C-114/94
ECLI:EU:C:1996:142
- Súd
- Súdny dvor Európskej únie
- IČS
- 61994CC0114
- Zdroj
- eur-lex.europa.eu ↗
IDE v COMMISSION
OPINION OF ADVOCATE GENERAL COSMAS delivered on 28 March 1996 *
Summary
I — Introductory remarks I - 806
II — Factual and legal context I - 806
A — Community activity of which the contract concluded between the parties
forms part I - 806
B — The contract at issue I - 807
C — The background to the dispute I - 814
III — Forms of order sought by the parties I - 817
IV — Admissibility of the counterclaim I - 818
V — Main heads of the principal claim and counterclaim 1-819
A — Objectivity of the 'Evaluation Panel' I - 819
B — The circumstances in which the product delivered was evaluated and the
criteria applied in that evaluation I - 822
C — Performance by IDE of its principal obligation I - 823
1) The essential clauses of the contract I - 823
2) The subject-matter of IDE's part of the contract I - 824
3) The 'Evaluation Panel's' report I - 827
4) The question whether IDE failed to fulfil its principal obligation I - 828
D — Failure to fulfil the other contractual obligations I - 830
1) Failure by IDE to fulfil its obligations to manage the project properly and to keep the Commission informed I - 831 2) IDE did not submit to the Commission the comprehensive final report covering the whole project or a consolidated statement of expen- diture I-832
* Original language: Greek.
I-805
OPINION OF MR COSMAS — CASE C-114/94
3) The composition of the group of organizations collaborating with IDE was changed without the approval of the Commission I-833 4) IDE's relations with the other members of the consortium I - 835 5) IDE's allegation that the Commission failed to fulfil its contractual obli- gations I - 837 VI — Other claims made in the application I - 838 1) Claim for the payment of extra-judicial expenses I - 838 2) Claim for the payment of interest I - 839 3) Claim for damages I - 839 (a) Admissibility I-839 (b) Substance I-840 VII — Possibility of apportioning liability between the Commission and IDE I - 841 A — Conditions governing the apportionment of liability I - 842 B — Proposed solution I - 843 VIII — Costs I-845 IX — Conclusion I - 845
I — Introductory remarks bution provided for in the contract con- cluded between the parties and the payment of damages. The Commission's counterclaim is for repayment of the amounts paid by it to IDE, together with interest. 1. The present case concerns a dispute aris- ing in the course of the performance of a contract concluded on 31 January 1990 by the Commission of the European Communi- ties with the Netherlands limited company Intelligente systemen, Database toepassin- II — Factual and legal context gen, Elektronische diensten ('IDE'). The dis- pute was brought before the Court pursuant to the arbitration clause contained in the contract, in accordance with Article 181 of A — Community activity of which the con- the EC Treaty. tract concluded between the parties forms part
2. The action brought by IDE is for pay- 3. O n 17 July 1987 the Commission pub- ment of the balance of the maximum contri- lished a call for declarations of interest for
I-806
IDE v COMMISSION
pilot/demonstration projects aiming at the B — The contract at issue development of a Community information services market. 1
6. O n 31 January 1990 the Commission con- cluded a contract with IDE which, according to the wording, concerned the development by IDE of software, that is to say, a com- 4. O n 12 July 1988 the Commission pub- puter program, consisting in an intelligent lished an advance notice of calls for propos- interface enabling uniform and user-friendly als for pilot/demonstration projects aiming consultation of various kinds of information, at the development of a Community infor- and the setting up of a network giving access mation services market. 2 The Commission to interconnected electronic information was to provide financial support for the sources, in accordance with the specification projects within the limits of the budgetary in the 'technical annex' attached to the con- appropriations available. The Community's tract. The project was to be carried out in average financial support was to be between collaboration with other organizations in the 25% and 35% of the total cost of the Member States and IDE was to coordinate projects. The priority areas selected by the their work. Commission included intelligent interfaces to electronic information sources.
7. According to the contract, IDE's obliga- tion to develop software included that of creating a toolkit in collaboration with the 5. In July 1988 the Council of Ministers of Netherlands research organization T N O and the European Communities approved a plan the University of Amsterdam. The adapta- of action for setting up an information ser- tion of the software to the specific needs of vices market, 3 known as 'Impact', and the information sources and the establish- decided (second paragraph of Article 4) that ment of the network was to be carried out the contractors should bear a substantial by a dozen organizations from various share of the financing amounting to at least Member States, most of which owned agri- 50% of the total cost. cultural activity databases. According to the Commission, the development of the soft- ware amounted to approximately one third 1 — OJ 1987 C 188, p. 2. of the project's total budget, the remainder 2 — OJ 1988 C 182, p. 4. being intended for the completion and estab- 3 — Council Decision 88/524/EEC of 26 July 1988 concerning lishment of the network. At the technical the establishment of a plan of action for setting up an infor- mation services market (OJ 1988 L 288, p. 39). level, development of the network could
I-807
OPINION OF MR COSMAS — CASE C-114/94
only commence after an operational version 10. Article 2, 'Duration', provides: of the toolkit was available to the owners of the databases.
'The Contractor undertakes to carry out the Project within 30 months following the date of commencement of work, hereinafter referred to as "the Operative Commence- 8. Both the rights and the obligations of the ment Date", in accordance with the timetable contractors are defined in the contract and in laid down in Annex I. annexes I, II and III thereto.
The Contractor shall notify the Commission in writing of the Operative Commencement Date within one month of signature of the 9. Article 1, entitled 'Subject-matter of the contract.' contract', provides as follows:
11. Article 3, 'Reports and deliverables', provides:
'Within the framework of the Impact pro- gramme of the European Economic Com- munity (Council Decision of 26/7/88), the Contractor hereby undertakes to carry out the work set out in Annex I and entitled "Domain Independent Intelligent Infor- '3.1 The Contractor shall submit to the mation Services Network Interface Commission the following reports, stating — Disnet" (hereinafter referred to as "the the progress of work and the results Project"). obtained, together with statements of expen- diture incurred during the preceding period:
— first progress report (3 copies) within 6 months of the Operative Commencement ...' Date;
I-808
IDE v COMMISSION
— second progress report (3 copies) within 3.2 On completion of the work, the Con- 12 months of the Operative Commence- tractor shall make a demonstration of the ment Date; successful completion of the Project on the premises of the Commission in Luxembourg, or at an alternative location acceptable to the Commission.
— third progress report (3 copies) within 18 months of the Operative Commencement Date; 3.3 Within two months of the completion, cessation or termination of the work pro- gramme set out in Annex I, the Contractor shall furnish to the Commission a final com- prehensive report covering the whole project. It shall be accompanied by a consoli- — fourth progress report (3 copies) within dated statement of expenditure together with 24 months of the Operative Commence- supporting documents and the accounts will ment Date. thereby be considered closed.
3.4 Deliverables are any significant outputs of the Project to be submitted in accordance with Annex I.' In addition, the Contractor shall submit to the Commission:
12. Article 4 contains the 'Financial provi- sions': — Management Reports (3 copies) every 3 months;
'4.1 The total estimated costs of the Project are 2 349 400 ECU (two million three hun- — edited progress reports suitable for pub- dred forty-nine thousand four hundred lication every 12 months after the Opera- European Currency Units), for the work tive Commencement Date. specified in Annex I.
I-809
OPINION OF MR COSMAS — CASE C-114/94
4.2 The European Economic Community and following approval by the Commis- shall grant to the Contractor a financial con- sion of the progress reports to be sub- tribution of 38, 74% of the actual cost mitted in accordance with Article 3 of incurred in carrying out the work specified this contract. Periodic payments shall be in Annex I, exclusive of tax, as verified and calculated by reference to the percentage accepted by the Commission, but shall not in given in Article 4.2 heretofore applied to any event exceed 909 900 E C U ...' the approved statement of expenditure and by deduction of 15% representing a proportionate amount of the advance payment. Such payments shall be consid- ered as advances until acceptance of the appropriate deliverables specified in Annex I;
13. Article 5, 'Payments', fixes the timetable for the Commission to fulfil its obligations as regards payments:
(c) a retention shall be made of 20% of the '5.1 The European Economic Community total financial contribution. This reten- shall pay its financial contribution by instal- tion shall be released as required to pay ments in E C U as follows: the outstanding balance of the financial contribution after approval by the Com- mission of all the reports and any other deliverables required by this contract, and of the consolidated cost statement;
(a) an advance payment of 136 485 E C U (15% of the maximum financial contri- bution) within 2 months after the Com- mission has been informed pursuant to Article 2 of the Operative Commence- ment Date;
(d) the total of the advance and periodic payments shall not exceed the total financial contribution of the Commis- (b) periodic payments within 2 months in sion less the amount deducted by way of respect of the statements of expenditure retention.
I-810
IDE v COMMISSION
5.2 The Commission, after notifying the 14. Article 6 of the contract, Organization Contractor, may defer or modify the various and performance of the work', provides as payments if verifications of the documents follows: and information provided for in Article 3 and in paragraphs 3 and 4 of Article 5 reveals irregularities, and in particular in the case that the work is not being carried out in accordance with the programme in Annex I, or that the statement of expenditure does not correspond to the work actually carried out '6.1 Technical and financial responsibility or fundamentally deviates from the cost esti- mates in Annex I. In such cases, payment may be made only after the Contractor has provided satisfactory explanations. Where verification reveals that certain amounts have been wrongly paid to the Contractor, he shall repay them immediately to the Com- The Contractor shall have technical and mission. financial responsibility for the work speci- fied in Annex I. He shall provide the person- nel, facilities, equipment and materials neces- sary for the proper performance of the contract. In so far as the work is to be car- ried out by organisations associated with the Contractor for this purpose, the Contractor is responsible for ensuring that the Commu- nity financial contribution is shared amongst 5.3 The Contractor shall, following the the participating organisations according to completion of the work, demonstrate, as the progress of work and the participation of mentioned under Article 3.2. above, the suc- each organisation. cessful completion of the project to the Commission's representatives. Failing such demonstration, the Commission may request full or partial repayment of the amounts paid as financial contribution together with inter- est on those amounts from the end of one month following the Commission's request. 6.2 Participation of third parties in carrying The rate of interest applied shall be the aver- out the project age over three months of the inter-bank rate for ECUs plus two per cent on the first day of the month of the Commission's request.
