← Späť na vyhľadávanie
Súdny dvor Európskej únie·22.10.1991

C-209/90

ECLI:EU:C:1991:403

Súd
Súdny dvor Európskej únie
IČS
61990CC0209

OPINION OF MR LENZ — CASE C-209/90

OPINION OF ADVOCATE GENERAL LENZ delivered on 22 O c t o b e r 1991 *

Mr President, necessary for the implementation of Members of the Court, approved projects.

A — The facts 3. Under Clause 1.1 of the contract, the contracting party undertook to carry out a project which was described as follows:

1. The parties are in dispute over a claim by the Commission under a contract originally concluded between the European Economic 'Piggery for production of heat required for Community and Felix Schulze Isfort-Ekel, a anaerobic processes using solar energy and farmer, in which the defendant later took conversion of sewage gas (biogas) into heat the place of the original party to the and electrical energy.' contract. In the Commission's opinion, the Court's jurisdiction in the present case is founded on Clause 13 of the contract, which contains the following provision: According to the timetable of works in Annex I (Table 3), the final phase of the project (bringing into operation, demon- stration, measurements programme) was to 'The contracting parties agree that the be completed by the end of 1984. Court of Justice of the European Communities shall have exclusive juris- diction over all disputes on the validity, interpretation and application of this contract.' 4. In Clauses 1.2 and 3 of the contract the Community undertook to pay the contracting party financial support, defined as 40% of the actual cost of the project, as checked and approved by the Commission, 2. The terms of the contract are based on excluding value-added tax and not Council Regulation (EEC) No 1302/78 of exceeding D M 240 000. 12 June 1978 on the granting of financial support for projects to exploit alternative energy sources, 1Article 8 of which provides inter alia that the Commission is to negotiate and conclude the contracts 5. Clause 14 of the contract states that it is governed by German law. The contract 'f Original language: German. further contains inter alia a series of 1 — OJ 1978 L 158, p. 3. detailed provisions concerning situations in

I - 2622

COMMISSION v FEILHAUER

which the contracting party must repay the view to the substitution of the party financial support in whole or in part. One of contracting with the Community, stipulates these provisions is Clause 8, which the on this point that Mr Schulze Isfort-Ekel Commission relies on in putting forward its 'assigns' to the defendant his rights and claims. That clause reads as follows: obligations under the contract 'including those relating to the financial support already paid by the Commission under this contract'.

'In the event of failure by the contracting party to comply with an obligation under this contract, the Commission may rescind this contract, if it has given notice of default 7. It is not disputed that the project which to the contracting party by registered letter was the subject of the contract was not and he has not complied with the obligation carried out. This resulted in extensive corre- in question within one month. The contract spondence between the parties, starting in may also be terminated if the contracting 1985. The Commission first — unsuc- party has made false statements in order to cessfully — requested the defendant to obtain the financial support, in so far as he repay the said amount. In a registered letter is liable for those statements. In either case of 9 December 1986, received by the the contracting party must repay to the defendant on 17 December 1986, it then Commission without delay the financial gave the defendant notice of default and support, together with interest from expiry stated that it would rescind the contract in of the said period of one month. The the event that the defendant did not within interest rate shall be that applied by the one month prove that he had land available European Investment Bank in force at the and had obtained the necessary official time of the Commission's decision to grant permits. The defendant did not produce any the financial support for the project.' of the proof required within that time-limit.

8. In subsequent correspondence — which 6. The Commission's principal claim is for again proved fruitless — the Commission repayment of a sum of DM 72 000 which repeatedly — inter alia in a letter of 16 the defendant's predecessor in title received September 1987 — called on the defendant from the Community as part of the financial to pay the said sum together with interest. support which had been agreed, and which In a letter of 8 July 1988 it stated that legal he passed on (together with interest) to the proceedings would be taken in the event of defendant after the latter took over the non-payment. It also confirmed the contract. The supplementary contract, rescission, firstly in two letters — copies of concluded between the Community, the which were sent to the defendant — of defendant and his predecessor in title with a 20 March and 31 July 1987 to the Landrat

I - 2623

OPINION OF MR LENZ — CASE C-209/90

(Chief Administrative Officer) of Kreis 11. The Commission claims that the Court Neustadt an der Aisch-Bad Windsheim, should: who had informed the Commission that the defendant now had suitable land available for the project, and then in a letter of 8 December 1988 to the defendant himself. (1) order the defendant to pay the Commission of the European Communities the sum of D M 72 000 together with interest at the rate of 6% from 24 January 1983 and at the rate of 11.9% from 18 January 1987;

