← Späť na vyhľadávanie
Súdny dvor Európskej únie·Rozsudok·11.5.1983

C-303/81

ECLI:EU:C:1983:129

Súd
Súdny dvor Európskej únie
IČS
61981CJ0303

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

designed to confer the benefits of the 3. One of the essential prerequisites clause on those undertakings whose under the laws of the Member States utilization rates are relatively far for an acknowledgement that an removed from the Community emergency situation exists is that the average. perilous situation justifying the Since the crisis was widespread and unlawful act shall not have been thus common to all steel under- brought about by the author of that takings, the Commission was entitled act. That prerequisite is not fulfilled to take the view that the output in a case in which the circumstance restrictions imposed could not entail which has supposedly brought the "exceptional" difficulties except for emergency situation upon an under- undertakings satisfying certain taking derives from a choice of economic policy made by the under- conditions relating to the utilization taking itself. rate of their production capacities. To set the threshold at a deviation of 10% below the average rate of the capacity-utilization of the Community 4. The system of production quotas undertakings cannot be considered which was lawfully set up on the basis unlawful. The deviation required by of Article 58 of the ECSC Treaty by the Commission should, on the one Decision 2794/80, compliance with hand, enable the substantial integrity which is required of every under- of the quota system to be maintained taking concerned, would be gravely and, on the other hand, permit compromised — or indeed set at exceptional circumstances due to the nought — if every undertaking were enforcement of such a system to be able, by pleading an emergency taken into account. situation due to serious economic difficulties, to excuse itself from 2. By fixing a clearly defined reference observance of the restrictions and to period for determining the reference exceed at will the production quota production figures of undertakings in allocated to it. The chain reaction the steel industry, Decision 2794/80 thereby released would culminate in does not allow anything other than the collapse of the system, so that the actual productive capacity during Article 58 of the Treaty would that period to be taken into account. become a dead letter.

In Joined Cases 303 and 3 1 2 / 8 1

K L Ö C K N E R - W E R K E A G , a steel u n d e r t a k i n g having its registered office in Duisburg, represented b y Professor B o d o Borner of C o l o g n e University, with an address for service in L u x e m b o u r g at the C h a m b e r s of Ernest A r e n d t , 34 B R u e Philippe-Il, applicant,

v

KLÖCKNER-WERKE v COMMISSION

COMMISSION OF THE EUROPEAN COMMUNITIES, represented by its Legal Adviser, N o r b e r t Koch, acting as Agent, asisted by Professor Eberhard Grabitz of the Free University of Berlin, with an address for service in Luxembourg at the office of Oreste M o n t a k o , a m e m b e r of its Legal D e p a r t m e n t , Jean M o n n e t Building, Kirchberg,

defendant,

A P P L I C A T I O N S for a declaration that the individual decisions adopted by the Commission on 19 and 28 O c t o b e r 1981 are void,

T H E C O U R T (Fourth C h a m b e r )

composed of: A. O'Keeffe, President of C h a m b e r , P. Pescatore, G. Bosco, T . K o o p m a n s l a n d K. Bahlmann, Judges,

Advocate G e n e r a l : G. Reischl Registrar: P. H e i m

gives the following

JUDGMENT

Facts and Issues

I — Facts a n d w r i t t e n p r o c e d u r e In accordance with Articles 2 to 4 of the general decision, the Commission fixes, in respect of every undertaking, quarterly production quotas for crude Faced with a manifest crisis in the steel steel and for each of the four groups of market within the meaning of Article 58 rolled products, the first of which relates of the ECSC Treaty, the Commission to the products at issue in these cases. adopted Decision 2794/80/ECSC of The quotas are calculated on the basis of 31 October 1980 (Official Journal L 291, the quarterly reference production fig- p. 1) establishing a system of steel ures of each undertaking. To that end production quotas for undertakings in reference is made, for each month of the the iron and steel industry. relevant quarter, to the same month

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

during the period from July 1977 to June 4 April 1981, after the quotas had been 1980 during which the total production revised so as to exclude products of the four groups of rolled products was exempted from the restrictions. The two the highest. The three months thus individual decisions were not the subject chosen, which are not necessarily of any legal action, and Klöckner's consecutive, form the reference period. production quota for the first quarter of The reference production figures for 1981 in respect of rolled steel in Group 1 crude steel and for each of the four was fixed at 539 003 tonnes. groups of rolled products are equal to the output of each of those products during the reference period. On 4 February 1981 Klöckner submitted to the Commission an application under Article 14 of the decision seeking an increase in the quota granted to it, However, in the contingencies envisaged compliance with which would have by Article 4 (3) to (5) of the decision, the involved it in "exceptional difficulties". Commission may, within certain limits, By a letter of 19 October 1981 in the increase the reference production figures nature of an individual decision, the and consequently the quotas allocated to Commission rejected the application as the undertakings concerned. unfounded.

The decision further provides (Article Klöckner had meanwhile during the first 14) that, where the production or quarter of 1981, exceeded by 28 682 delivery restrictions imposed by it or tonnes the production quota imposed on by its implementing measures entail it in respect of rolled products in Group exceptional difficulties for an under­ I. The Commission reproved Klöckner taking, it may refer the matter to the for that overproduction and in a letter of Commission, providing all appropriate 15 July 1981 asked it to submit its supporting documentation. The Com­ comments pursuant to Article 36 of the· mission is to examine the case without ECSC Treaty. Klöckner did so, in letters delay in the light of the objectives of the dated 27 July and 25 August 1981, which decision and, where appropriate, to were supplemented by statements of the adapt the provisions of the decision to undertaking's representative at the the specific circumstances. hearing held on 24 September 1981. The Commission did not accept the explan­ ations put forward by the undertaking, and, by a decision of 28 October 1981, fined it 2 151 150 European currency In pursuance of the above-mentioned units in pursuance of Article 9 of decision, the Commission, in a letter Decision 2794/80. dated 19 December 1980, notified the steel undertaking known as Klöckner- Werke AG of Duisburg of its reference production figures and production In pursuance of Article 33 of the ECSC quotas resulting from the application of Treaty, Klöckner brought ā first legal the abatement rates contained in Article action, which was lodged at the Court 5 of the decision, in respect of the first Registry on 30 November 1981, seeking quarter of 1981. Since the decision was a a declaration that the Commission's provisional one it was confirmed on decision of 19 October 1981 refusing to

