← Späť na vyhľadávanie
Súdny dvor Európskej únie·Rozsudok·28.3.1984

C-29/83

ECLI:EU:C:1984:130

Súd
Súdny dvor Európskej únie
IČS
61983CJ0029

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

behaviour of the two undertakings specific non-member country con­ was the result of concerted action by stitute an infringement of Article 85 them. of the Treaty when they are es­ sentially designed to prevent the re­ export of the goods to the country of production so as to maintain a system That requirement is not satisfied of dual prices and restrict competition where the undertakings concerned are within the common market. able to prove that facts which the Commission considered could not be explained other than by a concerted practice can be satisfactorily explained 5. However a reciprocal assistance in a way which does not involve such contract between producer under­ a practice. takings might generally be evaluated in relation to the prohibitions con­ tained in Article 85 of the Treaty, 3. In order to determine whether an such a contract is prohibited if it agreement has as its object the appears that the conditions for its restriction of competition, it is not application are so wide and so vague necessary to inquire which of the two that they may be used to restrict contracting parties took the initiative competition. in inserting any particular clause or to verify that the parties had a common intent at the time when the agreement was concluded. It is rather a question That is the case, for example, where of examining the aims pursued by the the undertakings, to provide mutual agreement as such, in the light of assistance do not just relate to cases the economic context in which the of force majeure and comparable agreement is to be applied. situations, but to all cases of "serious disruption", of whatever kind and from whatever source, particularly if 4. Export clauses inserted in a contract the contract is concluded for an of sale which oblige the dealer to indeterminate period and if large export the goods in question to a quantities of products are involved.

In Joined Cases 29 and 30 / 83

(1) COMPAGNIE ROYALE ASTURIENNE DES MINES SA, whose registered office is in Paris , represented by Ivo van Bael and Jean-François Bellis, of the Brussels Bar , with an address for service in Luxembourg at the Chambers of Messrs Elvinger and Hoss , 15 Côte d'Eich ,

applicant in Case 29 / 83 ,

CRAM AND RHEINZINK / COMMISSION

and

(2) RHEINZINK GMBH , whose registered office is in Datteln (Federal Republic of Germany), represented by its directors, Volker Groth and Rolf Wölfer, assisted by Rainer Bechtold, Rechtsanwalt of Stuttgart, as representative ad litem, with an address for service in Luxembourg at the Chambers of Ernest Arendt, 34 B Rue Philippe-Il,

applicant in Case 30/83, v

COMMISSION OF THE EUROPEAN COMMUNITIES, represented in Case 29/83 by its Legal Adviser, Giuliano Marenco, and in Case 30/83 by its Legal Adviser, Norbert Koch, acting as Agents, with an address for service in Luxembourg at the office of Oreste Montako, Jean Monnet Building, Kirchberg,

defendant, APPLICATION for a declaration that, to the degree set out in the conclusions of the applicants, Commission Decision 82/866/EEC of 14 De­ cember 1982 relating to a proceeding under Article 85 of the EEC Treaty (IV7/29.629 — Rolled zinc products and zinc alloys — Official Journal L 362, p. 40) is void,

THE COURT (Fourth Chamber)

composed of: T. Koopmans, President of Chamber, K. Bahlmann, P. Pescatore, A. O'Keeffe and G. Bosco, Judges,

Advocate General: S. Rozès Registrar: J. A. Pompe, Deputy Registrar

gives the following

JUDGMENT

TABLE OF CONTENTS

I —• Facts and procedure \b%2 1. The applicants W&Ï 2. The purpose of the application 1682 3. The contested decision 1683 4. The facts on which the contested decision is based ·. 1684 A — The measures to protect markets 1684 B — The reciprocal assistance contract 1687 5. Procedure 16g8

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

II — Conclusions of the parties 1688

III — Submissions and arguments of the parties 1688 1. The liability of Rheinzink for the behaviour of its predecessor 1688 2. The infringement of procedural rules 1689 3. The concerted practices between CRAM and RZ 1690 (a) The arguments of CRAM 1690 (b) The arguments of Rheinzink 1691 (c) The Commission's defence 1692 4. The agreement between RZ and Schütz 1694 5. The reciprocal assistance contract between CRAM, RZ and VM 1695 6. The amount of the fines 1697

IV — Oral procedure 1697

Facts and Issues

The facts of the case, the course of the Rheinisches Zinkwalzwerk GmbH & Co. procedure and the conclusions, sub­ (hereinafter referred to as " RZ ") is a missions and arguments of the parties German company specializing in the may be summarized as follows: rolled zinc sector. On 8 December 1981, it was transformed, with effect retro­ active to 1 October 1981, into a limited I — Facts and procedure liability company under the name of Rheinzink GmbH (hereinafter referred to as "Rheinzink") · That transformation 1. The applicants took place pursuant to the Umwand­ lungsgesetz (German Law on the Trans­ The two applicant companies are among formation of Companies). Rheinzink is the six largest producers of zinc in the the legal successor of RZ. The contested European Community. Commission Decision of 14 December 1982 is addressed to RZ, which, at that The Compagnie Royale Asturienne des time, was part of the international Mines (hereinafter referred to as Metallgesellschaft group. Since 1 Oc­ " CRAM "), the applicant in Case 29/83, tober 1982, three German undertakings is a French company whose main factory have shared the capital of Rheinzink, the is at Auby-les-Douai, in the North of applicant in Case 30/83. France. It exports a not insignificant part of its production of rolled zinc, in particular to the Federal Republic of 2. The purpose of the applications Germany. The company also has mining, industrial and commercial interests in The present applications are aimed at Spain, Morocco and Norway. the same Commission Decision, that of

CRAM AND RHEINZINK / COMMISSION

14 December 1982 — 82 / 866 / EEC — contests all of the above-mentioned parts relating to a proceeding under Article 85 of the decision. of the EEC Treaty (Official Journal L 362, p. 40). That decision records various infringements of Article 85 3. The contested decision committed by five undertakings pro­ ducing rolled zinc, including the applicants. The latter contest only part of For the purposes of the present ap­ that decision. plications, the relevant provisions of the decision are as follows:

The infringements which are the subject "Article 1 of the present applications concern in particular measures to protect markets taken by CRAM and RZ in 1976, on the 1. The concerted action taken in 1976 one hand, and a reciprocal assistance by CRAM and RZ with a view to contract concluded in 1974 between the protecting the German market against two applicants and a third undertaking, parallel imports of rolled products by the company Vieille Montagne, whose Schütz constitutes an infringement of registered office is in Angleur (Belgium), Article 85 of the Treaty. on the other. As regards the measures to protect markets, the Commission found, in its decision, two distinct infringements 2. The agreement concluded in 1976 of Article 85. In the first place, CRAM between CRAM and Schütz on the one and RZ are said to have acted in concert hand, and between RZ and Schütz on in 1976 to protect the German market the other requiring the latter to resell against parallel imports of rolled zinc rolled zinc products in a specific country products being made by a Belgian with the object of restricting parallel company, Gebr. Schütz NV (hereinafter imports into the Community constituted referred to as "Schütz"). In the second an infringement of Article 85 of the place, CRAM and RZ, it is said, both Treaty. concluded contracts with Schütz in 1976, whereby the latter was required to sell rolled zinc products in a specific non- Article 2 member country so as to limit the risk of parallel imports into the European Community. 1. For their involvement in the infringement referred to in Article 1 (1), the following fines are hereby imposed on the following undertakings: The fines were only imposed for the concerted practices which took place in 1976 between CRAM and RZ. CRAM, a fine of 400 000 (four hundred thousand) ECU, i. e. FF 2 625 000,

Rheinisches Zinkwalzwerk GmbH & In its application CRAM, the applicant Co., a fine of 500 000 (five hundred in Case 29/83, contests the decision in thousand) ECU, i. e. DM 1 157 230. question in so far as it relates to the concerted action taken in 1976. Rheinzink, the applicant in Case 30/83, 2. ...

