C-156/97
ECLI:EU:C:1999:576
- Súd
- Súdny dvor Európskej únie
- IČS
- 61997CC0156
- Zdroj
- eur-lex.europa.eu ↗
OPINION OF MR MISCHO — CASE C-156/97
OPINION OF ADVOCATE GENERAL MISCHO delivered on 23 November 1999 *
1. In the context of its jurisdiction under 3. Those three companies are: Article 181 of the EC Treaty, the Court of Justice has received an application from the Commission of the European Communities for an order that Van Balkom Non-Ferro Scheiding BV (hereinafter 'Balkom'), a company with which the Commission con- cluded a contract, reimburse to the Com- — Balkom, whose registered office is in mission an overpayment and pay to it Oss, Netherlands, interest on the sum due.
— Van Balkom Seeliger GmbH (herein- after 'VBS'), whose registered office is in Heidelberg, Germany,
both represented at the signing of the contract by their director, Antoon van 2. The contract at issue falls within the Balkom, scope of Council Regulation (EEC) No 3640/85 of 20 December 1985 on the promotion, by financial support, of demon- stration projects and industrial pilot pro- jects in the energy field. 1It was concluded by the Commission on 4 December 1990 and with three companies for the execution by them, in exchange for financial support given by the Community, of a project for the production of energy from crushed motor vehicle scrap metal. — Deutsche Filterbau GmbH, whose * Original language: French. registered office is in Düsseldorf, Ger- 1 — OJ 1985 L 350, p. 29. many (hereinafter 'DF').
I - 1096
COMMISSION V VAN BALKOM
4. Under the terms of the contract, the 6. Under Clause 13 of the contract, juris- three companies are jointly and severally diction to rule on any dispute between the liable vis-à-vis the Community. The Com- parties concerning the validity, interpreta- munity's financial support for the execution tion or application of the contract is of the project is fixed at 17% of the actual conferred on the Court of Justice, but cost, excluding VAT, up to a maximum of under Clause 14, the contract is governed ECU 987 343. by German law. Annex I to the contract contains a programme of work which is divided into five phases: 'Engineering', 'Production and Delivery', 'Installation', 'Demonstration' and 'Final Report and Documentation', and is scheduled for com- 5. Clause 8 of the contract provides the pletion by 30 June 1993, and which the Commission with the option of withdraw- Community's partners undertake to comply ing from it in the event of the contracting with under Clause 2. undertakings' failing to fulfil their obliga- tions, whilst the first paragraph of Clause 9 stipulates that:
7. Performance of the contract encountered various problems which led the Commis- sion, on 16 August 1994, to exercise the 'The present contract may be terminated by termination option open to it under Clause any of the signatories, giving two months' 9, cited above, and, on 29 November 1994, notice, where the programme of work set to claim from Balkom the reimbursement out in Annex I becomes inoperative by of a sum of ECU 334 481, including reason, in particular, of a foreseeable interest. To that end, on 8 February 1995, technical or economic failure or an exces- it drew up a recovery order. sive overrun on the costs of the project in relation to the estimates',
8. Those various problems may be sum- marised as follows: and the third paragraph thereof that:
At the beginning of 1991, the Commission 'If an audit reveals that the amounts paid paid to VBS, as provided in Annex II to the by the Commission are too high, the sum contract, a sum of ECU 296 203, by way of paid in error, plus interest due as from the an advance. On 21 August 1991, DF sent a date of ending or finishing the work letter to the Commission stating that it, DF, stipulated in the contract, shall be reim- was no longer in a position to be involved bursed forthwith by the other party to the in the project since, following measures contract.' adopted within the group of companies to
I - 1097
OPINION OF MR MISCHO — CASE C-156/97
which it belonged, it no longer had a all DF's commitments would be taken on licence for the technology to be implemen- by the new partner. ted.
13. VBS did, however, mention certain 9. In that letter, a copy of which was sent to difficulties which had been encountered in VBS, it was stated that the contractual obtaining permission to build in Heidelberg amendments made necessary by that with- the facilities specified in the contract, which drawal would be made with VBS. made it impossible to comply with the programme of work stipulated, and so it was going to propose that the programme of work should be amended.