9. The defendant conceded that the project had failed, but did not make repayment. In (2) order the defendant to pay the costs. a letter of 19 July 1988, he claimed the right to set-off D M 71 000, as he had made considerable purchases of materials in performance of the contract. In this respect, he referred in a later letter to the legal 12. The defendant contends that the doctrine of culpa in contrahendo and an application should be dismissed and the assurance of 30 April 1985 by the Commission ordered to pay the costs. Commission that '40% of purchases of materials would be accepted as reimbursable items'. With reference to this letter, the Commission states in its application, without 13. I will come back to further details of being contradicted by the defendant, that it the facts and arguments of the parties, if does indeed mean that the Commission necessary, as part of my analysis; otherwise intended to finance 40% of the purchases of I refer to the Report for the Hearing. materials, but that promise was subject to the condition that the materials had been purchased before 31 December 1984 and the purchases attested by invoices and proofs of payment; the defendant did not B — Analysis however produce any proof.

Part 1 — Jurisdiction of the Court of Justice

14. The defendant objected that the Court 10. The Commission also puts forward a of Justice lacked jurisdiction, first in an claim for interest under two heads: interest application for an extension of time made at 6% from the date when the amount of even before the lodging of the defence, and D M 72 000 was paid to the defendant's again later at the hearing. Under Article predecessor in title, and interest at 11.9% 42(2) of the Rules of Procedure, all pleas in from the expiry of one month after the law must be contained in the first written notice of default in the letter of pleading (in this case, the defence: see 9 December 1986. Article 40(1) of the Rules of Procedure).

I - 2624

COMMISSION v PEILHAUER

Subject to Article 42(1), they cannot be since the defendant is not registered in the introduced later unless they are based on commercial register as a trader {Kaufmann), matters of law or of fact which come to he could not validly agree on jurisdiction light in the course of the procedure. That is before the dispute arose. not the case here. The defendant bases his argument on the wording of the contract, which has remained unaltered since it was concluded.

18. This argument lacks cogency. The defendant's interpretation of Clause 14 of the contract contradicts Clause 13 of the contract, which stipulates that the Court of Justice is to have exclusive jurisdiction. In view of the Community law background of 15. Although the defendant's objection does the contract and the possibility of conferring not therefore need to be considered (either jurisdiction expressly allowed by Article 181 on the ground that it was not made in due of the EEC Treaty, it must be assumed that form or was out of time), as it is a question the parties intended to base their arbitration of jurisdiction, I consider it appropriate in clause on that article. As can be seen from this instance for the Court to dismiss the the different way it is worded, Clause 14 objection on the merits. It should apply was intended not to render that clear Article 92(2) of the Rules of Procedure and decision ineffective, but merely to determine state expressly that it has jurisdiction under the substantive law to be applied to the Article 181 of the EEC Treaty to decide on contract. Moreover, that is consistent with both the Commission's claim and the the generally recognized principle that each defendant's counterclaim. court applies its own procedural rules, including rules on jurisdiction. 2 The procedural law of the Court of Justice includes Article 181 of the EEC Treaty, but not the (corresponding) provisions in the procedural codes of individual States. Besides, Article 181 should be regarded as a special rule applying to all courts equally, 16. On this point, I would make a number taking precedence over divergent provisions of observations. of national law, and governing the particular case of the Court's jurisdiction being founded on an arbitration clause. 3 This case is therefore from the outset outside the scope of the general rules of the German Code of Civil Procedure referred to by the defendant, which consequently cannot be relied on here. The Court of 17. 1. In objecting that the Court of Justice Justice therefore has jurisdiction under lacks jurisdiction to rule on the Clause 13 of the contract combined with Commission's claims, the defendant relies on Clause 14 of the contract. The reference 2 — Krück, IN: von der Groeben/Theising/Ehlermann, in that clause to German law is understood Kommentar zum EWG-Veitrag, 4th edition, Baden-Baden, 1991, Article 181, point 18, with further references. by the defendant as including also German 3 — T h e Court also appears to have adopted this approach in procedural law, in particular the Code of Pellegrini (on Article 153 of the EAEC Treaty): see Case 23/76 Pellegrini v Commission [1976] ECR 1807, Civil Procedure. Under those provisions, paragraph 9 et seq.

I - 2625

O P I N I O N OF MR LENZ — CASE C-209/90

Article 181 of the EEC Treaty (which does from the percentage financed, 6 is directly not provide for any requirement of the type connected with the Commission's mentioned by the defendant) to give a contractual obligation to finance the decision on the claims put forward by the project). Both in this respect and also in Commission, which bases them all on respect to the principles of the German law Clause 8 of the contract (either on its own of obligations, referred to at the hearing by or in combination with supplementary the defendant (Paragraph 346 of the Bürger- provisions of German law). liches Gesetzbuch (German Civil Code) — BGB, provisions of the law on contracts of employment and contracts for services, Paragraph 242 of the BGB), which lay down the rights and obligations of contracting parties in particular situations in more detail, the connexity required by the Court of Justice is present.

