C-328/96
ECLI:EU:C:1999:5
- Súd
- Súdny dvor Európskej únie
- IČS
- 61996CC0328
- Zdroj
- eur-lex.europa.eu ↗
OPINION OF MR ALBER — CASE C-328/96
OPINION OF ADVOCATE GENERAL ALBER delivered on 19 January 1999 *
A — Introduction munity law since they infringed, inter alia, the advertising rules, the obligation to inform unsuccessful tenderers and the rules on specifications, and drew the Austrian Government's attention to those findings by letter of 12 April 1995. Some time later, 1. The present proceedings for failure to as a response to that letter, the Commission fulfil obligations under the Treaty concern received notification of a Vergabegesetz the assessment under Community law of (Law on the Award of Contracts) published the award of a series of works contracts in by the Land of Lower Austria on 31 May connection with a large project to construct 1995, which itself gave cause for objection government and administrative buildings since it contained an exemption clause for and a cultural centre forming part of a plan the 'St Polten Land Administrative and to base the government of the Land of Cultural Centre' project (the so-called 'Lex Lower Austria at St Polten. St Polten') and thereby, in practice, exclu- ded the project from the application of the law.
2. The following events underlie the pro- ceedings for failure to fulfil obligations under the Treaty. Work on this large project started in 1992 in the case of the admin- 3. All the issues involved were discussed at istrative centre and in 1994 in the case of a bilateral meeting between the Commis- the cultural centre. At the beginning of sion and the Austrian authorities on 27 and February 1995, a complaint drew the 28 November 1995. The Commission Commission's attention to the invitation alleged infringements of Council Directive to tender for a supply contract in connec- 93/37/EEC of 14 June 1993 1 and Council tion with the project, which was published Directive 89/665/EEC of 21 December only in the Niederösterreichisches Amts- 1989 2 and of Article 30 of the EC Treaty. blatt (Lower Austrian Official Gazette). Having been informed of the objections, The Commission considered that the All- the Austrian authorities gave an undertak- gemeine Angebots- und Vertragsbedingun- ing that the AAVB would be amended, that gen (General Tendering and Contract Con- ditions, AAVB'), on which the invitation to tender was based, were contrary to Com- 1 — Directive concerning the coordination of procedures for the award of public works contracts (OJ 1993 L 199, p. 54). 2 — Directive on the coordination of the laws, regulations and administrative provisions relating to the application of review procedures to the award or public supply and public * Original language: German. works contracts (OJ 1989 L 395, p. 33).
I - 7482
COMMISSION V AUSTRIA
the exemption clause in the Vergabegesetz 6. The Austrian authorities' willingness to would be repealed and that the contracting adapt their award practices did not go far authority, the Niederösterreichische Land- enough for the Commission, with the result eshauptstadt-Planungsgesellschaft mbH that, by letter of formal notice of (hereinafter 'Nöplan'), would modify its 15 December 1995, it initiated proceedings practices relating to the award of contracts. for failure to fulfil obligations under the Treaty. In that letter of formal notice, the Commission argued that the Austrian authorities had undertaken to intercede with the responsible decision-making bodies in order to ensure compliance with 4. The Commission hoped that, as a result Community law from the end of January of the discussions, the Austrian authorities 1996 onwards. 3 In the letter of formal would take immediate action by ensuring notice the Commission stated, inter alia, that that it was extending its complaints 'speci- fically to include those lots for which the contract has already been awarded but where the tendering procedure was not in conformity with Community law'. It requested the Republic of Austria 'to ensure — the award procedures still to be initi- that Community law is complied with in ated would be carried out correctly, the contracting procedures still outstand- ing' and 'to suspend the legal effects or prevent the completion of contracts already awarded in contravention of Community law, to defer pending award decisions until such time as compliance with Community — the procedures already initiated but not law is secured, and to ensure that the yet concluded by the award of con- Lower Austrian Vergabegesetz and the tracts would be corrected, and AAVB are amended without delay'. 4 In the letter of formal notice of 15 December 1995, the Commission laid down a period of one week for the submission of observa- tions.
— contracts awarded in contravention of Community law but not yet performed would, as far as possible, be cancelled. 7. The Austrian Government replied by letter of 22 December 1995. In that letter it stated that, notwithstanding the 'schedul- ing difficulties made known at the bilateral meeting', Nöplan's bodies were 'looking 5. The Austrian authorities agreed in prin- into the subject of contract awards' and ciple but pointed out that they would require a sufficient transitional period in 3 — See point 6 of the letter of formal notice. order to amend the relevant legal provi- 4 — See point 10, first and fifth paragraphs, of the letter of sions (Vergabegesetz and AAVB). formal notice.
I - 7483
OPINION OF MR ALBER — CASE C-328/96
had decided 'that Nöplan must apply the 9. In the meantime, the Nöplan award EU directives with immediate effect'. 5 committee had decided, at a meeting on Finally, it is again stressed 'that, notwith- 6 February 1996, to suspend all pending standing additional costs and scheduling procedures and to invite tenders for and disruptions, the EC directives must be award, in conformity with Community law, applied with immediate effect to all invita- the contracts still to be awarded. Subse- tions to tender'. 6 quently, the defects complained of in regard to the Vergabegesetz were remedied and the AAVB were brought into conformity with Community law. Since then, the contract- ing practices followed have been manifestly in accordance with Community law. 8. In its reasoned opinion of 21 February 1996, the Commission pointed out that the contracting authorities of the Land of Lower Austria were 'under an obligation resulting directly from the directly applic- able Community legislation to comply with the requirements thereof in the absence of transposition in conformity with Commu- 10. Nevertheless, on 3 October 1996, the nity law'. 7The Commission also consid- Commission brought an action for failure ered that the Austrian Government's reply to fulfil obligations under the Treaty, which to the letter of formal notice was inade- was registered at the Court on 7 October quate. In that reply it could find no 1996, seeking a declaration that the Repub- acknowledgement of an obligation to act lic of Austria had failed to fulfil its in respect of pending procedures, 'since the obligations under Community law in observations concerning the obligation to awarding contracts, which were concluded advertise ... relate only to the future'. The before 6 February 1996 but which, on Commission pointed out that it had asked 7 March 1996, that is, at the time of expiry the Austrian Government 'to send it a list of the period laid down in the reasoned of the contracts for which an award opinion of 21 February 1996, had not yet procedure has already been initiated or will been performed or could reasonably have be advertised in the future, and to give it been cancelled. In essence, the Commission details of the values of those orders'. It alleges that the Republic of Austria made stressed: 'To date no satisfactory list has no effort to cancel the contracts awarded been sent'. Finally, it requested the Austrian after the bilateral meeting of 28 November authorities 'to take all appropriate steps to 1995, that is, when it was aware of the put an end to the infringements problems with respect to Community law. described'. 8For that purpose it prescribed a period of two weeks from notification of the opinion.