10. On 26 August 1991, VBS informed the Commission of DF's withdrawal and told it that the technology which DF was to provide now came under another company 14. So far as this point is relevant, it had in the same group, Deutsche Engineering taken steps to obtain another site, this time der Voest-Alpine Industrieanlagenbau in Thüringen. GmbH, Essen (hereinafter 'DE'), with which VBS had been in contact, so that continuation of the project appeared to it to be fully assured. 15. On 7 October 1991, VBS sent to the Commission the first technical and finan- cial reports, as stipulated in the contract, again referring to the difficulties it was 11. In that same letter, VBS gave assurances encountering in obtaining the necessary that negotiations had begun with DF and administrative permission to construct the that other company in order to draw up the technical facilities. In the light of that necessary contractual provisions, and that report, the Commission made a further the Commission would be kept fully advance payment of ECU 39 169 to VBS. informed of how the negotiations were progressing.
16. On 29 October 1992, VBS sent to the Commission the second technical and 12. Also in that letter, VBS stated that it financial reports, informing it, first, that, would continue to honour its own commit- since the parent company of DF and DE ments ('Selbstverständlich wird sich an der had withdrawn from the high-temperature Einhaltung unserer Verpflichtungen gegen- gasification sector, it had found a new über der EG-Kommission im Rahmen des partner, Veba Oel Technologie GmbH, and Demonstrationsvorhabens nichts ändern') it hoped that the Commission would agree and that, in view of the negotiations which to the latter's involvement and, second, that were under way, it should be assumed that the project required a number of technical
I - 1098
COMMISSION V VAN BALKOM
amendments since different technology was 21. In the Commission's view, the situation to be used. was as follows:
17. A few weeks later, however, VBS wrote — VBS and DF were withdrawing from a letter to the Commission, signed by Mr the project due to economic difficulties; Van Balkom, informing it that for various reasons it was no longer in a position to be involved in the execution of the project and that it was therefore withdrawing from it, relinquishing any rights vis-à-vis the Com- mission which it might have under the — Balkom was continuing the project on contract. the following conditions:
18. It also stated that it would forward to — an amended version of the techni- Balkom all the documents and information cal annex to the contract to be it had acquired so that the project could submitted, continue and requested the Commission's agreement to those measures.
— permission to construct the facil- 19. By further letter of 16 February 1993, ities to be obtained by 31 Decem- VBS asked the Commission to draw up the ber 1993 at the latest, final statement on the basis of the second financial report and informed it of the financial difficulties being encountered by Balkom which would make it impossible to reimburse any overpayment. — no money to be paid by the Com- mission until that date.
20. On 9 March 1993, the Commission sent a letter to Mr Van Balkom, in his capacity as director of Balkom, following a Lastly, the Commission reserved the right, meeting in which he had taken part on if the time-limit set was not complied with, 3 March, in order to establish the project's to terminate the contract under Clause 9 progress. thereof.
I - 1099
OPINION OF MR MISCHO — CASE C-156/97
A copy of that letter was sent to the person discussion', the Commission planned that responsible for the project within VBS. the reimbursement which it was entitled to claim under Clause 9 of the contract could be calculated on the basis of expenditure incurred by the other contracting parties amounting to DM 1 127 800, in so far as 22. On 27 September 1993, Mr Van the corresponding documentary evidence Balkoni, in his capacity as liquidator of was available. VBS, wrote to the Commission in order to inform it of a series of events. It was a matter, first, of the judicial decision refus- ing to allow VBS, by reason of its lack of assets, to initiate bankruptcy proceedings and, second, of Balkom's serious difficulties 26. On 14 April 1994, VBS informed the as a result of the difficulties of the group to Commission of the existence of a buyer, which it belonged. who would be very interested in pursuing the project. By fax of 8 June 1994, the Commission granted to VBS an extension of the time-limit until 30 June 1994.
23. Since Balkom was in a state of insol- vency, it owed its salvation entirely to an agreement between its creditors and its bank and to the arrival of a new investor, who was subsequently to withdraw. In 27. On 29 June 1994, again by fax, VBS's those circumstances, Balkom was not in a lawyer requested the Commission not to state either to continue with the project bring the contract to an end in view of the alone or to meet its commitments in the talks still in progress with a possible buyer. event of termination of its contract with the Commission.
28. On 16 August 1994, by letter sent to both Balkom and VBS, the Commission 24. As regards the matter of VBS being in conveyed its decision to bring the contract liquidation, talks were under way to find a to an end and requested them to produce buyer. However, Mr Van Balkom did not the documents necessary to establish the despair of finding one before the time-limit final accounts, failing which Balkom would expired on 31 December 1993. be required to reimburse, with interest, the full amount of the assistance already paid.