19. 2. The jurisdiction of the Court to determine the counterclaim must be recognized, in the light of the principles set out in the Zoubek judgment. 4 According to that judgment, the Court can hear and 21. It follows from the above considerations determine under Article 181 of the EEC that the Court has jurisdiction to determine Treaty only claims arising from the contract both the Commission's claims and the concluded with the Community which defendant's claims for set-off. contains the arbitration clause or claims that are directly connected with the obligations arising from that contract. 5

Part 2 — Claim by the Commission 7 to the principal sum (DM 72 000) under Clause 8 of the contract

20. The defendant initially based his claim for set-off on two grounds: alleged fault on the part of the Commission when concluding the contract (that is, conduct 22. I. Let me first make a preliminary which in German law can found a claim, remark on the application of Clause 14 of whose basis in law is taken to be a breach of the good faith demanded in contractual 6 — See Clause 3 of the contract in conjunction with Annex I, Part B(l) and (2). negotiations), and an alleged undertaking 7 — Although in the text of the contract the Community by the Commission to finance 40% of the appears as the party with which the defendant is contracting, Clause 8 provides that the sums mentioned costs of materials (which, as can be seen there are to be repaid to the Commission. The Commission can therefore bring the claim to repayment in its own name. The problems which might arise therefrom 4 — Case 426/85 Commission v Zoubek [1986] ECR 4057. in connection with claims which go beyond the text of 5 — Zoubek judgment, paragraph 11, referring to Article 6(3) Clause 8, or in connection with claims set off by the of the Convention of 27 September 1968 on Jurisdiction defendant, are of no relevance here; as explained below, and the Enforcement of Judgments in Civil and only the claims by the Commission based on the wording Commercial Matters. of Clause 8 are justified.

I - 2626

COMMISSION v FEILHAUER

the contract. It is indeed true that the unnecessary to discuss the scope of that parties therein refer generally to German clause if the conditions for applying the law, but that reference must be considered relevant German provision arc not met in in its context. The present contract is a the first place. public law contract for a subsidy and its purpose is to implement the aims of Regu- lation No 1302/78. The parties intended by the individual clauses of the contract to regulate this special, by no means typical constellation of interests, and they were 25. In the light of the above considerations, unable to refer to a codification of the further question whether Clause 14 Community law in so doing. In view of refers also to rules of German public law, in those special factors, it is obvious that rules particular administrative law, need not be of German law cannot be applied under examined. Firstly, Clause 14 of the contract Clause 14 if their application is not corresponds in that regard to the parallel compatible with the nature and purpose of provision of the second sentence of the contract or its individual provisions, as Paragraph 62 of the Verwaltungsverfahrens- follow from the wording, structure and gesetz, and secondly, the applicability of context of that provision. Clause 14 must provisions of German public law is therefore be given a restrictive interpretation moreover not relevant, as will be explained in this sense. This applies in particular also below. to the provisions of the BGB, which the parties surely had in mind when referring to 'German law'.

26. II. Since the use of Clause 8 of the contract as the basis for the claim 23. Similar considerations appear inci- presupposes that the contract was validly dentally to be behind the second sentence of concluded between the defendant and the Paragraph 62 of the German Verwaltungs- Community, the defendant's arguments verfahrensgesetz (Law on Administrative must first be considered, in so far as they Procedure). 8 It contains a general can be understood as addressing this point. reference, in connection with public law contracts, to the 'provisions of the Civil Code'; however, these apply only by analogy and are therefore not applicable where they are inconsistent with the nature of the public law contract. 9 27. 1. The defendant maintains to begin with that the project was 'not feasible in Germany'. As can be seen from two letters from the Hassberge local authority, copies of which are annexed to the defence, he 24. That interpretation of Clause 14 will founds this argument on problems therefore be followed below. It is of course connected with building regulations which are said to have prevented the project being 8 — Law of 25 May 1976 (Bundesgesetzblatt (Federal Gazette) carried out on a specific piece of land which I, p. 1253), as amended. the defendant intended to use for that 9 — See Stelkens/Bonk/Leonhardt, Verwaltungsverfahrens- gesetz, Kommentar, 3rd edition, Munich, 1990, Paragraph purpose. He then goes on to argue that 62, point 12. because of the Energiewirtschaftsgesetz

