sections, permanent quarter to below 5 5 % . The large way material) and light sections (coiled variation in the decline in production, wire rod, concrete reinforcing bars and from one undertaking or region to other merchant bars). another, caused economic and social imbalance between undertakings and According to Article 3 (1) of the regions. decision, the quarterly production quotas are to be fixed by the Commission for Between January and September 1980 each undertaking on the basis of the the fall in demand resulted in a slump reference production figures of that in steel prices in the Community. They undertaking and by application of fell by 1 3 % , whilst production costs abatement rates to those reference increased by 5 % in the same period. production figures.

Article 4 of the decision lays down the The Commission of the European method of determining the quarterly Communities therefore considered that reference production figures for each the European iron and steel industry was undertaking for both rolled products and in a situation in which the attainment of crude steel. the objectives set out in Article 3 of the ECSC Treaty, in particular the modern- (a) The general rules are fixed by ization and restructuring of production, paragraphs (1) and (2) as follows: the improvement of workers' conditions and the securing of orderly supplies to the common market, was seriously (1) For each month of the relevant jeopardized and that the Community was quarter, reference is to be made confronted with a period of manifest to the same month during the crisis within the meaning of Article 58 of period from July 1977 to June the ECSC Treaty. 1980 during which the total production of the four groups of rolled products was the highest. The indirect courses of action available The three months thus chosen, to the Commission proved to be which will not necessarily be ineffective or insufficient and the consecutive, are to constitute the Commission considered it necessary to reference period. intervene directly, by means of binding measures relating to production, in order (2) The reference production figures to restore the balance between supply are to be the same, for crude and demand. By Decision N o 2794/80 steel and for each of the other of 31 October 1980 (Official Journal groups of rolled products, as the L 291, p. 1) it established a system of production of the corresponding production quotas for steel manufac- items during the reference turers in the Community. period.

Article 2 of that decision provides that (b) Paragraphs (3), (4) and (5) of Article the Commission is to fix quarterly 4 describe the particular cases in production quotas for crude steel and for which the reference production four groups of rolled products: hot- figures, and consequently the quotas, rolled wide and narrow strip; reversing are to be increased.

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

According to Article 4 (3), the the Commission shall, on certain Commission must, while taking account conditions and within specific limits, of the criteria given, increase the adapt the reference production of that reference production figures of under- undertaking. takings which, during the period from July 1977 to June 1980, had an average rate of utilization of production facilities Article 4 (5) provides for an increase in of 10 percentage points or more below an undertaking's reference production the average rate of utilization of the figures to take account of restructuring. same facilities of the other undertakings of the Community during the years The rates of abatement for rolled 1977, 1978 and 1979. products, having been fixed for the fourth quarter of 1980 by Article 5 (1) of Article 4 (4) provides that where, further Decision N o 2794/80, were fixed for the to an investment programme duly first quarter of 1981 by Article 1 of reported and not the subject of an un- Commission Decision No 3381/80/ favourable opinion, the undertaking ECSC of 23 December 1980 (Official activates a new plant after 1 July 1980, Journal L 355, p. 37) as follows:

Group I Hot rolled wide and narrow strip 27.73 %

Group II Reversing mill plate and wide flats 22.76 %

Group III Heavy sections (sheet piling, wide flanged beams, other beams and other sections, permanent way material) 19.59 %

Group IV Light sections (coiled wire rod, concrete reinforcing bars and other merchant bars) 27.64 %

Article 5 (2) of Decision N o 2794/80 mission must, where appropriate, adapt provides that the rate of abatement for the provisions of the decision. crude steel which the Commission communicates to undertakings is to correspond to the average abatement Article 2 of the Act of 24 May 1979 rates of the four groups of rolled concerning the Conditions of Accession products weighted according to the of the Hellenic Republic and the reference production of each of those Adjustments to the Treaties (Official groups of products. Journal L 291, p. 17, hereinafter referred to as "the Act of Accession") provides that "from the date of accession, the Under Article 14 of Decision No provisions of the original Treaties and 2794/80, where the production or the acts adopted by the institutions of the delivery restrictions imposed by the Communities shall be binding on the decision or its implementing measures Hellenic Republic and shall apply in that entail exceptional difficulties for an State under the conditions laid down in undertaking, it may refer the matter to those Treaties and in this Act". the Commission. The Commission must examine the case without delay in the light of the objectives of the decision. On the basis of the Act of Accession, in After examining the case the Com- particular Article 2 thereof, and Article 3

HALYVOURGIKI v C O M M I S S I O N

of Decision No 2794/80 and Decision Thus, by telex messages of 19 January No 3381/80, the Commission informed 1981, the Commission communicated to the Greek iron and steel undertakings in Halyvourgiki Inc., M e t a l l u r g i k i Halyps January and February 1981 of their SA and Helleniki Halyvourgia SA their reference production figures and pro- reference production figures and pro- duction quotas resulting from the ap- duction quotas for the first quarter of plication of the abatement rates for the 1981 as fixed by individual decisions first quarter of 1981. Those quotas were adopted respectively on 19 January, based on reference production figures 3 February and 20 January 1981 calculated in accordance with Article 4 and notified to those concerned on (1) and (2) of Decision No 2794/80. 3 February.

The figures thus fixed were as follows:

(a) Halyvourgiki Inc.