KLÖCKNER-WERKE v COMMISSION

increase its production and delivery Dismiss the application as unfounded; quotas for the first quarter of 1981 was void. Order the applicant to pay the costs. Under Articles 33 and 36 of the ECSC Treaty, Klockner brought a second action, lodged at the Court Registry on Ill — Submissions and argu- 15 December 1981, seeking a declaration m e n t s of the p a r t i e s that the Commission's individual de- cision of 28 October 1981 fining it for having exceeded the quota was void, and 1. Case 303/81 requesting, in the alternative, a reduction in the amount of the fine. In its first submission, the applicant By order of 5 May 1982, the Court, contests the lawfulness of the reasons having regard to the affinity between the cited by the Commission's decision of two cases, ordered that they be joined 28 October 1981, according to which for the purposes of the oral procedure the existence of exceptional difficulties and judgment. within the meaning of Article 14 of the general decision could not be conceded On hearing the report of the Judge- unless the undertaking's utilization rate Rapporteur and the views of the was more than 10% below the level Advocate General, the Court decided to of other manufacturers within the open the oral procedure without any Community. In that connection, the preparatory inquiry. By order of 13 applicant maintains that it is insufficient October 1982, it decided to assign the merely to adhere to an automatic two joined cases to the Fourth Chamber. criterion such as 10%. On the contrary, where the utilization of capacity is less than 10% below the level in question, II — C o n c l u s i o n s of t h e p a r t i e s the Commission is, according to the applicant, required to investigate all the circumstances of the case in order to In Case 303/81, the applicatif claims that ascertain whether they do not, after all, the Court should: afford evidence of an exceptional difficulty. Not having undertaken such Declare the defendant's decision of an investigation, the Commission, it is 19 October 1981 void. claimed, infringed the ECSC Treaty and has misused its powers. In Case 312/81, the applicant claims that the Court should: The applicant's second objection to the 1. Declare the defendant's decision of decision at issue lies in the fact that, in 28 October 1981 null and void; assessing the utilization rate of the wide- strip mill at 50.4% when granting the 2. Alternatively, reduce the fine imposed quota, the Commission proceeded on the by the contested decision to a sum basis of too high a figure. In fact, the which appears to the Court to be mill had been running at that time at no appropriate; and more than 39% of capacity, that is, 17% below the Community's average 3. Order the defendant to pay the costs. utilization rate of approximately 5 5 % . The difference between the utilization In both cases, the Commission contends rate adopted by the Commission, which that the Court should: is 5.4% lower than the average, and the

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

actual utilization rate, which is 17% point is unimportant. It considers that, lower than the average, is due to the for the purposes of applying Article 14 of defendant's having based its calculations Decision 2794/80, it is not earlier or on too low an assessment of the theoretical output capacity which should capacities of Klöckner's N o II hot-rolled be taken into account, but actual current wide-strip mill; the Commission had capacity; it maintains that the statistics in assessed that capacity at 355 000 tonnes question were supplied as a matter of per month whereas the actual capacity routine and that therefore it should be amounted to 459 000 tonnes per month. permitted to revise them in the light of the true data. The fact that the under- taking thereby supplied incorrect infor- mation to the Commission on the In pointing to the above figure, the aforementioned questionnaire might applicant relies on the Technical Audit cause the Commission to fine it but does Report of 1 May 1981. The first part of not warrant the imposition of too low a the report, drawn up jointly by the production quota. Belgian Centre de Recherches Métal- lurgiques [Centre for Metallurgical Research] and the Japanese Kawasaki Steel Corporation, specifies that Finally, the applicant argues that, when Kawasaki estimated the capacity of the assessing its output capacity, the No II hot-rolled wide-strip mill in defendant in any case failed to take Bremen at 487 000 tonnes per month, account of the capacity of the other mill whilst the Centre for Metallurgical in the Bremen works (the Bremen No I), Research put it at a lower figure merely the running of which had been because it did not take as its basis the temporarily halted in April 1974 for the actual productive capacity as sub- purpose of restructuring the works. sequently confirmed. That demonstrates that the figure of 459 000 tonnes per month established by Klöckner in its action is therefore too low rather than too high. In reply, the Commission contends, first, that Article 14 of Decision 2794/80 is a derogative provision and that the powers thereby conferred on it are subject to the precondition that the exceptional Should the Court consider that difficulties confronting the undertaking Kawasaki's expert report is insufficient derive from the enforcement of the to prove the true output capacity of the quota system. Bearing that premise in mill in question, the applicant asks that mind, the defendant has always accepted the latter be run at maximum capacity that an undertaking had to contend with for six weeks under expert supervision, exceptional difficulties whenever, fol- which would enable the problem to be lowing the enforcement of the quota settled once and for all. system, the utilization rate of that under- taking was at least 10% less than the average utilization rate amongst Community undertakings. That yardstick Whilst admitting that the Commission enables the Commission to exercise the based its estimate on information discretion conferred upon it by Article 14 supplied by itself by way of Ques- of the decision objectively and without tionnaire No 2 / 6 1 , the applicant under- the risk of discriminating between the taking none the less maintains that the undertakings concerned. The specific

KLÖCKNER-WERKE v COMMISSION

circumstances contemplated by Article 14 Commission, in its decision of 19 may arise where an undertaking's December 1980 fixing Klöckner's reference production figures, which must production quota for the first quarter of be established in accordance with Article 1981, had already increased its reference 4 (1) and (2) of Decision 2794/80, production under Article 4 (3) of the deviated sharply from the Community general decision; since one of the average, yet without its being possible to conditions attaching to the increase was envisage increasing them by virtue of that an undertaking's average utilization paragraphs (3), (4) and (5) of that rate of its output potential between July article. Situations of that type may arise 1977 and June 1980 must lie 10 on account, for example, of prolonged percentage points or more below the or recurrent technical problems, or average utilization rate of the same plant strikes, leading to exceptionally low by other Community undertakings reference production figures. In such during 1977, 1978 and 1979, and since cases, enforcement of the general rules the applicant maintained that the on quota fixing would cause the capacity of 459 000 tonnes per month utilization rate of the capacity of the already prevailed between July 1977 and undertaking concerned to be reduced to June 1980, the reference production a level far below the Community calculated in pursuance of Article 4 (3) average. Besides, experience has shown of the decision should have been further that a deviation of less than 10% from increased in the notice of 19 December the average utilization rate falls into the 1980 announcing the quotas. However, category of normal fluctuations. It had that happened, the difference follows, the Commission argues, that between the applicant's utilization rate only a larger deviation may be taken into and the Community average would, in account without a risk of discrimination. the Commission's contention, have been The criterion adopted in applying Article lower than 10%, to wit 6.4%. 14 is therefore perfectly logical and lawful.