I - 2627

O P I N I O N OF MR LENZ — CASE C-209/90

(Law on Energy Policy) it was impossible to 31. 2. The defendant maintained at the arrange for independence from the public hearing that the contract was 'virtually electricity supply or even to feed surplus immoral', since implementation of the power produced into the public electricity project was more difficult for him than for a network. farmer, but that argument cannot be accepted. The mere fact that performance of a contract is comparatively 'difficult' for the contractor does not mean that it offends against morality and thus does not mean that it is void under Paragraph 138 of the BGB. Moreover, as the defendant's 28. This argument could be understood as representative stated at the hearing, the referring to Paragraph 306 of the BGB, scheme was 'more or less the defendant's which states that a contract whose subject- idea and he drafted and worked out the matter is impossible to perform is void. It is plan'. He was thus perfectly familiar with accepted that that provision presupposes an the difficulties of the project. For this reason impossibility of performance which is alone the objection of immorality is original, that is, existing at the time of completely unfounded. conclusion of the contract, and objective (not relating only to the specific contracting party). 10 This condition is clearly not fulfilled with respect to the problems regarding building regulations, since they were connected with the situation of the piece of land in question, as the two letters show. It was not, however, agreed in the contract that the project should be carried 32. 3. Finally, the defendant complained in out on a specified piece of land. his defence that the Commission's staff had 'persuaded' or 'pressurized' him into taking over the rights and liabilities under the contract. The Commission denies this.

29. As for the questions of energy law, the defendant has not provided any information as to what legal possibilities the project presumed in this respect and in what way this was prevented by provisions of German law. 33. All these arguments could at most be relevant in the context of Paragraph 123 of the BGB, which states that a declaration of intent can be challenged if the person making it has been induced to do so by deceit or unlawful threats. The defendant has not indicated any facts which could 30. The contract cannot therefore be constitute such deceit or threats, nor does it regarded as invalid under Paragraph 306 of appear that he has challenged the the BGB. declaration of intent on his part which led to conclusion of the contract. Paragraph 10 — Palandt, Bürgerliches Gesetzbuch, Kommentar, 50th 123 of the BGB thus cannot apply in any edition, Munich, 1991, Paragraph 306, point 3 (by Heinrichs). event.

I - 2628

COMMISSION v FEILHAUER

34. 4. None of the above aspects thus referring to its letter of 9 December 1986, allows the conclusion that the contract with and following a similar letter of 24 June the defendant is invalid and that 1987, again called on the defendant to pay, corresponds with the position he finally and thereby confirmed that it did not intend adopted at the hearing, when he stated that to pursue the implementation of the the law on unjust enrichment did not apply contract but wished to bring it to an end in where there was a contract and that the accordance with Clause 8. If there was no Commission was, in his opinion, wrong in earlier declaration of rescission, that would assuming that the principle of unjust at any rate be one. For the Court's decision enrichment applied. on the principal sum, the date of rescission is not relevant. The above dispute between the parties can therefore be left undecided, as can the question whether there was already a rescission in an earlier letter of 1987 or in any event in a later letter, that of 8 December 1988. If the Commission's 35. III. It is therefore necessary to examine letter of 9 December 1986 is to be inter- Clause 8 of the contract, on which the preted as a declaration of rescission, it is Commission relies. According to that clause, also irrelevant whether it could be condi- a claim to repayment presupposes the tional on proof of certain factual existence of a rescission and various requirements as to performance of the conditions for rescission. contract and whether it could be combined with the notice of default.

36. 1. Firstly, as far as the necessary declaration of rescission 1 1is concerned, 37. 2. The conditions for rescission in the parties are ultimately in dispute only on Clause 8 of the contract are: the point in time when the defendant received such a declaration, in other words whether it was already contained in the letter of 9 December 1986. The Commission considers that it was, but the defendant argues that that letter merely contains a statement (combined with the notice of default) that the contract would be rescinded, but not yet the rescission itself. — failure to comply with an obligation However, he conceded on page 3 of his under the contract; defence and at the oral hearing that the contract was ('indisputably') 'terminated' 12 by a letter of 16 September 1987. It is correct that on that date the Commission,

11 — See the first sentence of Clause 8 of the contract: ... the Commission may rescind this c o n t r a c t . . . . 12 — This obviously refers to rescission, as maintained by the Commission, rather than termination under Clause 9 of — notice of default given by registered the contract. letter;