Reference production Quota Reduction 1 st January 1980 February 1980 March 1979 Total Quarter 1981

tonnes tonnes tonnes tonnes % tonnes

Rolled products Category I 24 433 31 681 35 367 91 484 27.73 66 113 Category II 7 213 5 664 5 436 18 313 22.76 14 145 Category III — — — — — — Category IV 30 713 32 250 30 567 93 530 27.64 67 678

Total I to IV 62 359 69 595 71 370 203 324 147 936

Crude steel 34 323 37 908 31 156 103 387 27.24 75 224

(b) Helleniki Halyvourgia SA

Reference production Quota Reduction 1 st January 1980 February 1980 March 1979 Total Quarter 1981

tonnes tonnes tonnes tonnes % tonnes

Rolled products Category I — — — — — — Category II — — — — — — Category III — — — — — — Category IV 11 196 10 476 10 625 32 297 27.64 23 370

Total I to IV 11 196 10 476 10 625 32 297 23 370

Crude steel 11 577 12 225 12 530 36 332 27.64 26 289

J U D G M E N T O F 16. 2. 1982 — J O I N E D CASES 39, 43, 85 A N D 88/81

On 19 and 20 February 1981 five Greek and, in one case, information obtained in steel undertakings, including Haly¬ situ by its own inspectors, the vourgiki Inc. (Case 39/81), Metallurgiki Commission had adopted decisions on Halyps SA (Case 41/81) and Helleniki 13 March 1981 amending its original Halyvourgia SA (Case 43/81), brought decisions on production quotas for the actions under Article 33 of the ECSC first quarter of 1981. Treaty for the annulment of the Com- mission decisions fixing the production (a) In particular, pursuant inter alia to quotas for the first quarter of 1981; they Article 14 and Article 5 (2) of Decision also applied under Article 39 of the No 2794/80, the decision of 13 March ECSC Treaty and Article 83 of the Rules 1981 made the following amendments to of Procedure for the operation of those the production quotas of Halyvourgiki decisions to be suspended. Inc. for the first quarter of 1981 :

By an order dated 13 May 1981 the Court decided to join the five Quotas fixed applications registered under Nos 39/81, by decision Quotas fixed by decision 40/81, 41/81, 42/81 and 43/81 for the of 19 January of 13 March 1981 1981 (in tonnes) purposes of the procedure and the (in tonnes) judgment. Rolled Products Category I 66 113 91481 Following the withdrawal of their applications by the two undertakings in Category II 14 145 — Cases 40/81 and 42/81, the Court, by an Category III — — order dated 16 September 1981, removed Category IV 67 678 86 275 those cases from the register and ordered each of the undertakings to bear one fifth of the costs incurred until the date Crude steel 75 224 187 775 of withdrawal, including the costs of the proceedings for the adoption of interim measures.

The written procedure followed a (b) In the case of Helleniki Haly- normal course in Cases 39/81 (Haly- vourgia SA, pursuant to Article 14 of vourgiki Inc), 41/81 (Metallurgiki Decision No 2794/80 the decision of Halyps SA) and 43/81 (Halyvourgia 13 March 1981 made the following SA). amendments to the original decision:

On 20 March 1981, after four of the five applicant undertakings had withdrawn Quotas fixed Quotas fixed by decision their applications for the adoption of of 20 January by decision of 13 March 1981 interim measures, the President of the 1981 (in tonnes) (in tonnes) Court made an order ([1981] ECR 841) in Case 41/81 R (Metallurgiki Halyps Rolled Products SA). Category IV 23 370 32 297

As a result of the observations submitted Crude steel 26 289 36 322 by the Greek undertakings concerned

HALYVOURGIKI v COMMISSION

On 13 April 1981 Halyvourgiki Inc., On hearing the report of the Judge- Helleniki Halyvourgia SA and two other Rapporteur and the views of the Greek steel undertakings, brought Advocate General, the Court decided to actions for the annulment of the open the oral procedure in those cases Commission's amending decisions of 13 without any preparatory inquiry. March.

By an order dated 13 May 1981 the At the hearing on 10 November 1981 Court decided to join the applications counsel for Metallurgiki Halyps SA, registered under Nos 85/81, 86/81, Ernest Arendt, of the Luxembourg Bar, 87/81 and 88/81 for the purposes of the asked the Court to disjoin Cases 41 and procedure and the judgment. 121/81 from the other joined cases and to postpone the oral procedure in those two cases; alternatively, he proposed to withdraw the applications. After hearing By an order dated 16 September 1981 the Commission's observations and the the Court removed Cases 86/81 and views of the Advocate General and 87/81 from the register following the deliberating on the matter, the Court withdrawal of the applications by two decided at the hearing that, although no undertakings, each of which was ordered reason had been adduced which might to bear one quarter of the costs incurred justify the postponement or disjoinder of until the date of withdrawal. Cases 41 and 121/81, Metallurgiki Halyps SA should be allowed to withdraw its applications.

The written procedure in Cases 85/81 (Halyvourgiki Inc.) and 88/81 (Helleniki Halyvourgia SA) followed a normal course. The applicants decided not to That decision became effective by an lodge a reply. order of the Court dated 10 February 1981 ordering Cases 41 and 121/81 to be removed from the register and reserving costs. On 15 May 1981 an application was lodged under No 121/81 by Metallurgiki Halyps SA against a Commission decision of 14 April amending its production quotas as fixed by a decision At the hearing on 10 November 1981 of 3 February. oral argument was presented by Mr Elvinger for Halyvourgiki Inc. and Helleniki Halyvourgia SA and by Mr van Ackere for the Commission. The written procedure in that case followed a normal course. The applicant decided not to lodge a reply. By order of 25 November 1981 the Court ordered the applicant Metallurgiki By an order of 30 September 1981 the Halyps SA to bear its own costs in Cases Court decided to join Cases 39, 41, 43, 41 and 121/81 and one-third of the costs 85, 88 and 121/81 for the purposes of incurred by the Commission, prior to the the oral procedure and the judgment. withdrawal of the applications, in Joined

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

Cases 39, 41, 43, 85, 88 and 121/81. By III — Submissions and argu- the same order the parties in Case 41/81 m e n t s of t h e p a r t i e s R were ordered to bear their own costs, the costs having previously been reserved by the order of the President of 20 In support of their applications for a March 1981. declaration that the individual decisions concerning them are void, the applicants The Advocate General delivered his contend that the general decisions on opinion at the sitting on 12 January which they are based, Decisions Nos 1982. 2794/80 and 3381/80, are, in the first place, not applicable to Greek under- takings or at any rate void as far as they II — C o n c l u s i o n s of t h e p a r t i e s are concerned and, secondly, vitiated by illegality owing to the infringement of an essential procedural requirement, the The applicants claim that the Court failure to give an adequate statement of should: reasons and the infringement of the ECSC Treaty, in particular Articles 58 (a) In Cases 39 and 43/81 : and 74 thereof. Declare void the decisions of 19 and 20 January 1981 whereby the The Commission considers that by virtue Commission fixed steel production of the Act of Accession Decisions Nos quotas for each of the applicants 2794/80 and 3381/80 apply to Greek pursuant to Decisions Nos 2794/80/ steel undertakings and are entirely valid ECSC and 3381/80/ECSC; and as against them; moreover, they comply with the ECSC Treaty and are properly Order the Commission to pay the reasoned. costs.