5 — See point 1 of the reply of 22 December 1995; emphasis added. 6 — See 'With regard to point 8' in the reply of 22 December 11. The Republic of Austria puts forward 1995; emphasis added. several objections to the admissibility of the 7 — See point 15 of the reasoned opinion of 21 February 1996. action which it also considers to be sub- 8 — For the citations in this paragraph, see point 16 of the reasoned opinion of 21 February 1996. stantively unfounded.
I - 7484
COMMISSION V AUSTRIA
12. The Commission claims that the Court under Council Directives 93/37/EEC of should: 14 June 1993 and 89/665/EEC of 21 December 1989 and under Arti- cle 30 of the EC Treaty in connection with the construction of a new admin- istrative and cultural centre for the 1. Declare that the Republic of Austria Land of Lower Austria at St Polten in has failed to fulfil its obligations under awarding contracts, which were con- Council Directives 93/37/EEC of cluded before 6 February 1996 but 14 June 1993 9 and 89/665/EEC of which, on 7 March 1996, had not yet 21 December 1989 10 and under Arti- been performed or could reasonably cle 30 of the EC Treaty in connection have been cancelled; with the construction of a new admin- istrative and cultural centre for the Land of Lower Austria at St Polten in awarding contracts which were con- cluded before 6 February 1996 but which, on 7 March 1996, had not yet 2. Order the European Commission to been performed or could reasonably pay the costs. have been cancelled;
2. Order the Republic of Austria to pay 14. I will come back to the arguments of the costs. the parties in the course of the legal assessment.
13. The Republic of Austria claims that the Court should:
B — Opinion
1. Dismiss as inadmissible (if appropriate, as unfounded) the European Commis- sion's action of 7 October 1996 for a declaration that the Republic of Aus- tria has failed to fulfil its obligations I. Admissibility
9 — Directive concerning the coordination of procedures for the award of public works contracts (cited in footnote 1). 10 — Directive on the coordination of the laws, regulations and 15. The Austrian Government considers administrative provisions relating to the application of the action inadmissible on a number of review procedures to the award of public supply and public works contracts (cited in footnote 2). grounds.
I - 7485
OPINION OF MR ALBER — CASE C-328/96
1. Inadmissibility of the subject-matter of fronted with new complaints in the appli- the proceedings cation.
The Austrian Government asserts that the subject-matter of the proceedings, as indi- 17. The question is therefore whether the cated by the form of order sought by the complaint of failure to cancel contracts action, renders the action inadmissible. It awarded before 6 February 1996 constitu- argues that the Court has consistently held tes a new and thus inadmissible plea. In this that the subject-matter of proceedings for regard, the pre-litigation procedure and the failure to fulfil obligations under the Treaty form of order sought by the action must be is delimited by the pre-litigation procedure. examined in the light of the actual course of It is determined by the Commission's events. reasoned opinion.
The action may therefore not be founded on complaints other than those referred to in the reasoned opinion. The demand that contracts awarded in 18. The Commission's letter of formal contravention of Community law but not notice of 15 December 1995, which was yet performed should, as far as possible, be addressed to the Austrian Government cancelled is not found in the Commission's following the bilateral meeting of 27 and reasoned opinion of 21 February 1996. It is 28 November 1995, objects, on the one at most touched upon in the letter of formal hand, to a legal situation which is contrary notice of 15 December 1995. The com- to Community law and, on the other, to plaint referred to in the action, namely, of award practices contrary to Community failure to cancel contracts which could still law which are based on that situation.
The be cancelled, on which the form of order request for the immediate bringing of the sought is decisively based, is therefore award practices into conformity with Com- inadmissible. munity law 1 1is to be found in the letter of formal notice. Elsewhere, the Commission extends its complaints 'specifically to 16. It must be conceded to the Austrian include those lots for which the contract Government that the Court has consistently has already been awarded but the tendering held that the subject-matter of proceedings procedure was not in conformity with for failure to fulfil obligations is defined by Community law'. 12 Finally, the Commis- the pre-litigation procedure and the form of sion requests the Republic of Austria 'to order sought by the action. At the same ensure that Community law is complied time, the application may not contain any with in the award procedures still out- complaints which are fundamentally differ- standing. It further requests the Republic of ent or new as compared with those dis- Austria to suspend the legal effects or cussed in the pre-litigation procedure. That prevent the completion of contracts already approach can be explained by reference to awarded in contravention of Community the structure of proceedings for failure to law [and] to defer pending award decisions fulfil obligations under the Treaty, which until such time as compliance with Com- gives the parties an opportunity to reach an munity law is secured, .
. .'. 13 amicable settlement in the course of the pre-litigation procedure, before the matter is referred to the Court. Moreover, the 11 — See the letter of formal notice, at point 7, paragraph 1. Member State's rights of defence must be 12 — See the letter of formal notice, at point 10, paragraph 1. safeguarded, so that it may not be con- 13 — Letter of formal notice, point 10, paragraph 5.