I - 2629

OPINION OF MR LENZ — CASE C-209/90

— failure by the contracting party to 40. It remains to examine whether the comply with the obligation in question defendant or his predecessor in title can be within one month. held responsible for the failure to perform the contract before and after the notice of default. The wording of the contract does not include any special conditions in this respect, and it may thus be presumed that mere objective non-performance is sufficient to found the liability and give the 38. It is not disputed that the defendant (or Commission the right to rescind. The result his predecessor in title) did not carry out the might be different if there was a project described in Clause 1.1 of the requirement of fault in this respect. The contract — contrary to the agreed Commission would then have had to specify timetable, which provided for the project to the circumstances indicative of fault on the be operational by the end of 1984 — either part of the defendant or his predecessor in before initiation of the rescission procedure title, and this it did not do. under Clause 8 of the contract or after the notice of default which, as is likewise not disputed, was contained in the Commission's letter of 9 December 1986. That this letter contained a notice of default 41. However, the Commission is rightly of for the purposes of Clause 8 of the contract the opinion that the reason for the is moreover not called into question by the non-performance by the defendant or his fact that the Commission, after stating that predecessor in title of his contractual obli- it was giving notice to the defendant, then gations is in principle 13 not relevant. The indicated that it was rescinding the contract contract is framed in such a way that if proof of certain facts was not produced implementation of the project is the sole within one month. At most, that could have responsibility of the party with whom the meant that the Commission would have Community is contracting. Clause 1.1 been precluded from exercising the right of categorically states: rescission under Clause 8 of the contract if the defendant had produced the said proof within the time-limit; however, this did not happen. In any event, it makes no difference as regards the validity of the notice of 'The contracting party undertakes to carry default. out the following project, according to the timetable of works specified in Annex I . . . '

42. In Clause 2, he undertakes to comply with the timetable laid down in Annex 1. 39. The second of the three aforesaid Under Clause 4.1 he has 'technical and conditions (notice of default) was thus financial responsibility' for the work to be undoubtedly fully complied with; with carried out. In relation to the Commission respect to the first and third conditions he is solely liable under Clause 6 for (failure to comply with a contractual obli- gation, failure to remedy the breach within 13 — The case where the Community (negatively) fails to fulfil one month), it must be stated that these are its own obligations or (positively) prevents or delays performance of the contract is not relevant here and may met, at least objectively. be left aside.

I-2630

COMMISSION v FEILHAUER

damage caused to third parties as a result of terminated before there is a breach of the carrying out the contract. type mentioned in Clause 8.

43. The role of the Community is restricted to the payment of financial support to the 46. Finally, this also corresponds to the contracting party (Clause 1.2) and the economic objectives of the contract. The receipt of his reports (Clauses 4.3 and 4.4) contract, like the other contracts drawn up and information and documentation (Clause on the same pattern under Article 8(1) of 4.5). Regulation (EEC) No 1302/78, was intended to realize the aims of Article 1 of that Regulation, namely to support projects which 'may serve as examples' (and which prior studies and research have shown to offer prospects of industrial and commercial 44. Under Clause 9, the contract can be viability). The injection of funds by the terminated by either of the contracting Community therefore achieves its aim only parties if the programme of work specified if the project is actually carried out. Clause in Annex I is no longer applicable, in 8 has the function of recovering public particular because of a foreseeable technical funds if the purpose is not achieved. That or economic problem or if the estimated clause must therefore be understood as not costs of the project have been exceeded to presupposing fault on the part of the an extent which is regarded as unacceptable. contracting party. The Commission may then in accordance with the terms laid down on commercial use (paragraphs I I . 1and II.2 of Annex II to the contract) demand repayment of the amount of financial support, with interest, if the partial implementation of the timetable of 47. It follows from the above considerations works has led to results which make that the Commission's claim to the principal commercial exploitation possible. sum under Clause 8 of the contract is justified both in principle and as to the amount, which is not in dispute.

45. These provisions taken together yield the principle that in order to obtain the financial support the contracting party was 48. IV. It must now be considered whether to bear in full the risk involved in carrying the claim for this amount should not be out the project and would not retain a claim dismissed because of the claim which has to that support if the project was not carried been made for set-off. out (in accordance with the timetable), whereas the Community on the other hand was not to be exposed to the risk of a failure, even where there was no fault. An exception to this principle, which confirms it and at the same time slightly mitigates its 49. It is apparent, however, that the claims severity, is contemplated in Clause 9 of the put forward by the defendant by way of contract, but only if the contract is set-off are unfounded.

I - 2631

OPINION OF MR LENZ — CASE C-209/90

50. 1. With respect to the claim on the basis et seq. and Paragraph 631 et seq. of the of fault in concluding the contract, the BGB), do not, contrary to the defendant's defendant has not stated what conduct on opinion, give rise to any claim in his favour, the part of the Commission is considered to even if account is also taken of the found such fault. entitlement under Paragraph 670 to the reimbursement of expenditure, which under Paragraph 675 may be applied in the law on contracts of employment and contracts for services.