(b) In Cases 85 and 88/81: A — The applicability of Decisions Nos Formally take note that the appli- 2794/80 and 3381/80 to Greek steel cants maintain the actions which undertakings they commenced against the Com- mission's decisions of 19 and 20 January 1981; The applicants consider that Decisions Nos 2794/80 and 3381/80 are not Declare void the amended terms of applicable to them or in any event void those decisions as set forth in the as against them. Commission's letters of 13 March 1981;and (a) Decisions Nos 2794/80 and Order the Commission to pay the 3381/80 are not measures enacted by the costs. institutions of the Community as enlarged by the entry of Greece because they were adopted before 1 January In all the cases the Commission contends 1981, the date on which accession took that the Court should: effect. Dismiss the applications as unfounded; and N o r were they signed or ratified under the documents concerning accession, Order the applicants to pay the costs. since they were subsequent to those

HALYVOURGIKI v COMMISSION

documents; therefore they could not be adopted by the institutions, does not the subject either of transitional measures mention future acts any more than does pursuant to Article 9 of the Act of Article 2. Accession, or of the adaptations provided for in Articles 21 and 22 thereof, as acts adopted by the The "Community patrimony" ["acquis institutions. communautaire"] consists of those treaties and acts of the institutions existing at the date of the Treaty of It is true that Article 2 of the Act of Accession, as adapted by that Treaty. Accession provides that the acts adopted by the institutions of the Communities are to be binding on the Hellenic (b) It is true that Article 146 of the Act Republic "from the date of accession"; of Accession envisages the entry into the principle of the applicability of force from the date of accession of Community legislation is in no way contested by the applicants. However, certain "adaptations" to the acts of the that principle does not apply to future Community institutions not included in legislation and, according to Article 2 of that Act and made by the institutions the Act of Accession, is to be put into before accession; however, that provision effect only "under the conditions laid has in view adaptations to the acts and down . . . in this Act". In the absence of not the acts themselves, and the adap- any express provision to that effect, tations are intended only to "bring those Greece cannot be deemed to have agreed acts into line" with the provisions of the by treaty to future acts which were Act of Accession. The "acts of the unknown and wholly undetermined at institutions" in question are clearly acts the time when the Treaty was signed and which are already known and in force which were to be adopted subsequently and which could not be adapted under by institutions in which Greece was not Articles 21 and 22 of the Act of represented and without any involvement Accession owing to the great number of on its part. regulations; although it was only a question of adaptations and not of new acts, those adaptations necessarily had to be effected without the involvement of The surrender of sovereignty involved in the new Member State and without its accession to the Treaty is inconceivable being represented within the Community without the participation of the new institutions. Member State in the Community institutions; in order for Greece to be bound and to agree to be bound by Article 146 of the Act of Accession is provisions which are not dealt with in obviously restrictive in nature.' it is the Treaty of Accession or in measures intended to enable the Community adopted by institutions truly "enlarged" institutions not yet "enlarged by the through its participation, the Treaty of entry of Greece" to adapt the measures Accession would have had to contain adopted by the institutions; it does not an express and unequivocal provision allow the institutions not yet enlarged to establishing such an indeterminate and adopt new measures. unlimited surrender of sovereignty.

If, for the sake of argument, it is Article 9 of the Act of Accession, which assumed that Article 146 of the Act of provides for transitional measures in Accession could be construed as applying relation to the application of acts to legislation subsequent to the Treaty

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

but prior to accession, it would have to Such nullity is only relative: it affects be recognized that it requires such future Decision N o 2794/80 only as regards legislation to be adopted; in the present Greece. case it would require the Commission, after adopting Decision N o 2794/80, to comply with the mandatory requirement to adapt it to the case of Greece.

The decision is also void as regards Greece for failing to contain a sufficient statement of the reasons on which it is based: no reasons are given for the (c) The information and consultation future entry into force of the decision in procedure provided for by the Final Act Greece and the situation of that country of 28 May 1979 (Official Journal L 291, is not taken into consideration at all. p. 191) for the adoption of certain decisions and other measures to be adopted during the period prior to accession should have been in operation already with a view to making the "adaptations" referred to in Article 146 of the Act of Accession. Taken together, Article 146 and the provisions on the (d) Decision No 2794/80 is not information and consultation procedure applicable to Greece because of the very make it impossible to accept that content of the decision and reasons on between the signing and the entry into which it is based: the fall in demand and force of the Act of Accession the new period of manifest crisis referred to in Member State, although informed and the preamble to the regulation are consulted where appropriate, had only to representative only of the situation in submit to and follow the legislative the Community without Greece; the decisions of institutions in which it was statement that undertakings have failed not yet represented. to fulfil their individual voluntary commitments and refused to commit themselves for the future obviously cannot apply to Greek undertakings; the method of determining quotas provided for in Article 4 (3) and (4) clearly excludes adjustments for undertakings In any case, neither the statement of which were not part of the Common reasons in the preamble to Decision N o Market in the previous years. The fixing 2794/80, although detailed, nor the of quotas on the basis of actual statement that certain consultations had production between 1977 and 1980 is taken place mentions that information entirely inappropriate in the case of had been given to Greece. It is a Greek undertakings, which, not being principle of administrative law that part of the Common Market in those decisions must show that they have been years, did not enjoy protection either adopted in a proper manner. The failure against other Member States or against to mention that an essential procedural non-member countries and were not only requirement has been satisfied precludes denied the support machinery introduced evidence to the contrary and renders the by the Community but owing to decision null and void.

