C-284/82
ECLI:EU:C:1984:47
- Súd
- Súdny dvor Európskej únie
- IČS
- 61982CJ0284
- Zdroj
- eur-lex.europa.eu ↗
JUDGMENT O FT H E COURT (SECOND CHAMBER) 9 F E B R U A R Y 1984 1
Acciaierie e Ferriere Busserà SpA ν Commission of the European Communities
( E C S C — Q u o t a system for steel p r o d u c t i o n — Force majeure)
Case 284/82
1. Community law — General principles — Force majeure — Concept
2. Procedure — Time-limit for instituting proceedings — Barring — Cases of force majeure — Concept — Limits (Statute of the Court of Justice of the ECSC, Art. 39, first and third paras)
1. Apart from special cases in specific 2. The temporary closure of an under areas in which it is used, the concept taking, which does not mean either its of force majeure requires basically winding-up or the termination of the unusual circumstances making ac responsibility of its management for complishment of the matter in hand the normal conduct of business, impossible. Even though it does not cannot be regarded as a case of force presuppose absolute impossibility it majeure within the meaning of the nevertheless requires abnormal diffi third paragraph of Article 39 of the culties, independent of the will of the Statute of the Court of Justice of the person concerned and apparently ECSC justifying disregard of the inevitable even if all due care is taken. time-limit for instituting proceedings laid down in the first paragraph thereof.
In Case 284/82
ACCIAIERIE E FERRIERE BUSSENI S P A , at p r e s e n t subject to court-controlled m a n a g e m e n t p r o c e d u r e , having its registered office at N a v e (Brescia, Italy), in t h e person of its sole administrator, M a u r i z i o Busseni, represented by
1 — Language oftheCase:Italian.
JUDGMENT OF 9. 2. 1984 — CASE 284/82
Fabrizio Massoni, Gino Alberto Bergmann and Gerolamo Pellicano, with an address for service in Luxembourg at the Chambers of André Elvinger, 15 Côte d'Eich, applicant, ν
COMMISSION OF THE EUROPEAN COMMUNITIES, represented by Sergio Fabro, acting as Agent, with an address for service in Luxembourg at the office of Oreste Montalto, both members of its Legal Department, Jean Monnet Building, Kirchberg, defendant,
APPLICATION for a declaration that the individual decision of the Commission of 13 August 1982 imposing a fine on the applicant is void,
T H E C O U R T (Second Chamber)
composed of: K. Bahlmanm, President of Chamber, P. Pescatore and O. Due, Judges,
Advocate General: G. Reischl Registrar: H. A. Rühi, Principal Administrator
gives the following
JUDGMENT
Facts and Issues
The facts of the case, the course of the I — Facts procedure and the conclusions, sub- missions and arguments of the parties Confronted with a situation of manifest may be summarized as follows : crisis in the iron and steel market within
BUSSENI ν COMMISSION
the meaning of Article 58 of the ECSC examines the case without delay in the Treaty the Commission adopted general light of the objectives of the decision Decision No 2794/80/ECSC of 31 Oc and, where appropriate, adapts the tober 1980 (Official Journal, L 291, p. 1) provisions of the decision to the as amended by Decision No 3333/80/ particular case. ECSC (Official Journal, L 349, p. 21) establishing a system of steel production quotas for undertakings in the iron and steel industry. Article 9 of the decision provides that the Commission is to fine firms exceeding their production quota or that part thereof which under Article 7 (2) and (3) Under Articles 2 to 4 of the general may be delivered within the common decision the Commission fixes quarterly market. The fine is generally to be 75 production quotas for each undertaking European currency units [ECU] pel in respect of crude steel and for each of tonne of excess for ordinary steels and the four groups of rolled products, the 150 ECU per tonne of excess for special fourth of which concerns the products in steels. question in this case. The calculation of those quotas is based on the quarterly reference productions of each under taking. For that purpose for each month By letters dated 19 December 1980 and 6 of the relevant quarter, reference is made April 1981 the Commission informed to the same month during the period Busseni of its reference production and from July 1977 to June 1980 during production quota for the first and second which the total production of the four quarters of 1981 as a result of the groups of rolled products was the application of the abatement rates highest. The three months thus chosen, provided for in Article 5 of the general which are not necessarily consecutive, decision and amended the figures by constitute the reference period. The a letter dated 1 February 1982. The reference production figures are the decision allocating the production quota same, for crude steel and for each of the has never been challenged by Busseni four groups of rolled products, as the before the Court. production of the corresponding items during the reference period. However, in the cases provided for by Article 4 (3), (4) and (5) of the general decision the On 24 April and 18 May 1981 Busseni Commission may within certain limits asked for its quota for the first quarter of 1981 to be adjusted but never received increase the reference production and a reply from the Commission. consequently the quotas allocated to the undertakings in question.