I - 7486
COMMISSION V AUSTRIA
19. Those words clearly express not only 21. Moreover, neither the reasoned opinion the Commission's requirement that further nor the actual course of events suggested conduct contrary to Community law be that the request to intervene in award prevented with immediate effect, but also procedures already being implemented, the demand that award decisions taken in which had already been made in the letter contravention of Community law be denied of formal notice, had been complied with. operative effect. However, the latter It may be assumed from this that the demand can only imply retaking such Austrian Government understood the decisions subsequently in a manner consis- Commission's request in the sense tent with Community law. An obligation to described here. In its reply of 22 March cancel award decisions already taken must 1996, it devoted over three-and-a-half therefore be inferred from the Commis- pages to commenting on these issues, under sion's request as formulated in the letter of the heading 'The contracts already awar- formal notice. ded'. 16 Any allegation of a breach of the principle of a fair hearing, which could be inferred from the objection to admissibility, is therefore also without foundation.
20. A request to intervene in award proce- dures already subject to implementation cannot be inferred with equal certainty from the Commission's reasoned opinion of 22. The Austrian Government is of the 21 February 1996. Nevertheless, it may be opinion that an express request to cancel inferred from the reasoned opinion that contracts already awarded should have pending procedures are included in the been included in the reasoned opinion. general complaint that award practices The steps to be taken should have been were contrary to Community law. When specified. Once a number of points, such as the Commission takes the view that the amendment of the Lower Austrian Verga- undertakings given by the Austrian Gov- begesetz and the AAVB, had been men- ernment concerning the obligation to tioned, it was entitled to expect that no advertise in the future expressly do not go further measures would be required. far enough, and when it complains that they do not cover 'those cases of awards where contracts are, for example, adver- tised nationally', 1 4there can be no doubt that the Commission is identifying breaches 23. That view cannot be accepted. The of Community law in respect of past award Court has held 17 that the Commission is practices and is demanding that they be not required to specify what steps are to be remedied. Thus the Commission empha- taken to remedy a situation which is sises 'that it is incumbent on the Austrian contrary to the Treaty. That allocation of authorities to take all appropriate steps to tasks is also sensible since it is a Member put an end to the infringements State's responsibility to decide how and by described'. 15
16 — See the Austrian Government's reply of 22 March 1996, at 14 — See the reasoned opinion, at point 16, paragraph 4. Chapter IV. 15 — See the reasoned opinion, at point 16, paragraph 6; 17 — Judgment in Case C-247/89 Commission v Portugal emphasis added. [1991] ECR I-3659.
I - 7487
OPINION OF MR ALBER — CASE C-328/96
what means it will comply with the 2. Putting an end to the infringements requirements of Community law. If the before the expiry of the period laid down Commission were required to specify the in the reasoned opinion steps to be taken, jurisdictional conflicts would arise whenever the Member State has discretion as to the manner in which it creates a situation which is in conformity with Community law. 26. The Austrian Government points out that under the second paragraph of Arti- cle 169 of the Treaty and the case-law relating thereto the material time for the existence of a Treaty infringement is the end of the period laid down in the reasoned opinion. However, on that date, 7 March 24. Nor, in this case, did the Commission 1996, Austria had put an end to all the create a legitimate expectation which infringements complained of in the rea- would have entitled the Austrian authori- soned opinion. ties to assume that, by amending the legal situation, they had done everything neces- sary to remedy the Treaty infringement. On the contrary, as already explained, the Commission included the pending proce- dures in the letter of formal notice. In the reasoned opinion it expressly drew atten- 27. The AAVB, it submits, have been tion to the obligations resulting 'directly amended along the lines required by the from the directly applicable Community Commission and, in their new version, have legislation' for the contracting authorities formed the basis for all invitations to of the Land of Lower Austria in the tender published in accordance with Com- 'absence of transposition in conformity munity provisions since as long ago as with Community law' 18 and emphasised 12 December 1995. Moreover, the award that it was incumbent on the Austrian practices have also been modified since authorities to take all appropriate steps to 6 February 1996. Since that date, the put an end to the infringements. working committee on awards has no longer approved award recommendations submitted to it for a decision, and has decided to terminate immediately all pend- ing award procedures not conducted in conformity with Community law and to hold a new invitation to tender in confor- 25. Against that background, the com- mity with Community law. Award deci- plaint of failure to cancel contracts con- sions in respect of contracts with a total cluded in contravention of Community law value of ATS 217 000 000 were deferred, can be regarded as falling within the and by 7 March 1996 contracts with a total subject-matter of the proceedings properly value of approximately ATS 470 000 000 defined in the form of order sought by the had been put up for tender and awarded in action. conformity with Community law. Since the Austrian authorities had complied with the requests on 7 March 1996, the action is 18 — See the reasoned opinion, at point 15, paragraph 2. claimed to be inadmissible.