Turning to the problem of the output capacity of the No II mill in Bremen, the As to the second objection, whereby the Commission refers to the statement applicant alleges that its utilization rate which it submitted in Case 119/81. It was 17% lower than the average wishes to stress, however, that its amongst Community undertakings, the estimates regarding the capacities of Commission confines itself in essence to undertakings were based on the annual summarizing the arguments which it put notification supplied in Questionnaire forward in Cases 119/81 and 244/81, in No 2/61. In that connection, the which that same problem was raised in Commission states that Klöckner, having relation to the second quarter of 1981. initially declared in the statistical ques- However, the Commission adds that, tionnaires a capacity of 3 770 000 tonnes even if it were correct that the applicant a year for 1979 and 1980, in 1980 — by possessed a No II wide-strip mill in contrast — entered a higher capacity in Bremen with a capacity of 459 000, and respect of the same two years, namely not 355 000, tonnes per month, that fact 4 260 000 tonnes a year. Following that could not have led to a raising of the new declaration, the Commission carried quota under Article 14 of the general out a check which led it to allow the decision. That was so because the higher capacity. Finally, from 1981

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

onwards, the applicant declared that its the facts and check whether or not there output capacity was — and had pre- are exceptional difficulties. viously been — higher still, namely 5 508 000 tonnes a year, or 459 000 tonnes a month. It is difficult to accept The applicant further disputes that there that the applicant had, in the course of the same year, discovered yet another are contradictions between the ar- mistake which it had supposedly guments which it has put forward in this committed in the matter of its output case and those adduced in other cases, capacity. and it adds that such alleged divergences are unimportant in any case, since they arose in different proceedings having different objectives. Lastly, it supports its As far as Kawasaki's expert report is claims with a new expert report, drawn concerned, the Commission takes the up on 12 January 1982 by Professor R. view that it is based on a purely Jeschar. The report allegedly discloses theoretical concept of capacity (though it that Klöckner's output capacity was is referred to as a technical one), not on higher than that previously stated by the the concept of maximum feasible undertaking itself. Finally, the applicant productivity, which was the sole explains the economic situation in which determining factor in this case. The it would be placed as a result of the expert report is therefore irrelevant. excessively low quotas fixed for it by the Commission.

Lastly, the Commission points out the The Commission contends that the contradictions existing between the economic situation of the undertaking arguments put forward in this case and cannot enter into the reckoning in those submitted in other, analogous, evaluating whether there are exceptional cases. difficulties, inasmuch as it cannot be regarded as a consequence of applying the production-quota system, since an The applicant disputes the Commission's undertaking's financial standing is arguments in support of the criterion determined not only by the volume of its employed to ascertain the existence of output but also by the price obtained. exceptional difficulties, observing that The poor financial situation of the the latter may manifest themselves not undertaking is, the Commission only at the technical level but also at the maintains, a pre-existing state of affairs economic level — in the matter of and not a consequence of the quota servicing debts, for example — and it system, which was set up precisely as a points to the margin of uncertainty in result of the fall in demand and the calculating the deviation between the collapse of steel prices. utilization rate of the undertaking in question and the Community average. It further disputes the relevance of the The Commission reasserts, moreover, considerations cited by the Commission, that, since the applicant failed to contest as to what would have happened if the the decision fixing the quotas for the first undertaking had raised the present quarter of 1981, that decision has problem at the time when Article 4 (3) of become immune to challenge. Hence the the general decision was being applied. applicant's claim that the capacity of its In its opinion, the Commission should, No II Bremen mill had already reached when applying Article 14, simply keep to 459 000 tonnes a month during the years

KLÖCKNER-WERKE v COMMISSION

1977 to 1980 is quite irrelevant, for counter to the promise which the procedural reasons. Since the applicant Commission allegedly made to it, to cites that figure as its productive capacity waive any pecuniary sanction for for the first quarter of 1981, it must be exceeding the quota limit. In that concluded that that capacity must have connection, the applicant maintains that increased since 1980. However, that in order to overcome Klöckner's growth in capacity, and the resultant resistance to participation in the so- decline in the utilization rate cannot be called Eurofer II negotiations designed regarded as exceptional difficulties to secure agreement from the larger within the meaning of Article 14, since European steel-works on voluntary they are not a result of the establishment cutbacks in production, Mr Defraigne, of the quota system. the Chef de Cabinet to the Vice- President of the Commission, Mr Lastly, the Commission contests the Davignon, acting for and on behalf of relevance and evidential cogency of the the latter, made two promises in the new expert report, inasmuch as, like course of a telephone conversation with Kawasaki's report, it relates to the the chairman of the applicant's executive computation of the technical capacity, board, Herbert Gienow, on 19 March not the maximum feasible output. 1981, namely:

2. Case 312/81 (i) First, that the officers of the Commission would endeavour to ensure that the applicant was The applicant, in its second application properly treated in the negotiations; seeking a declaration by the Court that the individual decision of 28 October 1981 fining it for having exceeded the (ii) Secondly, that the Commission quota fixed for the first quarter of 1981 would "solve the problem" arising in respect of Group I products is void, from the fact that during the first puts forward the following submissions: quarter of 1981 the applicant was due to produce more than what was (1) The decision under challenge is allowed under the purely provisional unlawful because it runs counter to a quota which had been previously promise binding the Commission; allocated to it. The .adjustment was to be effected irrespective of the (2) The decision under challenge is success or failure of the Eurofer II unlawful because it is founded on negotiations. the defendant's unlawful decision of 19 October 1981, which was the subject of the previous action; The applicant adds that, at the very beginning of the conversation, it (3) The decision under challenge is informed the defendant that all the unlawful because it is based on forecasts indicated that it would have general Decision 2794/80, which is exceeded its production quota by likewise unlawful, especially Article 9 100 000 tonnes by the end of the first thereof. quarter of 1981.

A — First submission It was on the strength of those promises that Klöckner took part in the The applicant maintains that the disputed negotiations, which enabled an decision is unlawful in so far as it runs agreement to be reached in respect of

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

certain products, and at the same time it lation, and in no circumstances do they refrained from bringing an action therefore serve to demonstrate the seeking a declaration of the nullity of the existence of a legal obligation binding decision which was finally given on 1 the authority concerned. April 1981 and which fixed definitively its production quota for the quarter in question. In any event, the Commission denies that Mr Defraigne made the statements attributed to him by the applicant.

The applicant takes the view that the promise whereby the Commission waived According to the Commission, the any pecuniary sanction — implied by the alleged promise is furthermore totally promise to "solve the problem" •— is invalidated because it was not in writing; binding on the defendant inasmuch as it since the only legal means of attaining was made by the competent Member of the goal desired was to fix the quota the Commission, namely Mr Davignon, afresh at a higher level, that could have for whom Mr Defraigne acted merely as been done only by means of a fresh a messenger. The promise was, fur- decision, which would have had to be in thermore, clear and precise in its content writing by virtue of Article 1 of Decision as far as the Commission's waiver of a 22/60 of the Commission of 7 September fine was concerned, even if the means to 1960 on the implementation of Article 15 be adopted to attain that end (for of the Treaty (Official Journal, English example the raising of production quotas Special Edition, Second Series, VIII, under Article 14 of general Decision p. 13). 2794/80, or the amendment of the basis of calculation) were not yet specified. Lastly, the Commission takes the view that the alleged promise by Mr Defraigne cannot in any case commit the Moreover, in view of the fact that, defendant, for want of confirmation during the'hearing of the applicant at the or ratification by the competent headquarters of the Commission, the department. In legal terms however, such latter's representative stated that Mr ratification is impossible since the fine is Defraigne denied having made the mandatory whenever the quota is aforementioned promises, the applicant exceeded. It follows that any ratification offers to call witnesses to prove the would have given rise to an infringement point. of Community law.