51. 2. The provisions of the BGB on the law of obligations, cited by the defendant at the hearing, do not found any claim either, so that from this point of view too the claim for set-off fails, quite apart from the procedural question of late submission. 55. It is in fact clear from the nature and structure of the contract that the person contracting with the Community was not to have any rights other than those specified in the contract. The financial support from the 52. (a) Paragraph 346 of the BGB, which Community appears in view of the way it is the defendant initially relies upon, states calculated to be a limited reimbursement of that in the event of rescission the parties are expenses, since it is intended as a maximum obliged to return what they have received amount to cover a certain proportion of the from each other. For services performed or costs. However, it also has in part the for the use of an object, the value must be characteristics of remuneration, in so far as paid, or monetary compensation if that is it must be repaid (under Clause 8) if the determined in the contract. project is not put into practice. To a certain extent, it also resembles a loan, as it has to be repaid (in part) under Section II of Annex II in the event of commercial use of results of the project.

53. However, it is not evident what consideration in any form the Commission (or the Community) is supposed to have received from the defendant under the contract. Even if the implementation of the project were to be regarded as consideration from the defendant for the financial support 56. Since the contract is structured in such of the Community, such implementation did a specific way which is evidently intended to not take place, as stated above. regulate conclusively all claims between the parties, it would be incompatible with the essence of the contract to take into account other rules which would lead to other claims going beyond those agreed on. They should thus not be applied. 14 54. (b) The rules on contracts of employment or for services (Paragraph 611 14 — See points 22, 23 and 24 above.

I - 2632

COMMISSION v FEILHAUER

57. (c) Finally, the defendant argues, if I covered only the costs of materials including have correctly understood him, that there delivery 15 and assembly costs. 16 would be a breach of Paragraph 242 of the BGB if he did not have the right to reim- bursement of expenses to the extent claimed. Under that provision, a debtor is obliged to perform a contractual obligation in good faith having regard to accepted practice. 61. (b) As to the costs of equipment, which the defendant puts at DM 44 190, and other costs of materials, which in the defendant's opinion amount to DM 37 083, the Commission admittedly did not argue that they were not covered by its promise. However, the defendant has not even itemized the 'costs of equipment' of 58. However, in view of the abovemen- DM 44 190 and in particular has not shown tioned objectives of the contract, I cannot any connection between those costs and the find in the result objected to by the project in question. The same is true of the defendant, namely that he has no such other costs of materials (allegedly claims, any breach of the principle of good amounting to DM 37 083). Furthermore, in faith. accordance with the burden of proof to be applied in connection with this type of promise, the Commission imposed a condition for payment, namely that the purchases of materials should be evidenced by invoices and proofs of payment. But neither before the proceedings nor in his defence (a rejoinder was not submitted in 59. 3. The defendant also relies on the time) has the defendant produced such Commission's promise, which, it does not documents or other evidence to show dispute, was given in its letter of 30 April whether — and if so to what amount — he 1985, to finance 40% of the cost of or his predecessor in title actually incurred materials. However, this submission too the costs claimed. The letter from the fails. Gartner undertaking which has been produced in that connection merely shows that the defendant ordered the materials in question, which is also how he puts it in his defence; neither the letter from Gartner nor the defence refers to delivery or payment.

60. (a) Firstly, with reference to the claims for administrative fees, travel and accommo- dation costs and for compensation for time spent, it must be held that, as has been stated by the Commission and not disputed, those items are not covered by the promise. 62. For all the foregoing reasons, the Moreover, the Commission rightly points defendant's argument regarding a set-off out that those costs would not have formed part of the financial contribution even if the 15 — See Annex I to the contract, Sections B 1 and 2,and the description of item 2.1.2 in Table 1 to Annex 1. project had been carried out. It in fact 16 — As previous footnote, but item 2.1.3.