By letters dated 24 November 1981 and 4 February 1982 the Commission Further, Article 14 of the decision complained that Busseni had exceeded its provides that where the production or quota for Group IV products by 4 576 delivery restrictions imposed by the tonnes and 3 476 tonnes and asked it to decision and its implementing measures submit its comments pursuant to Article entail exceptional difficulties for an 36 of the ECSC Treaty. In its obser undertaking, it may refer the matter to vations by telex message of 9 December the Commission, providing all appro 1981, letters of 17 December 1981 and priate documentation. The Commission 19 February 1982 and during the course
JUDGMENT OF 9. 2. 1984 — CASE 284/82
of a hearing granted to its representatives II — W r i t t e n procedure and on 26 March 1982 Busseni did not deny conclusions exceeding the quota but disputed the extent. Following that correspondence the excess for the fourth quarter of 1981 Upon hearing the report of the Judge- was reduced from 4 576 tonnes to 3 398 Rapporteur and the views of the tonnes. Nevertheless as justification for Advocate General the Court invited the the excess Busseni cited the heavy applicant and the Commission to supply financial and social burdens which certain information which was given to forced it to maintain a production higher the Court by letters of 13 July 1983 from than that allocated by the Commission. the applicant and of 11 July 1983 from The Commission took the view that the Commission and which is reproduced Busseni's arguments were inadequate and below. by decision dated 13 August 1982 imposed on it a fine of 514 875 ECU, The Court thereupon decided to open that is, LIT 680 289 981, pursuant to the oral procedure without any Article 9 of the general decision. The preparatory inquiry. decision of 13 August 1982 was sent to Busseni from Brussels on 19 August 1982 by letter dated 17 August 1982 and the By order dated 22 June 1983 the Court acknowledgment of receipt was signed assigned the case to the Second by Busseni on 26 August 1982 in Nave Chamber. (Italy). The applicant claims in its application that the Court should :
Meanwhile Busseni had been under the 1. "Declare void the Commission Cassa Integrazione Guadagni [income decision of 13 August 1982 and as a supplement fund] pursuant to the Italian preliminary suspend the operation Law No 675 of 12 August 1977 and thereof; subjected to the system of concordato stragiudiziale [out-of-court settlement]. 2. In the alternative, reduce the fine; By order of the Tribunale [District Court], Brescia, dated 23 April 1982, the court-controlled management procedure 3. In the further alternative defer was started against Busseni. payment of the fine whatever the. outcome of the proceedings."
The Commission contends in its defence Pursuant to Article 33 of the ECSC that the Court should Treaty Busseni instituted proceedings by application sent from Milan on 22 October 1982 and received at the Court 1. "Declare the application inadmissible Registry on 25 October 1982 for a for disregard of Article 39 of the declaration that the individual decision Statute of the Court of Justice of the of the Commission of 13 August, 1982 ECSC; imposing on it a fine for exceeding the said quota was void or in the alternative 2. Alternatively, if the above contention for a reduction of the amount of the fine that 'the claim is barred is dismissed, and in the further alternative time for declare the applicant's claims inad- payment of the fine. missible;
BUSSENI ν COMMISSION
3. In any event order the applicant to The applicant's second submission is that pay the costs." it cannot be held to be at fault in exceeding the quotas since it was not able to observe them without irreparably and still more precipitously aggravating its economic and financial situation. It was thus absolutely impossible for it to The applicant claims in its reply that the act differently. application is admissible.