I - 7488
COMMISSION V AUSTRIA
28. The Commission replies that the situa- 3. The determination of periods in the pre- tion was not completely regularised on litigation procedure 7 March 1996. The contracts already awarded but not yet performed on 6 Feb- ruary 1996, and the contracts already awarded and (partly) performed but which 31. The Austrian Government further could still reasonably have been cancelled claims that the periods prescribed in the on 6 February 1996, remained in place. pre-litigation procedure were too short, with the result that, for that reason also, the action for failure to fulfil obligations under the Treaty is inadmissible. It refers to Austria's federal structure in which certain decision-making processes are bound to 29. It is in fact the case that, by its action take certain time. The period of one week for failure to fulfil obligations under the laid down in the letter of formal notice and Treaty, the Commission is no longer bring- that of two weeks laid down in the ing the charge that the legal situation is reasoned opinion were extremely short. contrary to Community law, any more than As early as 25 January 1996, the Commis- it is criticising the award practices followed sion informed the international press that it after 6 February 1996. It nevertheless con- had decided to address a reasoned opinion siders that the failure to cancel, within the to Austria, but that opinion was not bounds of possibility, contracts concluded notified until 21 February 1996. in contravention of Community law con- stitutes a continuing infringement of the Treaty. As already observed above, it has admissibly made that plea the subject- matter of the action. 32. The Commission should also have taken into consideration, when setting the periods, the fact that its complaints referred exclusively to the past since, as notified to the Commission on 7 February 1996, the Austrian authorities had adapted their 30. Since the Commission considers and award practices since 6 February 1996. alleges that there existed, at the time of Finally, it submits that the period of 21 expiry of the period laid down in the days provided for in Article 3(3) of Direc- reasoned opinion, a situation which it tive 89/665 is an indication of what con- regards as contrary to Community law stitutes a reasonable period. and which continues to produce legal effects, the requirements as to the admissi- bility of the action should be met. Whether an infringement of the Treaty actually existed at the material time is a question concerning the substance of the action. 33. The Commission, on the other hand, Thus, although on 7 March 1996 the takes the view that the shortness of the Austrian authorities had already complied periods was reasonable under the circum- with the Commission's requests in substan- stances. According to the information pro- tial respects, the action is admissible in vided by the Austrian authorities, contracts respect of the complaints still subsisting. of substantial value were still outstanding
I - 7489
OPINION OF MR ALBER — CASE C-328/96
at the beginning of December. An assurance only the periods prescribed in the docu- that those contracts would be awarded ments served on the Member State can be with due regard for Community law and binding. A Member State cannot act on that pre-existing infringements would be 'hearsay' in the context of a formal pre- remedied therefore had to be obtained from litigation procedure. There can therefore be the Austrian Government as quickly as no question of regarding the period possible. between learning of the Commission's intentions through the press and formal service of the opinion as preparation time. 34. The Austrian Government's reply to the letter of formal notice allowed doubts to subsist as to its willingness to correct all the 36. Beyond the purely legal assessment, I infringements complained of. Nor did it also consider it bad form to publish a press send the promised list with the calculation release about the imminent dispatch of a of the value of contracts still to be awarded. reasoned opinion in Treaty infringement The Commission had to assume that, even proceedings against a Member State when at the beginning of 1996, a significant the document in question is not served on volume of contracts was still due to be the Member State concerned until almost awarded and had to prevent the creation of four weeks later. The Commission could a fait accompli. Nor did the complaints in have allowed a longer period by dispatch- the reasoned opinion refer only to the past. ing the reasoned opinion at an earlier date. The Commission definitely had in view the Earlier dispatch would have been possible situation existing at the time of expiry of under the circumstances. the period laid down in the reasoned opinion. Finally, the Austrian Government had learned prematurely of the Commis- sion's intentions through the press, so that it may not rely on the unreasonableness of 37. For the remainder of the examination, the periods. therefore, it must be assumed that only the periods prescribed in the pre-litigation documents are relevant.
35. It is appropriate to begin the examina- tion of the objection to the admissibility of the action by considering this last point. It 38. In order to be able to assess the must be assumed that the procedure pre- reasonableness of a period, it is first ceding the Treaty infringement action is important to ascertain what response it is subject to a certain stringency of form. This hoped to elicit within the prescribed period. is borne out by the requirements governing Alteration of a legal situation can certainly the designation of the subject-matter of not be expected to take place within a proceedings and the reasonableness of period measured in weeks. Thus, the pre- periods to be complied with, which, if not litigation procedure was certainly con- observed, result in inadmissibility of the cerned in part with a clause in the Lower action. Matters which are of importance to Austrian Vergabegesetz which was contrary the Member State concerned must be to Community law. There is no dispute that unambiguously apparent from the Com- amendment of the law had not yet been mission's documents marking the indivi- carried out when the period laid down in dual stages of the procedure. Consequently, the reasoned opinion expired on 7 March
I - 7490
COMMISSION V AUSTRIA
1996. The procedure was not concluded Government complied with the request by until May 1996. Nevertheless, in that means of the statements in its reply of respect the Commission refrained from 22 December 1995. The discrepancy bringing the action for failure to fulfil between words and actions must be exam- obligations under the Treaty, since the ined separately. amendment of the law entered into force without significant delay.
39. What mattered to the Commission, 42. With regard to the circumstances at the however, was that the Austrian Govern- time of the adoption of the reasoned ment should realise and formally acknowl- opinion, it is striking that it was only after edge that the situation was contrary to the formal decision to dispatch the rea- Community law so that, on the one hand, soned opinion had become known in the further awards of contracts could be pre- press that the award committee, on 6 Feb- vented and, on the other, the contracts ruary 1996, took the decision, inter alia, to awarded in contravention of Community suspend current award procedures. The law could, as far as possible, be cancelled. Commission therefore had reason to sup- pose that the Austrian authorities were creating a fait accompli and that urgency was required. Viewed in that way, the short period of two weeks laid down in the 40. In response to the letter of formal reasoned opinion also seems reasonable. notice of 15 December 1995 the Austrian Government also gave an assurance, within the period of one week, that it would, 'with immediate effect', 19 apply the Community directives to the contracts still to be awar- ded. In reality, however, the authorities continued to award the contracts still out- standing. The award committee's decision 43. The possibility of applying for interim to suspend the current procedures, which legal protection, to which attention was had been expected earlier, was not taken drawn in both pre-litigation documents and until 6 February 1996. which was also raised at the hearing, must also be viewed in this context. Under Article 186 of the Treaty, the Court may prescribe necessary interim measures only in cases already pending before it. How- 41. In view of the urgency of stopping ever, an action under Article 169 of the further awards of contracts, at least for the Treaty may be brought only after the pre- time being, the period of one week was litigation procedure has been concluded. reasonable in this case. Indeed, the Austrian Where there is increased danger in any delay, the Commission must therefore bring the pre-litigation procedure to a rapid 19 — The Austrian Government's reply of 22 December 1995, conclusion in order, as far as possible, to pp. 2 and 7. prevent irreparable infringements.