I-2633

OPINION OF MR LENZ — CASE C-209/90

also fails. The claim for the principal sum flat-rate calculation should be carried out to must therefore be upheld. determine the interest rate, the amount of interest actually earned on the principal sum by the defendant being irrelevant. The interest rate generally prescribed in Germany for such cases is 6%. On this point the Commission refers to Paragraph Part 3 — The Commission's entitlement to 44a(3) of the Bundeshaushaltsordnung the interest claimed (Federal Budget Code). 20 That provision reflects the principle that the recipient of a subsidy from public funds should not, if that subsidy has to be repaid, retain interest gained on the sum he has been paid. 63. I. Firstly, it must be stated that the Commission is entitled under the contract to interest (on the principal sum) at the rate of 11.9% from 18 January 1987, as claimed. The claim is justified in principle, since under Clause 8 of the contract it is linked to the claim for repayment (of the principal 65. However, the claim finds no support in sum) without any further conditions, and is any of the bases cited by the Commission, also justified as to quantum, as the rate nor in any other discernible basis. claimed of 11.9% undisputedly corresponds to the terms of the contract 17 and the time-limit provided for in the third sentence of Clause 8 of the contract, namely one month from the notice of default, 18 expired on 17 January 1987, which corresponds to the Commission's claim that interest is 66. 1. With respect to the contract between payable from 18 January 1987. the parties, it must be stated that the wording of Clause 8 is clear and unam- biguous as to the effects of the rescission provided for therein, conferring on the Commission certain precisely specified rights. There is no doubt — nor is it 64. II. The Commission also claims interest, disputed — that this claim for interest is not however, for the period from 24 January one of those rights. 1983 (to 17 January 1987). In its opinion, the contract provides in the event of rescission by the Commission for a resti- tution procedure intended to restore the status quo ante. The Commission considers, referring to Zoubek, 19 that this procedure must also embrace the interest which has 67. 2. It is therefore necessary to examine accrued since payment of the advance. A the Commission's argument, referred to above, that this part of the claim follows 17 — The interest rate of the European Investment Bank in from the fact that the restitution procedure force at the time of the Commission's decision to grant under the contract is intended to restore the financial support for the project. status quo ante. 18 — It is not disputed that this reached the defendant on 17 December 1986. 19 — See note 4 above. 20 — Of 19 August 1969 (Bundesgesetzblatt I, p. 1284).

I-2634

COMMISSION v FEILHAUER

68. There are various possible ways of clas- rules on public law contracts which could be sifying this argument as a matter of law, used to fill lacunae, and on the other the and I will return to this below. Whichever is application of national law involves a risk of chosen, however, the argument fails in any major imponderabilities in view of the case, as follows from the interpretation of non-typical nature of the contract, as the Clause 8 of the contract. present case indeed shows.

69. That provision is to be understood as 71. Accordingly, the Commission's meaning that apart from the claims to argument that rescission as defined in interest specified there, no further claims of Clause 8 of the contract is intended to that type were to be allowed. That Clause 8 restore the status quo ante is untenable. That of the contract was intended to have such a is true first of all, with no further expla- conclusive character can be deduced from nation being required, if the said argument Article 8(1) of Regulation No 1302/78, is to be understood simply as an interpre- which defines the competence and tation of the term 'rescission'. But it is also procedure for the conclusion of contracts true if the Commission was thereby for financial support as follows: referring to a principle which it believed could be found in Community law, applicable to rescission of public-law contracts involving subsidies. Even if such a principle did exist, it would scarcely be of 'The Commission shall negotiate and equal rank with the law of the EEC Treaty conclude the contracts necessary for the and legal rules equated thereto, but would implementation of projects selected pursuant rank with secondary Community law and to Article 6. To that end the Commission would here be overridden by the provision, shall draw up a model contract setting forth based on Article 8 of Regulation the rights and obligations of each party and No 1302/78, of the contract for financial in particular the procedures for any support. repayment of amounts of financial support.'

72. Moreover, in so far as the Commission 70. Where — as clearly happened in the seems to believe that the existence of such a present case — in accordance with that principle of Community law has already provision a 'model contract' is to be used been acknowledged in 'Zoubek, 21 this which sets forth 'in particular the argument cannot be accepted either. procedures for any repayment of amounts Paragraph 8 of that judgment admittedly of financial support', this has a clearly states: discernible purpose, namely in the likely event of contractual problems to create clarity as to the various legal consequences of termination of the contract. Such clarity could only be achieved, however, by means 'In the event of the termination of a of an exhaustive set of rules, since on the contract, the parties must be restored to the one hand there are no codified — and hence substantively clear — Community 21 — Sec note 4 above.

I - 2635

O P I N I O N OF MR LENZ — CASE C-209/90

position in which they would have been if thus not transposable to this case, regardless they had never entered into the contract. of whether the contract which was the The meaning of the principle of restitutio ad subject of that judgment was even of the integrum is that the parties are under an same legal nature as the public-law contract obligation to return whatever they have in this case. received from one another. That obligation extends not only to the asset or sum of money received but also to any yield from that asset or interest generated by the sum received since payment thereof.' 75. 3. The Commission's arguments based on German law, which applies subsidiarily, also lack cogency.

