← Späť na vyhľadávanie
Súdny dvor Európskej únie·29.5.1997

C-304/96

ECLI:EU:C:1997:272

Súd
Súdny dvor Európskej únie
IČS
61996CC0304

HERA v USL GENOA A N D ROMAGNOLI

OPINION OF ADVOCATE GENERAL LENZ delivered on 29 May 1997 *

A — Introduction low, with the result that the contract was awarded to Impresa Romagnoli SpA.

1. This reference for a preliminary ruling from the Tribunale Amministrativo Region- 4. The contracting authority based its ale (Regional Administrative Court), Liguria, decision on Law N o 109 ('Legge quadro in concerns the Community legislation govern- materia de lavori pubblici'), 2 in the version ing the award of public works contracts. resulting from Decree-Law N o 101 of 3 April 1995, 3 and Law N o 216 of 2 June 1995. 4 Article 21(la) of Law No 109 pro- vides that 'until 1 January 1997, 5 tenders in which the percentage discount exceeds by more than one-fifth the average of the dis- counts in all the tenders admitted shall be 2. O n 19 December 1995 the Unità Sanitaria excluded from public works contracts for Locale N o 3, Liguria (the local health auth- amounts above or below the Community ority), published an invitation to tender for threshold'. works relating to the internal reorganization and technological adaptation of the 'Vecchio Istituto del Presidio Socio Sanitario' in Genoa. ' According to the invitation to ten- der, the contract was to be awarded to the tenderer offering the maximum discount against the base price of LIT 16 463 000 000. 5. Hera brought an action contesting the decision to exclude it from the tendering procedure, relying in particular on the rel- evant provisions of Council Directive 93/37/EEC of 14 June 1993 concerning the coordination of procedures for the award of public works contracts. 6 Article 30 of that 3. Hera SpA submitted the best tender, offering a discount of 17.3%. However, that bid was excluded from the tendering pro- 2 — Published in Supplement N o 29 to the Gazzetta Ufficiale cedure on the ground that it was abnormally della Repubblica Italiana (GURI) N o 41 of 19 February 1994. 3 — GURI N o 78 of 3 April 1995, p. 8. 4 — GURI N o 127 of 2 June 1995, p. 3. This amended Decree- Law N o 101 and converted it into a law. * Original language: German. 5 — Emphasis added. 1 — See the original text in Italian. 6 — OJ 1993 L 199, p. 54.

I - 5687

OPINION OF MR LENZ — CASE C-304/96

Directive concerns the criteria on which However, until the end of 1992, 7 if current awards are to be based. Article 30(4) pro- national law so permits, the contracting vides as follows: authority may exceptionally, without any discrimination on grounds of nationality, reject tenders which are abnormally low in relation to the works, without being obliged to comply with the procedure provided for in the first subparagraph if the number of such tenders for a particular contract is so high that implementation of this procedure would lead to a considerable delay and jeop- 'If, for a given contract, tenders appear to be ardize the public [interest] attaching to the abnormally low in relation to the works, the execution of the contract in question. contracting authority shall, before it may Recourse to this exceptional procedure shall reject those tenders, request, in writing, be mentioned in the notice referred to in details of the constituent elements of the ten- Article 11(5).' der which it considers relevant and shall verify those constituent elements taking account of the explanations received.

6. The national court concluded that, in the case before it, the contracting authority had correctly applied the Italian legislation pro- The contracting authority may take into viding for the exclusion of abnormally low consideration explanations which are justi- tenders. It held, however, that there was a fied on objective grounds including the 'clear discrepancy' between that legislation economy of the construction method, or the and Article 30(4) of Directive 93/37. technical solution chosen, or the exception- ally favourable conditions available to the tenderer for the execution of the work, or the originality of the work proposed by the tenderer.

7. The national court accordingly concluded that, in order to arrive at a decision in the dispute before it, it was necessary to seek a preliminary ruling from the Court of Justice under Article 177 of the EC Treaty. It there- fore referred to the Court the question If the documents relating to the contract whether the Community rules allow — and provide for its award at the lowest price ten- dered, the contracting authority must com- municate to the Commission the rejection of tenders which it considers to be too low. 7 — Emphasis added.

I - 5688

H E R A v USL G E N O A A N D R O M A G N O L I

if so in what cases — a Member State to therefore to be upheld. It is clear from the make temporary exceptions regarding the order for reference that the national court is entry into force of directives where the ^ter asking whether provisions such as Article set an express time-limit. 8 21 (la) of Law N o 109 are compatible -with Article 30(4) of Directive 93/37 regarding the treatment of abnormally low tenders.