6.2.1 The Contractor, acting in accordance with the procedure laid down in Article 6.2.2, may entrust the performance of part of the work programme set out in Annex I to third parties, whether natural or 5.4 ...' legal persons. He shall not thereby be
I-811
OPINION OF MR COSMAS — CASE C-114/94
released from his obligations to the Commu- 6.3 Duty to provide information nity under this contract, in particular as regards his technical and financial responsi- bility as referred to in paragraph 1 hereof.
The Contractor shall, without delay, provide the Commission with full particulars of any incident or event likely to prejudice the per- formance of this contract. 6.2.2 The drafts of all subcontracts whereby the Contractor proposes to have part of the work programme carried out by a third party must be notified by registered letter to the Commission, which may, provided it acts within 15 working days following the receipt 6.4 Technical and financial control of such a letter, refuse to approve the sub- contracting. If the Commission does not act within the prescribed period it shall be deemed to have approved the sub- contracting. 6.4.1 The Contractor shall, without delay, supply the Commission with any infor- mation which the latter may request con- cerning the implementation of the work pro- gramme specified in Annex I and during the five years following its completion or cessa- tion. 6.2.3 The requirements of the present Article shall not apply to day-to-day orders for materials, equipment and services made in conformity with the work programme set out in Annex I. 6.4.2 The Contractor shall make available to the Commission and to the Court of Audi- tors of the European Communities the tech- nical and financial documents required to verify that the work programme is or has been carried out; such documents may, if 6.2.4 With respect to any right of the Com- necessary, be verified at the place where they mission under this contract and in particular are normally kept. concerning the performance of the work or any technical or financial control, the Con- tractor shall impose on any sub-Contractor the same obligations as would apply to him under this contract were he to do the work himself. 6.5 ...'
I-812
IDE v COMMISSION
15. Article 7 is entitled Ownership and 17. Article 9, 'Variations or additions', pro- exploitation of results'. Under Annex II, to vides: which Article 7 refers, it is for the Contrac- tor to exploit and circulate the results of the project, since they are its property.
'Any variation of or addition to provisions of this contract must be agreed in writing between the parties hereto. The work pro- gramme and the timetable set out in Annex I may be modified by agreement between the parties in the light of progress.' 16. Article 8, 'Liability', provides:
18. Article 10, 'Termination in the event of the Contractor's breach', is worded as fol- lows:
'8.1 The Contractor shall be solely liable for any loss, damage or injury suffered by him in or in connection with the performance of this contract. 'In the event of non-performance by the Contractor of one or more of its obligations under this contract the Commission may, by registered post with acknowledgement of service, serve notice upon the Contractor. If on the expiry of one month following such service the Contractor is still in breach of its obligation, the Commission may without further formality terminate the contract. The 8.2 The Contractor shall be solely liable for contract may also be terminated where in any loss, damage or injury to its employees order to obtain the subsidy the Contractor or to third parties resulting from the perfor- has made false statements and may properly mance of this contract. It shall hold the be held responsible for such statements. In Commission fully indemnified against any both cases, the Contractor shall immediately award of damage, together with such legal repay to the Commission the amount of the costs as may be awarded with them, made in subsidies received by it, together with inter- favour of a third party for loss, damage or est from the end of the period of one month injury arising out of the execution of this referred to above. The rate of interest shall contract.' be the average over three months of the
I-813
OPINION OF MR COSMAS — CASE C-114/94
inter-bank rate for ECUs plus two per cent Failing a settlement by mutual agreement, on the first day of the month during which the Court of Justice of the European Com- the said period expires.' munities shall have sole jurisdiction to settle any dispute between the contracting parties concerning this contract.'
19. Article 14, 'Annexes', provides: C — The background to the dispute
'Annexes I, II and III form an integral part of this contract.' 21. 15 March 1990 was fixed as the date for the launching of the Disnet project. Accord- ing to the contract, the work was to be com- pleted by 15 September 1992.
Annex I, 'Disnet Technical Annex', describes in particular the project in detail and con- tains a workplan. Annex II is entided 'Own- ership, commercial exploitation and circula- tion of the results of the project'. Finally, 22. According to the first six-month Annex III lists the allowable costs. progress report, the technical programme was being carried out as provided in the con- tract although, according to the Commis- sion, organizations collaborating with IDE expressed certain unease because the compo- sition of the consortium was unstable and, furthermore, IDE had not paid to those organizations their share of the Community contribution. 20. According to Article 16, 'Applicable law and conferment of jurisdiction':
23. Following an inspection in October 1991, an expert, whose impartiality is chal- 'The provisions of the law of the Grand lenged by IDE, found in his report of 3 Duchy of Luxembourg shall govern exclus- December 1991 that the project as completed ively this contract and shall likewise apply to did not fulfil the contractual obligations and all rights and obligations of the parties not he recommended that the Commission laid down therein. should suspend its financial support.
I - 814
IDE v COMMISSION
24. In May 1992 the Commission ordered a 28. O n 11 March 1993 IDE sent the Com- financial audit of the project. According to mission the software it had undertaken to the report drawn up on 22 June 1992 by the design, taking the view that it had discharged accountants appointed for the purpose, IDE all its obligations as set forth in the contract had, without seeking the Commission's and its annexes. More specifically, IDE sent approval, sub-contracted part of the work to the Commission three diskettes labelled Hungarian undertakings. The report, which 'Disnet final beta release 3' together with a covered the first 18 months of the project, number of documents. challenged the statements of expenditure and for that reason proposed to reduce the declared expenditure by 34%.
29. In a letter dated 30 April 1993 the Com- mission pointed out that the product deliv- ered did not comply with the specifications in the technical annex. Moreover, it empha- sized that IDE had not paid to the group of 25. In March and April 1992 the Commis- companies collaborating with it on the sion invited IDE to Luxembourg in order to project, the membership of which, according discuss problems which, in its view, had to the Commission, was continually chang- arisen in the performance of the contract. In ing, the sums due to them, even though the its correspondence with IDE, the Commis- Commission had already paid to IDE sion also mentioned the changes in the com- E C U 533 456. It stated that it would not position of the group of organizations col- insist on a demonstration of the finished laborating with IDE, the delay with which product in order to avoid additional costs IDE communicated to them the results of and because, in its view, it did not appear the work and various technical failures. that such a demonstration would change its initial negative assessment. Moreover, by way of an amicable settlement, it proposed to limit its contribution to 75% of the maxi- mum amount provided for in the contract (ECU 682 425) and not to pay the remainder (ECU 682 425 less E C U 533 456, that is to say E C U 148 969) until IDE had submitted 26. As a result, the technical annex to the the final report and a consolidated statement contract was amended. of expenditure and proved that it had ful- filled all its contractual and financial obliga- tions in respect of all its existing and former partners.
27. O n 12 February 1993 the Commission and IDE agreed to extend the duration of the contract by six months, that is to say until 30. O n 31 May 1993 IDE rejected the Com- 15 March 1993. mission's proposal.
I-815
OPINION OF MR COSMAS — CASE C-114/94
31. By letter of 17 June 1993 the Commis- 35. It appears from the report, dated 30 July sion, in reliance on the terms of the contract, 1993, drawn up by the two Commission decided to request IDE to make a demon- officials who were members of the 'Evalua- stration before an 'Evaluation Panel' to tion Panel' and from the report dated 2 establish that the project was duly com- August 1993, drawn up by the observer pleted. appointed by the Commission that, regard- less of which of the two versions of the project was to be considered the definitive version, the software presented by IDE was defective.
32. Although it was prepared to demonstrate the project, IDE expressed reservations on account of the fact that the Commission had already made it known that it did not insist on a demonstration of the results of the Dis- 36. According to the 'Panel's' report, (a) the net project. software only met between 50% and 75% of the specifications in the technical annex to the contract and (b) the network part of the Disnet project was missing.
33. The 'Evaluation Panel' was composed of two Commission officials who had not taken part in the Disnet project and an expert who, 37. According to the Commission, the third according to the Commission, had been member of the 'Evaluation Panel' concurred approved by IDE. The work of the 'Panel' with the findings of the report of 30 July was also followed by two observers, one act- 1993. Unlike the observer appointed by the ing on behalf of the Commission and the Commission, the observer appointed by IDE other on behalf of IDE. did not submit a report.
34. The demonstration took place on 20 July 38. O n 7 September 1993 the Commission 1993. The software demonstrated was that sent those reports to IDE. In a covering let- sent to the Commission on 11 March 1993. ter it made the following observations: (a) However, it appears from the 'Panel's' report IDE had failed to fulfil its obligations under that a more recent version, submitted by the specifications in the technical annex to IDE after the expiry of the contract, was also the contract; (b) the final report, dated examined. 17 May 1993, received by the Commission
I-816
IDE v COMMISSION
was unsatisfactory; (c) the statement of 41. More specifically, IDE claims that the expenditure covering the fifth half-year Court should: period was not in conformity with the con- tract; (d) the Commission had not received the statement of expenditure for the sixth half-year; and (e) it had not received the documents necessary to evaluate the total cost of the project. The Commission indi- cated that it would not make any further payments and that it expected to recover the — order the Commission to pay to IDE (a) sums already paid. ECU 376 500, 4(b) extrajudicial costs of E C U 37 650, (c) interest at the rate pre- scribed by law from 31 May 1993 until the day on which full settlement is made and (d) compensation in respect of any other damage suffered by IDE as a result of the Commission's conduct contrary to its contractual obligations; 39. O n 15 and 27 September, IDE informed the Commission of its reservations as to the findings of the evaluation report, insisted that the demonstration had taken place under particularly difficult circumstances and challenged a number of the 'Panel's' techni- cal evaluations. — order the Commission to pay the costs under Article 69 of the Rules of Pro- cedure.