In reply, the applicant claims that the The Commission contends that the words promise at issue was clear and precise in allegedly uttered by Mr Defraigne do content, since the "problem" which had not disclose what it was that the been the subject of the discussion defendant promised the applicant, since between Mr Defraigne and Mr Gienow the words "solve the problem" and was specifically that of the breach of the "adjustment" — being open to several quota limit and its consequence, namely interpretations — do not support the the imposition of the fine. Hence the inference that Mr Defraigne promised solution to the problem could have the applicant to refrain from fining it. meant only the elimination of that legal Likewise, the words cannot be consequence. Furthermore, the content interpreted as a promise to increase the of the promise is borne out by the quota or to amend the basis of its calcu- general context in which the conver-

KLÖCKNER-WERKE v COMMISSION

sation must be seen, initiated as it was by As far as that submission is concerned, Mr Defraigne who had contacted Mr the Commission confines itself to Gienow in order to request his parti- referring back to the arguments set forth cipation in the Eurofer II negotiations. in Case 303/81.

Finally, the applicant persists in stating that Mr Defraigne spoke solely as a mere C — Third submission messenger for Mr Davignon, that is, for a person empowered to represent and bind the Commission. The defendant's The applicant takes the view that objection that the promise was not Decision 2794/80, which is the legal reduced to writing is irrelevant inasmuch basis for the individual decision im- as it was a promise which did not pugned is unlawful on four grounds: necessarily involve a refixing of the quota, since the means to be employed in order to give effect to the waiver of the (i) Breach of the duty to guarantee a fine were not expressly stated. minimum level of utilization,

In its rejoinder, the Commission stresses (ii) Failure to observe the implications the ambiguity of the statements attaching to the prohibition of attributed to Mr Defraigne and the subsidies laid down by Article 4 (c) impossibility in legal terms of of the ECSC Treaty, implementing the alleged promise. It again denies that Mr Davignon ever instructed Mr Defraigne to give the (iii) Absence of assent on the part of the promise in question on his behalf. As Council, regards the problem of reduction to writing, the Commission observes that a (iv) Unlawfulness of imposing quota promise relating to an administrative restrictions on exports. measure must in any case assume the same form as was laid down for the measure itself. From the unlawfulness of the general decision derives that of the contested individual decision, owing to the direct B — Second submission link which exists between the two.

The applicant maintains that the disputed decision is unlawful inasmuch as it is (a) Admissibility of the submission founded on a similarly unlawful decision of 19 October 1981, whereby the defendant rejected a request to have the The Commission maintains that the production quota increased for the first submission is admissible only in so far as quarter of 1981. The unlawful nature of the applicant maintains that Decision the rejection of that request has been 2794/80 is illegal in its entirety for lack demonstrated in Case 303/81, and, if the of the assent of the Council. In that case, Court were to decide to grant this Article 9 of the general decision is also application, then the disputed fine would unlawful. According to the judgment of have to be cancelled as well, because the the Court of 31 March 1965 (Mac- consequence would be that the cbiorlati v High Authority, Case 21/64 applicant's definitive quota could not be [1965] ECR 175), the unlawfulness of a treated as having yet been fixed. general decision may not be pleaded

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

unless there is a direct legal link between capacity amongst the steel undertakings that decision and the measure in dispute. of the Community. That is indicated That applies to Article 9 of Decision both by the inferences which may be 2794/80, since it lays down both the drawn from the provisions of the ECSC conditions for imposing fines and the Treaty and by a general principle to be quantum thereof. found in the legal systems of all Member States. Hence the Commission is prohibited from reducing reference production by a given and invariable In addition, the argument is inadmissible percentage, without taking account of because the applicant has not indicated the productive capacity in existence at which the specific provisions are against the outset; it should rather protect those which the submission is directed. undertakings which are potentially worst Moreover, it would likewise be affected by the cutback, namely those in inadmissible if the applicant were to raise which the utilization rate of productive it in order to assert the unlawfulness of capacity is particularly low at the outset. Articles 4 and 5 of the general decision, as no direct legal link exists between those provisions, which fix the bases for calculating the reference production In its defence, the Commission confines figures and the quotas, and the itself to reiterating its objection of individual decision under challenge. inadmissibility.

The applicant replies that its strictures The applicant replies that, in this case relate to Decision 2794/80 as a whole, too, its objection is aimed at the general and it therefore contests the objection of decision as a whole inasmuch as it inadmissibility. infringes Article 58 of the ECSC Treaty, not as containing any specific unlawful provision but for want of a provision which should legally have been present. Since in any case claims are designed, (b) Breach of the duty to guarantee a not to cause the defendant to insert minimum level of utilization further articles into the general decision but rather to obtain the Court's declaration that the two individual decisions adopted pursuant to the The applicant takes the view that general decision at issue are void, it Decision 2794/80 is unlawful inasmuch could not have achieved its end by as it fails to guarantee a minimum bringing an action for failure to act, utilization of output capacity by the whereas it was free to pursue the same undertakings concerned. Indeed, since it end by alleging the unlawfulness of the is more dangerous for an undertaking general decision. That being so, the cutting back its production by, say, 10 % objection of inadmissibility is, according to reduce a 50 % utilization rate to to the applicant, unfounded. 45 % than to lower the rate from 100 % to 90 %, the production quota fixed for an undertaking must not depress the utilization rate below a certain limit. In its rejoinder, the Commission., whilst That limit must be in keeping with the insisting on its objection of in- average rate of utilization of productive admissibility, adds that the argument is

KLÖCKNER-WERKE v COMMISSION

unfounded even in substantive terms, According to Klöckncr, the Commission since Article 58 of the ECSC Treaty cannot confine itself to referring to the does not restrict the Commission's possibility of taking action against those freedom of choice as regards the basis infringements under Article 88 of the for the equitable determination of ECSC Treaty (never, incidentally, used quotas. It is therefore impossible by the defendant for that purpose), nor reasonably to deny that selecting the can it refer to Article 67 thereof, since criterion of undertakings' actual output the latter provision does not relate to may serve as an equitable basis for quota subsidies forbidden under Article 4 (c). fixing, since it is a criterion which represents an objective basis of as- sessment and enables total output to be reduced without altering the under- The Commission replies that the takings' respective positions on the argument is unfounded inasmuch as market. Article 58 of the ECSC Treaty is not intended to rectify distortions of competition due to State subsidies, in respect of which the Commission has Both parties also refer to the written other means of action available to it. pleadings submitted in Case 119/81.