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

Article 3 German markets were higher than those charged in the other countries of the The reciprocal assistance contract dated Community. Noticeable price differences 5 August 1974 between CRAM, RZ and also existed in comparison with the VM constitutes an infringement of prices charged in certain non-member Article 85 of the Treaty. countries. However, the prices charged by the two applicant undertakings in one (...) and the same country differed from each other only slightly. Article 6

The parties referred to in Article 7 are In order to benefit from those price hereby ordered to bring to an end differences, the German company forthwith the infringements established Kestermann, arranged with Schütz, a and to refrain in future from any con­ Belgian importer of sanitary equipment, tractual provision or concerted practice that the latter would buy rolled zinc having the same effect. products from CRAM and RZ, on the terms applied by those producers to their sales in Belgium; and then sell the Article 7 products to Kestermann with a view to their disposal in the Federal Republic of This Decision is addressed to : Germany.

1. In its entirety: Compagnie Royale Asturienne des At the beginning of 1975, with a view to Mines carrying out such parallel imports, 42 Avenue Gabriel Schütz ordered rolled sheets from F-Paris Cedex 08; CRAM. CRAM refused to supply them on the ground that, although the 2. As regards Articles 1, 2 and 3: dimensions requested were widely sold in Rheinisches Zinkwalzwerk GmbH & Germany and France, there was no Co. demand for them in Belgium. Sub­ Bahnhofstraße 90 sequently, Schütz tried to obtain the D-4354 Datteln; same sheet metal by informing CRAM that it was intended for re-export to 3. ... Egypt. On that express condition, CRAM agreed to supply the goods 4. ... requested and quoted Schütz a price even lower than that offered in Belgium.. 5. ...

(· · • ) • " Schütz was thus able, between February and October 1976, to secure a com­ mitment from CRAM that it would 4. The facts on which the contested supply a total of almost 2 000 tonnes of decision is based rolled products. CRAM, for its part, attached importance to strict compliance A — The measures to protect markets with the condition concerning export to Egypt. In that regard, the contested During the period from 1974 to 1977, decision refers to certain invoices the prices of zinc on the French and endorsed "destination Egypt". Further-

CRAM AND RHEINZINK / COMMISSION

more, in various items of corres­ products ordered from CRAM and RZ pondence, Schütz was reminded of its were stored at the port of Antwerp, only undertaking and asked to prove that it was to be loaded shortly afterwards on to being complied with by sending the rel­ lorries bound for Germany. So that the evant documents. change of destination could not be discovered by examination of the foreign trade statistics, Schütz declared the goods to the customs authorities as "double galvanized sheet metal". From April to October 1976, Schütz used the same stratagem vis-à-vis RZ. Again under the pretext of exporting to the Middle East and in particular to Egypt, Schütz ordered a total of 1 252 tonnes of rolled zinc products from RZ. This system of parallel imports came to an end in October 1976. Those orders were fulfilled by RZ at the prices then charged by that firm for its sales in Belgium, which were, at least initially, 19% lower than those which it charged on the German market. The contested decision points out that Between 8 September and 11 October initially, at least, RZ delivered goods to 1976, CRAM accepted three further Schütz at prices identical to those orders from Schütz for 240 tonnes and charged at the time by CRAM for its 631 tonnes of rolled zinc intended for deliveries to Schütz. Egypt and 44 tonnes of rolled products to be re-exported to Iran. Those orders were confirmed. On 13 October 1976, CRAM started to deliver the orders at the rate of about two lorry-loads a day. As in the case of orders from CRAM, The deliveries continued until 20 RZ's supplies were granted to Schütz on October, when they were suspended the express condition that they were re­ without any explanation. At that date, 20 exported to the Middle East, and this is tonnes out of the new order for 240 confirmed by certain telex messages from tonnes of rolled products intended for RZ quoted in the contested decision. Egypt remained to be delivered. That destination was accepted by Schütz, which, for example, confirmed, by telex message of 26 October 1976, an order for 550 tonnes accompanied by the following instructions: "Delivery, one On 21 October 1976, the date on which tonne pallet free-at-port Antwerp Dock CRAM suspended its deliveries, RZ 130 at the premises of our charterer accused Schütz of not having observed 'United Stevedoring'. Ask for 'John'. the condition relating to export to Egypt. Each pallet must be marked 'Genoa- RZ made its last delivery to Schütz on Alex'. Destination: via Genoa to 28 October 1976. Following visits made Alexandria and Iran". by two of its employees on 27 October to Schütz and on 29 October to Kestermann, RZ considered that it had proof that its rolled products were being re-imported into Germany. On 29 However, instead of being loaded on to October 1976, therefore, it decided to ships bound for the Middle East, the cease dealing with outstanding orders.

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

At that time, CRAM and RZ were main­ 8 September 1976. We confirm our taining regular contact in connection telephone conversation of 8 No­ with their trading policies and, in vember 1976 when we pointed out particular, their prices, as can be seen that, according to our agents in from the telex that RZ sent to CRAM on Germany, the rolled zinc products 26 October 1976: we supplied to you for export to Egypt have been sold in whole or in part on the German market. In view "Change in prices of zinc semi-finished of the special rates we quoted you for export to the Middle East, we products in Germany feel this is a breach of good faith which justifies the above demands. As a result of exchange rate trends and the resulting fall in raw material prices, 3. Not until points 1 and 2 have been the domestic German price of zinc in settled will we discuss with you the strip and sheet form has dropped from question of the deliveries concerning DM 318.20/100 kg to DM 307.90/100 the 631 tonnes for Egypt plus 44 kg with effect from 26 October 1976. tonnes for Iran . . ."

Basic gage: 0.70 mm. In its Decision of 14 December 1982, the Commission deduced, from all of the facts set out above, the existence of a This price applies to quantities of at least concerted practice, in 1976, between five tonnes carriage paid. The current CRAM and RZ, the main purpose of price differentiation according to dif­ which was to protect the German market ferent gages remains unchanged. in respect of sales of the products in question. In its legal assessment of the facts, it points out that it was during the This is for your information. same brief period from 21 October 1976 (cessation of deliveries by CRAM) to 29 October 1976 (cessation of deliveries by RZ) that CRAM and RZ exerted Signed: MFG, Meyer, Rheinzink, pressure on Schütz in order to induce it Datteln." to cease its exports to the Federal Republic of Germany.