III — Forms of order sought by the parties
42. The Commission, first by letter dated 29 June 1994 and subsequently by a counter- claim submitted to the Court on 7 July 1994, sought the repayment of the amounts paid to IDE, together with interest. 40. By application lodged at the Court Reg- istry on 15 April 1994, IDE sought an order of the Court requiring the Commission to 4 — The amount claimed by IDE is ECU 376 500. This sum fulfil all its contractual obligations and make together with the amount already received totals good the damage which it caused to IDE as a ECU 909 956. IDE clearly seeks payment of the maximum contribution (ECU 909 900) provided for in Article 4.1 of result of its failure to fulfil those obligations. the contract.
I - 817
OPINION OF MR COSMAS — CASE C-114/94
43. The Commission contends that the IV — Admissibility of the counterclaim Court should:
— dismiss the action as unfounded; 45. In its reply to the counterclaim made by the Commission, IDE raises the question of its admissibility. It plainly considers that the Court has no jurisdiction to hear and deter- mine the counterclaim.
— order the applicant to pay to the Com- mission E C U 533 456, together with interest at 7.97% per annum;
46. O n that point, I would refer to the rel- evant case-law of the Court, 5 according to which (a) the conditions governing the admissibility of a counterclaim are to be — order the applicant to pay the costs of the assessed on the basis of the provisions of the proceedings. Treaty, that is to say, the question whether it has jurisdiction to hear and determine a counterclaim and, more generally, any ques- tion related to its admissibility must be assessed solely in the light of Article 42 of the ECSC Treaty, Article 181 of the EEC Treaty, Article 153 of the EAEC Treaty and the Court's Rules of Procedure and (b) the jurisdiction of the Court to hear and deter- mine claims which arise from a contract con- 44. With regard specifically to the Commis- cluded with the Community and containing sion's counterclaim, IDE contends that the an arbitration clause, or claims that are Court should: directly connected with the obligations aris- ing from that contract, means that it also has jurisdiction to hear and determine a counter- claim arising from the same contract or from the facts on which the principal claim is based.
— declare the Commission's counterclaim inadmissible or, at least, dismiss it and 5 — See Case 426/85 Commission v Zoubek [1986] ECR 4057, order the Commission to pay the costs. paragraphs 10 and 11.
I-818
IDE v COMMISSION
47. In view of that case-law and since the that it fulfilled all its obligations and accord- Commission's claim derives from the con- ingly requests the Court to order the Com- tract which forms the subject-matter of the mission to pay to it the remainder of the principal claim, it is clear that the Court also contribution, together with interest, and to has jurisdiction to hear and determine the make good all other damage suffered by it. counterclaim.
50. The respective submissions of the parties V — Main heads of the principal claim and should now be dealt with as follows: first, counterclaim the parties' submissions as regards the objec- tivity of the 'Evaluation Panel'; secondly, those relating to the evaluation conditions and criteria of the product delivered; thirdly, the parties' respective arguments concerning the extent to which IDE fulfilled its principal obligation, namely to deliver a product in 48. In its counterclaim the Commission, conformity with the specifications imposed; relying on Article 5.3 of the contract, seeks finally, I will deal with the Commission's the repayment by IDE of the sums it has submissions on IDE's failure to fulfil other paid to it, together with interest. The Com- contractual obligations and the latter's sub- mission bases this head of claim mainly on missions with regard to the Commission's the negative report of the 'Evaluation Panel', failure to fulfil its contractual obligations. according to which the product delivered by IDE did not fully satisfy all the specifica- tions set forth in the technical annex. The Commission considers that the fact that IDE did not fulfil its obligation to supply a prod- uct corresponding to all the specifications in the technical annex constitutes sufficient grounds for upholding its counterclaim. Its submissions concerning IDE's failure to ful- A — Objectivity of the 'Evaluation Panel' fil other contractual obligations must be regarded as put forward in the alternative.
51. In the documents it lodged in reply to 49. IDE claims that the 'Evaluation Panel's' the Commission's submissions (paragraph 11 report is not reliable, first, because it was not of the reply in the main proceedings and in certain that that 'Panel' was objective and, the reply to the counterclaim) and also dur- secondly, because its evaluation of the prod- ing the hearing IDE challenged the 'Evalua- uct was erroneous in substance. It also states tion Panel's' objectivity on the following
I-819
OPINION OF MR COSMAS — CASE C-114/94
grounds: (a) there was no provision in the appointed by it, since they were to represent contract for its establishment; (b) its compo- it, means that the said demonstration was to sition was decided solely by the Commis- take place before persons who would com- sion; (c) its members were paid by the Com- prise, albeit informally, an 'Evaluation Panel' mission; (d) the 'Panel' leaned in favour of and who would be in possession of the tech- the Commission, since it had been appointed nical knowledge necessary to evaluate the by it. This means that IDE is challenging the demonstration. impartiality of the 'Panel' of three members appointed by the Commission to evaluate the results of the Disnet project delivered to it by IDE and is requesting, therefore, that a new experts' report be obtained.
54. The Commission states that it had appointed two of the three members of the 'Panel' itself who were officials of its staff, and that IDE had appointed the third mem- ber to act as an independent expert. IDE cat- 52. Article 5.3 of the contract provides that, egorically denied having appointed the third on completion of the work, the Contractor is member of the 'Panel' and claimed that the to demonstrate the successful completion of Commission had refused to allow a person the project to the Commission's representa- appointed by IDE to participate in the tives. The contract gives the Commission the 'Panel'. right to require IDE to carry out such dem- onstration to its representatives after completion of the work connected with the Disnet project.
55. However, since the contract confers on the Commission the power to appoint all of the members of the informal 'Evaluation Panel', there is no particular purpose in ascertaining whether or not IDE appointed 53. It is true that the contract does not one of its members. specify the body before which such a dem- onstration is to be carried out. However, from the wording of the contract, interpreted in the light of Article 1135 of the Civil Code of the Grand Duchy of Luxembourg, 6 which is applicable in the present case, it fol- lows that the clause concerning the demon- 56. Moreover, the fact that the third member stration carried out on the Commission's of the 'Panel' was paid by the Commission, premises before the representatives as IDE points out (paragraph 18 of the rejoinder to the counterclaim) is not, of itself, of any particular significance because, 6 — According to Article 1135, a contract is binding not only as since, pursuant to the contract, the Commis- regards its express terms but also as regards all consequences sion appointed the members of the 'Panel', it which, according to its nature, flow from it by virtue of equity, custom or statute. was obliged a fortiori to pay them.
I-820
IDE v COMMISSION
57. Furthermore, the question whether or 61. However, IDE has not substantiated not the members of the 'Panel' had been those assertions, which must therefore be involved in the Disnet project is irrelevant disregarded. since, according to the contract, the Com- mission was unfettered as to whom it appointed.
62. That the objectivity of the 'Panel' cannot be put in question is also clear from the fact that, of the observers whom the contracting 58. Accordingly, the impartiality of the parties had appointed as independent experts 'Panel' cannot be called in question merely for the purposes of following the demonstra- on the grounds that the Commission alone tion, only the Commission's expert drew up had appointed and paid its members. a report, dated 2 August 1993 (Annex III to the defence), in which he confirmed the con- clusions of the 'Evaluation Panel' on the matter, while the expert appointed by IDE had not submitted a report.
59. The Commission points out that the two members of the 'Panel' drew up the report and the third member who, as it maintains, had been appointed by IDE, approved its conclusions by fax. That much is set out in 63. IDE's representative stated at the hearing the letter of 30 July 1993 which the two that its observer had not had the chance to other members of the 'Panel' sent to the participate in the discussion and that was Commission official responsible for the why he had not lodged a report; after a dis- supervision of the Disnet project (Annex XV cussion with him, IDE had itself lodged a to the application). report. However, the Commission's repre- sentative replied that the recording of the conversations during the demonstration proved the opposite.
60. To this IDE objects the 'Panel' acted with partiality to the benefit of the Commis- sion since, by letter of 30 April 1993, the official whom the Commission had placed in 64. The vague and unsubstantiated assertions charge of the project had clearly indicated put forward by IDE to challenge the impar- that the Commission no longer insisted on a tiality of the 'Evaluation Panel' must there- demonstration of the end product. fore be rejected.
I-821
OPINION OF MR COSMAS — CASE C-114/94
65. Moreover, in view of the foregoing 68. In that same letter, IDE's lawyer pro- analysis, IDE's request that a fresh expert's posed that the product delivered on report should be obtained should also be 15 March 1993 and an improved later version rejected since the mere fact that the Com- should be evaluated. The Commission mission, exercising the rights conferred on it refused (see its letter of 16 July 1993), but by the contract itself, appointed the members finally a later version of the original product of the 'Panel' does not prove that the latter was also demonstrated to the 'Panel' as con- acted with partiality. firmed by the latter in its report.