On this point, too, the parties refer moreover to the memoranda submitted (c) Non-observance of the prohibition in Case 119/81. of State subsidies

The applicant argues that the distribution (d) Absence of assent by the Council of the quotas in pursuance of the general decision at issue is not determined on an equitable basis in yet another respect, inasmuch as the Commission took no According to the applicant the general account of the effects of subsidies decision at issue was not the subject of granted to the steel industry in certain the Council's assent as laid down by Member States, contrary to Article 4 (c) Article 58 (1) of the ECSC Treaty. The of the ECSC Treaty. The applicant Commission, although asked on several claims that the defendant should have occasions to produce the Council's taken those unlawful subsidies into decision giving its assent, confined itself consideration either by granting a higher to producing a press bulletin from the quota to the unsubsidized undertakings General Secretariat of the Council — a or else by reducing the quota awarded to document having no relevance at all. those undertakings which enjoyed such Indeed, it was only by examining the assistance. Indeed, the aforesaid in- documents submitted by the Commission fringement of the Treaty entailed, in the to the Council for the purposes of the case of recipient undertakings, increases meeting at which the assent was clue to in production which would not have be given, together with the minutes and occurred without the subsidies, since the tape-recording of that meeting, that such undertakings were able to make is was possible to discover whether an larger investments than the other under- "assent" really was forthcoming and takings. whether it had the content required by

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

the ECSC Treaty. There is therefore, in Council did indeed give its assent. The the first place, a lack of evidence. Commission adds that the first subpar- agraph of Article 58 (1) of the ECSC Treaty does not specify what is to be understood by "assent"; the scheme and purpose of the text, however, show that In any case, the applicant, concurring it is unnecessary for the Commission to with the pleadings lodged in analogous transmit to the Council a proposal for a cases (Cases 119 and 244/81), maintains quota system which is formulated in that the Council's assent is necessary in every detail and submitted in the form of respect of all the constituent parts of a a draft decision. On the other hand, quota system, not merely in relation to Article 58 institutes a decision-making certain supposedly essential aspects procedure in three phases. In accordance thereof — factors which are, moreover, with the'first subparagraph of Article 58 unidentifiable except by means of an (1), the Commission notes, as the first objective criterion which the Commission phase, that the Community is confronted has been unable to specify. That being with a period.of manifest crisis and that so, the Council's "assent" would not, the means of action provided for in even if it was given in this case, have the Article 57 are not sufficient to deal with content laid down by the Treaty. In fact it; as the second phase, the Commission in Case 119/81 — in which the same takes the decision to establish a system of question was raised — the Commission production quotas. Article 58 (2), as a produced the text of its proposals to the third phase, authorizes the Commission Council for the adoption of the system to arrange the system in detail and to of production quotas (document of make it mandatory by means of one or 6 October 1980, reference No C O M / more instruments. It is only in the second 80/586 Final). A comparison of that text, phase that the Council is involved in the which the applicant wishes to have procedure. In order to establish a quota produced in this case as well, if appro- system the Commission must obtain the priate, with the definitive text of Council's assent but is not required to do Decision 2794/80 would disclose the so as far as its arrangement and its existence of many important differences. embodiment in legal instruments are In those circumstances, it is impossible to concerned. Since those principles were discover from the documents on the file observed in this case, the procedure in relation to which text the Council whereby Decision 2794/80 was adopted gave its alleged assent. Furthermore, in was consistent with the requirements of the absence of any objective criterion it Article 58 of the ECSC Treaty. is impossible to check whether or not any divergences between the two texts have a bearing on essential points. The primary requirement of legal certainty is thereby disregarded. (e) Unlawfulness of imposing quota restrictions on exports

Both at law and in fact the Commission The applicant notes for the first time in contests the applicant's arguments, as its reply that under Decision 2794/80 the well as the requests for production of Commission has fixed a further quota, in fresh documents, which it regards as respect of the share of steel output which unnecessary. As may be seen from the is intended for export to non-member preamble to Decision 2794/80, the countries, and observes that it is illegal

KLÖCKNER-WERKE v COMMISSION

since all power over exports to non- must also take account of the fall in member countries of goods covered by demand on the world market. That the ECSC Treaty is retained by the opinion is borne out by the consideration Member States. The Commission has that Article 3 (a) of the Treaty requires therefore acted beyond its powers. the Community institutions'to ensure an Moreover, the control thereby exerted orderly supply to the common market, by the defendant over the volume of "taking into account the needs of third goods offered on the markets of non- countries". When production quotas are member countries penalizes only fixed, therefore, regard may even be had products originating in the Community, to demand from non-member countries. contrary to the objectives of the ECSC Treaty. IV — O r a l p r o c e d u r e The Commission contends that that submission, too, is quite unfounded. At the sitting on 15 December 1982 oral Article 58 of the Treaty, which auth- argument was presented by Klöckiier- orizes the Commission to establish a Werke AG, represented by Professor system of production quotas, in seeking Bodo Borner, and the Commission, to obtain a general reduction in supply, represented by Norbert Koch, a member makes no distinction between production of its Legal Department, acting as Agent, intended for export outside the assisted by Professor Eberhard Grabitz. Community and that intended for In the course of the sitting, the marketing within the common market. Commission's representative submitted Furthermore, since the fall in demand in two documents. the common market was the result of the The Advocate General delivered his world-wide economic situation, the opinion at the sitting on 23 February means employed to combat the crisis 1983.

Decision

1 By an application lodged at the C o u r t Registry on 30 N o v e m b e r 1981, K l ö c k n e r - W e r k e A G , a steel undertaking having its registered office in Duisburg, Federal Republic of Germany, instituted proceedings under the second paragraph of Article 33 of the E C S C T r e a t y , seeking a declaration that the Commission's decision dated 19 O c t o b e r 1981 refusing it an increase in its production and delivery quotas for the first quarter of 1981 (Case 303/81) is void.

2 By an application lodged at the C o u r t Registry on 15 December 1981, Klöckner b r o u g h t a further action under the second paragraph of Article 33

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

and the second and third paragraphs of Article 36 of the ECSC Treaty, seeking a declaration that the Commission's decision of 28 October 1981 fining it for exceeding the aforementioned quotas is void, or, in the alter- native, seeking to have the fine reduced (Case 312/81).

3 By an order of 5 May 1982, the Court, having regard to the relationship between the two cases, ordered that they be joined for the purposes of the oral procedure and judgment.

4 By a letter of 19 December 1980, the Commission, in pursuance of general Decision 2794/80/ECSC, establishing a system of steel production quotas for undertakings in the iron and steel industry, had notified Klöckner of its reference production figures and production quotas for the first quarter of 1981. Those arrangements were confirmed by a letter dated 4 April 1981, . after the quotas had been revised so as to exclude products falling outside the restrictions.

5 In those notices, which were not the subject of any proceedings, Klöckner's production quota for the aforesaid quarter in respect of rolled steel products in Group I was fixed at 539 003 tonnes. However, on 4 February 1981, Klöckner, acting under Article 14 of general Decision 2794/80, requested the Commission to increase the quota, alleging that the output restrictions imposed on it would entail "exceptional difficulties" for it.