On Monday 8 November 1976, CRAM telephoned Schütz, accusing it of having The Commission then refers to the telex diverted to Germany all or part of of 26 October 1976 in which RZ the goods intended for Egypt. On 12 informed CRAM of its reduction in November, CRAM called upon Schütz prices of about 3 % on the German by telex to settle eleven outstanding market; that notification was devoid of invoices for October. That telex also purpose as between competitors other included the following message : than as part of a concerted effort to combat together parallel exports to that market. Finally, the Commission states " 2 . You will have to furnish proof that that it is significant that CRAM awaited the 240 tonnes have been exported the outcome of the inquiries conducted to Egypt, as you promised in your by RZ in regard to Schütz and orders of 7 September 1976 and Kestermann before demanding from

CRAM AND RHEINZINK / COMMISSION

Schütz, on 8 November 1976, payment The contract was valid until 31 De­ of the sums which were owed to it. It cember 1976 and was to be renewed for concludes that, in those conditions, successive periods of one calendar year concerted action cannot be doubted. unless terminated in writing at least .six months before the end of a calendar year by one or two contracting parties. At the B — The reciprocal assistance contract end of 1979, none of the three under­ between CRAM, R2 and Vieille takings had availed itself of its right to Montagne (hereinafter referred to terminate the agreement. as " VM ")

According to the contested decision, On 5 August 1974, CRAM, RZ and VM since the contract entered into force, it. concluded a contract whereby they has been applied during the following undertook to supply each other with periods and in the following circum­ rolled zinc products in the event of stances: serious disruption resulting in the significant loss of production at any one of their factories, for whatever reason. (a) From April to June 1977, by tie Assistance was to be forthcoming as soon delivery by CRAM to VM, following as the production shortfall of the under­ stoppage due to a strike at the taking availing itself of the agreement latter's plant, of 2 427 tonnes of exceeded 20 tonnes per day, or a total of rolled zinc products; 200 tonnes. The procedure was as follows: (b) From May to August 1977, again because of the strike, by the delivery "Article 4.2: Each contracting party by RZ of 850 tonnes of rolled zinc undertakes to effect delivery of not more products to VM's German subsidi­ than 1 500 tonnes on condition, how­ ary; ever, that its own production is not disrupted. Where only one contracting party suffers a loss of production, it may (c) In 1977, by the delivery by RZ to only require that the shortfall be made CRAM, following technical problems up equally by the other two contracting with the latter's slitting line, of 550 parties . . . tonnes of rolled products under an "open-ended" contract for a total of 750 tonnes. These deliveries were stopped as soon as the defective Article 4.3: Where two contracting machinery was again working parties are affected simultaneously by a properly. total loss of production, the third contracting party undertakes to supply not more than 2 000 tonnes per month to make up for the quantities lost and to According to the Commission, the divide that amount equally between the aforementioned contract is an infringe­ two contracting parties concerned, unless ment of Article 85 of the Treaty, because one of them asks for a smaller quantity. a contract of such general scope and In the event of a partial loss of of such long duration institutionalizes production by one or both contracting mutual aid in lieu of competition and is parties, the supplier shall determine the thus likely to prevent any change in the quotas corresponding to the losses in respective positions on the market in question .. ." question.

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND -30/83

5. Procedure JI — Conclusions of the parties

A — In Case 29/83 By application lodged at the Court Registry on 23 February 1983, CRAM The applicant claims that the Court instituted proceedings against the should: Commission's Decision of 14 December 1. Declare void Article 1 (1) of the 1982, seeking a declaration that Article 1 Commission Decision of 14 December (1) of the said decision is void. By an 1982; application registered at the Court on 25 February 1983, Rheinzink instituted 2. Declare void or, at the very least, proceedings against the above-mentioned reduce the fine imposed on the decision in so far as it was concerned by applicant by Article 2 (1) of the said it. decision; 3. Order the Commission to pay the The written procedure followed its costs. normal course in both cases. However, in Case 29/83 the applicant waived its The Commission of the European right to reply. Communities, the defendant, contends that the Court should: By order of 23 November 1983 the 1. Dismiss the application as unfounded; Court assigned both cases to the Fourth Chamber, pursuant to Article 95 (1) of 2. Order the applicant to pay the costs. the Rules of Procedure. B — In Case 30/83 Upon hearing the report of the Judge- Rapporteur and the views of the The applicant claims that the Court Advocate General the Court decided to should: open the oral procedure without any 1. Declare void Articles 1, 2, 3, 6 and 7 preparatory inquiry. However, it re­ of the Commission Decision of 14 quested the Commission to reply in writing to the following question: December 1982, which concern the company RZ ;

"Would the Commission submit any 2. Order the Commission to pay the evidence which will enable the Court to costs. assess the possibility of concerted action having been taken by Rheinzink and the The Commission of the European Compagnie Royale Asturienne des Mines Communities, the defendant, contends with regard to the level of prices charged that the Court should: by those two undertakings for sales in 1. Dismiss the application; respectively France and the Federal Republic of Germany, such as might 2. Order the applicant to pay the costs. explain the inclusion of the condition regarding export in the contracts Ill — Submissions and argu­ concluded by those two undertakings ments of the parties with Schütz?" 1. The liability of Rheinzink for the By order of 30 November 1983 the behaviour of its predecessor Court (Fourth Chamber) joined the two cases for the purposes of the oral The first submission — concerning a procedure and judgment. preliminary issue —• made by Rheinzink,