HALYVOURGIKI v COMMISSION

Community protection were also cannot be the case that the entire body exposed to increased pressure both from of Community legislation enacted the Member States and from non- between the signing of the documents member countries; in 1981, under the concerning accession and the date on terms of Articles 25 and 29 of the Act of which accession took effect may never Accession, the customs barriers between apply to Greece. the Community and Greece were still at 90 % of the old level.

The measures adopted by the institutions of the Communities are most certainly applicable to Greece on the conditions (e) In reply to the Commission's laid down in the Act of Accession, that is assertion that if the applicants' views to say subject, first, to the "adaptations" were accepted all Community legislation made necessary by the entry of a tenth enacted over a period of 19 months Member into the Communities and the would for ever remain inapplicable to corresponding extension of their geo- Greece, the applicants state that a treaty graphical scope and, secondly, to the may not be construed and applied solely temporary derogations and transitional on grounds of expediency and, measures provided for in the Act of moreover, that from 1 January 1981 the Accession itself, in particular in Article 9 quite exceptional situation of Greece thereof. necessitated in practical terms a supp- lementary decision based on Article 58 of the ECSC Treaty, since Regulation No 2794/80 was clearly unsuitable for application to Greece. In the steel sector, there are special provisions for the introduction of the ECSC unified tariff (Articles 32 to 34) and for the setting of prices by iron and steel undertakings (Article 129). The Commission disputes all the However, there is no provision anywhere arguments denying that the general to the effect that measures adopted decisions at issue are applicable or valid pursuant to Article 58 of the ECSC as regards Greek steel undertakings. Treaty may not apply to Greece or may only apply to it on certain conditions in derogation from Community law.

(a) Article 2 of the Act of Accession contains a fundamental principle: the "acquis communautaire" on 31 "Adaptations" to the acts of the December 1980, that is to say the institutions not contained in the Act of original treaties and acts adopted before Accession itself or the annexes thereto that date by the institutions of the were made, where necessary, by the Community, is applicable in Greece from institutions before the accession of its accession on 1 January 1981. Having Greece under the procedure laid down in become a full Member of the Article 146 (2) of the Act of Accession. Communities, Greece had to accept all They were intended to bring the the obligations incumbent on the nine measures adopted by the institutions into existing Member States on that date. Any line with the Act of Accession; they other view is truly inconceivable: it concerned not only additional technical

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

adaptations but also adaptations to contained in the acts of the institutions legislation enacted between the signing require a statement of the reasons on of the documents concerning accession which they are based: measures not and the date of accession and, more contained therein require no such generally, all the amendments to acts of statement. the institutions which may have appeared necessary owing to the new temporary rules provided for in the Act of Accession. Unless otherwise stated, all (e) The statement of reasons contained the acts adopted by the institutions of the in a general decision cannot take account Communities before accession apply to of the specific situation of each steel Greece, as they do to the other Member undertaking considered State by State, of the Communities, as first enacted or old or new. Decision No 2794/80 is of subject to any amendments found to be general concern to all the steel under- necessary. takings in the Community, as it is composed at the time when the terms of the decision are applied.

(b) The adaptations provided for by Moreover, the interests of the Greek Article 146 of the Act of Accession were steel industry were taken into account by required only where it was necessary to the transitional measures contained in take account of any special provisions the Act of Accession. The Act did not, for Greece envisaged by that act; they however, exempt Greece from any were not necessary for the purposes of application of Article 58 of the ECSC the application of Articles 47 and 58 of Treaty. Furthermore, when the decision the ECSC Treaty. on the quotas was taken, no need was felt to add specific new measures for the benefit of Greece. The fact that Greek undertakings had not participated in the previous anti-crisis measures was no (c) The agreement on the procedure reason for excluding them from the for adopting certain decisions and other system of production quotas; that fact measures to be taken during the period was by no means unfavourable to them. leading up to accession, which is annexed to the Final Act, is evidence that the decisions to be taken by the Council during the interim period were meant to apply to Greece: otherwise, what reason B — The alleged failure to give adequate would there be for involving Greece in reasons the adoption of those decisions?

The applicants point out that under Article 58 (1) of the ECSC Treaty the (d) The information procedure was in Commission may establish a system of fact followed with regard to Greece, production quotas "accompanied to the which did not request consultations necessary extent by the measures within the Interim Committee: Therefore provided for in Article 74". Therefore, the statement of reasons given for when it took the decision to apply Decision No 2794/80 did not have to Article 58 the Commission was under an refer to consultations which had not absolute obligation to consider whether taken place. In any case, only measures the system to be established should be

HALYVOURGIKI v COMMISSION

accompanied by the measures provided In any case, the reasons on which acts of for in Article 74. But the provisions the institutions are stated to be based referred to in the preamble to Decision must justify the measures adopted and N o 2794/80 do not include Article 74; in contained in those acts; they do not need fact there is no mention of that provision to justify the failure to adopt measures either in the preamble or the articles of which are not contained therein. the decision.