6 By decision of 19 October 1981, the Commission rejected the request as unfounded. Klöckner brought an action under Article 33 of the ECSC Treaty, which was lodged at the Registry on 30 November 1981, seeking a declaration that that decision was void.

7 During the first quarter of 1981, Klöckner exceeded the production quota imposed on it in respect of rolled products in Group I by a margin of 28 682 tonnes. Klöckner was reprimanded for the surplus in a letter dated 15 July 1981, whereby the Commission asked it to submit its comments pursuant to the first paragraph of Article 36 of the ECSC Treaty. Klöckner complied

KLÖCKNER-WERKE v COMMISSION

with that request by way of letters dated 27 July and 25 August 1981, supplemented by the statements of its representatives at the hearing held on 24 September 1981.

8 By a decision of 28 October 1981 pursuant to Article 9 of Decision 2794/80, the Commission rejected the explanations put forward by Klöckner and fined it 2 151 150 European currency units. In réponse to that decision Klöckner brought an action under Articles 33 and 36 of the ECSC Treaty, which was lodged at the Registry on 15 December 1981 and which sought either a declaration that the Commission's decision imposing on it the above- mentioned fine was void or, in the alternative, a reduction in its amount.

T h e a p p l i c a t i o n a g a i n s t t h e d e c i s i o n of 19 O c t o b e r 1981 r e f u s i n g to i n c r e a s e t h e q u o t a s u n d e r A r t i c l e 14 of g e n e r a l Decision 2794/80 (Case 303/81)

9 In support of this action, the applicant puts forward two submissions, the first of which concerns a disregard of the concept of "exceptional difficulties" contained in Article 14 of general Decision 2794/80, and the second the erroneous and unrealistically low assessment of the applicant's productive capacity and hence of the utilization rate of those capacities.

First submission, alleging a disregard of the concept of "exceptional difficulties" contained in Article 14 of Decision 2794/80

10 Article 14 of Decision 2794/80 is worded as follows:

"Where the production or delivery restrictions imposed by this decision or its implementing measures entail exceptional difficulties for an undertaking, it may refer the matter to the Commission, providing all appropriate supporting documentation.

The Commission shall examine the case without delay, in the light of the objectives of this decision.

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

Where appropriate, the Commission shall adapt the provisions of this decision."

1 1 In its administrative practice, founded on experience acquired in the steel market, the Commission has been applying the provision in the sense that it takes the existence of "exceptional difficulties" into consideration whenever it finds that the rate of utilization of an undertaking's productive capacity is more than 10% lower than the average utilization rate of capacity among Community undertakings.

12 The applicant maintains that, by adopting that criterion, the Commission is not only infringing Community law but also misusing its powers, inasmuch as that criterion, which is purely automatic and formal, is not contained in Article 14, of which it contravenes both the spirit and the letter. The Commission is, on the contrary, required to take into consideration all the special circumstances of each particular case, in order to assess whether the undertaking concerned has encountered exceptional difficulties, even at a strictly economic and financial level.

1 3 The Commission contends that it is required to avoid any differentiation in its treatment of the undertakings involved, and hence to adhere to a strictly objective criterion such as the one' adopted. It further stresses that, in the application of Article 14, only those difficulties may be taken into consideration which have resulted directly from the establishment and enforcement of the quota system, whereas that is not the case with difficulties of an economic nature connected with an undertaking's prof- itability.

1 4 It should be observed first of all that the equity clause in Article 14 does not apply unless an undertaking is experiencing exceptional difficulties which are caused by the enforcement of the system of production quotas. Whilst it is true — as the applicant states — that the equity clause is aimed at difficulties brought upon certain undertakings by the enforcement of general rules which do not take account of specific situations, the Commission cannot however be taken to task for fixing a threshold designed to confer the

KLÖCKNER-WERKE v COMMISSION

benefits of the clause on those undertakings whose utilization rates are relatively far removed from the Community average.

is Since the crisis was widespread and thus common to all steel undertakings, the Commission was entitled to take the view that the output restrictions imposed could not entail "exceptional" difficulties except for undertakings satisfying certain conditions relating to their utilization rates.

i6 Further, to set the threshold at a deviation of 10% from the average cannot be considered unlawful. The deviation required by the Commission should, on the one hand, enable the substantial integrity of the quota system to be maintained and, on the other hand, permit exceptional circumstances due to the enforcement of such a system to be taken into account. By setting the margin at 10%, therefore, the Commission has not exceeded the bounds of its discretion under Article 14.

i7 As far as the allegation of a misuse of power is concerned, it should be pointed out that the applicant has explained it in its reply by alleging that the Commission, in adopting the disputed individual decision, wrongly thought that where the utilization rate was less than 10% below the average, it was no longer empowered to exercise its discretion with a view to ascertaining whether in the applicant's case there were "exceptional difficulties". The allegation merges with the applicant's main argument, namely that the criterion adopted by the Commission infringes Article 14 of the general decision inasmuch as it excludes from the ambit of the article those circum- stances which do not give rise to a utilization rate more than 10% below the Community average. As that interpretation of Article 14 has already been refuted by the Court, that claim cannot be upheld.

is The first submission must therefore be dismissed.

Second submission, alleging an underestimation of the applicant's productive capacity

i9 The applicant argues in the alternative that, even if the lawfulness of the criterion adopted by the Commission in applying Article 14 is accepted, an

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

increase in its quotas should be allowed. The defendant is wrong, it maintains, in claiming that the rate of utilization of Klöckner's capacity stood at only 5.4% below the average, because in fact the deviation was 17%. In the first place, the Commission is relying on inaccurate data concerning the output capacity of the Bremen N o II hot-rolled wide-strip mill and, in the second place, it wrongly omitted to give consideration to the capacity of the other rolling-mill in the same works (the Bremen N o I mill), the running of which was temporarily halted during 1974. Hence, once these mistakes have been corrected, the Commission must increase the disputed quotas precisely by virtue of its usual criterion.

20 As regards the first part of that argument, concerning the output capacity of the Bremen N o II mill, reference should be made to the reasons stated in the judgment of the Court of 7 July 1982 (Case 119/81, [1982] ECR 2627) on the subject of Klöckner's production quotas for the second quarter of 1981, in connection with which the same problem had previously been raised.

2i Once again, the applicant refers to the "Kawasaki expert opinion" of 1 May 1981, which is a report drawn up jointly by a group consisting of experts from the Belgian Centre de Recherches Métallurgiques [Centre for Metal- lurgical Research] and from the Japanese company, Kawasaki. The Court has held that opinion to be valueless owing, in particular, to the divergence of views which it discloses between the two groups of experts who drafted it, inasmuch as the Belgian institution gives a lower estimate of the capacity at issue than that adopted by the Commission, whereas the experts from the Japanese company postulate an appreciably higher capacity.