The applicant's third submission is that payment of such a fine would have made the company insolvent and prevented it III — Submissions and argu from properly concluding the court- m e n t s of t h e p a r t i e s controlled management procedure.
The Commission in the first place raises The applicants first submission is that it an objection that the action is was impossible for it to observe the inadmissible. It is of the opinion that the quotas allocated by the Commission. The applicant has not observed the period of undertaking encountered exceptional one month for bringing an action difficulties which should have led the commencing with the date of notification Commission to consider its case as soon of the individual decision in question as as possible pursuant to Article 14 of laid down in Article 39 of the Statute of general Decision No 2794/80. The the Court of Justice of the ECSC and undertaking experienced an extremely extended by 10 days in this present case serious crisis, leading in 1977 to heavy pursuant to Article 81 of the Rules of debts of approximately 19 000 million Procedure of the Court and Article 1 of lire, massive recourse to the Cassa Annex II thereto. Thus although the Integrazione Guadagni, a staff reorgani application should have been lodged at zation, the signature of an out-of-court the Registry before 6 October 1982 it settlement in 1978 and finally the did not arrive at the Court until 25 commencement of the court-controlled October 1982. The Commission denies management procedure under the that the applicant may rely on the fact Tribunale, Brescia. During that period that the undertaking was closed from 17 Busseni reduced its steel production from March to 13 September 1982 after being 121 804 tonnes in 1976 to 74 446 tonnes put under the Cassa Integrazione in 1981 which represents a catastrophic Guadagni pursuant to Italian Law No reduction in the quantity of steel 675/77 and that such closure constitutes produced, a situation which is corrob a case of force majeure within the orated by the reduction in its meaning of Article 39 of the Statute of consumption of energy. The reduction in the Court of Justice of the ECSC. The production made it impossible to meet Italian Law does not provide either for the normal commitments of production the dissolution of the company or the management or the commitments arising dismissal of its staff. On the contrary, the from the out-of-court settlement and undertaking retains its organization impossible to discharge the special intact and maintains its legal personality obligations. so that it is able to take all the legal
JUDGMENT OF 9. 2. 1984 — CASE 284/82
measures which are necessary, as is system would lose all effectiveness since proved by the declaration of the Pre- no one would observe it. fettura di Brescia from which it appears that the undertaking's management negotiated with the trade unions to fix the date for resuming work while the company was still under the Cassa As for payment of the fine the Integrazione Guadagni. Commission observes that its officers were authorized to grant considerable time for payment to undertakings which proved that they were experiencing economic difficulties. It follows that the Even if the validity of the applicant's Court cannot in any event agree to the arguments were accepted the application applicant's claims. would nevertheless have been out of time since if it were agreed that the period commenced to run on 13 September 1982 when the undertaking re-opened, The applicant contends in its reply that the application should have been lodged the objection of inadmissibility put at the latest on 23 October 1982 whereas forward by the Commission is it was not lodged until 25 October 1982. completely unfounded. Busseni was completely closed as a result of a very serious company crisis from 17 March to 13 September 1982 so that there were "unforeseeable circumstances" of "force On the substance the Commission majeure" within the meaning of Article confines itself to observing that the 39 of the Statute of the Court of Justice applicant's argument as to the existence of the ECSC, which provided sufficient of exceptional difficulties cannot exclude reason for not observing the time-limits. its liability for exceeding the production The article cited requires neither the quotas. If the Commission had auth- dissolution of the company nor the orized Busseni to exceed its quotas in the dismissal of its staff to satisfy the event of long-standing difficulties it aforesaid conditions. In this case the would have had had to do likewise with closure of the undertaking led to the a large number of other undertakings accumulation of six months' post, which which would have made the system of prevented the management from taking production quotas ineffective as a whole. cognizance of the notification of the The criterion of the exceptional nature Commission's decision for 18 days at of the economic difficulties must have a least after the re-opening of the company solid basis to be applicable in an on 13 September 1982. exceptional period.