C — The alleged infringement of Articles Articles 58 and 74 are so closely linked 58 (1) and 74 of the ECSC Treaty that, at least as regards point (3) of the first paragraph of Article 74, no decision on either article may be taken without having regard to the possible application The applicants consider that, since of the other. Therefore, whenever Article recourse to Article 58 (1) of the ECSC 58 is applied, the extent to which it is Treaty is unquestionably justified in this "necessary" to apply Article 74 must be case, the failure to take action under considered; thereafter the decision must Article 74 at the same time constitutes an be taken to apply or not to apply Article infringement of both those provisions. 74, depending on whether it is "necessary" to do so. The fact that the Commission has some discretion in the matter does not prevent the legality of the decision not to take The failure to state whether the action under Article 74 from being possibility of applying Article 74 was submitted to judicial review: the Court considered and the failure to give has the power to verify whether the reasons for the conclusion arrived at decision is based on a correct application mean that the reasons which Decision of the Treaty. N o 2794/80 gives for the application of Article 58 are inadequate. In this case, it is evident not only that merely to reduce production in the countries of the Common Market is The Commission believes that the link insufficient to bring supply down to the between Articles 58 and 74 of the ECSC level of demand, but also that the very Treaty has a fundamentally different act of reducing production in the effect in the case of each article: the countries of the Common Market must statement of reasons for the introduction inevitably open a greater part of the of quantitative restrictions pursuant to market to producers in non-member point (3) of the first paragraph of Article countries after the first quarter of 1981 74 must state that the conditions laid in view of the inadequate action taken down in Article 58 exist; however, on the basis of other provisions both Article 58 makes no mention of the unilaterally and through agreements. conditions laid down in Article 74 and therefore Article 74 does not have to be mentioned in the statement of reasons on According to the Commission, the which a decision taken pursuant to assessment of the "necessary extent" to Article 58 is based, unless it contains which measures adopted under Article 58 provisions based on that article, which is should be accompanied by measures not the case with Decision No 2794/80. adopted under Article 74 is a matter of

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

policy: it is a question of balancing, on part of the Community and Article 4 (4) the one hand, the usefulness of measures is not applicable to undertakings whose to curb imports, which are in fact investment programme could not be the quantitative restrictions, and on the other subject of a Commission opinion for the hand, the compatibility of such same reason. Therefore Decision N o restrictions with the Communities' obli- 2794/80 blatantly discriminates between gations towards non-member countries, the last category of undertakings and the particularly under GATT, as well as the others. repercussions which the introduction of import restrictions might have on Community exports in general and on exports of steel products in particular. (b) As a result of the manner in which After considering those various factors Article 14 of Decision No 2794/80 has and taking into account the various been construed further discrimination is measures which had already been created between those undertakings implemented, including some on the which remain viable despite the basis of Article 74, as well as those to be restrictions and those which suffer taken at the same time as the decision "exceptional difficulties owing to those introducing the quota system, the measures". Commission decided that there was no need for the quota system to be accompanied by additional measures (c) Any provision which bases quotas against imports on the basis of Article 74 on actual production during the refer- or on any other basis;, it was already ence period instead of on production sufficiently accompanied by other capacity will inevitably result in discrim- measures. ination contrary to the equitable basis required by the strict words of Article 58 of the ECSC Treaty. That view was not invalidated by sub- sequent experience. (d) Discrimination does not consist solely of treating undertakings in similar circumstances differently; in the present D — The allegation of discrimination case the discrimination is due to the fact that undertakings in different circums- tances are treated in the same way. The applicants point out that, according to the first subparagraph of Article 58 (2) of the ECSC Treaty, the production (e) Account should be taken here of quotas are to be determined "on an the principle of proportionality, which is equitable basis, taking account of the recognized in the decisions of the Court: principles set out in Articles 2, 3 and 4" compared to the Community's crude of the Treaty. steel production of 140 million tonnes a year in 1979 and 1980, the total production of the Greek undertakings, which barely exceeds one million tonnes, (a) Article 4 (3) of Decision N o is insignificant. 2794/80 is not applicable to under- takings which could not participate in the delivery programmes drawn up by The Commission contests all those the Commission because they were not submissions.

HALYVOURGIKI v COMMISSION

(a) The basic method of fixing adapted the quotas for two Greek under- production quotas described in Articles takings pursuant to Article 4 (4). That 3, 4 and 5 of Decision No 2794/80 takes provision clearly does not discriminate into consideration, in order to determine between Greek companies and other reference production figures for each companies in the Community or in fact undertaking, a period sufficiently recent between any undertakings operating in to reflect actual structures and suf- similar circumstances. ficiently long to eliminate any fortuitous circumstances. It sets individual abatement rates for each category of products, so as to take account of the Article 4 (5) seeks to prevent the quota particular situation on the market for system from jeopardizing efforts at reor- each category. ganization which some undertakings have successfully made since 1974, when the crisis began.

The aim of Article 4 (3) is to avoid any unfairness which certain undertakings which had participated in the voluntary The last subparagraph of Article 5 (2) delivery programmes might have makes provision for undertakings to suffered. The Greek undertakings did apply for an adjustment of their crude not participate in those programmes, so steel quotas to enable them to produce there was no need to make adjustments the quantities of rolled products fixed by for their benefit. However, no discrimi- their production quotas. Such an nation is caused thereby: it is not an adjustment has already been made in the instance of treating undertakings in case of one Greek undertaking. similar circumstances differently.

(b) Article 14 makes it possible to Article 4 (4) allows account to be taken reduce the disproportionate sacrifices of the production capacity of new plant which the application of the general rules put into operation after 1 July 1980 of Decision N o 2794/80 might have because the output of such plant could required of some undertakings. The not have been reflected in the reference quotas of any undertaking experiencing production figures. Since the Greek exceptional difficulties may be adapted undertakings were not bound before on that account. Non-application of that 1 January 1981 by Decision No 22/66 of provision is not discriminatory at all: it the High Authority of 16 November does not entail different treatment of 1966 on information to be furnished by similar cases but different treatment of undertakings about their investments different cases. (Official Journal, English Special Edition 1965-1966, p. 280), an application from them was considered necessary in order to obtain an adjustment under Article 4 (4). Having regard to such applications (c) The fixing of quotas according to and having determined that the actual production during the reference investments in question would not have period, which consists of each under- received an unfavourable opinion if they taking's best months of production, had been notified in the form of enables every undertaking to be treated investment programmes, the Commission in the same way.