22 In these proceedings the applicant has failed to furnish any new factual information which might enable the above finding to be revised. By producing the Jeschar report, based on a mathematical simulation, the applicant is endeavouring to revise one aspect of the report by the Belgian institution and Kawasaki, which has been held by the Court to be in any case inconclusive. As to the Wollert-Elmendorf report relied on by the applicant, it is an accountancy document designed to evaluate the financial consequences of the fixing of the production quotas allocated to the under- taking for the third quarter of 1981, as compared with a hypothetical situation described by the applicant, consisting in the allocating of quotas

KLÖCKNER-WERKE v COMMISSION

based on a hypothetical output consistent with average capacity utilization amongst Community undertakings. That accountancy report, which is intended to evaluate what is financially at stake in the litigation between the applicant and the Commission, is based on an assessment of a productive capacity (459 000 tonnes a month, or 5 508 000 tonnes a year) which the Court has already expressly rejected in its judgment of 7 July 1982. The report therefore sheds no new light on the question raised by the applicant concerning its productive capacity.

23 As to the second part of the submission, concerning the failure to give consideration to the capacity of the Bremen No I rolling-mill which was taken out of commission in 1974, it is sufficient to recall that the Court took the view, in the judgment mentioned above, that since Decision 2794/80 fixes a very definite reference period, it does not allow anything other than the actual productive capacity during that period to be taken into account. In view of the fact that the Bremen No I rolling-mill was out of commission during those periods, the Commission was justified in disregarding its productive capacity.

24 Since the second submission also cannot be upheld, the application in Case 303/81 as a whole must be dismissed.

T h e a p p l i c a t i o n a g a i n s t t h e d e c i s i o n of 28 O c t o b e r 1981 fining t h e a p p l i c a n t for e x c e e d i n g t h e q u o t a limits ( C a s e 3 1 2 / 8 1 )

25 In support of its second application, the applicant puts forward a number of submissions which may be summarized as follows:

1. Illegality of general Decision 2794/80, which is the legal basis for the individual decision in dispute;

2. Illegality of the individual decision of 19 October 1981 refusing to increase the quotas under Article 14 of Decision 2794/80, which is the logical premise of the individual decision in dispute;

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

3. Breach of a promise given to the undertaking by the Commission's rep- resentative, namely to waive any pecuniary sanction for exceeding the relevant quota limits;

4. Existence of an emergency situation justifying the over-production and precluding its penalization by way of a fine.

Submissions alleging that Decision 2794/80 and the individual decision of 19 October 1981 are illegal

26 During the oral procedure, in view of the fact that the above-mentioned judgment of 7 July 1982 had upheld the legality of Decision 2794/80 by rejecting all of Klöckner's submissions in that connection in Case 119/81, the applicant declared that it would desist from raising the question again. There is therefore no further reason for the Court to examine it.

27 The second argument has likewise become devoid of purpose on the ground that the action brought against the individual decision of 19 October 1981 has been dismissed as unfounded.

Submission alleging breach of the promise not to impose the fine

28 T h e applicant points o u t that in M a r c h 1981, by which time it was already clear that K l ö c k n e r w o u l d exceed the quotas granted to it for the first quarter of 1981, the Commission p r o m o t e d the negotiations k n o w n as Eurofer II, which s o u g h t to obtain agreement from the larger E u r o p e a n steel-works o n v o l u n t a r y restrictions of p r o d u c t i o n , in o r d e r to avoid extending the q u o t a system. In that connection, talks w e r e held between the Commission a n d Klöckner, because the applicant had n o intention of taking part in the negotiations and the Commission was endeavouring to overcome its resistance.

29 In that connection it is alleged that Mr Defraigne, the Chef de Cabinet of the Vice-President of the Commission, Mr Davignon, acting for and on behalf of the latter, made a promise to Mr Gienow, the chairman of

KLÖCKNER-WERKE v COMMISSION

Klöckner's executive board, during a telephone conversation on 19 March 1981, namely that if Klöckner undertook to participate in the negotiations, the Commission would "solve the problem" arising from the fact that by the end of the first quarter of 1981 the applicant was due to produce more than the provisional quota hitherto allocated to it; the adjustment was to be effected irrespective of the success or failure of the Eurofer II negotiations.

30 Klöckner takes the view that the promise in question is binding on the Commission because it was made by the responsible authority, for whom Mr Defraigne acted merely as a messenger. Klöckner claims that, regard being had to its context, the promise was clear and precise in content, its subject- matter being the Commission's waiver of a fine, even if the means to be employed in achieving that end were not specified.

3i The Commission disputes the basis of Klöckner's argument on both factual and legal grounds, contending that Mr Defraigne, in telephoning, did not use the words alleged by the applicant, nor had he given any promises "for and on behalf of Mr Davignon, as his messenger"; and that, in any event, there can be no question of a promise such as might commit the defendant, regard being had to the general nature of the utterances ascribed to Mr Defraigne.

32 The Commission further argues that the supposed promise was not such as to bind it, for lack of ratification by the competent department; that a hypothetical ratification would have been unlawful in any case, since the fine is mandatory whenever quotas are exceeded; and finally, that if the supposed promise were interpreted to mean that it envisaged an increase in the quotas sufficient to cover the margin of excess for the quarter at issue, it was invalid for lack of being evidenced in writing.

33 Klöckner's argument must be disallowed, first on account of the general nature of the utterances ascribed to Mr Defraigne. The use of the expression "solve the problem", even if examined in the context expounded by the applicant, cannot be regarded as a commitment to engage in a specific course of action.

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

34 Whatever the circumstances, even if it were hypothetically possible to accept that the utterances attributed to Mr Defraigne concerned the non- enforcement of the fine, such a declaration would be devoid of legal force, for if the "promise" related to the waiver of the legal consequences of over- production officially determined, it would be illegal inasmuch as Article 9 of Decision 2794/80 requires the Commission to impose the fine whenever production in excess of the quotas is determined.

35 It follows that that submission also must be dismissed.

Submission as to an emergency situation

36 The applicant maintains that if it had observed the quotas allocated to it, the resultant losses would have been so serious that it could not have survived. That state of affairs is allegedly due, primarily, to the excessively low level of the quotas granted to it, which entailed a rate of utilization of output capacity far lower than the Community average, and hence inadequate revenue in relation to overhead costs. In the second place, the undertaking is encountering special difficulties at the economic and financial level, owing to the very high cost of restructuring the plant which it has brought into operation since 1973, in response to the suggestion and inducements of the Commission itself. Those expenses led to a lack of liquid funds which had repercussions on the indebtedness and the reserves of the business. The presence of precarious financial circumstances is proved by an expert report prepared by accountants and submitted by the applicant. Lastly, the under- taking refers to the crisis in the steel market.