CRAM AND RHEINZINK / COMMISSION

the applicant in Case 30/83, is that the the absence of formal legal succession, acts described by the Commission in its be held liable where the operation in decision of 14 December 1982 were question involves economic succession committed by its predecessor, the (Joined Cases 40 to 48, 50, 54 to 56, company RZ. The applicant considers 111, 113 and 114/73, Suiker Unie and that, as it became the successor to RZ on Others v Commission of the European 1 October 1981, that is to say, before the Communities, cited above). The Com­ notification of the said decision, it is mission adds, in its rejoinder, that only liable for the obligations of RZ the applicant is putting forward an which arose during that company's erroneous interpretation of the above- existence. If the Commission had mentioned judgment. The Suiker Unie imposed the fine at a date when RZ still case concerned two distinct companies existed, the applicant would certainly be which had coexisted for a certain period liable as its successor. That is not so in of time. There being no legal succession, the present case. Consequently, the an additional element was considered applicant cannot be sued on a debt necessaiy for the acts of one company incurred in respect of a fine subsequent to be imputed to the other, namely to the legal transformation. It adds, in its continuity between the companies con­ reply, that an undertaking which carries cerned. In the present case, the applicant on the commercial activity of its prede­ lias continued the commercial activity of cessor cannot have the latter's behaviour its predecessor without any modification. imputed to it. No such principle of law Under those circumstances there can be exists. In that connection, the applicant no doubt that Rheinzink is liable for the refers to the judgment of the Court of 16 infringements committed by RZ. December 1975 (Joined Cases 40 to 48, 50, 54 to 56, 111, 113 and 114/73, Suiker Unie and Others v Commission of the European Communities, [1975] ECR 1663, particularly at p. 1950 et seq.), in which it was held that the successor is 2. The infringement of procedural rules only liable for the behaviour of its pre­ decessor where there is "obvious continuity". In the present case, there is no such continuity. In its second submission, again on a pre­ liminary issue, Rheinzink, the applicant in Case 30/83, claims that its right to a fair hearing has been infringed by the Commission inasmuch as the latter did In its defence, the Commission of the not allow it to examine, during the European Comnumities, the defendant, administrative procedure, all the docu­ maintains that the acts committed by RZ ments on which the contested decision are imputable to the applicant, because was based. the two undertakings are, in competition law, two successive legal forms of one and the same undertaking. RZ has simply changed its name and its legal form, while its objects, its registered The applicant states that it did not have office and its management have knowledge of all the documents relating remained unchanged. According to the to the delivery agreements between Commission, the Court has accepted the CRAM and Schlitz even though principle that the successor may, even in CRAM's attitude is being invoked

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

against RZ. After notification of the arguments which can be summarized as contested decision, it asked the follows. Commission to allow it to consult all the supporting documents which the Commission had used. The Commission only allowed it to consult the documents submitted by RZ itself and the (a) The arguments of CRAM correspondence between RZ and the Commission. All these documents were already known to the applicant. The Commission should have given it the (A) The Commission was wrong to opportunity to consult and evaluate the consider that CRAM had stopped documents which it had obtained from deliveries to Schütz on 20 October 1976 third parties. without any explanation. In fact, deliveries were interrupted at that date quite simply because the order to which they related, namely the order for The defendant replies that this submission 240 tonnes of rolled zinc products, had is manifestly unfounded. As far as been entirely fulfilled. Consequently, 20 CRAM's conduct is concerned, the facts tonnes of rolled products did not remain on which the contested decision was to be delivered on 20 October 1976, as based were the cessation of deliveries by the Commission claims in its decision. CRAM to Schütz on 21 October 1976 Thus, the cessation of deliveries on the and the pressure put on Schütz by above-mentioned date was in no way CRAM, such as, in particular, the telex abnormal. message from CRAM to Schütz on 12 November 1976, calling upon the latter to cease its exports to the Federal Republic of Germany. The Commission points out that those facts were (B) The Commission was wrong to communicated to the applicant in the suggest, in the contested decision, that statement of objections. It adds that there was some connection between the neither the cessation of deliveries by cessation of CRAM's deliveries to Schütz CRAM nor the contents of the on 20 October 1976, on the one hand, aforementioned telex communication and the complaint made to Schütz by RZ have been contested by the applicant. on 21 October 1976 that the former had failed to observe the clause concerning exportation to Egypt, on the other. According to CRAM, there was no relationship between those two events. Furthermore, the Commission has not 3. Concerted action between CRAM and proved that CRAM knew of the RZ complaint made by RZ to Schütz.

In this context, the two applicant under­ takings make one and the same (C) RZ's telex communication to submission: the Commission has not CRAM on 26 October 1976 in no way produced proof of concerted action constitutes proof of concerted action between them relating to the protection between the two undertakings. A brief of the German market. In support of this examination of the text of the said telex submission, they put forward several message · will demonstrate that it had

CRAM AND RHEINZINK / COMMISSION

nothing to do with the behaviour of According to CRAM, the observations CRAM towards Schütz. set out above demonstrate that its behaviour towards Schütz had nothing to do with concerted action with.RZ. What is more, examination of the "various signs" relied upon by the Commission in support of its complaint of concerted action shows that they do not support that complaint. (D) The Commission was wrong in considering that CRAM· awaited the outcome of the inquiries conducted by RZ in regard to Schütz and Kestermann before demanding from Schütz, on 8 November 1976, payment of the sums which were owed to it. In fact, on 14 October 1976, CRAM had sent a telex communication to Schütz demanding, (b) The arguments of Rheinzink inter alia, payment of six outstanding invoices for September 1976. Schütz responded to that telex message by promising to pay the invoices before the end of October 1976. However, on 31 October 1976, CRAM found that three of the six invoices were still outstanding. Consequently, it sent Schütz another telex message, on 2 November, de­ (A) If CRAM's.cessation of deliveries manding payment of the sums due. What to Schütz on 21 October 1976 was due is more, Schütz also showed itself to be to concerted action with RZ, as the unable to meet invoices relating to Commission claims in its decision, it is deliveries made between 13 and 20 hard to understand why RZ did not October 1976 which were due for immediately stop deliveries to Schütz payment at the beginning of November instead of waiting until 29 October 1976. 1976. With regard to those, it proposed In fact, on 26 October, RZ had received to CRAM, by telex message of 9 No­ and confirmed another order made by vember 1976, that it would pay one half Schütz. The same day RZ gave instruc­ by means of a draft and the other by tions to fulfil that order, worth about means of an irrevocable credit, on DM 250 000. If RZ had known of condition in both cases that CRAM fulfil Schiltz's operations from 21 October, it the two other orders of 11 October would have had every interest in 1976. It was in response to that message blocking all deliveries to Schütz. that CRAM, on 12 November 1976, formally requested Schütz to pay the eleven outstanding invoices for October without further delay. The Commission's view that there is some connection between the inquiries carried out by RZ in regard to Schütz and Kestermann on 27 and 29 October 1976 and CRAM's formal request for payment on 12 November 1976 is thus without foun­ (B) RZ's telex message to CRAM on dation. 26 October 1976 had no connection with

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

CRAM's cessation of deliveries to the European Communities, cited above, Schütz. The Commission was not able to or judgment of 14 July 1981, Case establish any link between those two 172/80, Züchner v Bayerische Vereins- events. Even if the communication had bank AG, [1981] ECR 2021). As regards no meaning "other than as part of a contact between CRAM and RZ, the concerted effort to combat together Commission has only proved the parallel exports" to the German market, existence of the telex message of 26 as the Commission puts it, that is not October 1976, which bears no relation to enough to establish a plausible con­ its behaviour towards Schütz. nection with the behaviour towards Schütz. In that connection, the applicant draws attention once again to the fact that RZ had, on that very day, given instructions for a large order from Schütz to be fulfilled. The result of all these considerations is that RZ did not take part in a concerted practice contrary to Article 85 (1) of the Treaty.