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

The criterion based on an undertaking's Moreover, production calculated on a actual production is objective, accurate national basis does not provide the and quantifiable; the concept of relevant figures. Decision N o 2794/80 "production capacity", on the other introduced a system of quotas concern- hand, is less precise and more difficult to ing undertakings and the production of define. Moreover, the fixing of quotas by each of the five Greek undertakings is reference to the maximum production not negligible; it exceeds by far the capacity of undertakings would inevi- threshold of 3 000 tonnes under which tably penalize those which, owing to small undertakings are exempt from rational management, utilize their ca- quotas. By virtue of the principle of pacity to a very high degree and would solidarity the sacrifices demanded of the unjustifiably benefit those operating at a Greek undertakings should be, and are, low rate of utilization; it would also be the same as those demanded of other contrary to the aims of Article 3 of the undertakings in the Community. ECSC Treaty, particularly those set out in paragraphs (a) and (e). The system of quotas introduced by Decision N o 2794/80 does not impose on the undertakings concerned burdens (d) The claim that the principle of which are out of proportion to the aim proportionality has been breached is a pursued, namely the adaptation of supply new submission which Article 42 (2) of to the reduced demand for steel. It has the Rules of Procedure prevents from been held by the Court that the being adduced. obligation of the Community institutions to ensure that in exercising their powers In fact, the Commission is by no means the burdens imposed on undertakings are ignorant of the situation of the Greek no greater than is required to achieve the steel industry, whose production, aims to be accomplished is not to be moreover, exceeds that of Denmark and measured in relation to the individual is nearly fifteen times greater than that situation of any particular group of of Ireland. undertakings.

Decision

1 By applications l o d g e d at the C o u r t Registry o n 19 a n d 20 F e b r u a r y 1981 a n d registered u n d e r N o s 3 9 / 8 1 and 4 3 / 8 1 the G r e e k steel u n d e r t a k i n g s H a l y v o u r g i k i I n c . and Helleniki H a l y v o u r g i a SA, both i n c o r p o r a t e d u n d e r the laws of G r e e c e and having their respective registered offices at A t h e n s a n d Piraeus, b r o u g h t actions u n d e r Article 33 of the E C S C T r e a t y for a declaration t h a t decisions fixing their p r o d u c t i o n quotas for c r u d e steel a n d rolled p r o d u c t s for the first q u a r t e r of 1981 are void. T h o s e decisions w e r e a d o p t e d on 19 a n d 20 J a n u a r y 1981 respectively p u r s u a n t to C o m m i s s i o n

HALYVOURGIKI v COMMISSION

Decision N o 2794/80/ECSC of 31 October 1980 establishing a system of steel production quotas for undertakings in the iron and steel industry (Official Journal 1980, L 291, p. 1) and Commission Decision N o 3381/80/ ECSC of 23 December 1980 fixing the rates of abatement for the first quarter of 1981 (Official Journal 1980, L 355, p. 37).

2 The applicants' main contention is that Decisions N o 2794/80 and N o 3381/80, the general decisions on which the contested individual decisions are based, are not applicable to Greek undertakings, or at any rate are void as against them, because they were adopted unilaterally by the Community without the collaboration of the Greek authorities during the interim period between the signing of the documents concerning the accession of the Hellenic Republic to the Communities — to be precise, 24 May 1979, the date of the decision adopted by the Council of the European Communities on the accession of the Hellenic Republic to the European Coal and Steel Community and of the Act annexed to that decision concerning the conditions of accession (Official Journal 1979, L 291, pp. 5 and 17) — and accession itself, which took effect on 1 January 1981.

3 In the alternative, the applicants argue that Decision N o 2794/80 is illegal because it fails to state properly the reasons on which it is based and because it infringes Articles 14, 58 and 74 of the ECSC Treaty; furthermore, the application of certain criteria laid down in that decision is said to entail discriminatory treatment against Greek undertakings in relation to other undertakings in the Community.

4 After the Commission had, by letters dated 13 March 1981, amended its original decisions pursuant, in particular, to Article 14 of Decision N o 2794/80, the two companies, by applications registered on 13 April 1981 under Nos 85 and 88/81, extended the actions to those amending decisions. They consider that, although those amendments are in general favourable to them, they do not dispose of any of the objections made against Decisions N o 2794/80 and N o 3381/80 and the application thereof to Greek under- takings.

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

T h e a p p l i c a t i o n of D e c i s i o n s N o 2 7 9 4 / 8 0 a n d N o 3 3 8 1 / 8 0 to Greek undertakings

5 In the decisions fixing the applicants' production quotas the Commission stated that the decisions were adopted "on the basis of the Act concerning the accession of Greece, in particular Article 2 thereof, and pursuant to Article 3 of Decision N o 2794/80/ECSC and to Decision N o 3381/80/ ECSC".

6 The applicants consider that the individual decisions adopted with respect to them are void on the ground that the general decisions on which they are based are not applicable to Greek undertakings: on the one hand, those general decisions, which were adopted before Greece's accession on 1 Jan- uary 1981, are not acts of the Community institutions as enlarged by the entry of Greece; on the other hand, since those decisions were adopted after the documents concerning the accession of Greece were signed, they have not been the subject of any undertaking or ratification on the part of Greece. In this regard they submit that it is not possible to accept that the reference to the acts of the institutions in Article 2 of the Act of Accession could include future acts, which, because their terms were not yet settled, were not known to the parties on the date on which the international agreement was concluded.

7 It is argued that, even on the supposition that the general decisions in question may be extended to Greek undertakings, those undertakings are still justified in contesting their applicability.

Those decisions were not dealt with under the adaptation procedure provided for in Articles 22 and 146 of the Act of Accession or under the information and consultation procedure provided for in the agreement annexed to the Final Act signed in Athens on 28 May 1979 (Official Journal 1979, L 291, pp. 179 and 191).