B — The circumstances in which the product delivered was evaluated and the criteria applied in that evaluation 69. In the aforementioned letter of 12 July 1993, IDE's lawyer indicated a number of essential aspects which were to be demon- strated. He also mentioned four different options for the demonstration and pointed out a number of possible technical difficulties 66. Article 3.2 of the contract provides that, that the Luxembourg demonstration might on completion of the work, the contractor is present. to make a demonstration of the successful completion of the project on the premises of the Commission in Luxembourg, or at an alternative location acceptable to the Com- mission.
70. The Commission pointed out in the abovementioned letter of 14 July 1993 that 67. IDE requested that the 'Evaluation the evaluation criteria which the 'Panel' Panel' should examine the delivered product would apply in carrying out the duties in a place, at a date and under conditions assigned to it would be the elements set out acceptable to the Commission. Specifically, in the technical annex and that the evaluation in his letter of 12 July 1993, attached to the would focus on the aspects to which the application to the Court, IDE's lawyer pro- Commission official in charge of the supervi- posed that the demonstration take place in sion of the project had objected in his letter Luxembourg at specified premises which, in to IDE of 30 April 1993 (annexed to IDE's its view, had the necessary infrastructure. H e application). It expressly excluded that the also requested that someone of its choice evaluation criteria should be unilaterally should take part in the work of the 'Panel' as defined by IDE. It also mentioned a number an independent expert. The Commission of technical details intended to ensure that finally agreed to those proposals by letter of the demonstration took place under the best 14 July 1993. possible conditions.
I-822
IDE v COMMISSION
71. By letter of 15 July 1993, IDE's lawyer the evaluation report). Nevertheless, the urged that an environment be created in 'Panel' rejected those assertions and attrib- Luxembourg at the site where the demon- uted the problems to IDE's product's stration was to take place similar to that incompatibility with the Unix environment. which existed during the installation process Finally, it considered that those problems did at the Disnet partners' sites. It appears from not undermine the reliability of the test. a letter from the Commission of 16 July 1993 that special technical facilities had been made available to IDE to enable it to conduct the demonstration of its product successfully.
74. In view of the foregoing considerations, IDE's submission that the demonstration took place under extremely unfavourable conditions must be rejected as unfounded. 72. As confirmed in the 'Panel's' report, IDE was authorized to install the day before the demonstration the software it had devel- oped. The 'Panel' also stated in its report that it arrived at its conclusions at the end of the demonstration of five hours' duration presented by IDE on 20 July 1993 and that five hours seemed sufficient to demonstrate C — Performance by IDE of its principal the end product. It also observed that, obligation despite a number of technical problems which arose at the beginning of the demon- stration, IDE had agreed to continue with the demonstration. None the less, no inci- dents attributable to the network occurred, according to the 'Panel's' report, once the demonstration had begun or during it. 1) The essential clauses of the contract
75. It appears from the wording of the con- 73. Admittedly, during the demonstration tract and of its technical annex that the IDE mentioned some technical problems Commission and IDE entered into a synal- connected with the site of the demonstration lagmatic contract under which the former and the shortcomings of the local Unix net- agreed to pay a sum of money by way of work and the telecommunications links as contribution for the performance by the lat- well as other problems which had a detri- ter of work consisting in the development of mental effect on the demonstration (see p. 4 the Disnet software, which was to be com- of IDE's comments of 15 September 1993 on mercially viable and marketable.
I-823
OPINION OF MR COSMAS — CASE C-114/94
76. IDE was to coordinate the work of a the provisions of Luxembourg law governing group of organizations from the Member the resolution of disputes relating to the States. The product, that is to say the result interpretation of the clauses of a contract of that work, was to remain the property of which concern the subject-matter of the ser- IDE and the group of partners, as set out in vices to be provided. The court adjudicating detail in Annex II. on the merits may, considering the clauses of a contract in the light of Articles 1134 and 1135 of the Civil Code, 7 make certain find- ings regarding the content of the obligations of the parties.
77. The Disnet project was to be carried out under the supervision of the Commission and the contribution was to be paid on con- dition that IDE fulfilled all its obligations, as 80. IDE undertook to produce a 'domain is expressly stated in Clause 5.1(c) of the independent intelligent information services contract. That contribution covered 38.4% network interface', namely the Disnet soft- rather than the whole of the actual cost of ware. the project.
81. According to the contract (Clause 1) and the technical annex, the subject of the con- 78. IDE states (at paragraph 13 of its state- tract was the production of software, that is ment in reply to the defence and in answer to say a computer program, capable of being to the counterclaim) that it was not merely used in different domains for different pur- open to but was incumbent on the Commis- poses. This was to be achieved by means of sion to pay the whole of the sum agreed. the installation of a network interface which Such payment was not to be made unless would allow access to interconnected sources IDE fulfilled with all due diligence its obli- of electronic information. gations under the contract and its annexes.
82. In both the original and the amended 2) The subject-matter of IDE's part of the versions of the technical annex (p. 3 et seq.), contract it is provided that there are three end prod- ucts: (a) the Disnet software, which should be marketable and should run under DOS,
7 — Article 1134 of the Civil Code provides that contracts law- fully entered into have the force of law for the contracting 79. Since Clause 16 of the contract states parties. It thus reproduces the principle of Roman law that that the law of the Grand Duchy of Luxem- 'pacta sunt servanda'. It further provides that contracts must be performed in good faith. Article 1135 has already been bourg is applicable, it is necessary to examine referred to at footnote 6 above.
I-824
IDE v COMMISSION
Windows 3 and Unix; (b) a network to be set More specifically, it states that the three up between a number of European hosts objectives of the project were attained. Those and networks using the Disnet interface; and objectives consisted in producing Disnet: (a) (c) applications that were to be built using as a toolkit; (b) as a network; and (c) as a the Disnet interface by a number of basis for a large range of applications to be organizations participating in the Disnet built by its partners (p. 2 of the letter of project. 2 May 1993, which is attached to the applica- tion and which IDE sent to the project supervisor appointed by the Commission).
83. It is apparent from the whole of the documents relating to the principal claim and to the counterclaim, as well as from the hear- 86. IDE states (paragraph 9 of its rejoinder ing that in the present case there is a funda- in the counterclaim proceedings) that the mental divergence of views as to the subject- product which it delivered was commercially matter of the contract and, consequently, as attractive enough to be exploited on the mar- to whether or not the product delivered to ket and that external observers had acknowl- the Commission by IDE was in conformity edged as much. At the hearing it described with the specifications set out in the contract the product as delivered as outstanding, as and defined in the technical annex. constituting software which was ahead of its time and as commercially successful.
84. According to the Commission, the prod- uct delivered by IDE did not meet the speci- fications of the contract: it did not have the 87. Similarly, IDE, relying on the technical agreed features because it did not work as annex, considers (paragraph 1 of its reply in expected and was not marketable, as required the original action and in its defence to the by the technical annex, that is to say that it counterclaim) that it had undertaken to was not sufficiently commercially attractive deliver a beta release toolkit, but not a stable to enable it to be exploited on the market software ready for sale on the market, on the (paragraph 7 et seq. of the statement in ground that that requirement is contrary to rejoinder in the original action and in reply the contract itself. in the counterclaim proceedings).
88. In support of its contention that it was 85. IDE refuted those assertions and main- not bound to present a product with the tained that it had fulfilled all its obligations. abovementioned features, as required by the
I-825
OPINION OF MR COSMAS — CASE C-114/94
Commission, IDE states that a correspond- Commission describes the Disnet project as ing increment to the Community contribu- a pilot/demonstration project. tion had not been provided for (paragraph 1 of the reply in the original action and the defence to the counterclaim).
91. The fact that the Commission describes the Disnet project as a pilot/demonstration project is of no particular significance 89. In the light of the foregoing analysis, because it is the contract alone which is with regard to the product which IDE had binding on the contracting parties. More par- undertaken to deliver, I have to take the view ticularly, the precise characteristics and, more that the term 'marketable product' used in generally, the description of the project are the technical annex with regard to Disnet laid down in the contract itself and in its describes a product with characteristics (such technical annex and the fact that the Com- as its stability and fitness for the purpose to mission describes the project in a certain way be served) such that it is capable of being in some other document unconnected with exploited on the market. Accordingly, IDE's the contract cannot in itself alter the obliga- contention that it would run counter to the tions of the parties. contract itself to require it to deliver stable software ready for sale on the market is unfounded. However, the fact that the resources made available by the Commission were inadequate, as it claims, does not sub- stantiate its assertions regarding the charac- teristics of the product which it was to deliver. Moreover, IDE states that the end product, with the improvements it had 92. IDE emphasized at the hearing that it already incorporated, is commercially suc- was necessary to take into account the deve- cessful. lopment of the software, which is a collec- tion of extremely complex data which is con- stantly evolving. It pointed out that the final version of Disnet had reached a particularly advanced stage, that it was nearly completed, that it met all the specifications of the con- tract and took into account technological developments, since the contract had been signed on 31 January 1990. It concluded by 90. IDE also maintains that it was to deliver saying that the project was in its initial stages a pilot/demonstration project (paragraph 8 and would be completed in the form of a of its rejoinder in the counterclaim proceed- network. That network was ultimately cre- ings) and relies on this point on a Commis- ated by the group of organizations collabo- sion document, dated December 1992 and rating with IDE and belonging to all the attached to that rejoinder, in which the Member States of the Community.
I-826
IDE v COMMISSION
93. Those assertions of IDE's are, however, language module which is considered to be unfounded. The question whether IDE ful- an element of the overall project. filled all its obligations must obviously be decided on the basis of the provisions of the contract. Accordingly, it is irrelevant that IDE fulfilled them at a later date, after the expiry of the time-limits laid down in the contract.