Even on the assumption that only the Further, the Commission maintains that date of the re-opening is relevant the every undertaking is bound to observe action was brought in time since the quota system so long as the according to Article 80 of the Rules of Commission has not considered it Procedure of the Court the period of necessary to bring into operation the one month provided for bringing an derogations provided for in Article 15 of action began to run on 14 September the general decision. Otherwise the 1982 and expired, in view of the 10
BUSSENI ν COMMISSION
additional days provided for by Article 1 In its rejoinder the Commission of Annex II to the Rules of Procedure, challenges the facts as presented by the on 24 October 1982. Since that day was applicant, namely that the closure of the a Sunday the period in fact expired on undertaking might be regarded as just 25 October 1982 when the application ification on the basis of force majeure or was lodged at the Court Registry. The unforeseeable circumstances, concepts action is therefore fully admissible from which are defined in the case-law of the the point of view of the time-limit. Court as external events independent of the will of the person owing the obligation and therefore unforeseeable as regards both their occurrence and their consequences. Although that definition covers a natural catastrophe or a strike, it cannot apply in this case since on the As to the substance, the applicant re one hand the event was not only fore asserts its argument that the exceptional seeable but requested by the applicant difficulties which it encountered and in and moreover since it is clear that all particular its insolvency justified the the company responsibilities were fully application by the Commission of Article performed, the administrators had a duty 14 of the general decision. If when the to carry on at least current management. matter was duly put to it the The Commission considers that the fact Commission did not consider it needed that the administrators did not even take to act thereunder, that constitutes an the trouble to open correspondence additional defect in the contested amounts to blatant negligence on the decision. part of the management.
Further the applicant alleges that the fine should be quashed along with the Finally the Commission reasserts its view decision at issue pursuant to Article 4 (5) that the Cassa Integrazione Guadagni of the general decision since, on the basis organization docs not affect the legal of the applicant's economic situation the capacity of the undertaking. That is Commission, it claims, ought to have easily apparent from consideration of the increased its reference production so as rules governing the system which go to reach the total equivalent to the back to Legislative Decree No 788 of the production for the corresponding quarter Lieutenant General of the Kingdom of of 1974. The production for that year on 9 November 1945 and conclude after which the ECSC levies were calculated various amendments with Law No 675 of amounted to some 180 000 tonnes 12 August 1977 cited by the applicant. whereas the average for the three reference years was less than 120 000 tonnes. There is in consequence a reduction in production of 60 000 tonnes as against 1974. Thus the 6 800 tonnes excess of which complaint is made against Busseni is amply compensated for and absorbed by that difference in the On the substance the Commission refers reference production. to the observations set out in its defence.
JUDGMENT OF 9. 2. 1984 — CASE 284/82
IV — A n s w e r s to t h e questions 2794/80 under which the fine is to be 75 p u t by t h e C o u r t ECU per tonne of excess. It added however that in fact it ought to have The Court asked the applicant to provide applied the second paragraph of Article 9 it with the relevant documents governing since it was not a first offence since the the closure of its establishment and the excess arose in two quarters, that is to documents in relation of the out-of-court say the first and second quarters of 1981, settlement and the court-controlled so that according to its practice in the management procedure referred to in the exercise of its discretion the amount of application and any decisions of the the fine in relation to the excess for the national court following application of second quarter ought to have been that procedure and relating to the increased by 10% since the case involves management of the undertaking. The an undertaking with a negative balance. applicant placed before the Court its application of 17 April 1982 to the Tribunale Civile e Penale, Sezione Fall- V — Oral procedure imentare [Civil and Criminal District Court, Insolvency Division], Brescia, At the sitting on 22 September 1983 the pursuant to Article 187 of Royal Decree Commission of the European Communi- No 267 of 16 March 1942. ties, represented by S. Fabro, acting as Agent, presented oral argument. The Court also asked the Commission to explain the amount of the fine. The The Advocate General delivered his Commission answered that in this case it opinion at the sitting on 17 November applied Article 9 of Decision No 1983.