8 Finally, the applicants contend that, in so far as Decision N o 2794/80 is based on the finding that there exists a state of manifest crisis within the meaning of Article 58, as stated in the preamble to that decision, it is representative only "of the situation in the Community without Greece". They therefore submit that the decision is by its very nature inapplicable to Greek undertakings.

HALYVOURGIKI v COMMISSION

T h e effect of D e c i s i o n s N o 2 7 9 4 / 8 0 a n d N o 3 3 8 1 / 8 0

9 Article 2 of the Act of Accession provides that "from the date of accession, the provisions of the original Treaties and the Acts adopted by the institutions of the Communities shall be binding on the Hellenic Republic and shall apply in that State under the conditions laid down in those Treaties and in this Act". In accordance with Article 2 of the Decision of the Council of 24 May 1979, Greece's accession to the European Coal and Steel Community took effect on 1 January 1981 with the deposit on that date of its instrument of accession. Read together, those two provisions show that it is with reference to 1 January 1981, rather than the date of the Council's decision or of the signing of the documents concerning accession, that it must be determined which acts of the institutions are binding on the Hellenic Republic and applicable in that State.

10 Articles 22 and 146 of the Act of Accession are not relevant to the issue raised. Those provisions apply only to acts of the institutions the adaptation of which, recognized to be necessary when the documents concerning accession were signed, had to be carried out during the interim period. As regards new measures to be adopted in that period, the institutions were aware of the imminent accession of Greece, which was given an opportunity to assert its interests where necessary, in particular through the information and consultation procedure described in an agreement annexed to the Final Act (Official Journal 1979, L 291, p. 191).

1 1 It is therefore incontestable that Decision N o 2794/80 adopted on 31 Oct- ober 1980, and Decision N o 3381/80, adopted on 23 December 1980, are amongst the acts of the institutions which entered into force, unadapted, with respect to Greece and in its territory when accession became effective on 1 January 1981 pursuant to Article 2 of the Act of Accession.

12 It should be added that only in this way is it possible to avoid discontinuity in the Community legal system in its application to Greece. The scheme of the Act of Accession shows that the acceding State accepts all the measures adopted by the institutions prior to the time when its accession takes effect, whereas the applicants' argument would lead to the creation of a legislative

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

vacuum in regard to that State extending over the interim period between the time when the documents concerning accession were signed and the time when accession took effect.

T h e i n f o r m a t i o n and c o n s u l t a t i o n p r o c e d u r e

1 3 It is stated in the Final Act signed in Athens on 28 May 1979 that "the Plenipotentiaries and the Council have also taken note of the arrangement regarding the procedure for adopting certain decisions and other measures to be taken during the period preceding accession which has been reached within the Conference between the European Communities and the Hellenic Republic and which is annexed to this Final Act".

1 4 By virtue of the agreement annexed to the Final Act, entitled "Information and consultation procedure for the adoption of certain decisions", provisions were made in order to ensure that the Government of Greece was kept informed of any proposal or communication from the Commission which might lead to decisions by the Council other than administrative decisions.

15 Even if it is assumed that that obligation may be taken to extend to the draft of the decisions under Article 58 of the ECSC Treaty, which were to be adopted by the Commission itself, subject to the assent of the Council, the explanations given by the Commission show in any case that the information procedure was duly followed in the interim period. The applicants have not adduced any evidence to suggest that the Greek Government was not able to assert its interests with regard to the draft decisions of the Commission in accordance with the provisions of the agreement annexed to the Final Act.

T h e f i n d i n g of a s t a t e of c r i s i s

16 The applicants' argument that the finding of a state of crisis was not represen- tative of the situation in the Community after the accession of Greece ignores the fact that the existence of such a crisis must be ascertained in the light of the situation in the Community as a whole. Therefore the intro- duction of measures under Article 58 may not be ruled out even if under- takings in some Member States or some regions of the Community are less

HALYVOURGIKI v COMMISSION

affected than others by a widespread state of crisis. In any case, it has not been proved that the effect of Greece's entry into the Community was sub- stantially to alter the general situation of the market for steel products in the Community as a whole. The argument must therefore be rejected.

17 It follows from all the foregoing considerations that the application of Decisions N o 2794/80 and N o 3381/80 to Greek undertakings from 1 January 1981 cannot be contested.

T h e o b j e c t i o n s b a s e d o n A r t i c l e s 5 8 , 74 a n d 14 of t h e ECSC Treaty

18 Under this head the applicants put forward a number of arguments whereby they submit that the Commission has infringed Articles 58 and 74 of the Treaty, that the reasons on which Decision N o 2794/80 is stated to be based are insufficient and that Greek undertakings have been discriminated against. They do not specify wherein the infringement of Article 14 lies, so that this objection need not be examined in the absence of any clarification.

T h e r e l a t i o n s h i p b e t w e e n A r t i c l e s 58 a n d 74

19 In the first place, the applicants contest the validity of Decision N o 2794/80 on the ground that, contrary to the provisions of Article 58 (1) of the Treaty, that decision imposed production quotas on undertakings without accompanying the quota system with restrictions on imports of steel products pursuant to Article 74 of the Treaty.

20 Article 58 (1) states that in the event of a manifest crisis and if the means of action provided for in Article 57 prove to be insufficient the Commission must "establish a system of production quotas, accompanied to the necessary extent by the measures provided for in Article 74". In such a situation Article 74 empowers the Commission to make recommendations to the Member States with a view to introducing appropriate restrictions on imports.

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

21 It follows from the provisions cited that if production quotas are imposed they do not necessarily have to be accompanied by import restrictions. The introduction of such restrictions depends on the Commission's assessment of the state of the steel market and of the need to afford that market protection. That need depends in turn both on the possibility of disposing of existing production on the internal market and on external trade. But in this regard it is necessary to take into account obligations entered into by the Community towards non-member countries and the repercussions which the introduction of import restrictions might have on Community exports in general and on steel products in particular.