I - 7491
OPINION OF MR ALBER — CASE C-328/96
44. That situation may be regarded as a but it fails to provide a definition of weakness of the system, but it can be reasonableness. The form of order sought remedied only by amendment of the rele- is therefore too imprecise to form the basis vant legal bases. Nor do the possibilities of an obligation to act resulting from provided for by Directive 89/665 20 offer a Article 171 of the Treaty, thus rendering satisfactory solution as a way out of the the action as such inadmissible. dilemma. The directive applies primarily to the relationship between the tenderer and the contracting authority. Moreover, the possibilities afforded to the Commission in Article 3 of the directive are not suited to all situations and in any case do not limit 47. The Commission takes the view that the Commission's authority to initiate pro- the Court is not required to rule on what is ceedings for failure to fulfil obligations and what is not to be regarded, in specific under the Treaty. terms, as reasonable in a Member State. That is the task of the national courts applying national law. Observations on the question of reasonableness are therefore irrelevant from the outset in the context of 45. In the light of all the foregoing con- these proceedings before the Court. siderations, the periods prescribed by the Commission in the pre-litigation procedure must be regarded as reasonable under the circumstances. 48. On this point, the Commission's view must be endorsed without qualification. It is neither the task of the Commission nor 4. The clear and precise nature of the form that of the Court to investigate the possi- of order sought by the action bilities for cancelling contracts concluded in the field of public procurement. On the contrary, an instruction — whether from the Commission or the Court — to cancel a 46. The Austrian Government expresses contract under a Member State's legal rule legal reservations about the phrase 'con- to be specified would constitute an ultra tracts, which were concluded before 6 Feb- vires act by the Community institutions vis- ruary 1996 but which, on 7 March 1996, à-vis that Member State's authorities. That had not yet been performed or could freedom of the Member State to choose the reasonably have been cancelled' in the form form and the means must necessarily also of order sought by the action. By using the find expression in a request by the Com- expression 'could reasonably have been mission to put an end to a situation cancelled', the Commission shows that it, contrary to the Treaty. This relative lack too, does not think that there is an of precision as regards the steps to be taken unlimited obligation to cancel contracts, is therefore, in the final analysis, a mani- festation of the division of powers between the Community and the Member State. The 20 — See the Directive on the coordination of the laws, wording at issue defines the objective of regulations and administrative provisions relating to the unwinding contracts awarded in contra- application of review procedures to the award of public supply and public works contracts (cited in footnote 2). vention of Community law within the
I - 7492
COMMISSION V AUSTRIA
limits of what is legally possible. The form II. Merits of order sought is therefore not open to objection.
51. The Commission points out, firstly, that Austria has been required to comply 5. Legal interest in bringing proceedings with the provisions of Community law, including the legislation on the award of contracts, since its accession to the EEA Agreement with effect from 1 January 1994 and, a fortiori, since the date of its 49. The question concerning the legal inter- accession to the European Union, that is est in bringing the present action represents 1 January 1995. an objection to admissibility which, while not expressly raised by the Austrian Gov- ernment, nevertheless follows implicitly from the objections to admissibility which are raised by it. When the Austrian Gov- ernment asserts that the infringements 52. It alleges that, in the case of the concerned are by their very nature irrepar- contracts awarded in the period from able, it is indeed questionable whether any 27 November 1995 to 6 February 1996, interest is served by an abstract finding of which had a total value of more than failure to fulfil obligations under the ATS 360 000 000, Austria infringed sev- Treaty. The Austrian Government's view, eral provisions of Community law. Thus, that the denunciation of a Member State is Articles 8, 10(6), 11(6) and (11), 12 and 30 neither the subject-matter nor the purpose of Directive 93/37, Article 30 of the Treaty of Treaty infringement proceedings, must and Articles 1(1) and (3) and 2(l)(c) of be endorsed. Directive 89/665 were infringed. The Com- mission sets out the alleged infringements in detail. There is, it argues, no justification under Community law for the conduct engaged in during the period in question, 50. In order to assess the legal interest in which was aimed at 'getting the contracts bringing proceedings, it is important to home and dry'. ascertain whether the Commission's request is directed towards an objectively impossible act or whether there are ways and means of complying with the Commis- sion's requirements, on the basis that the material time is the end of the period laid down in the reasoned opinion. The issue 53. As evidenced by the Austrian Govern- thus identified is ultimately a question to be ment's reply to the reasoned opinion, the answered in the examination of the merits Austrian authorities consciously acted 'at of the action. The answer to the question their own risk'. Modification of the award concerning the legal interest in bringing practices would not, unlike amendment of proceedings must therefore await an exam- the Vergabegesetz, have necessitated any ination of the merits of the action. time-consuming procedures, a fact proved
I - 7493
OPINION OF MR ALBER — CASE C-328/96
by the award committee's decision adopted 56. In conclusion, the Austrian Govern- subsequently. Finally, the award of some of ment raises two points of law of a funda- the contracts in question 21 could have been mental nature. Firstly, it brings up the legal delayed without harm to the project as a status of Nöplan, and links to that the whole. question of how far individuals are entitled to rely on a directive as against that institution. Secondly, it considers that it has not been made clear why the large St Polten project should have been made 54. The Austrian Government takes the subject to the directives on the award of view that the cancellation of contracts contracts since as long ago as Austria's concluded in contravention of Community accession to the European Economic Area. law cannot be required in the context of The project, which must be viewed as a Treaty infringement proceedings. The sec- whole and therefore cannot be divided up, ond paragraph of Article 2(6) of Directive was started even before the entry into force 89/665 leaves a Member State free to limit of the EEA Agreement and before Austria's itself to awarding damages to any person accession to the Community. harmed by an infringement. In principle, the Commission cannot require more in proceedings under Article 169 of the Treaty.
55. Moreover, it submits, the Commission 57. The Commission replies that its powers shows that even it does not assume that under Article 169 of the Treaty are separate there is an absolute obligation to cancel from the procedure under Directive 89/665. contracts. In any case, the principle of the The Court has already found to that effect protection of legitimate expectations pre- elsewhere. 2 2 With regard to Nöplan's role, cludes such an obligation. The legitimate it observes that it has indisputably been expectations of parties to a contract are unanimously assumed that Nöplan is to be worthy of protection and take precedence regarded as the extension of the Land of over the Commission's application. Finally, Lower Austria in its function as a contract- the practical effect of Directive 93/37, in ing authority. the form of equal conditions of competi- tion, can no longer be ensured even by the cancellation of contracts. The initially suc- cessful tenderers had made arrangements giving them clear advantages over their competitors. Cancelling the contracts con- cerned would have entailed stopping the construction work and therefore, in the 58. For reasons of methodology, it is final analysis, have been impossible for that appropriate to begin the examination with reason also. the last-mentioned legal reservations expressed by the Austrian Government.