96. Accordingly, IDE's assertion that the contract did not expressly provide that it was to develop a natural language processing module is unfounded. The question as to who would ultimately develop that part of the project was left to IDE's discretion, pro- vided that the expected result was attained in conformity with the provisions of the con- 94. Finally, particular mention must be made tract. Moreover, IDE points out that that of a point on which the Commission and part of the project was ultimately completed, IDE do not agree (paragraph 2 of the state- even though the Commission was not satis- ment in reply to the defence and in answer fied with the final result. to the counterclaim). In its original wording, the technical annex (p. 2) states in particular that 'a natural language facility using a lim- ited syntax and vocabulary will be offered as extras', whereas, in the later, amended, ver- sion, the words 'as extras' and the relevant explanatory note were deleted. I consider that such a change to the wording is signifi- cant since it reveals that it was the parties' 3) The 'Evaluation Panel's' report express wish that the end product should include a natural language facility using a limited syntax and vocabulary.
97. In its report the 'Evaluation Panel' acknowledged that the conceptual basis for Disnet was innovative and raised high expec- tations. However, it found that the end 95. Moreover, in support of its arguments, product as demonstrated did not live up to the Commission lodged (Annex II to the those expectations, that is to say, it did not statement in rejoinder in the original action meet the specifications set out in the techni- and in reply in the counterclaim proceed- cal annex. It emphasized that that finding ings) a document from IDE entitled 'System held true irrespective of whichever version of Design' which deals with the natural Disnet was considered.
I-827
OPINION OF MR COSMAS — CASE C-114/94
98. More specifically, according to the 102. In a subsequent report dated 15 Sep- 'Panel', IDE only met the first of its obliga- tember 1993, IDE challenged the findings tions, namely the creation of a toolkit, and contained in the 'Panel's' report and in par- then not entirely successfully. The toolkit ticular the criticisms on which the 'Panel' did not constitute a completed and market- had based its evaluation of the product able product; it met only to a limited extent which IDE had demonstrated to it. IDE also objectives fixed, particularly as regards the denied that it had failed to deliver two of the knowledge base and the natural language three products referred to in the contract, the component of the interface. The product as network and the domain-specific applica- delivered was unstable and required subse- tions of the toolkit, and maintained that a quent improvement. demonstration which also covered those aspects would have required more time. However, all were agreed that the time allo- cated for that demonstration had been adequate.
99. Moreover, according to the 'Panel's' report, IDE failed to deliver two products which were also included in the contract: it 103. It follows from the foregoing consider- did not complete the network or the ations that the 'Evaluation Panel's' report is domain-specific applications of the toolkit. not lacking in objectivity and that its find- ings must be accepted, namely that IDE did not fulfil its obligations. Moreover, IDE has not furnished any evidence such as to sup- port its argument and thus refute the 'Pan- el's' unfavourable substantive evaluation according to which the product demon- strated did not meet the specifications set out in the technical annex. N o r did the expert 100. In view of the foregoing, the 'Panel' appointed by IDE issue an opinion in writ- considered that the Disnet project had not ing to the contrary. been successfully completed and that it met between 50% and 75% of the specifications set out in the technical annex.
4) The question whether IDE failed to fulfil its principal obligation
101. In a report lodged on 2 August 1993 (annexed to the defence), the expert appointed by the Commission made similar 104. The object of the contract concluded negative observations on the results of the between the Commission and IDE was to demonstration. create a marketable domain-independent
I-828
IDE v COMMISSION
intelligent information services network extent) the specifications in the contract interface. As I have observed above, the and the technical annex. technical annex, in both its original and amended forms (p. 3 et seq.), provides that the project which IDE was to demonstrate and deliver to the Commission was to comprise the following three end products: (a) the Disnet toolkit; (b) the network, to be set up between a number of European hosts and networks using the Disnet interface; and (b) Where, upon the end product's being (c) the applications that could be built, using demonstrated, it is found that the project the Disnet interface, by a number of meets only part of the specifications set organizations participating in the Disnet out in the contract, the Commission may project. Thus, IDE was to provide a service not call for full repayment of the relating to three different products which amounts paid by way of financial contri- may be regarded as equally important to the bution but only part repayment. In such completion of the work. a case, the precise amount which the Commission may call to be repaid depends on the measure in which the product demonstrated meets the specifi- cation set out in the contract and the technical annex. 8
105. Article 5.3 of the contract provided that should no such demonstration of the project take place or the demonstration not be suc- cessful, the Commission could call for full or partial repayment of the amounts paid as a financial contribution together with interest. From that article, in my opinion, the follow- 106. According to the findings of the 'Evalu- ing inferences may be drawn: ation Panel', IDE had delivered only the first of the three products which it was to supply. Furthermore, the completed product, that is to say the Disnet toolkit demonstrated, met 50% to 75% of the specifications in the tech- nical annex. In view of this, the Commission may not call for repayment of the full amount of the contribution paid by it but only part of that amount. (a) The Commission may call for total repayment of the amounts paid only where no demonstration takes place or the end product demonstrated does not 8 — That view is confirmed by the fact that, according to Article 3.4 of the contract, the deliverable products are any signifi- at all meet (or meets only to a negligible cant outputs of the completed Disnet project.
I-829
OPINION OF MR COSMAS — CASE C-114/94
107. Under Article 4.2 of the contract the 7.97% per annum, a figure which IDE does amount which the Commission was to con- not challenge. Furthermore, interest begins tribute towards the Disnet project was to be to run from the end of one month following E C U 909 900. Two of the three end products the date (29 June 1994) on which the Com- were missing from the work submitted by mission called for repayment of the amounts IDE. Accordingly, the amount of the Com- already paid, that is to say as from 29 July munity contribution should be reduced by 1994. two-thirds. Furthermore, in so far as the end product as demonstrated met, albeit in part, the specifications set out in the contract, IDE is entitled to keep a corresponding propor- tion of the Community contribution. Thus, since the product which was demonstrated met 50% to 75% of the specifications in the technical annex, IDE should keep 75% of the amount of the Community contribution corresponding to the first part of the Disnet project and repay the remainder which it has D — Failure to fulfil the other contractual already received. obligations
109. For the sake of completeness, I shall 108. Since in my view the three end prod- consider the Commission's alternative sub- ucts were equally important to the comple- missions relating to the failure of IDE to ful- tion of the project as a whole, a third of the fil other contractual obligations. E C U 909 900, that is to say E C U 303 300, corresponds to the completion of each of the end products. Thus, since the product deliv- ered attained 75% of the objectives set, according to the evaluation which is most favourable to IDE, the latter should keep solely the amount remaining after subtract- ing 25% (that is E C U 75 825) of E C U 303 300, corresponding to the first of 110. These submissions are put forward as the three products encompassed by the an alternative basis, first for the counterclaim project. Accordingly, IDE is entitled to for the repayment of the amounts already keep E C U 227 475 (ECU 303 300 less paid and, secondly, for refuting IDE's asser- E C U 75 825) and must reimburse to the tions that it fulfilled all its obligations and Commission E C U 305 981 (ECU 533 456 that the Commission should therefore pay it less E C U 227 475), together with interest. the remainder of its contribution. I shall also The rate of interest to be applied, fixed in consider IDE's arguments alleging failure on accordance with Article 5.3 (in fine) of the the part of the Commission to fulfil its con- contract, is, according to the Commission, tractual obligations.
I-830
IDE v COMMISSION
1) Failure by IDE to fulfil its obligations to 114. It appears from reports drawn up at the manage the project properly and to keep the request of the Commission, first, by an inde- Commission informed pendent expert and, secondly, by a firm of accountants (Annexes I and II to the defence), that certain irregularities in the sphere of management were noted in IDE's implementation of the project.
111. Under Article 3.1 of the contract, the contractor, that is to say IDE, was to submit to the Commission at regular intervals throughout the duration of the work reports 115. First, the report of 3 December 1991, stating the progress of the work and the drawn up by the expert appointed by the results obtained, together with statements of Commission (pp. 7 and 8), relating to the expenditure incurred during the preceding first 18 months of the contract, refers to sig- period. nificant deviations from the original cost plan and with respect to the overall conduct of the project, discrepancies which were not in accordance with IDE's contractual obliga- tions. The document also mentions that members of the consortium stated that the timetable for the execution of the project 112. The Commission states that it was not was not being observed and the costs had able to follow the development of the project not been properly assessed. Those findings because IDE failed to keep it informed, an provided grounds for considering that the obligation laid down in the contract. In par- project ran a serious risk of not being com- ticular, in a letter to IDE dated 7 September pleted in accordance with the agreed time- 1993 (Annex XV to the application), the table and that it was necessary to redefine its Commission states that the statement of objectives, inasmuch as neither the agreed expenditure it received for the period timetable nor the available budget was suffi- 15 March to 15 September 1992 was not in cient. The report proposed, moreover, that conformity with the contract and therefore the Commission should suspend payment of not acceptable since it was contrary to the its financial contribution until IDE put for- provisions of Annex III to the contract. The ward a clear strategy for an alternative solu- Commission has not received since then any tion. corrected version of that statement of expen- diture.
116. Secondly, the report of 22 June 1992, drawn up by the firm of accountants, con- cerned the audit of the progress made by the 113. In the same letter the Commission project in periods 1, 2 and 3 (from 15 March points out that it has not received the state- 1990 to 15 September 1991). The audit ment of expenditure for the period 15 Sep- started on 18 May 1992. According to the tember 1992 to 15 March 1993. report, IDE did not make available the
I-831
OPINION OF MR COSMAS — CASE C-114/94
ledgers for the period in question, reserva- 2) IDE did not submit to the Commission tions were expressed as to the accuracy of the comprehensive final report covering the the costs statements submitted and a 34% whole project or a consolidated statement of reduction in expenditure was proposed. expenditure
119. Under Article 3.3 of the contract, the contractor, IDE, was, within two months of the completion of the work programme, to furnish to the Commission a final compre- hensive report covering the whole project, accompanied by a consolidated statement of expenditure together with final supporting 117. IDE contests the results of the assess- documents. ment made by the accounting firm in ques- tion (paragraph 8 of the statement in reply to the defence and in answer to the counter- claim) and states that it managed its expendi- ture scrupulously and kept an hourly record of work during the project.