22 As the Court has already stressed in its judgment of 18 March 1980 in Joined Case 154, 205, 206, 226 to 228, 263 and 264/78, 39, 31, 83 and 85/79 SpA. Ferriera Valsabbia and Others [1980] ECR 907 and in its judgment of 16 February 1982 in Case 258/80 Rumi [1982] ECR 487, the taking into consideration of those factors requires the assessment of a complex economic situation, which means that the link established by Article 58 (1) between the introduction of production quotas and the imposition of restrictions on imports of competing products cannot be in any way automatic. The applicants have not been able to specify circumstances which might give reason to believe that the Commission exceeded the discretion which Articles 58 and 74 of the Treaty accord to it in this matter.

T h e " e q u i t a b l e b a s i s " r e f e r r e d t o in A r t i c l e 58 (2)

23 In the second place, the applicants contend that the production quotas provided for by Decision N o 2794/80 were not established on an "equitable basis" within the meaning of Article 58 (2) of the Treaty. More precisely, they believe that instead of being established with reference to actual production they should have been fixed on the basis of the production capacity of undertakings.

24 In reply to that argument it should be pointed out first of all that it appears from the uncontested figures provided by the Commission that in the period under consideration the applicants did not even manage to exhaust the production quotas allocated to them, so that the question whether the quotas were determined on one basis rather than another appears to be immaterial in this case.

HALYVOURGIKI v COMMISSION

25 Moreover, it should be observed that Article 58 (2) of the Treaty does not restrict the Commission's freedom to choose the basis upon which the quotas may be equitably determined in a given economic situation. It follows from the explanations given during these proceedings that there are no reasonable grounds for denying that the Commission's choice of the criterion based on undertakings' actual production may constitute an "equitable basis" within the meaning of Article 58 (2). Indeed that criterion, as adjusted by Article 4 of Decision N o 2794/80, constitutes, in the first place an objective basis of assessment which avoids the uncertainties inherent in determining a factor which is partly conjectural, such as production capacity; secondly, it enables total production to be reduced without altering the positions of the under- takings on the market as between each other.

26 It follows from the foregoing t h a t the complaints of an infringement of Articles 58 a n d 74 must be rejected.

The complaint of discrimination

27 The applicants contend finally that the application of Decision N o 2794/80 led to discrimination against Greek undertakings because that decision was based, for the purpose of fixing the production quotas, on criteria to which Greek undertakings cannot be subjected. It is argued that those criteria relate to a period in which those undertakings were not yet subject to the rules of Community law. More precisely, the applicants refer in this regard, first, to the criterion adopted by Article 4 (3), concerning the average rate of utilization of production facilities, subject to the condition that the under- taking "undertook to comply from July 1977 to June 1980 with the delivery programmes established by the Commission", and, secondly, to the investment programmes duly reported and not the subject of an unfavourable opinion of the Commission which are referred to in Article 4 (4).

28 O n this point it need only be observed that, u n d e r the scheme of Decision N o 2 7 9 4 / 8 0 , the aim of both the provisions cited — w h i c h , m o r e o v e r , did n o t apparently play any part in d e t e r m i n i n g the applicants' q u o t a s — is t o help some u n d e r t a k i n g s by rectifying the results obtained by t a k i n g into a c c o u n t the reference p r o d u c t i o n figures defined by Article 4 (1) a n d (2).

JUDGMENT OF 16. 2. 1982 — JOINED CASES 39, 43, 85 AND 88/81

More precisely, the aim of the provisions cited by the applicants is to adapt the reference production figures of some undertakings, having regard to their participation during the period under consideration in voluntary reduction programmes and to the restrictions placed upon them as a result of the control exercised by the Commission over new investment. As those factors could not have affected Greek undertakings precisely because they were not yet subject to the rules of the Community, the measures taken to enable the reference production of undertakings belonging to the old Community to be assessed on an equitable basis cannot be regarded as discrimination against the Greek undertakings.

29 Therefore these complaints must also be rejected.

30 It follows from the foregoing that the applications must be dismissed.

Costs

31 Under Article 69 (2) of the Rules of Procedure the unsuccessful party is to be ordered to pay the costs.

32 As the applicants have failed in their submissions they must be ordered to pay the costs.

On those grounds,

THE COURT

hereby:

1. Dismisses the applications;

2. Orders the applicants to pay the costs, including the costs incurred as a result of their applications for the adoption of interim measures, less

HALYVOURGIKI v COMMISSION

the costs which other parties were ordered to pay by orders of 16 September and 25 November 1981.

Mertens de Wilmars Bosco Touffait Due Pescatore M a c k e n z i e Stuart O'Keeffe Koopmans Everling Chloros Grévisse

Delivered in o p e n c o u r t in L u x e m b o u r g o n 16 F e b r u a r y 1982.

P. H e i m J. M e r t e n s de W i l m a r s

Registrar President

OPINION OF MR ADVOCATE GENERAL VERLOREN VAN THEMAAT D E L I V E R E D O N 12 J A N U A R Y 1982 1

Mr President, crude steel and rolled products for the Members of the Court, first quarter of 1981.

Those individual decisions were based on the general decisions of the Commission 1. Introduction N o 2794/80/ECSC of 31 October 1980 (Official Journal 1980, L 291) My opinion today concerns Joined Cases establishing a system of steel production 39, 43, 85 and 88/81, which still remain quotas for undertakings in the iron and to be dealt with following the steel industry and N o 3381/80/ECSC of withdrawal of the action brought be 23 December 1980 (Official Journal Metallurgiki Halyps SA. In these four 1980, L 355). According to the preamble cases two Greek steel producers seek to to Decision N o 2794/80, the main have declared void, under Article 33 reason for these crisis measures was the of the ECSC Treaty, the individual abrupt fall in demand for steel in the decisions by thich the Commission third quarter of 1980, both on the imposed production quotas on them for Community market and on the world

1 — Translated from the Dutch.

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Rozsudok C-39/81 – Súdny dvor Európskej únie | AI Pravnik