(C) RZ stopped deliveries to Schütz because the latter had deceived it and because the re-export of goods to the Federal Republic of Germany was likely (c) The Commission's defence to damage it. The behaviour of RZ could thus, without difficulty, be explained solely by reference to its own interest. CRAM's cessation of deliveries on 21 October 1976 played no role in this context. In its reply to CRAM's observations, the Commission of the European Communities, the defendant in both cases, observes first of all that, in its decision, it assumed incorrectly that on 20 October 1976, the date of CRAM's last delivery to Schütz, there remained undelivered 20 (D) The contested decision is based on tonnes of rolled products from the order the idea that a concerted practice Ís for 240 tonnes of 8 September 1976. proved by the simple fact that two under­ CRAM has proved, in its application, takings react in the same way to the that in reality, with the delivery of same events. According to the applicant, 20 October 1976, all of that order had this approach does not conform to the been delivered. However, that is only Court's case-law, which requires, to a mistake of detail. CRAM has not prove a concerted practice, "coordi­ contested that, by 20 October 1976, it nation", "practical cooperation" know­ had accepted the other two orders from ingly substituted for the risks of Schütz, namely an order for 631 tonnes competition and "contact" between the for Egypt and an order of 44 tonnes for undertakings (see, for example, judgment Iran, to be delivered before the end of of 16 December 1975, Joined Cases 40 November 1976. Those two orders were to 48, 50, 54 to 56, 111, 113 and 114/73, never fulfilled. As regards CRAM's Suiker Unie and Others v Commission of cessation of deliveries on 20 October

CRAM AND RHEINZINK / COMMISSION

1976, the contested decision, according that CRAM awaited the outcome of the to the Commission, retains its sig­ inquiries conducted by R2 in regard nificance. Even if the order for 240 to Schütz and Kestermann before tonnes had been entirely fulfilled, there demanding from Schütz, on 8 November were still 675 tonnes of rolled products 1976, payment of the sums which were to be delivered. The Commission adds owed to it was incorrect. The Com­ that the mistake in question was already mission adds, however, that this passage contained in the statement of objections of the decision still holds good. The and that CRAM did not point it out decision merely sought, on this point, either in its written reply or in the course to refute CRAM's explanation of its of the hearing. cessation of deliveries, which was based on the question of outstanding invoices. In this connection, CRAM's statement is not convincing, because it ignores the fact that, even after the invoices had been paid, Schiltz's two other orders of October 1976 were not fulfilled. Further­ As regards RZ's telex message to CRAM more, CRAM's telex message to Schütz on 26 October 1976, the Commission of 12 November 1976 disclosed the real emphasizes that this is one of several reason, which was the failure to observe factors which allowed it to conclude that the clause concerning exportation to a concerted practice existed between the Egypt. The attempt to explain the two undertakings. It was the totality of cessation of deliveries by reference to the those factors, and not each one taken in invoice problem was thus doomed to isolation, which allowed that conclusion failure. to be reached. The Commission adds that the telex message of 26 October 1976 is interesting not only because of its contents, but also because of the confused replies which the two under­ takings provided at the hearing, when invited to explain it. The transcript of the hearing shows that R2 claimed that In the light of the above observations, exchanges of price information between the Commission continues to argue that, producers were not unusual in this in 1976, concerted action was taken by industry. CRAM, for its part, obvserved CRAM and RZ with a view to protecting that, in the Federal Republic of Ger­ the German market against parallel many, such exchanges, without being imports of rolled products being made by unusual, were rather rare. Schütz.

Finally, the Commission points out that In its answer to Rbeinzink's statement, the it was unaware of CRAM's telex Commission points out that the applicant messages to Schütz of 14 October and does not contest the allegations made 2 November 1976 demanding payment about its behaviour towards Schütz. of outstanding invoices. In the light of Furthermore, it once again points out this new information, it recognizes that that the behaviour of RZ and that of the statement, in the contested decision, CRAM and the contents of the telex

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

message of 26 October 1976 can be delivered to Schütz was not part of the explained only when seen against the obligations which RZ imposed, by background of concerted action between contract, on Schütz. That condition was the two undertakings of the kind in fact formulated on its own initiative to indicated in the decision. obtain delivery of the goods in question at more favourable export prices. The applicant adds that RZ delivered at parti­ cularly low prices because Schütz gave it false information. If RZ had known from In its reply, Rheihzink, the applicant in the start that Schütz would re-export Case 30/83, answers that the only proof the goods to the Federal Republic of the Commission has of concerted action Germany, it would certainly have is the telex message of 26 October 1976. demanded the German market price. However, the defendant has not proved any connection between that telex message and the alleged concerted action to protect the German market. (B) There is thus no question of an agreement whose object or effect is to restrict competition. Restriction of com­ In its rejoinder, the Commission, the petition is the object of an agreement defendant in both cases, reiterates that RZ only when the two contracting parties and CRAM put pressure on Schütz from have decided upon such an object. That 21 October 1979 to discontinue its is not so in the present case. exports to the Federal Republic of Furthermore, the agreements concluded Germany. It is clear that RZ and CRAM with Schütz did not have the effect of reacted in a concerted manner from the restricting competition, since Schütz fact that the cessation of deliveries exported all the goods it bought from coincided with RZ's communication to RZ to Germany. CRAM concerning the increase in its selling prices in Germany.

(C) Even if, by indicating the country of destination, an agreement invariably restricts competition, the disputed 4. The agreement between RZ and Schütz agreement did not have an appreciable effect either on competition or on trade between the Member States.

Rheinzink maintains that the agreement concluded between RZ and Schütz in 1976 does not infringe Article 85 of the In its defence, the Commission observes Treaty. In support of that submission, it first of all that the applicant wrongly relies on three arguments which can be claims that Schütz was free to sell the summarized as follows. rolled zinc products which had been supplied to it by RZ in any country. In fact, there was a consensus between the two parties to the effect that Schütz (A) The export to a non-member would export the goods to a non- country of the rolled zinc products member country. That consensus

CRAM AND RHEINZINK / COMMISSION

emerges clearly from the text of the the disputed agreement, the attitude of declarations of offer and acceptance Schütz, which never intended to observe which are attached to the application. the agreement, is certainly pertinent in the present case. According to the Court's case-law, it must be clear that The Commission then states that the even the party subject to the competitive object of an agreement must be restriction actually had that restriction in determined by reference to the aims mind (see, for example, the judgment of objectively pursued by that agreement as the Court of 29 October 1980 in Joined they appear to an observer, in the light Cases 209 to 215 and 218/78, van of the economic context in which the Landewijck v Commission, [1980] ECR agreement must be applied. In the 3125). That was never so in the present present case, the objective aim of the case. agreement in dispute was to compel Schütz to sell the rolled zinc products outside the European Community and more particularly in Egypt and Iran. In its rejoinder, the Commission replies There is thus no need to consider that it is in flat contradiction of the whether the agreement did or did not general principles of civil law to have the effect of restricting competition. consider, as the applicant does, that the intention of one of the parties to a contract can determine its purpose. Furthermore, the application of Article Finally, the Commission contests the 85 of the Treaty to deliberate restrictions view that the agreement made with on competition would, if the applicant's Schütz had no appreciable effect either view was accepted, be subject to sub­ on competition or on trade between the jective considerations arising from the Member States. It points out first of all decision-making process within the that the circumstances which constitute a undertaking, a situation which by its very disruption of trade between the Member nature would exclude any form of veri­ States do not include a requirement that fication. there should actually be an appreciable effect. It is sufficient if an agreement is of such a nature as to be likely appreciably to affect such trade (see, for example, the judgment of the Court of 5. The reciprocal assistance contract be- 1 February 1978, Case 19/77, Miller v tween CRAM, RZ and VM Commission, [1978] ECR 131). It points out in this connection that, if the agreement in question had not existed, the applicant would not have been able Finally, the applicant complains that the to sell rolled products at low prices Commission has wrongly considered the to buyers outside the Federal Republic reciprocal assistance contract of 5 August of Germany without undermining the 1974 to be a restriction on competition higher price level in its home market. It within the meaning of Article 85 (1) of is thus legitimate to think that trade the Treaty. In support of that view, it between the Member States would have puts forward three arguments which can developed differently were it not for the be summarized as follows. disputed agreement.