Decision
1 By application lodged at the C o u r t Registry on 25 O c t o b e r 1982 Acciaierie e Ferriere Busseni SpA (hereinafter referred to as "Busseni"), w h o s e registered office is at N a v e (Italy), b r o u g h t an application u n d e r the second p a r a g r a p h of Article 36 of the E C S C T r e a t y claiming on the one h a n d that the C o u r t should declare void Commission Decision C (82) 1 1 9 1 / 3 of 13 August 1982 fining it 514 875 E C U , that is L I T 680 289 9 8 1 , pursuant to Article 58 (4) of the E C S C T r e a t y and Article 9 of the general Commission Decision N o 2 7 9 4 / 8 0 / E C S C of 31 O c t o b e r 1980 establishing a system of steel p r o d u c t i o n quotas for undertakings in the iron and steel industry (Official J o u r n a l , L 2 9 1 , p. 1) and o n the other h a n d , in the alternative, the reduction o f . t h e a m o u n t of the fine and the grant of time for payment.
2 T h e statement of the reasons on which the contested decision is based refers to the fact that for the first and second quarters of 1981 Busseni exceeded by
BUSSENI ν COMMISSION
3 398 and 3 467 tonnes respectively the production quotas allocated to it for Group IV products under the steel production quota system established by Decision N o 2794/80. The Commission ordered Busseni to pay the fine within a period of two months from notification of the decision.
3 The decision was forwarded to Busseni by letter dated 17 August 1982 and received by Busseni on 26 August 1982 at its registered office in Nave.
Admissibility
4 The Commission raises an objection that the application is inadmissible. It alleges in that respect that Busseni has not observed the period of one month from notification of the disputed decision, laid down by Article 39 of the Statute of the Court of the ECSC and extended by 10 days in the present case pursuant to Article 81 of the Rules of Procedure of the Court and Article 1 of Annex II thereto. The application which ought thus to have been made before 6 October 1982 did not in fact reach the Court until 25 October 1982.
5 Busseni on the contrary maintains that the application is fully admissible with regard to the time-limit. It was not able to make application within the pres cribed period because the undertaking was under the Cassa Integrazione Guadagni because, by order of the Tribunale, Brescia, of 23 April 1982 it had been placed under court-controlled management for two years with the appointment of a Commissario Giudiziale and because it had been completely closed from 17 March to 13 September 1982. In those circum stances the management of the company had been prevented from taking cognizance of the service of the decision at issue before a date which Busseni puts at 18 days at least after the re-opening on 13 September 1982 by reason ' of the accumulation of six months post.
6 In the applicant's view the closure represented a very serious crisis constituting unforeseeable circumstances or force majeure within the meaning of the third paragraph of Article 39 of the Statute of the Court of Justice of the ECSC and thus interrupted the running of the prescribed period.
JUDGMENT OF 9. 2. 1984 — CASE 284/82
7 Alternatively Busseni maintains that even on the assumption that only the date of the re-opening is to be taken into account the application ought to be treated as made in time since according to Article 80 of the Rules of Procedure of the Court the period of one month prescribed for bringing an action would have started to run on 14 September 1982 and would have expired, in view of the 10 additional days provided by Article 1 of Annex II to the Rules of Procedure, on 24 October 1982. Since that day was a Sunday the period in fact expired on 25 October 1982 when the application was registered at the Court.
8 It must be stated that the period for bringing an action must be strictly observed and cannot be extended save on grounds of distance as provided in the second paragraph of Article 39 of the Statute of the Court of Justice of the ECSC. Nevertheless the third paragraph thereof provides that no right shall be prejudiced in consequence of the expiry of a time-limit if the party concerned proves the existence of unforeseeable circumstances or of force majeure.