25. On 8 October 1993, by letter to Mr Van Balkom, the Commission confirmed that the time-limit of 31 December 1993 29. On 17 October 1994, Balkom's lawyer was mandatory. On 20 January 1994, in a told the Commission that it was already in 'note which could form a basis for ... possession of the documents it requested, I - 1100
COMMISSION V VAN BALKOM
which had been given to it by VBS, which 33. This summary of the events which took had always dealt with all financial matters. place between the time the contract was signed and the time the case was brought before the Court, as it emerges from the documents produced by the parties, may seem a little long, but I think it will prove useful when it comes to assessing the merits of the arguments between the parties, 30. On 29 November 1994, the Commis- which I shall now set out. sion sent a letter to Balkoni and VBS, telling them that it would not set any further time-limits and that, on the basis of accepted expenditure amounting to DM 34. In the view of the Commission, the 943 662.74, that is to say ECU 492 489, it reason for its action being brought solely was claiming from the debtors, who were against Balkom is that, by March 1993 at jointly and severally liable, reimbursement the latest, DF and VBS were no longer of a sum of ECU 251 649, to which would parties to the contract. Moreover, even if be added ECU 82 832 in interest, due as that withdrawal were not valid, Balkom from 16 October 1994, that is to say a total could, by virtue of the joint and several of ECU 334 480. liability agreed between the Community's three contracting parties, still be in receipt of a claim for the whole amount in respect of which the Commission is entitled to seek reimbursement under Clause 9 of the contract. 31. On 8 February 1995, the Commission issued a recovery order for that amount against Balkom and VBS. 35. As regards the termination of the contract, the Commission claims that, since a precise timetable for performance had been agreed from the outset, it is not a contract of unspecified duration within the meaning of German law, which can be 32. Another three letters followed, the first terminated only vis-à-vis all the parties. For from the Commission, dated 30 May 1995, that reason, the termination of the contract proposing to Balkom that it pay off its debt would still have been valid, although it was in instalments, the second from Balkom's not notified to DF, even if, quod non, DF adviser, dated 15 June 1995, rejecting that had still been a party to the contract on the proposal, and the third, also from Balkom's date it was terminated. adviser, dated 28 June 1995, challenging the validity of the recovery order sent to Balkom and complaining that it was unrea- sonable to make it, Balkom, responsible for 36. As regards the merits of the termina- the entire reimbursement, but proposing, tion, the Commission considers that the none the less, that a compromise be sought. conditions of Clause 9, namely a foresee- Finally, the Commission brought the pre- able economic failure, were clearly satisfied sent action on 23 April 1997. in 1994, in view of the various problems
I - 1101
OPINION OF MR MISCHO — CASE C-156/97
mentioned above, in particular the fact 40. Balkom flatly contradicts those various that, following withdrawal by DF and VBS, arguments. As far as it is concerned, the Balkom itself faced serious financial diffi- contract was never validly terminated. culties and was clearly no longer in a Since this is a contract which it deems to position to complete the project. be of unspecified duration, termination is valid only if it takes effect vis-à-vis all the contracting parties. The Commission has never notified its decision to terminate the contract to DF which, contrary to what the Commission claims, was still a party to the 37. Although scheduled for completion in contract on the day that decision was June 1993, the project was in any case held taken. up because of the lack of permission to construct the facilities needed in order to complete it.
4 1 . Balkom points out in this connection that DF's withdrawal must be regarded as 38. As regards the amount claimed, the assignment of the contract, which may be Commission explains that it has deducted effected only by an agreement between all from the total of the money paid to VBS, the parties, an agreement which, under for which Balkom is jointly and severally Clause 7 of the contract, would have liable, the amount corresponding to 1 7 % needed to be in writing. of the cost excluding VAT of the sums expended, as they appear from the first financial report, which it audited and approved, and points out that, by its letter of 9 March 1993, it had stated that it would make no further payments if admin- istrative permission to construct the facil- 42. The Commission has failed to produce ities were not obtained by 31 December any such document by which the Commis- 1993 at the latest. sion itself, VBS and Balkom agreed with DF the conditions under which DF would withdraw and the transfer of its rights and obligations to its two partners.
39. The Commission adds that it cannot therefore be accused of not having taken action on the second financial report. It claims, moreover, that under the third paragraph of Clause 9 of the contract, on 4 3 . However, even if the termination had the basis of which it terminated the con- been carried out in accordance with formal tract, interest is due as from 1 July 1991, requirements, it would not have been at all since it was on that date that the first phase justified since, according to Balkom, it is of the project, the only one to have been impossible to claim that there was a actually carried out, was completed. foreseeable economic failure.