120. According to the Commission, IDE's comprehensive final report on the project, dated 17 May 1993, does not fulfil the requirements of the contract because it does not explain clearly the objectives and the results of the project and contains statements that are in contradiction with the interim reports (see the letter of 7 September from the Commission to IDE, annexed to the application).
118. Moreover, IDE did not submit half- yearly statements of expenditure for the whole duration of the project and, conse- quently, has not shown that it fulfilled the relevant obligations incumbent on it under 121. The Commission further points out Article 3.1 of the contract. The negative that it did not receive a consolidated state- assessment of IDE's accounting made by the ment of expenditure accompanied by the firm appointed by the Commission bears out requisite supporting documents. It was for the latter's assertions whereas IDE's asser- these reasons that it ceased paying its finan- tions to the contrary have not been proved. cial contribution to IDE.
I-832
IDE v COMMISSION
122. IDE objects by stating (paragraph 16 of sion does not act within the prescribed its statement in reply to the defence and in period it is to be deemed to have approved answer to the counterclaim) that adjustment the subcontracting. of the statement of expenditure already lodged and submission of the comprehensive final report made little sense because the Commission had made known early on its intention not to pay the remainder of its contribution. IDE, however, remained pre- pared to meet those requirements. 125. The Commission maintains that IDE failed to fulfil its contractual obligations because (a) it concluded subcontracts with- out prior approval and (b) it resorted to the services of Hungarian undertakings for the performance of part of the work programme.
123. Since IDE did not lodge, within two months after the delivery of its work, the comprehensive final report covering the whole project, the consolidated statement of expenditure or the final supporting docu- 126. In reply to the Commission's assertion ments, it is clear that it failed to fulfil its that, in the course of the project, the compo- obligations under Article 3.3 of the contract. sition of the group of organizations collabo- rating with IDE had been continuously changed, IDE admitted that changes had in fact taken place but it denied any responsi- bility in this regard. Those changes, accord- ing to IDE (see p. 7 of the letter sent to the Commission on 2 May 1993, referred to 3) The composition of the group of organi- above), were due to economic reasons which zations collaborating with IDE was changed led certain members of the original group to without the approval of the Commission withdraw or to the irresponsible behaviour of the original partners.
124. Article 6.2 of the contract provides that 127. However, IDE insists that the Commis- the contractor may entrust the performance sion approved those changes expressly or of part of the work programme to third par- tacitly, in conformity with Article 6.2.2, and ties subject to the condition that the drafts of that all the rights and obligations of the part- all subcontracts are to be notified by regis- ners who withdrew were transferred to the tered letter to the Commission, which may, new co-contractors. This proves, according provided it acts within 15 working days fol- to IDE, that there was no problem with lowing the receipt of such a letter, refuse to regard either to the approval of subcontracts approve the subcontracting. If the Commis- by the Commission or to the supervision of
I-833
OPINION OF MR COSMAS — CASE C-114/94
the whole of the work programme, which it establishment of a plan of action for setting was required to undertake in its capacity as up an information services market. It appears coordinator of the work of the group. from the recitals in the preamble to and the provisions of that decision that the plan of action was directed at organizations in the Member States of the European Communi- ties and was intended to set up a Commu- nity information services market. 128. There is no provision in the contract which places an obligation on IDE to ensure that the composition of the group remains stable from the beginning to the end of the project. That means that IDE could, with the express or implied approval of the Commis- sion, change, for reasons of its own, the 131. Moreover, the technical annex (p. 3 of composition of the group of organizations the original version and p. 2 of the amended collaborating with it. The Commission's version) indicates that, during the course of assertions to the contrary are therefore the Disnet project, IDE was to work closely unfounded. with a number of organizations from seven (original version) or ten (amended version) Member States. As the Commission rightly points out, it therefore excludes non- Community companies from participating in the group entrusted with carrying out the 129. According to the Commission, con- Disnet project. trary to the provisions of the contract, IDE subcontracted, without its prior authoriza- tion, certain work to Hungarian undertak- ings (p. 9 of the defence). It stresses that the Impact programme concerns the Commu- nity information services market and that therefore, by subcontracting work to Hun- 132. I D E states that all it did use was some garian undertakings, IDE acted in breach of Hungarian workers and that, in conformity its contractual obligations. with Hungarian law, the temporary recruit- ment of workers must be notified to a spe- cific organization which registers this (para- graph 17 of the rejoinder in the counterclaim proceedings). IDE counters the Commis- sion's assertion that it resorted to subcon- 130. According to Article 1 of the contract tracts which were not authorized under the between the Commission and IDE, at issue contract by claiming that in each case it noti- in this case, the contract was concluded in fied the subcontracts, as required under the framework of the Community's Impact Article 6 of the contract, and it produces a programme on the basis of the Council's registered letter concerning six new partners Decision of 26 July 1988 9 concerning the but not the disputed subcontract with a Hungarian company (Annex VIII to the statement in reply to the defence and in 9 — Referred to in footnote 3. answer to the counterclaim).
I-834
IDE v COMMISSION
133. The Commission's assertion, so far as it interface; and (b) the integration of that concerns one Hungarian company, is sub- interface in a number of applications in dif- stantiated by a photocopy of a contract ferent sectors and different functions. dated 29 August 1990 which it has produced (Annex VI of the statement in rejoinder in the original action and in reply in the coun- terclaim proceedings). That contract con- cerned the carrying out of that part of the Disnet project relating to the natural lan- guage component. Accordingly, IDE's denial that it concluded a contract with a Hungar- ian undertaking is untenable.
136. According to the technical annex, the two phases would normally be executed con- secutively. That means that as soon as the intelligent interface was ready it could be used for applications. However, since that 4) IDE's relations with the other members of would take too much time, the timescale of the consortium the Impact I project being two years, certain activities coming under the second phase were to be carried out concurrently as from the commencement of the first phase in order to prepare the participants for the sub- sequent application and integration of the 134. Under Article 6.1 of the contract, the intelligent interface as a toolkit for their spe- contractor is to have technical and financial cial human interfacing needs. responsibility for the work and is to provide the personnel, the facilities, equipment and materials necessary for the proper perfor- mance of the contract. In so far as the work is to be carried out by organizations associ- ated with the contractor for this purpose, the contractor is responsible for ensuring that the Community financial contribution is shared amongst the participating organiza- tions according to the progress of work and the participation of each organization. 137. The Commission stresses that IDE, contrary to Article 6.1 of the contract and the terms of the technical annex and although it accepted technical responsibility for the performance of the work, failed to send its partners in good time an operational version of the toolkit. That omission pre- 135. The technical annex (p. 16 of the origi- vented them from starting work in good nal version and p. 10 of the amended ver- time on the adaptation of the toolkit in ques- sion) provides that the project has two tion to the specific requirements of their phases: (a) the building of the intelligent databases.
I - 835
OPINION OF MR COSMAS — CASE C-114/94
138. In support of its assertion, the Com- 141. At the same time, IDE states that mission refers specifically to the letter which unforeseen additional work on the natural one of the members of the consortium sent language module, the telecommunications on 4 June 1993 to IDE (Annex V to the network and the functions relating to that statement in rejoinder in the original action network overloaded the timetable for the and in reply in the counterclaim proceed- performance of the work. ings) which describes in detail IDE's omis- sions in relation to the delivery of the soft- ware which would allow it to begin its own work.
142. Whether IDE did or did not send to the other members of the consortium an opera- tional version of the toolkit a year before the expiry of the deadline for the completion of the whole project and whether a year was long enough to enable them to carry out 139. The Commission also refers to the min- their part of the work are questions of evi- utes of the meeting of the 17 partners of IDE dence. IDE has not furnished any proof of in the Disnet project, which took place in its assertion on those points so that the Luxembourg on 18 May 1993 (Annex III to assessment contained in the abovementioned the statement in rejoinder in the original minutes of IDE's partners' meeting will have action and in reply in the counterclaim pro- to suffice. ceedings), according to which the progress of the project had been unjustifiably delayed by IDE. The same document also indicates that it was not until February 1993 that IDE's partners received a release of the toolbox which should have been ready by November 1992 and that in July 1993 only a small num- 143. The Commission further maintains that ber of partners had been able to create IDE also failed to fulfil its obligation to allo- operational applications with that toolkit. cate the Community contribution between its partners, that is to say that it failed to ful- fil its financial obligations under Article 6.1.
140. IDE, on the other hand, maintains that 144. In support of its assertion, the Com- it sent in good time, that is to say one year mission produced (a) the abovementioned before the expiry of the deadline for the minutes of the meeting on the progress of completion of the whole project, the opera- the Disnet project held on 18 May 1993, tional version of the toolkit which it was to where it is stated (at paragraph 3.3) that IDE send to the other members of the consortium failed to pay its partners the share of the so that they could carry out the parts of the Community contribution due to them; and project allocated to them. (b) letters addressed to IDE containing cora-
I - 836
IDE v COMMISSION
plaints from two of the members of the paid were set off against the expenditure group collaborating with it (Annexes IV and incurred by the training which it had to give V to the statement of rejoinder in the origi- to the collaborator from that organization in nal action and in reply in the counterclaim order to enable him to perform his task in proceedings). In the first letter, dated 29 Sep- the context of the completion of the pro- tember 1993, the company points out to IDE gramme. that it would not deliver to it the product which it was to provide until the share of the Community contribution owing to it was paid. Mention is also made in the second let- ter, of 4 June 1993, of non-payment of amounts owing from the Community contri- bution. 147. Thus, the arguments put forward by IDE in this case, apart from being contradic- tory, do not fully substantiate its assertions, which must therefore be rejected for that reason.