(A) The applicant observes first of all In its reply, Rheinzink claims that, for that the contracting parties simply the purpose of determining the object of wanted to reduce the risk of not being

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

able to supply customers that they were assistance in such an event is quite obliged to supply. The contract in permissible. question was thus the basis of certain occasional deliveries by one party to another. It was a question of normal deliveries which, in the words of the The Commission's defence Court, did not have "as such the object or effect of interfering with competition" (judgment of the Court of 25 November The Commission emphasizes first of all 1971 in Case 22 / 71 , Béguelin Import v that the contract at issue obliges the G. L. Import Export, [1971] ECR 949). parties to reserve for each other part of Certainly, when a party to the contract is their production capacity. Such an obliged to deliver certain quantities to obligation does not in itself give rise to a another party in the event of the dis­ trading transaction. It does, however, ruption of the latter's production, it limit the freedom of the party subject to cannot deliver the same quantities to the obligation to make use itself of its third parties. Such an effect is, however, production capacity. That limitation on the normal consequence of every the parties' freedom of action has an contract of delivery. Furthermore, the appreciable effect on the position of contracting parties limited the scope of third parties in the market in question. the disputed contract to circumstances The Commission adds that, in the over which they had no control. The present case, the agreed upper limits object of that restriction was specifically represent more than one-third of the to preserve their freedom of decision as capacity of each of the three contracting regards the quantities to be delivered parties. Consequently, the disputed to their regular domestic or foreign contract has the object and effect of customers. It was not in any way a restricting competition within the restriction on the free play of com­ meaning of Article 85 (1) of the Treaty. petition.

The Commission then observes that the (B) Even if the contract at issue was question whether the restriction on capable of producing the effects competition is appreciable is not to be attributed to it by the Commission, it has resolved, as the applicant claims, by not caused appreciable damage either to reference to the number and size of the competition or to trade between Member deliveries actually made between the States. In fact, the Commission itself parties to the contract. The decisive could only find three periods, in 1977, factor is rather the latent unavailability during which deliveries took place on the of the production capacity for other uses. basis of the contract. Moreover, those It is the potential importance of the deliveries were of limited size. disputed contract which is decisive for the purposes of Article 85 of the Treaty.

(C) Furthermore, among the disrup­ Finally, the Commission claims that the tions noted by the Commission, two applicant has mistakenly described the were due to strikes. The contract at issue disputed contract as an agreement to is thus, to a large extent, an agreement provide assistance in the event of a to provide assistance in the event of a strike. The object of the contract is, strike. An obligation to provide mutual according to Clause 1, a reciprocal ob-

CRAM AND RHEINZINK / COMMISSION

ligation to provide emergency supplies in undertaking's turnover and less than the case of "technical or other disrup­ 0.015% of the turnover of the inter­ tion". It applies therefore to any disrup­ national group, Metallgesellschaft, of tion forming part of the risks attached which RZ was part at the time. The to the activity of the undertaking con­ Commission has thus taken account, in cerned. spite of the seriousness of the offence involved, of the short period during which the offence was committed. The fine imposed on RZ was 25 % higher 6. The amount of the fines than that imposed on CRAM because RZ was part of the Metallgesellschaft group, whose total turnover, which was more than DM 10 000 million in the CRAM maintains that, since the financial year 1980/81, is greater than complaint of concerted action is un­ CRAM's. Finally, the Commission states founded, the fine should be declared that the contested decision is based on a void. In the alternative, it requests a finding of deliberate behaviour by RZ in sizeable reduction in the fine imposed its concerted action with CRAM. because of the serious difficulties that the zinc industry in general and the applicant in particular is undergoing. CRAM adds that the amount of the fine is dispro- In its reply, Rheinzink observes again portinate to the length of the alleged that, when it was notified of the concerted action, which only took place contested decision, RZ was no longer a from 21 to 29 October 1976. The member of the Metallgesellschaft group. amount of the fine is therefore Its membership of the group could manifestly excessive. therefore play no role in fixing the fine.

Rheinzink takes the same view on this In its rejoinder, the Commission replies point, adding that the Commission has that RZ was a member of the Metall­ not even stated whether R2 acted gesellschaft group at the time when the deliberately or merely by negligence. facts at issue took place and that that Furthermore, it observes that Schiltz's was the material time for the purpose of behaviour is a mitigating circumstance fixing the fine. which justifies a reduction of the fine imposed.

IV — Oral procedure As regards CRAM, the Commission replies that the fine is less than 0.5% of the total turnover of that undertaking. Such a fine cannot be considered excessive, given the seriousness of the The parties presented oral argument at offence. the sitting on 14 December 1983.

As regards Rheinzink, the Commission The Advocate General delivered her observes first of all that the amount of opinion at the sitting on 1 February the fine represents less than 1.5% of that 1984.

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

Decision

1 By applications lodged at the Court Registry on respectively 23 and 25 February 1983, the Compagnie Royale Asturienne des Mines, SA, whose registered office is in Paris, and the company Rheinzink GmbH, whose registered office is in Datteln (Federal Republic of Germany), brought actions, pursuant to the second paragraph of Article 173 of the EEC Treaty, seeking a declaration that the Commission Decision of 14 December 1982 relating to a proceeding under Article 85 of the EEC Treaty (IV/29.629 — Rolled zinc products and zinc alloys), which was notified to the applicants and published in the Official Journal (L 362, p. 40), is partially void.

2 The first applicant (hereinafter referred to as Asturienne) requests that Article 1 (1) and Article 2 of the contested decision be declared void. The second applicant (hereinafter referred to as "Rheinzink") requests that Article 1 (1) and (2), Article 2 and Article 3 of the decision be declared void.

3 Article 1 (1) of the decision states that the concerted action taken in 1976 by Asturienne and Rheinzink with a view to protecting the German market against parallel imports of rolled products effected by Gebr. Schütz NV of Aartselaar, Belgium (hereinafter referred to as "Schütz"), constitutes an infringement of Article 85 of the Treaty. Article 2 of the decision imposes fines on the two undertakings "for their involvement in the infringement referred to in Article 1 (1)".