B — Analysis

10. The Italian Government takes the view Admissibility that there is no need to give a ruling on this ' question. It maintains that Directive 93/37 does not authorize the Member States to derogate from its provisions. Besides, in Cos- tanzo, I0 the Court has already ruled that the 8. It appears from the facts described that provisions applying at the time of that judg- the question here is whether, after 31 ment — which corresponded to Article 30(4) December 1992, the Italian authorities were of Directive 93/37 — have direct effect. Thus entitled to allow derogations from a provi- the judgment in Costanzo gave the national sion of Directive 93/37, which was to be court all the information needed to adjudi- transposed into domestic law by 19 July cate in the dispute before it. That court 1990 at the latest. As the Commission has should therefore refuse to apply the relevant rightly observed, the question referred by part of Article 21 (la) of Law N o 109 on the the national court has further implications. ground that it is contrary to Directive 93/37. The real question before the Court is, very generally speaking, whether a Member State may unilaterally postpone the date of entry into force of a directive and, if so, subject to what conditions. It is not, however, the Court's role in exercising its jurisdiction under Article 177 of the Treaty to deliver advisory opinions on general or hypothetical 11. I agree that the reply to the question questions. 9 referred may be deduced from Costanzo, as well as from the judgment in Furlanis. n It should nevertheless be emphasized that in principle it is for the national court to assess whether or not it is necessary to seek a pre- liminary ruling, having regard to the circum- 9. The Commission's proposal that the stances of the individual case. The fact that it wording of the question be adjusted ought is relatively simple, on the basis of existing

8 — Emphasis added. 10 — Case 103/88 Fratelli Costanzo v Comune Ji Milano [1989] 9 — See Case C-83/91 Mediche v ADV/ORGA [1992] ECR ECR 1839. 1-4871, paragraph 25. 11 — Case C-143/94 Furlanis v ANAS [1995] ECR 1-3633.

I - 5689

O P I N I O N O F MR L E N Z — CASE C-304/96

case-law, to answer a particular question Directive 89/440/EEC of 18 July 1989. 14 referred for a preliminary ruling does not in The measures implementing Directive itself mean that the question is inadmissible. 89/440, which was notified to the Member States on 19 July 1989, were to be adopted by the Member States in the year following its publication at the latest. 15 That deadline expired on 19 July 1990. The aim of Direc- tive 93/37 was to consolidate Directive 71/305 together with the provisions amend- ing it since the date of its adoption. I 6 That is why — as the Commission has rightly 12. By way of an aside, I would point out pointed out — that Directive did not set the that the Italian Government refers in its Member States a time-limit for its implemen- observations to the fact that the Minister tation. On the contrary, the applicable time- responsible called on the authorities con- limits are those that were fixed for the vari- cerned, by circular of 7 October 1996, 12 to- ous amending directives. interpret and apply Article 21(la) of Law N o 109 consistently with Directive 93/37. Any inferences to be drawn from that circular — which was published after the main proceed- ings were initiated — are a matter for the national court.

14. However, Article 29(5), fourth subpara- graph, of Directive 71/305 (corresponding to The question Article 30(4), fourth subparagraph, of Direc- tive 93/37) authorized, subject to strict con- ditions, and until the end of 1992, the rejec- tion of abnormally low tenders without the need to follow the verification procedure laid down in the first subparagraph. The Court has already ruled (in Furlanis) that that pro- vision must be narrowly construed and is 13. As the Commission has pointed out, the available only for procedures in which the rule set out in Article 30(4) of Directive definitive award was made by 31 December 93/37 corresponds in this case to that previ- 1992 at the latest. 17 A provision of domestic ously contained in Article 29(5) of Council law under which the verification procedure Directive 71/305/EEC of 26 July 1971 con- referred to above may continue to be waived cerning the coordination of procedures for after that date is therefore manifestly incom- the award of public works contracts. , 3 That patible with Directive 93/37. provision had been introduced by Council

14 — OJ 1989 L 210. p. 1. 12 — Published in Supplement N o 179 to G U R I N o 251 of 25 15 — Anicie 3 of Directive 89/440. October 1996. 16 — See the first recital in the preamble to Directive 93/37. 13 — OJ, English Special Edition 1971 (II), p. 682. 17 — Cited above (footnote 11), paragraphs 17 to 22.

I - 5690

HERA v USL GENOA AND ROMAGNOLI

15. The Court has already ruled in Costanzo vidual against the State. IS The same must be that Artide 29(5) of Directive 71/305 is true of Article 30(4) of Directive 93/37, unconditional and sufficiently precise to have which is to a large extent identical to that direct effect and be relied upon by an indi- provision.

C — Conclusion

16. I therefore p r o p o s e that t h e C o u r t reply as follows t o t h e question referred b y the Tribunale Amministrativo Regionale della Liguria:

A r t i d e 30(4) of C o u n c i l Directive 9 3 / 3 7 / E E C of 14 J u n e 1993 c o n c e r n i n g the c o o r d i n a t i o n of p r o c e d u r e s for t h e a w a r d of p u b l i c w o r k s contracts precludes d o m e s t i c legislation a u t h o r i z i n g , after t h e e n d of t h e y e a r 1992, w a i v e r of t h e p r o - cedure laid d o w n therein for t h e verification of a b n o r m a l l y l o w tenders.

18 — Cited above (footnote 10), paragraph 32.

I - 5691

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-304/96 – Súdny dvor Európskej únie | AI Pravnik