145. IDE denies having failed to fulfil its obligation to pay its partners the share of the Community contribution due to them and to that effect produces a number of statistical reports (Annex XI to the statement in reply 5) IDE's allegation that the Commission to the defence and in answer to the counter- failed to fulfil its contractual obligations claim). However, those reports merely prove the existence of a current account for the transactions between IDE and its partners. Moreover, it justifies its conduct by main- taining (at paragraph 16 of the rejoinder in the counterclaim proceedings) that the other members of the group collaborating with it 148. Under Article 6.3 of the contract the had not received any amounts because the contractor must, without delay, provide the advances paid were set off against the expen- Commission with full particulars of any inci- diture incurred by it on behalf of the whole dent or event likely to prejudice the perfor- consortium and, in any event, because the mance of the contract. Commission had not paid it the total amount of the contribution.
149. According to IDE (p. 3 of its letter to the Commission of 2 May 1993, referred to 146. In particular, IDE considers the com- above), the Commission failed to meet its plaints made by two of the members of the responsibilities because it did not reply to consortium to be unfounded because, in one IDE's repeated warnings concerning the dif- case, the partner in question did not deliver ficulties encountered in executing the project the program it was to supply, while in the as a result of the need to carry out unex- other case, the amounts which were to be pected additional work, which gave rise to
I-837
OPINION OF MR COSMAS — CASE C-114/94
the delays in drawing up Disnet project 153. Although IDE's assertions do not reports for the Community. establish that the Commission's conduct was contrary to the provisions of the contract, in other words, although they find no basis in the contract, they nevertheless leave open the question of the extent to which they may justify the Court's apportioning liability, a matter which I will examine below.
150. The contract concluded by the Com- mission with IDE did not impose any par- ticular obligation on the former to take spe- cific measures where the other party to the contract informed it of financial or technical difficulties in proceeding with the pro- gramme. VI — Other claims made in the application
151. More generally, in conformity with the spirit of the contract, IDE alone is respon- 154. In the event that the Court should sible for carrying out the project in its capac- allow the principal claim in IDE's applica- ity as the other party to the contract with the tion and order the Commission to pay it the Community, as Articles 1 and 6.1 of the con- remainder of the contribution, I will examine tract categorically state. 10 next the other heads of claim in the applica- tion.
152. Accordingly, IDE's assertion, referred to above, that the Commission failed to fulfil 1) Claim for the payment of extra-judicial its obligations under the contract is expenses unfounded. Moreover, its assertion that such failure on the part of the Commission pre- vented it from duly performing its obliga- tions has no basis in the contract and must also be rejected as unfounded.
155. IDE claims the payment of E C U 37 650 10 — See point 41 et seq. of the Opinion of Advocate General to cover extra-judicial expenses which, it Lenz in a similar case: Case C-209/90 Commission v Feil- bauer [1992] ECR I-2613. explains, it incurred for 'legal advice'.
I-838
IDE v COMMISSION
156. It is for IDE to prove that it incurred the contract and consisting in the non- such costs. However, since it has not pro- payment of the whole amount of the contri- duced any supporting documents, the claim bution due to it under the contract is admis- in question must be rejected as unsupported sible and well founded. by any evidence.
2) Claim for the payment of interest (a) Admissibility
157. IDE claims interest at the rate pre- scribed by law and calculated from 31 May 1993, the date on which it sent a letter to the Commission rejecting a proposal to reduce 160. I would observe that, in its originating the amount of the contribution due and application, IDE claimed damages to make demanding payment of the total amount of good the loss suffered by it because: (a) it ECU 376 435. had come close to insolvency as a result of its unfavourable situation in the market, lost goodwill, restricted its commercial activities and been forced to sell at a low price a large number of its assets (a building and motor cars); (b) it had dismissed most of its staff, which led to the stagnation of its activities 158. In view of the purely ancillary nature of and damaging delays on account of the need the abovementioned claim, interest must nec- to train new members of staff; and (c) it suf- essarily also be awarded if the principal claim fered the unfavourable consequences of the is allowed. devaluation of the E C U as against the florin. However, it reserved to a later date the detailed quantification of the exact amount of the damage suffered.
3) Claim for damages
161. Subsequently, in its reply, IDE quanti- 159. I will now consider whether IDE's fied the amounts as follows: (a) E C U claim for damages to make good the loss it 27 332.61 for the sale at a low price of says it has suffered as a result of conduct by a building belonging to the undertaking the Commission in breach of the terms of and the removals necessitated thereby;
I-839
O P I N I O N OF MR COSMAS — CASE C-114/94
(b) E C U 3 188.80 for the sale of two that request and sets a value on the amount company motor cars; (c) E C U 54 554.35 of the damage, the claim for compensation for dismissing most of its staff and being for damage formulated in the reply may be obliged to train new members of staff; and regarded as an amplification of the claim (d) E C U 68 331.52 for the considerable delay contained in the application and therefore as in entering the market, resulting in loss of admissible. 13 customers and goodwill. It failed, however, to quantify the amount of the damage it suffered as a result of the devaluation of the E C U against the florin.
164. In its application to the Court IDE sat- isfactorily defined from the outset the subject-matter of its claim. This means that the fact that it formulated its claim for com- pensation in the originating application, 162. Since IDE has not specified in its appli- without quantifying precisely the amount of cation the amount of the damage it suffered, the damage, which it did in its reply, does the admissibility of its claim poses a prob- not render that claim inadmissible, except for lem. The Court may consider this question the limb concerning damage suffered as a of its own motion, 1 1basing itself, obviously, result of the devaluation of the E C U against on its Rules of Procedure, since Article 16 of the florin but not quantified by IDE. the contract at issue, relating to the applica- tion of Luxembourg law, must be considered to refer only to the provisions of substantive law. 12
(b) Substance
163. Under Article 38(1)(d) of the Rules of Procedure of the Court, the application must state, inter alia, the form of order sought by 165. With regard to the question whether the applicant. The Court has held that, if an the claim is well founded, the Commission applicant includes in his application a request maintains that: (a) IDE must accept liability for a declaration with regard to the damage for the damage suffered by it because this is which may result from the contested meas- expressly provided in Article 8.1 of the con- ure and specifies in the course of the written tract; and (b) there is no causal link between and oral procedures the subject-matter of the damage suffered by IDE and any con- duct on the part of the Commission (pp. 6
11 — Joined Cases 19/60, 21/60, 2/61 and 3/61 Fives Lille Cail and Others v High Authority [1961] ECR 281. 12 — See paragraphs 4 and 10 in Commission v Zoubek, referred 13 — Case 25/62 Plaumann v Commission [1963] ECR 95. See to in footnote 5. See also point 7 of the Opinion of Advo- also Cases 74/74 CNTA v Commission [1975] ECR 533, cate General Tesauro in Case C-330/88 Grifoni v EAEC paragraph 47, and Case 90/78 Granaria v Council [1979] [1991] ECR I-1045. ECR 1081, paragraph 6.
I-840
DDE v COMMISSION
and 7 of the defence). O n those grounds, it 168. The first condition is not met because requests the Court to reject IDE's claim. the Commission has not failed to fulfil any of its contractual obligations. Even if the Court were to find otherwise, the second condition would not be met either because IDE describes the damage which it has suf- fered by specifying the amounts making up that damage, but does not adduce any evi- dence as to the actual damage and its extent. 166. As regards the first of the Commis- That lack of evidence makes it impossible to sion's arguments, I would observe that judge the extent to which there is a causal according to Article 8.1 of the contract IDE link between the damage suffered by IDE assumes sole responsibility for any damage and the Commission's conduct. or injury suffered by it in or in connection with the performance of the contract. That clause refers, however, to damage arising from matters unrelated to the contract. In the present case IDE requests compensation for damage which it claims to have suffered as a result of the fact that the Commission 169. In conclusion, even if the Court were did not fulfil its principal contractual obliga- to uphold the principal claim formulated by tion, namely to pay the whole of the agreed IDE in its application, namely for an order contribution. The contract does not appear, that the Commission pay the remainder of prima facie, to exclude the Commission's the contribution, its other claim, which is in liability in such an event. damages, should be dismissed, first, because it is unfounded and, secondly, because it is unsubstantiated by any evidence.