21 — Final cleaning of the Lower Austrian Land government building, public-address system for the shopping centre, 22 — Judgment in Case C-359/93 Commission ν Netherlands planting in the grove, etc. [1995] ECR I-157, at paragraphs 13 and 14.
I - 7494
COMMISSION V AUSTRIA
59. The question as to the applicability of 3. Where a work is subdivided into several the Community legislation on the award of lots, each one the subject of a contract, the contracts at the time of the Republic of value of each lot must be taken into Austria's accession to the EEA can be left account for the purpose of calculating the aside here since that legislation in any case amounts referred to in paragraph 1. Where became binding on the acceding Member the aggregate value of the lots is not less State by virtue of its membership of the than the amount referred to in paragraph 1, European Community on 1 January 1995 the provisions of that paragraph shall apply and did so — unless transitional periods to all lots. Contracting authorities shall be had been expressly negotiated — immedi- permitted to depart from this provision for ately upon accession. lots whose estimated value net of VAT is less than ECU 1 000 000, provided that the total estimated value of all the lots exempted does not, in consequence, exceed 20% of the total estimated value of all lots.'
60. The Commission has already expressed the view in the pre-litigation procedure that Directive 93/37 concerning the coordina- tion of procedures for the award of public 61. With regard solely to the value of the works contracts is applicable, pursuant to contract for the building services control Article 6 thereof, to the construction pro- system, which was the original cause of the ject. 2 3 dispute, the Commission stated in the reasoned opinion:
Article 6(1) and (3) provide: '... Although the value of the contract for the building services control system, for which tenders were invited only on a regional basis, is approximately ATS 26 - million, that is, below the threshold value laid down in the directive, the provisions of '1. The provisions of this Directive shall the directive are applicable to such a apply to public works contracts whose contract pursuant to the second sentence estimated value net of VAT is not less than of Article 6(3) (threshold value exceeded ECU 5 000 000. 24 when lots are aggregated)'. 2 5
62. That legal assessment, that is to say the finding that the contract is subject to Community law, is correct and also applies
23 — See the reasoned opinion, at point 13. 24 — ECU 1 is equivalent to ATS 13.7789 (as at 1.12.1998). 25 — See the reasoned opinion, at point 13.
I - 7495
OPINION OF MR ALBER — CASE C-328/96
to other contracts forming part of the eral meeting and finance committee) are project as a whole. Apart from its reference appointed by the owners . . . ' . 26 to the legal status of Nöplan, the Austrian Government has not otherwise adduced before the Court any facts which might preclude the applicability of the relevant directives.
64. Throughout the procedure before the Court the parties have assumed that Nöplan is an 'extension' ('verlängerter 63. The reference to the legal status of Arm', lit. 'extended arm') of the Land Nöplan should now be examined. That Government of Lower Austria. That term, body has already been the subject of although non-technical, graphically discussions in the preliminary stage of these describes the dependency of the legal proceedings, including with regard to its person on the politically responsible Land status. The annexes to the application authorities. The basic decision of 6 Febru- include a letter of 12 May 1995 from the ary 1996 to suspend the current proce- Austrian Government to the Commission, dures, which fundamentally changed the setting out the control structure of Nöplan, course of the proceedings, was taken by the which states: 'Vergabeausschuß' (Award Committee).
'... The N ö Landeshauptstadt Planungsge- sellschaft mbH (Nöplan) was established as a private-law partnership for the purpose of 65. Article 1(b) of Directive 93/37 defines carrying out all planning measures neces- contracting authorities as: 'the State, regio- sary in connection with the construction of nal or local authorities, bodies governed by the capital of the Land of Lower Austria, St Polten. Its ownership is 5 1 % in the hands of the Land of Lower Austria, 10% 26 — See the letter of 12 May 1995 from the Austrian Govern- ment to the Commission, at Annex 3 to the application. in the hands of the city of St Polten and The Austrian Government's reply of 22 December 1995 to 39% in the hands of the NO HYPO the Commission's letter of formal notice states: 'With regard to point 8 Leasinggesellschaft mbH. The award of Nöplan is not only a partnership established for the exclusive purpose of carrying out all the planning measures contracts with a value exceeding ATS 2 - necessary in connection with establishing St Polten as the million requires the approval of the award Land capital of Lower Austria. On the contrary, its activities also include, in addition to the construction committee. The award committee is schemes involved in that, a multitude of other schemes, including private residential and industrial and commercial appointed by the Land Government of construction projects, for which Nöplan has to compete Lower Austria. The members of the other commercially.' The purpose of the partnership has not been raised further organs of Nöplan (supervisory board, gen- as an issue before the Court.
I - 7496
COMMISSION V AUSTRIA
public law, associations ...'. It goes on to The lists of bodies and categories of bodies state: governed by public law which fulfil the criteria referred to in the second subpara- graph are set out in Annex I ....'