73. This passage should however be understood merely as an interpretation of the contract at issue in that particular case. This follows from the connection with 76. (a) A general principle, independent of paragraph 6 of that judgment, which states: express provisions, 23 that the recipient of a subsidy paid from public funds who is obliged to make repayment may not keep any interest which has been earned on the sum paid over to him, is not recognized in 'Article 7 of the contract, which stipulates German law. 24 The general rules of that the Commission may terminate the German administrative law on the matter — contract for non-performance or improper Paragraphs 48 and 49 of the Verwaltungs- performance on the part of the other verfahrensgesetz and Paragraph 44a of the contracting party, after giving notice to the Bundeshaushaltsordnung ·— which might latter by registered letter, constitutes an have yielded such a principle, do not apply expressed termination clause, according to to public law contracts in the first place, but which one party may, as a means of only to unilateral acts of the adminis- penalizing the other party for improper tration. 25 Precisely in the present case of performance of its obligations, terminate the the payment of a subsidy under a public-law contract without the intervention of the contract, the realization of the public courts.' interest, which would be the basis of the alleged principle (if such a principle did exist), is thus left to the contracting parties. 26

23 — On provisions relating to interest in certain special laws 74. There was also evidently a need for and regulations, see Die Rückforderung fehlgeschlagener Subventionen — Zugleich ein Beitrag zur Problematik interpretation of the contract at issue in that vorläufiger Subventionsbewilligungen, Göttingen, 1987, p. 202 f. case with respect to the interest due on sums 24 — The further issue of what effects the terras of a subsidy repayable in the event of termination. contract would have with respect to such a principle Unlike the contract in this case, it contained thereby becomes otiose. no specific provision on the matter. 22 The 25 — Cf. with reference to Paragraphs 48 and 49 of the Verwal- tungsverfahrensgesetz, in relation to which Paragraph 44a considerations in the Zoubek judgment are of the Bundeshaushaltsordnung merely contains special provisions in the field of voluntary subsidies, Stelkens/ Bonk/Leonhardt, op. cit., Paragraph 62, point 6 and 22 — Cf. paragraph 3 of the Report for the Hearing, [1986] Paragraph 48, point 28. ECR 4058, and the Opinion of Advocate General 26 — Subject to mandatory private law rules, which the contract Sir Gordon Slynn, loc. cit., p. 4062, at p. 4064. will refer to if necessary.

I - 2636

COMMISSION v FEILHAUER

77. Moreover, a principle as described by of Paragraph 44a(3) of the the Commission cannot even be deduced Bundeshaushaltsordnung. from the aforesaid rules of administrative law. For the purposes of annulment of an administrative act which was lawful at the time it was adopted — a case which corresponds (at the level of the granting of subsidy by means of a unilateral adminis- trative act) to the present one, since there is 78. It follows that the principle on which nothing to suggest that the contract between the Commission seeks to rely cannot be the Community and the defendant was not found in German law. lawful — such an act is regarded as a 'lawful' administrative act. 27 Under Paragraph 49 of the Verwaltungsverfahrens- gesetz it can therefore only be annulled or revoked with future effect, which by defi- nition excludes the possibility of interest being payable on the claim to reim- 79. (b) The third sentence of Paragraph 347 bursement for the period before the revo- of the BGB, which states that in the event of cation. 28 Paragraph 44a of the Bundes- rescission 'interest shall be payable on a sum haushaltsordnung, the special rule for of money from the time of receipt', is voluntary subsidies, which specifically likewise not a possible basis for this part of provides in subparagraph 3 for interest to be the claim to interest, since that provision, as payable on claims to reimbursement from the above observations show, is incom- the time when they arise, also makes no patible with the nature of the contract and provision for retroactive revocation, which hence not applicable. 30 would make the claim to reimbursement arise retrospectively from the time when the administrative act was adopted. On the contrary, it is within the administrative authorities' discretion to decide whether to annul the administrative act with future or with retrospective effect. 29 Even in the event of revocation with retrospective effect Part 4 — Costs the claim to interest can be waived in the circumstances stated in the second sentence

80. The decision on costs follows from Article 69 of the Rules of Procedure. As in my opinion the Commission's claim for payment of the principal sum should be 27 — Stelkens/Bonk/Leonhardt, op. cit., Paragraph 44, points upheld in full, and its claim for interest 7 ff, with further references to the case-law. upheld at least in part, it appears appro- 28 — This is especially clear if one considers the formulation used by the Bundesverwaltungsgericht that the revocation priate to order the defendant to pay the removes for the future, the legal basis for being allowed to entire costs of the proceedings in keep the payment (judgment of 11 February 1983 in Case 7 C 70/80, Neue Zeitschrift für Vcrwahungsrecht, 1984, accordance with Article 69(2). p. 36, at p. 38). 29 — See the first sentence of Paragraph 44a(3) of the Bundes- haushaltsordnung. 30 — See points 22, 23 and 24 above.

I - 2637

OPINION OF MR LENZ — CASE C-209/90

C — Conclusion

81. For all the above reasons, I propose that the Court rule as follows:

(1) The defendant is ordered to pay the Commission D M 72 000 together with interest at 11.9% from 18 January 1987.

(2) The remainder of the claim is dismissed.

(3) The defendant is ordered to pay the costs.

I - 2638

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-209/90 – Súdny dvor Európskej únie | AI Pravnik