4 Article 1 (2) of the decision states that the agreements concluded in 1976 between Asturienne and Schütz, on the one hand, and between Rheinzink and Schütz, on the other, requiring the latter to resell rolled zinc products in a specific country had as its object the restriction of parallel imports into the Community and therefore constituted an infringement of Article 85 of the Treaty.

5 According to Article 3 of the decision, the reciprocal assitance contract concluded on 5 August 1974 between Asturienne, Rheinzink and the Société des Mines et Fonderies de Zinc de la Vieille Montagne SA, whose registered office is in Angleur (Belgium), also constitutes an infringement of Article 85 of the Treaty.

CRAM AND RHEINZINK / COMMISSION

6 Before examining the submissions contesting the existence of the alleged infringements, the preliminary submission raised by Rheinzink must be considered. According to that submission, Rheinzink is not in any event liable for the infringements found by the Commission, because these may be imputed only to the company Rheinisches Zinkwalzwerk GmbH & Co., which was dissolved in 1981, that is to say, between the dates on which the alleged behaviour took place and the moment when the Commission adopted the contested decision. Rheinzink points out that the decision refers exclusively to the company Rheinisches Zinkwalzwerk GmbH & Co.

7 Rheinzink admits that it is the sole legal successor of the dissolved company, the latter having been transformed into a limited liability company under the name Rheinzink. It refers, however, to Article 15 (2) of Regulation No 17, which allows the Commission to impose fines only on those undertakings which have committed infringements of Article 85 of the Treaty, in support of the view that the legal succession which took place could not make Rheinzink liable for the acts of another company which in the meantime had ceased to exist.

s The Commission contends that, for the purposes of competition law, Rheinzink and Rheinisches Zinkwalzwerk GmbH & Co. are two successive legal forms of one and the same undertaking. The subjects of competition law are undertakings. The undertaking in question changed its name and its legal form at the moment of the transformation, but its objects, registered office and management remained unchanged. Consequently, the acts committed by the dissolved company may be imputed to Rheinzink as the sole legal successor of that company.

9 The Commission's argument must be accepted. Rheinzink has not contested that not only is it the legal successor of Rheinisches Zinkwalzwerk GmbH & Co., but it has continued the economic activities of that company. For the purposes of Article 85 of the Treaty, a change in the legal form and name of an undertaking does not create a new undertaking free of liability for the anti-competitive behaviour of its predecessor, when, from an economic point of view, the two are identical.

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

A — The concerted action

io The concerted action taken by Asturienne and Rheinzink which is the subject of Article 1 (1) of the contested decision must, according to the preamble to the decision, be seen against the background of measures taken to protect markets by certain major producers of rolled zinc products. Those measures were prompted by the fact that, at that time, the prices charged by those producers for rolled zinc products were higher in Germany and in France than in certain other Member States, in particular Belgium, and in many non-member countries. Those price differences, which were sometimes considerable, favoured the activity of importers who bought rolled zinc products in a country where prices were low in order to resell them in a country where prices were higher, in particular in the Federal Republic of Germany. The concerted action taken by Asturienne and Rheinzink was designed to prevent such parallel imports.

11 The two applicants maintain that the Commission has not proved that they took concerted action with a view to the protection of the German market. They consider that the Commission based its decision on a number of factors; however, those factors were insufficient to make out the complaint of a concerted practice set out by the Commission and, what is more, the Commission disregarded other factors unfavourable to its case.

i2 It is not disputed that during 1976 Asturienne and Rheinzink delivered large quantities of rolled zinc products to Schütz, in Belgium, for sale in Egypt, at prices close to those charged for sales intended for the Belgian market. The rolled zinc products sent to Belgium were relabelled by Schütz and then loaded on to lorries bound for Germany, where they were resold at prices lower than those normally charged in that country.

n It is also agreed that this practice continued until the end of October 1976, that two employees of Rheinzink discovered, at that time, that the products delivered to Schütz were being re-exported to Germany, and that both

CRAM AND RHEINZINK. / COMMISSION

Rheinzink and Asturienne discontinued their deliveries to Schütz between 21 and 29 October 1976.

H According to the contested decision, the cessation of deliveries to Schütz by the two undertakings could not be explained other than by an exchange of information between them with a view to taking parallel action against Schütz as part of a concerted practice protecting the level of prices on the German market, in particular by preventing parallel imports or the reintroduction of rolled zinc products originating in Germany.

is In arriving at that conclusion, the decision relies on the following factors :

On 21 October 1976, the date on which Asturienne suspended its deliveries to Schütz "for no apparent reason", Rheinzink accused Schütz of not complying with the clause concerning exportation to Egypt. The Commission maintains that it cannot be regarded as a coincidence that those events occurred on the same date.

On 26 October 1976, Rheinzink informed Asturienne by telex message that it intended to reduce its prices on the German market by about 3 %, a communication which would have been "devoid of purpose as between competitors other than as part of a concerted effort to combat together parallel exports to that market";

On 29 October 1976, Rheinzink discontinued its deliveries to Schütz after attempting unsuccessfully to induce the latter to put an end to its exports to the Federal Republic of Germany;

Not until 8 November 1976, that is to say, after the Rheinzink employees had completed their inqiuries in regard to Schütz and its German buyer, did Asturienne demand payment from Schütz of the sums which were still owed to it.

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

i6 The Commission's reasoning is based on the supposition that the facts established cannot be explained other than by concerted action by the two undertakings. Faced with such an argument, it is sufficient for the applicants to prove circumstances which cast the facts established by the Commission in a different light and which thus allow another explanation of the facts to be substituted for the one adopted by the contested decision.

i7 The applicants have in fact proved the existence of such circumstances. The Commission was obliged to admit that, contrary to the findings in the decision, Asturienne had completely fulfilled an order from Schütz for 240 tonnes of rolled zinc products at the time when it ceased deliveries to it on 21 October 1976. Asturienne has also proved, by producing invoices and telex messages, that it had already had difficulties with Schütz regarding the payment of certain invoices relating to deliveries made in September, that it had demanded payment of those invoices by telex communications of 14 October and 2 November, and that problems of the same kind had arisen over payment of the invoices relating to the 240 tonnes delivered in October, as can be seen from a telex communication of 12 November.

is In those circumstances, the cessation of deliveries to Schütz by Asturienne, and the moment at which that cessation tock place, can be explained by considerations arising from the financial relations between Asturienne and Schütz.

i9 The fact that on 26 October 1976 Rheinzink sent a telex communication to Asturienne concerning the reduction of prices on the German market does not, in itself, constitute evidence establishing the existence of a concerted practice, not least because the Commission has not proved or even alleged that this had an effect on the prices charged by Asturienne.

20 It follows from the foregoing that the Commission has not produced sufficiently precise and coherent proof to justify the view that the parallel behaviour of the two undertakings in question was the result of concerted action by them.

CRAM AND RHEINZINK / COMMISSION

21 Consequently , the applications of the two applicants must be granted on this point , and Article 1 (1) of the contested decision must be declared void.