37 The applicant was consequently confronted by the alternative of either contravening the quota system in order to achieve a revenue consistent with its economic situation or else abiding by the quotas and being thereby forced into insolvency. Klöckner therefore took action in an emergency situation, with the result that its conduct, although illegal in an objective sense, was justified, and that no sanction can be imposed upon it.

38 Klöckner maintains that, since an emergency situation is recognized in the legal systems of all Member States as justifying unlawful conduct, the same

KLÖCKNER-WERKE v COMMISSION

principle must prevail in Community law. Indeed, the fundamental right of every individual to survive is safeguarded in Community law, particularly in the field of the quota system for steel production inasmuch as it forms the basis for a number of provisions of the general decision of the Commission, such as those providing for the raising of the quotas in cases of exceptional difficulties or of excessively low rates of utilization of productive capacity, or again those providing for a reduction of the abatement rate applicable to the reference production of small undertakings manufacturing reinforcing bars or of undertakings in Greece. Those provisions are merely examples of the practical application within the Community of the principle of the emergency situation.

39 The applicant maintains that the fact that the above-mentioned provisions are applicable only to certain categories of small undertakings entails a breach of the principle of non-discrimination, inasmuch as the reservation in favour of the emergency situation must necessarily be general in character, regardless of the structure or the size of an undertaking.

40 According to the applicant, the conditions for recognizing an emergency situation are all satisfied in, this case. The interest infringed was merely formal in character, aiming to achieve an orderly running of the quota system, whereas the illegal conduct was designed to safeguard a fundamental right, namely the right to survival. The perilous situation constituting the emergency is a direct consequence, both of the establishment and of the enforcement of the quota system, and is in no way due to bad business- management or mistakes of economic policy. On the contrary, the under- taking has complied fully with the Commission's suggestions for modernizing the Community's steel industry. Lastly, the undertaking has been unable to have resort to any legal means in order to escape the danger of insolvency.

41 The Commission contends in the first place that an emergency situation cannot be invoked in the specific context of the quota system for steel production, owing to its incompatibility with the objectives of Article 58 of the ECSC Treaty. That article aims to distribute equitably amongst all Community undertakings the sacrifices required as a result of the crisis in the steel sector, with a view to maintaining or restoring their profitability in the long term, whereas that goal would be unattainable if every undertaking

JUDGMENT OF 11. 5. 1983 — JOINED CASES 303 AND 312/81

were able to exempt itself from any sacrifice by pleading an emergency situation. Breaches of the quota limits would, if permissible on that score, necessarily entail lowering the quotas of other undertakings, with the result that the latter, in their turn, might claim to find themselves in an emergency situation and thereby justify exceeding their quotas.

42 At all events, the Commission denies that the conditions for an emergency situation are fulfilled in this instance. In its view, the applicant's future was not at risk when the over-production at issue occurred; moreover, the supposed risk was not a result of the establishment of the quota system but was due to mistakes made by the applicant in its investment policy in previous years. The accountancy report does not afford reliable evidence to sustain Klöckner's arguments, inasmuch as it relates to a single sector of the undertaking and is based on data which cannot be checked. Conflicting interests set the survival of one undertaking against that of the majority, if not the totality, of the others. Lastly, the applicant could have removed the supposed threat to its existence by legal means and was therefore in no way justified in taking the law into its own hands.

43 Before consideration is given to the Commission's main contention, namely that the principle of an emergency situation is incompatible with Article 58 of the ECSC Treaty, the special circumstances pleaded by the applicant in support of its application must be examined.

44 As to the first circumstance which supposedly led to the emergency situation, namely the award of a quota which was insufficient in relation to the under- taking's actual productive capacity, it must be recalled that the Court has already refuted that argument, which cannot therefore be taken into consideration.

45 As to the other circumstance which supposedly brought about the emergency situation, namely the very high cost of the restructuring carried out by the undertaking since 1973, it should be observed that that fact derives from a choice of economic policy made by the undertaking itself. Under the legal systems of the Member States, however, one of the essential prerequisites for

KLÖCKNER-WERKE v COMMISSION

an acknowledgement that an emergency situation exists is precisely that the perilous situation justifying the unlawful act shall not have been brought about by the author of that act. That prerequisite is therefore not fulfilled in this case.

46 As far as concerns the manifest crisis which struck the steel market, it is appropriate to stress that the crisis affected steel undertakings in general and thus necessitated the establishment of the quota system provided for by Article 58 of the ECSC Treaty. That article provides that in the event of a decline in demand, if the Commission considers that the Community is confronted with a period of manifest crisis and that the other means of action provided for in the Treaty are not sufficient to deal with it, it is required, following the consultations stipulated therein, to establish a system of production quotas. The system was lawfully set up by the Commission by means of Decision 2793/80, compliance with which is required of every undertaking concerned. However, the system of production quotas would be gravely compromised — or indeed set at nought — if every undertaking were able, by pleading an emergency situation due to serious economic difficulties, to excuse itself from observance of the restrictions and to exceed at will the production quota allocated to it. The chain reaction thereby released would culminate in the collapse of the system, so that Article 58 of the Treaty would become a dead letter.

47 The above considerations indicate that, even supposing that the concept of an emergency situation were admitted in principle into Community law, the applicant's last submission alleging such a situation must be disallowed.

The alternative claim for a reduction in the amount of the fine

48 The applicant has not set forth any special arguments in support of its alter- native claim for a reduction in the amount of the fine. It must therefore be presumed that it is based on the same arguments as underlie the principal claim. In examining those arguments, the Court has found no reasons such as to justify a reduction of the fine.

OPINION OF MR REISCHL — JOINED CASES 303 AND 312/81

Costs

49 U n d e r Article 69 (2) of the Rules of P r o c e d u r e the unsuccessful p a r t y is to be o r d e r e d to p a y the costs if they have been asked for in the successful party's pleading. As the applicant has failed, it must be o r d e r e d to p a y the costs.

O n those g r o u n d s ,

T H E C O U R T (Fourth C h a m b e r )

hereby:

1. Dismisses the applications;

2. Orders the applicant to pay the costs.

O'Keeffe Pescatore

Bosco Koopmans Bahlmann

Delivered in open court in L u x e m b o u r g on 11 M a y 1983.

P. H e i m A. O'Keeffe Registrar President of the Fourth Chamber

OPINION OF M R ADVOCATE GENERAL REISCHL D E L I V E R E D O N 23 F E B R U A R Y 1983 '

Mr President, et seq.), which are already familiar from Members of the Court, a series of other proceedings. The decision was in force from 1 October 1980 until 30 June 1981. Both the cases on which I am expressing my views today are concerned, once The first of the two cases at issue here again, with the steel quota provisions as concerns a decision of the Commission laid down by Decision 2794/80 (Official whereby it refused to raise, pursuant to Journal L 291 of 31 October 1980, p. 1 Article 14 of Decision 2794/80, the

í — Translated from the German.

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Rozsudok C-303/81 – Súdny dvor Európskej únie | AI Pravnik