167. For it to be held that there is liability on the part of the Commission requiring it to compensate IDE, the three conditions for VII — Possibility of apportioning liability contractual liability must be met: 1 4(a) the between the Commission and IDE Commission must have failed to fulfil one of its contractual obligations; (b) IDE must have suffered damage; and (c) there must be a causal link between the conduct of the Com- mission in breach of the contract and the damage suffered by IDE. 170. I will now consider whether, in the event that the interpretation of Article 5.3 of 14 — For the conditions governing contractual liability in French the contract which I have proposed above is law, the rules of which are altogether similar to those of Luxembourg law, see Gerard Légier's analysis in his article not accepted by the Court, it is none the less 'Responsabilité Contractuelle' in Dalloz: Encyclopédie possible, in view of the applicable national Juridique. Repertoire de Droit Civil, vol. VIII, 2 n d ed., 1992, paragraph 17 et seq. law, in this case the law of the Grand Duchy
I-841
O P I N I O N OF MR COSMAS — CASE C-114/94
of Luxembourg, to apportion liability (a) there must exist an obligation to pay between the two parties, in this case between damages; (b) the person seeking damages the Commission and IDE. must have contributed through fault (action or omission) on his part to the breach by the defaulting party of his contractual obliga- tions; 16 and (c) that there must exist a causal link between the conduct of the injured party and the origin or aggravation of the damage he has suffered. A — Conditions governing the apportion- ment of liability
173. Where the conduct of the victim of the damage constitutes force majeure, that is to 171. Under the law governing contractual say if it is unforeseeable and inevitable, the liability, a contracting party who has not ful- defaulting party is exempted if no fault filled all his contractual obligations, or has attaches to him as a result of his act or omis- fulfilled them only in part, must make good sion. However, if it is proven that the con- the damage which his non-performance, be it duct of the injured party was neither unfore- total or partial, has caused to the other party seeable nor inevitable and contributed to an to the contract. In particular, Articles 1147 extension of the damage, then such conduct and 1148 of the Luxembourg Civil Code may lead to a partial exemption of the indicate when the party who has failed to defaulting party, if such conduct constitutes perform his contractual obligations is exempt fault. 17 from the obligation to pay damages. 15
174. For the most part such conduct (action or omission) of the victim constitutes fault. 172. French academic legal writing and Most often it concerns 'negligence' or 'a cer- French case-law conclude, on the basis of tain lack of care'. 1 8If, however, it appears analogous articles of the French Civil Code, that the conduct ascribable to fault has not whose content is altogether similar to the given rise to the damage but merely contrib- abovementioned articles of the Luxembourg uted to it, the court holds the defaulting Civil Code, that the problem of apportion- ment of liability is to be resolved as follows: 16 — See, for example, A. Weil and F. Terré Droit civil:les obliga- tions, Paris, Dalloz, 3 rd edition, 1980, paragraph 415, p. 483. 17 — Ibid. 15 — Article 1147 provides that a defaulting party is to be 18 — See Gérard Légier's analysis in his article 'Responsabilité ordered, where appropriate, to pay damages for non- Contractuelle' (referred to above in footnote 14), paragraph performance, or late performance of an obligation when- 186, and that of Genevieve Viney, in 'Les Obligations. La ever he fails to show that the breach stems from an external Responsabilité: Conditions', in Traité de Droit Civil (under cause which cannot be attributed to him and that there is the direction of J. Ghestin), vol. IV, Paris, LGDJ, 1982, no bad faith on his part. Article 1148 provides that no dam- paragraph 426 et seq. See also the analysis of Henri, Léon ages are to be awarded where, as a result of force majeure or and Jean Mazeaud i n 'Traité Théorique et Pratique de la unforeseeable circumstances, the defaulting party was pre- Responsabilité Civile Délictuelle et Contractuelle', vol. II, vented from giving or doing that which he was obliged to Paris, Montchrestien, 6 t h edition, 1970, paragraph 1447 et give or do, or has done that which he was forbidden to do. seq.
I-842
IDE v COMMISSION
party to be partially exonerated. 1 9With B — Proposed solution regard to contracts, the case-law does not appear to admit of the partial exoneration of the defaulting party where the injured par- ty's conduct does not amount to fault. 20 Once it has been established that the injured party's fault contributed to the occurrence of the damage, the court adjudicating on the 176. As I have already said, the Commission merits determines how liability is to be and IDE concluded a synallagmatic contract apportioned on the basis either of the gravity under which the former undertook to pay a of the fault on the part of the defaulting certain sum by way of contribution for the party and the injured party respectively, or performance of work by the latter, namely of the causal link between each such case of the creation of Disnet. This means that we fault and the supervening damage. Accord- are concerned with a contract under which ingly, the findings made by the court adjudi- the defaulting party, in this case IDE, is cating on the merits with regard to the exist- required to obtain a specific result (obliga- ence and gravity of the fault and the tion of result), that is to say that its principal apportionment of liability are therefore not obligation consists in the delivery of a spe- open to review. cific product. At the same time IDE was to perform a number of other obligations, of a secondary nature, which, as shown, it did not perform. 175. Where the defaulting party is required to produce a specific result (obligation of result), 21 that is to deliver a given product, liability is normally apportioned, where no fault on his part has been proved, on the basis of the causal link existing between the damage and the fault on the part of the 177. The Commission paid to IDE a large injured party, although the courts tend also part of the contribution due. The fact that to take into account the gravity of the the work was not successfully completed led fault. 22 to its decision to call for refund of the advance payments together with interest, pursuant to Article 5.3 of the contract.
19 — On the question of liability as apportioned by Luxembourg courts, see the judgments of: the Tribunal d'arrondissement (Distri« Court), Diekirch, of 10 May 1988, Case N o 5687; of the Tribunal d'arrondissement, Luxembourg, of 21 October 1983, Case N o 776/83, of 1 March 1984, Case N o 259/84, of 19 December 1984, Case N o 832/84, of 10 December 1987, Case N o 37251, and of 14 November 1991; and the judg- ments of the Cour d'appel (Court of Appeal) of 12 Decem- ber 1984, Case N o 7235, of 13 December 1984 (two judg- ments), and, finally, of 25 April 1985, Case N o 7403. 178. In the present case, the Commission 20 — See Gérard Légier's analysis in his article on 'Responsabilité has suffered damage giving rise to an obliga- Contractuelle' (referred to above in footnote 14), paragraph 187. tion on the part of IDE to repair it, inas- 21 — For the distinction to be drawn between the duty to exercise skill and care and obligations as to the results to be achieved, much as the damage suffered by the Com- see by way of guidance the analysis by Alex Weil and François Terré in the work referred to in footnote 16, paragraph 396 et mission is the result of its having paid most seq.; see also Gérard Légicr's article referred to at footnote 14, of the contribution without receiving from paragraph 188, and Fernand Derrida's analysis in his article 'Obligations' in Dalloz: Encyclopédie Juridique. Répertoire de the other party the agreed consideration. Droit Civil, vol. VII, 2 edition, 1992, paragraph 47 et seq. This means that there exists a causal link 22 — See Gérard Légier's analysis referred to above in footnote 14, paragraph 188. between the damage suffered by the
I-843
OPINION OF MR COSMAS — CASE C-114/94
Commission and IDE's breach of its con- 181. The claims put forward by IDE, which tractual obligations. are intended to show that the Commission acted wrongfully, are, however, unfounded. In so far as IDE submitted a project with a view to concluding a contract with the Com- mission involving a financial contribution by the latter towards the work it was to carry out, IDE should have taken into consider- ation all the factors which might make that 179. None the less, it may not be concluded project be more costly than expected and, that the Commission contributed by its fault accordingly, requested from the outset a (action or omission) to IDE's breach of its readjustment of the amounts specified in the contractual obligations, which gave rise to contract, that is to say the total cost of the damage. In other words, the necessary executing the project and the corresponding causal link between the Commission's con- contribution by the Commission. None the duct and IDE's breach of its obligations, less, this fact alone does not prove any which constitutes the event giving rise to the neglect on the part of the Commission which damage, is lacking. Moreover, the Commis- prevented IDE from fulfilling its obligations sion's intention in paying advances on its and which should be taken into consider- contribution was, ultimately, to bring about ation with a view to apportioning liability the realization of the objective of the project, between the two contracting parties. and for this reason it would be incorrect to conclude that it acted wrongfully and that liability should therefore be apportioned between itself and IDE.
182. It is true that although the Commis- sion, as it emphasizes, repeatedly had evi- dence of the improper manner in which IDE was performing its obligations and was aware, through the reports drawn up by the experts appointed by itself, particularly the 180. IDE charges the Commission with one report of 3 December 1991 (Annex I to the fundamental failure to fulfil its obligations. It defence), that the whole programme was not states that the budget made available to it by being implemented as agreed, it refrained the Commission for carrying out the agreed from taking at an earlier stage certain mea- work was inadequate because it did not cor- sures, in particular termination of the con- respond to the expenditure necessary in tract, as it was entitled to do under Article order to complete the work required by the 10; it waited until IDE had finally completed Commission (paragraph 1 of the statement in the whole project. reply to the defence and in answer to the counterclaim).* At the same time IDE points out that the unexpected additional work relating to the natural language processing module, the telecommunications links and related functions overburdened the original budget (p. 3 of the letter to the Commission 183. However, it would not be justified to of 2 May 1993, referred to above). conclude that, in this case, there is a causal
I-844
IDE v COMMISSION
link between, on the one hand, IDE's failure VIII — Costs to fulfil its contractual obligations and the resultant damage to the Commission and, on the other, the conduct of the Commission, which continued to pay its contribution not- withstanding the other party's defective per- formance of its obligations.
185. Under the first subparagraph of Article 184. Consequently, I consider that in the 69(3) of the Rules of Procedure the Court present case the requirements for an appor- may order that the parties bear their own tionment of liability are not satisfied, since costs if each party succeeds on some and fails on the Commission's part there was no fault on other heads. Since, as I have indicated contributing to IDE's breach of its contrac- above, the Commission's claims can be tual obligations which was the cause of the upheld only in part, the parties should bear damage suffered by the Commission. their own costs.
IX — C o n c l u s i o n
186. F o r the foregoing reasons I therefore p r o p o s e that the C o u r t should give j u d g - m e n t in the following terms:
(1) I D E ' s application is dismissed.
(2) T h e C o m m i s s i o n ' s counterclaim is allowed in p a r t and I D E is o r d e r e d t o p a y t o t h e C o m m i s s i o n t h e s u m of E C U 305 9 8 1 , t o g e t h e r w i t h interest at 7.97% per annum from o n e m o n t h following t h e date (29 J u n e 1994) o n w h i c h t h e C o m m i s s i o n requested r e i m b u r s e m e n t of t h e s u m s already paid, that is t o say as from 29 J u l y 1994.
(3) T h e parties are o r d e r e d t o bear their o w n costs.
I - 845