22 Article 2 of the decision, which imposes fines on the two undertakings solely by reason of their having committed the infringements referred to in Article 1 (1) must , as a consequence , also be declared void.

23 As a result of that declaration of nullity, it is no longer necessary to examine Rheinzink's submission concerning the non-consultation of documents relating to the cessation of deliveries to Schütz by Asturienne .

B — The export clauses

24 The decision states, in its preamble , that the clause stipulating that Schütz must export to Egypt the tonnages of rolled zinc products delivered by Asturienne and Rheinzink constitutes, by its very object, a restriction on competition . That clause, according to the decision, limits the freedom of the dealer to market the goods where he wishes and allows the two producers to prevent parallel imports within the common market . It thus serves to protect the German market , which is more vulnerable because of the high level of prices.

25 Rheinzink contends that the export clauses included in the contracts between it and Schütz did not infringe Article 85 of the Treaty . It maintains first of all that the condition regarding export to a non-member country was not imposed by it but was inserted into the contracts at the initiative of Schütz , which thereby sought to obtain the goods at more favourable export prices. It goes on to claim that an agreement can have as its object the restriction of competition , within the meaning of Article 85 of the Treaty , only if the two contracting parties have together set themselves such an objective, which is manifestly not what happened in the present case.

26 Those arguments cannot be accepted. In order to determine whether an agreement has as its object the restriction of competition , it is not necessary

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

to inquire which of the two contracting parties took the initiative in inserting any particular clause or to verify that the parties had a common intent at the time when the agreement was concluded. It is rather a question of examining the aims pursued by the agreement as such, in the light of the economic context in which the agreement is to be applied.

27 In that connection, the decision — the findings of which have not been contested on this point — states that Schiltz's first order to Asturienne, made at the request of a German buyer, was for rolled sheets in dimensions common in Germany and that Asturienne objected that such dimensions, while widely sold in Germany and in France, were not in demand in Belgium. Following that incident, Schütz obtained the same sheets from Asturienne and Rheinzink by leading them to believe that the sheets were to be re-exported to the Middle East and in particular to Egypt. The prices charged by the two producers were, however, almost identical to, or very close to, those which the same producers charged for their sales intended for the Belgian market.

28 In those circumstances, the conclusion cannot be avoided that the export clauses were essentially designed to prevent the re-export of the goods to the country of production so as to maintain a system of dual prices and restrict competition within the common market.

29 Rheinzink also claims that the agreement has had no appreciable effect either on competition or on trade between the Member States.

30 It does not however contest that, as far as production of zinc sheet is concerned, there are only six rolling mills of various sizes in the common market, of which Rheinzink is the only one in the Federal Republic of Germany. In that kind of market situation, it is impossible to accept the argument that a restriction of competition consisting of the isolation of the German market would not be appreciable.

CRAM AND RHEINZINK / COMMISSION

3i Those considerations lead to the conclusion that the complaints made against Article 1 (2) of the decision must be rejected.

C — The reciprocal assistance contract

32 By a contract concluded on 5 August 1974, Asturienne, Rheinzink and Vieille Montagne undertook to supply each other with rolled zinc products in the event of serious disruption resulting in significant loss of production at any one of their factories, for whatever reason. According to the contract, the assistance was to be forthcoming as soon as the production shortfall of the undertaking suffering the disruption exceeded 20 tonnes per day, or a total of 200 tonnes. Each of the other parties undertook, in such cases, to effect delivery of not more than 15 000 tonnes on condition, however, that its own production was not disrupted. The contract provided that it was to be valid until 31 December 1976 and automatically renewed for successive periods of one calendar year, unless terminated, which has not happened.

33 According to the contested decision, the contract constitutes a restriction on competition by virtue of both its object and its effect. It deprives the parties of their independence of action, of their ability to adapt individually to circumstances and of the possibility of benefiting, by increasing direct sales to customers, from production stoppages or reductions in output sustained by the other undertakings. The contract could, moreover, compel the parties to supply each other with considerable tonnages. On the basis of those considerations, the decision concludes that a contract of such general scope and· ofjuch long duration, being automatically renewable any number of times, "institutionalizes mutual aid in lieu of competition" and is likely to "prevent any change" in the respective market positions.

34 Rheinzink does not contest the facts found by the decision on this point. It considers, however, that the Commission has made an incorrect assessment of the reasons for the contract and its practical consequences. The three undertakings simply wished to reduce the risk of not being able to supply their regular customers in exceptional circumstances likely to interfere with

JUDGMENT OF 28. 3. 1984 — JOINED CASES 29 AND 30/83

production. The practical utility of the contract became apparent in a few exceptional cases where the contract served as a basis for occasional deliveries by one undertaking to another.

35 However a reciprocal assistance contract between producer undertakings might generally be evaluated in relation to the prohibitions contained in Article 85 of the Treaty, the terms of the contract in question are so general and indefinite that they could be put into effect in a way very different from that which the parties claim to have envisaged and which the have actually adopted until now. The undertakings to provide mutual assistance do not just relate to cases of "force majeure" and comparable situations, but to all cases of "serious disruption", of whatever kind and from whatever source. It thus appears that the conditions for the application of the contract are so wide and so vague as to serve as a restriction of competition. To that consideration must be added the indeterminate duration of the contract and the fact that large quantities of rolled zinc products are involved, given the uncontested figures set out in the decision.

36 The complaints directed against the findings regarding the reciprocal assistance contract cannot therefore be upheld .

37 Consequently, the provisions of Article 1 (1) and Article 2 of the contested decision must be declared void and the remainder of Rheinzink's application must be dismissed.

Costs

38 Article 69 (2) of the Rules of Procedure provides that the unsuccessful party is to be ordered to pay the costs if they have been asked for in the successful party's pleading. However, according to the first subparagraph of Article 69 (3), where each party succeeds on some and fails on other heads, the Court may order that the parties bear their own costs in whole or in part.

39 In Case 29 / 83 the defendant , having failed in its submissions, must be ordered to pay the costs.

40 In Case 30 / 83 the parties , having each failed in some of their submissions, must bear their own costs.

CRAM AND RHEINZINK / COMMISSION

On those grounds,

THE COURT (Fourth Chamber)

hereby:

1. Declares Article 1 (1) and Article 2 of Commission Decision 82/866/EEC of 14 December 1982 relating to a proceeding under Article 85 of the EEC Treaty (IV/29.629 — Rolled zinc products and zinc alloys — Official Journal 1982, L 362, p. 40) void;

2. Dismisses the remainder of the application in Case 30/83;

3. Orders the defendant to pay the costs in Case 29/83;

4. Orders the parties to bear their own costs in Case 30/83.

Koopmans Bahlmann

Pescatore O'Keeffe Bosco

Delivered in open court in Luxembourg on 28 March 1984.

J. A. Pompe T. Koopmans Deputy Registrar President of the Fourth Chamber

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Rozsudok C-29/83 – Súdny dvor Európskej únie | AI Pravnik