'A "body governed by public law" means 66. The Land of Lower Austria, as a local any body: or regional authority, is indisputably a contracting authority. Even if one does not wish to limit oneself to the assessment that Noplan is an 'extension' of the Land, which simply means that responsibility rests ultimately with the Land, viewing Nöplan in isolation also leads to a similar result. According to the account 27 of the — established for the specific purpose of purpose, legal personality and economic meeting needs in the general interest, control structure of Nöplan given by the not having an industrial or commercial Austrian Government in its letter of character, and 12 May 1995, the company fulfils the criteria 28 laid down in the second subpar- agraph of Article 1(b) of Directive 93/37 for classification as a 'body governed by public law'. Such a body is to be regarded as a contracting authority within the mean- ing of the directive. 2 9
— having legal personality, and
67. The question as to which body is liable, in the final analysis, to meet any claims for compensation made by tenderers is one which must be assessed according to the law of the Member State concerned. In any — financed, for the most part, by the event, it is the Member State which is liable State, or regional or local authorities, in relation to the Community. 30 Since there or other bodies governed by public law, or subject to management supervision by those bodies, or having an admin- 27 — Cited above, at point 63. istrative, managerial or supervisory 28 — See the judgment in Case C-44/96 Mannesmann Anlagen- board, more than half of whose mem- bau Austria [1998] ECR I-73, at paragraph 21. 29 — See the judgment in Case C-44/96, cited in footnote 28, at bers are appointed by the State, regio- paragraph 29. nal or local authorities or by other 30 — See most recently to that effect the judgment in Case C-353/96 Commission ν Ireland [1998] ECR I-8565, at bodies governed by public law; paragraph 23.
I - 7497
OPINION OF MR ALBER — CASE C-328/96
is thus no doubt about where liability in in form or in substance, its powers in principle lies under Community law gov Treaty infringement proceedings, which in erning the award of contracts, the issue to principle are wide-ranging. be resolved by the Court boils down to the legal and factual preconditions for the existence of an obligation to cancel con tracts already concluded.
69. A particular problem arises in this case from the fact that the contracts still out 68. It is first necessary to examine the standing as part of the overall project at the technical point that the powers in Treaty time of expiry of the period laid down in infringement proceedings should not go the reasoned opinion were awarded in beyond the possibility, expressly granted conformity with Community law. It must to a Member State by the secondary therefore first be established to what extent legislation, of limiting the consequences of an infringement still existed at that time. a contract award made in contravention of The alleged infringement can be summed Community law to the award of damages up in a short formula : by the conclusion of to the tenderer harmed. The submission contracts awarded in contravention of that both the procedure under Article 3 of Community law, the infringement was Directive 89/665 and Treaty infringement complete but not yet at an end. The proceedings have the same objective must contracts had still to be performed. be endorsed in so far as the objective is defined as compliance with the Community rules on the award of public contracts. However, it must also be borne in mind that the review procedures required by the directive are primarily concerned with the relationship between the tenderer and the contracting authority. The procedure under 70. The following should be said with Article 3 of the directive, which gives the regard to the contracts which were awar Commission power to act, is, as the Court ded. There is no doubt that the award of 31 has expressly held, a preventive measure. those contracts was objectively contrary to The Commission's powers under Arti Community law. A divergence between the cle 169 of the Treaty are neither altered legal situation in the Member State con nor replaced by the special procedure under cerned at that time and the requirements of 32 the directive. It can thus be assumed that Community law is now indisputable. The the powers conferred on the Commission Austrian Government came to share that by Directive 89/665 do not restrict, either assessment in due course and saw to it that both the criticised AAVB and the legal situation were adapted. It can also be assumed that the legislative bodies acted 31 —Judgment in Case C-359/93 Commission ν Netherlands, cited in footnote 22, paragraph 13. See, most recently, the on the basis that the general legislation on judgment in Case C-353/96 Commission ν Ireland, cited in footnote 30, paragraph 22. the award of contracts was applicable to 32 — See the judgment in Case C-359/93 Commission ν Nether the large St Polten project when they lands, cited in footnote 22, at paragraph 14, and the judgment in Case C-353/96 Commission ν Ireland, cited in included the disputed exemption provision footnote 30, at paragraph 22. in the Lower Austrian Vergabegesetz.
I - 7498
COMMISSION V AUSTRIA
71. However, the latter point is not of context: those discussions could have no decisive importance. It is established that legally binding effects. Moreover, initially the award procedures carried out in 1995 the Austrian authorities had, with good were objectively contrary to Community reason, taken a different view and only law. There is no need here to examine in later deferred to the Commission's views. detail the incompatibility of the legislation on the award of contracts which was then in force, since it has been acknowledged by the Austrian authorities and rectified by amending the law to bring it into confor- 75. It is indeed questionable how far the mity with the requirements of Community Austrian Government should have assumed law and the Commission no longer raises that the view expressed by the Commission this issue in these proceedings. at the bilateral meeting was binding. An informal meeting of that kind is not capable of producing direct legal effects. However, it must not be forgotten that, objectively speaking, an infringement 72. It is however questionable to what existed and there was a danger that con- extent, after 27 and 28 November 1995, tinuation of the practices contrary to Com- the objective breach of Community law munity law could have serious and, in part, assumed a different quality to which an irreparable economic consequences. Once obligation to cancel contracts concluded Treaty infringement proceedings had been after that date could, if appropriate, be officially initiated by the letter of formal attached. notice of 15 December 1995, the Austrian authorities were obliged to prevent further damage. As already intimated, that did not require a lengthy procedure to amend the law; provisional suspension pending inves- 73. The Commission takes the view that tigation of the situation would have suf- the Austrian authorities were already aware ficed. The subsequent decision adopted by of the problem with respect to Community the award committee on 6 February 1996 law as a result of the exchange of corre- shows that such an approach was also spondence which took place in the course possible in practice. of 1995. However, the whole issue was discussed in detail at the bilateral meeting on 27 and 28 November 1995, so that, in awarding contracts after that date, the Austrian authorities acted against their 76. I am therefore of the opinion that the better knowledge. awarding of contracts from the time of the official initiation of Treaty infringement proceedings until the decision of 6 Febru- ary 1996 constituted a serious infringement of Community law, to which an obligation 74. The Austrian Government's response is to cancel the contracts in question could to say, as the Austrian Government's repre- undoubtedly also be attached. These sentative expressly pointed out at the were, after all, contracts with a total hearing, that the discussions during the value c o n s i d e r a b l y in excess of meetings took place in a non-binding ATS 300 000 000, which were awarded
I - 7499
OPINION OF MR ALBER — CASE C-328/96
over a period of over six weeks. In so far as also be assessed against that background. the contracts concluded during that period The Commission's demand that the con- were valid and not yet performed on tracts be cancelled was made only with 3 March 1996, the infringement subsisted regard to those contracts which were and the Commission was entitled to require concluded at the contracting authority's cancellation of the contracts. That demand own risk in the knowledge that they were does not seem unreasonable, moreover, possibly contrary to Community law. The since the Austrian authorities expressly Member State could have avoided such a acted 'at their own risk'. 33 Acting 'at one's demand if it had, without delay, taken own risk' can hardly mean creating a fait steps, in the form of a decision such as that accompli to which no penalty can be adopted on 6 February 1996, in order to attached. prevent a fait accompli.