9 In the present case pursuant to Article 33 of the ECSC Treaty the period prescribed for bringing an action was one month extended on account of distance by a period of 10 days granted to Italian applicants pursuant to Annex II to the Rules of Procedure. In view of the fact that the decision at issue was notified to the applicant on 26 August 1982 and that according to Article 81 of the Rules of Procedure the period of time allowed for commencing proceedings against a measure adopted by an institution is to run from the day following the receipt by the person concerned of notification of the measure, the period for commencing proceedings expired on 6 October 1982 so that the application, registered at the Court on 25 October 1982, was out of time.
10 The admissibility of the application thus depends solely on the question of the existence in this case of force majeure within the meaning of the third paragraph of Article 39 of the Statute of the Court of Justice of the ECSC.
1 1 It is apparent from the established case-law of the Court that apart from special cases in specific areas in which it is used, the concept of force majeure essentially covers unusual circumstances which make it impossible for the relevant action to be carried out. Even though it does not presuppose absolute impossibility it nevertheless requires abnormal difficulties, independent of the will of the person concerned and apparently inevitable even if all due care is taken.
DUSSENI ν COMMISSION
12 It must be observed that it is apparent from the file that the closure of the Busserà undertaking did not mean either the winding-up of the undertaking or the termination of the responsibility of its management for the normal conduct of business. The fact that it received the support of the Cassa Integrazione Guadagni, that it was placed by order of 23 April 1982 of the Tribunale, Brescia, under court-controlled management for two years, that a Commissario Giudiziale was appointed and that it adopted managerial measures in the interest of its re-opening sufficiently shows a considerable activity intended to secure its survival and preservation.
1 3 In consequence it must be stated that in this case there are no abnormal and inevitable difficulties or external events independent of the will of the management of the undertaking which might have justified a failure to open correspondence relating to the business of the undertaking.
1 4 It follows that the institution of proceedings out of time is not due to force majeure and that the action is inadmissible.
Costs
15 Under Article 69 (2) of the Rules of Procedure the unsuccessful party is to be ordered to pay the costs. Since the applicant has failed in its submissions it must be ordered to pay the costs.
On those grounds,
T H E C O U R T (Second Chamber)
hereby:
1. Dismisses the application as inadmissible;
O P I N I O N O F MR REISCHL — CASE 284/82
2. Orders the applicant to pay the costs.
Bahlmann Pescatore Due
Delivered in open court in L u x e m b o u r g o n 9 February 1984.
J. A. Pompe K. Bahlmann Deputy Registrar President of the Second Chamber
OPINION OF MR ADVOCATE GENERAL REISCHL DELIVERED ON 17 NOVEMBER 1983 1
Mr President, its actual production only 16 689 tonnes. Members of the Court, In a letter dated 1 February 1982 the quota for the first quarter of 1981 was apparently increased by a further 1 178 The subject-matter of the application on tonnes. which I give my opinion today is a notice of fine which the applicant received pursuant to Article 9 of Decision No 2794/80 ECSC for exceeding the production quotas allocated to it for the first and second quarters of 1981. In fact however the applicant produced more than it was allowed. It referred for the first time in a letter dated 24 April The applicant was informed of its 1981 to a need to do so. Because of production quota for Group IV products heavy debts in 1978 it had made an out- for the first six months of 1981 by notice of-court settlement under which the dated 19 December 1980 fixing 12 279 balance was to be paid to banks before tonnes for the first quarter of 1981 and the end of 1981. Because its financial by notice dated 6 April 1981 for the situation had further deteriorated it second quarter of 1981. Later in a letter could not observe the production quotas dated 24 November 1981 the Com- without jeopardizing current business mission acknowledged that the quota for and the repayment under the settlement. the first quarter of 1981 should be In a letter dated 18 May 1981 the increased by a further 358 tonnes applicant further explained that con- because the applicant's quota for the last siderable debts had forced it in 1977 to quarter of 1980 was 17 047 tonnes and restrict production and reduce staff
1 — Translated from the German.