77. When the Austrian Government argues before the Court that it is impossible to 79. This approach is supported by a con- cancel contracts at issue, the nature of that sideration underlying Directive 93/37. Arti- impossibility, whether it is original or cle 7(3)(c) of the directive entitles the subsequent, in law or in fact, matters. In contracting authorities to award their pub- so far as it is subsequent impossibility on lic works contracts by negotiated procedure factual grounds, because the construction when, for reasons of extreme urgency, the project has in the meantime been carried time-limit laid down cannot be kept. How- out, that circumstance cannot in any way ever, the reasons invoked must be attribu- alter the situation with regard to obliga- table to events unforeseen by the contract- tions as at 7 March 1996. Moreover, the ing authorities in question. Court has held that a Member State may not rely on a fait accompli which it itself created so as to escape Treaty infringement proceedings. 34
80. Although the foregoing considerations are valid with respect to alleged cases of de 78. The argument based on the initial facto impossibility, the consequences of de impossibility of cancelling the contracts jure impossibility are still uncertain. The concerned because of the urgency of con- assessment under Community law comes tinuing with the construction work must up against a limitation here. As the Com- mission rightly states, and as has already been touched upon in the examination of 33 — See order of the President of the Court of Justice in Case admissibility, any cancellation of contracts C-87/94 R Commission v Belgium [1994] ECR 1-1395, at paragraph 34, on which the Austrian Government falls within the competence of the Member expressly relies. State. The legal bases and extent of any 34 — See the judgment in Case 39/72 Commission v Italy [1973] ECR 101, at paragraph 10; see also the Advocate General's cancellations are governed by national law Opinion in Case C-247/89 Commission v Portugal [1991] ECR 1-3670, at point 36; see also the order in Case and therefore cannot be established bind- C-87/94 R, cited in footnote 33, at paragraph 40. ingly here.
I - 7500
COMMISSION V AUSTRIA
81. The Austrian Government's submis- particular case is not, as has already been sions are therefore of vital importance. shown, a matter for the Court to assess. They contain a series of reasons explaining why contract cancellation after the event is impossible, yet at no stage is it maintained that this was a case of absolute initial impossibility on legal grounds. Since the 84. Finally, it is necessary to examine the Austrian Government has also consistently Austrian Government's argument that the expressed the view before the Court that practical effect of the directives could no the Commission's demand for contracts to longer be ensured once the contracts had be cancelled was unjustified, it can be been awarded. It is submitted that compe- assumed that it certainly made no attempt titive positions had been affected in such a to comply with the demand at the time. way that the situation which existed before the contracts were awarded could no longer be restored. The tenderers who had origin- ally participated would always have retained a competitive advantage over any subsequent tenderers. That line of argu- 82. For the remainder of this examination ment may be relevant in point of fact. it must be assumed that the impossibility of However, it cannot invalidate any attempt cancelling contracts was in any case not to put an end to illegal conduct. If neces- absolute. Even if there had been only one sary, a new invitation to tender issued on a possibility, the Commission's demand Community-wide basis, for example, would not have sought something which would have enabled undertakings to parti- was impossible. It must therefore be cipate which, under the circumstances, assumed that the Commission's demand simply had no knowledge of the original entailed a legal obligation to act. invitation to tender. Those potential ten- derers cannot — after the event — be individually identified, so that they will never be able to make any claims for damages. 83. The Austrian Government then con- tends before the Court that contract can- cellation was unreasonable because of the legitimate expectations of the parties to those contracts, which takes precedence 85. It must therefore be concluded that, on over the Commission's demand. That argu- 7 March 1996, the Commission's demand ment is mistaken. The Austrian Govern- entailed an obligation to take action, the ment is relying on third parties' legal objective initial impossibility of which it positions which were illegally created by has not been possible to establish. the contracting authority. As far as the fundamental situation regarding a Member State's obligations towards the Community is concerned, a Member State may not successfully rely on the consequences of its 86. Finally, it is necessary to return once illegal conduct in order to call into question again to the question concerning the legal the legal obligation as such. To what extent interest in bringing proceedings, which contract cancellation was reasonable in this could not be answered in the context of
I - 7501
OPINION OF MR ALBER — CASE C-328/96
the examination of admissibility. Since it Costs may be assumed that an abstract obligation to act existed but that the Austrian Gov- ernment has consistently disputed it, a legal interest in bringing proceedings must, for that reason alone, be acknowledged. More- over, a declaratory judgment in the present 87. In accordance with Article 69(2) of the proceedings may play a part in any litiga- Rules of Procedure, the unsuccessful party tion concerning any claims for damages, so is to be ordered to pay the costs. Since the that for that reason also a legal interest in Austrian Government has been unsuccess- bringing these proceedings must be ful in its arguments and submissions, it acknowledged. must be ordered to pay the costs.
C — Conclusion
88. In the light of the foregoing I propose that the Court:
(1) Declare that, in connection with the construction of a new administrative and cultural centre for the Land of Lower Austria at St Polten, the Republic of Austria has failed to fulfil its obligations under Council Directive 93/37/EEC of 14 June 1993 and Council Directive 89/665/EEC of 21 December 1989 and under Article 30 of the EC Treaty in awarding contracts which were awarded after the initiation of proceedings for failure to fulfil obligations under the Treaty and before 6 February 1996 but which, on 7 March 1996, had not yet been performed or could reasonably have been cancelled.
(2) Order the Republic of Austria to pay the costs.
I - 7502