I - 1102
COMMISSION V VAN BALICOM
44. In order to understand the meaning of 47. In Balkom's view, the refusal to make the term 'economic failure', it is necessary any additional payment, which the Com- to refer to Annex I, A, Point 4 to the mission notified to it by its letter of contract, which deals with the economic 9 March 1993, cannot be regarded as a and technical risks of the contract and decision on the second financial report defines failure in terms of an amount of submitted by VBS. investment which is too high in relation to the conditions prevailing on the market.
48. Lastly, as regards the date as from which interest becomes payable, Balkom disputes the date of 1 July 1991 since, in its view, the date of 30 June 1991 cannot be regarded as the end of the first phase of 45. At the stage reached in the execution of execution of the project, which actually the project, there were no grounds for continued well beyond that dale. stating that the cost of investment would ultimately exceed that amount. Admittedly, the execution of the project had encoun- tered difficulties leading to delays in rela- tion to a schedule based purely on esti- mates, but that by no means supports the Assessment conclusion that there was a foreseeable economic failure within the meaning of the contract. 49. How can one decide between these totally conflicting arguments? I think that, in order to proceed methodically towards a solution, it is necessary to isolate the various issues. In order to ascertain whe- ther the Commission is indeed entitled to 46. Taking its argument a step further, the amount which it is claiming from Balkom contends that the Commission Balkom, it is necessary to examine, first was not able to rely on the third paragraph of all, the validity of its decision to bring of Clause 9 in order to claim repayment of the contract to an end. That validity an overpayment because, since the work depends, in turn, on two conditions: did had not been completed, it was not possible the Commission comply with the formal to calculate the amount of any overpay- requirements laid clown for that termina- ment, and seeks to exercise a right to tion, and was the Commission entitled, in retention over part of the sums claimed by view of the state of the execution of the the Commission, on the ground that the project at the time when it adopted its Commission has not yet adopted a position decision, to exercise the option available to on the second financial report submitted to it under Clause 9 of the contract? The it by VBS, which sets out expenditure for assessment I shall have to make as to the period from 1 July 1991 to 30 June whether the formal requirements for termi- 1992 which is additional to that contained nating the contract were complied with will in the first report, which means an addi- itself depend on whether, contrary to what, tional payment by the Commission. by the Commission's own admission, was
I-1103
OPINION OF MR MISCHO — CASE C-156/97
the case, DF should have been notified of tempted to reply in the affirmative in view the Commission's decision irrespective of of the problems mentioned above. the announcement of its withdrawal.
53. It is true that DF's letter to the Com- 50. Once those various questions have been mission announcing its withdrawal, owing resolved, and assuming that it is concluded to its purely unilateral nature, could not by that the Commission was entitled to exer- itself have the effect of ending the contrac- cise the option to terminate granted to it tual links forged on 4 December 1990 and under Clause 9, it will remain to be seen must be regarded as a declaration of intent, whether the amount to be recovered was an offer of withdrawal and a renunciation calculated correctly by the Commission in of the rights conferred under the contract. respect of both the principal sum and the Was that offer accepted by the other parties interest. to the contract?
54. It seems to me that Balkom is now The validity of the termination of the badly placed to dispute it. The Commis- contract sion's agreement is not in doubt, although it is perhaps surprising that the Commission so readily accepted the defection of a partner who possessed the technology to 51. Let us begin by examining whether the be implemented in the project. It seems to Commission, when it terminated the con- me that VBS's agreement can be inferred tract by its letter of 16 August 1994, from its letter to the Commission of complied with the contract or German 26 August 1991. law, in so far as German law applies in the absence of a different stipulation in the contract. No-one disputes the fact that that letter was sent to VBS and Balkom, but not to DF. Should it have been? 55. Admittedly, in that letter VBS men- tioned the talks intended to resolve the contractual problems associated with DE's involvement in the project, which means that those problems had not been resolved 52. Certainly not, if we must accept as by that date, but it should be pointed out proven that, on that date, of the Commis- that VBS did not at any time impose sion's three original contracting partners, conditions on DF's withdrawal; on the there remained only one, Balkom, even if contrary, it regarded that withdrawal as the termination was also notified to VBS. an established fact, whereas it could have Can we consider that on that date DF no expressed reservations and made its agree- longer had any contractual link with the ment to that withdrawal subject to certain Commission? For my part, I should be requirements being met. I-1104
COMMISSION V VAN BALKOM
56. As regards Balkom, it is true that there principle of good faith, that, by March is no sign in the file of any document which 1993 at the latest, all the parties regarded is contemporaneous with DF's withdrawal DF's withdrawal as an established fact, and and which shows for certain that Balkom that it would be unjustifiably formalistic to agreed to that withdrawal. consider that such an agreement should have taken the form of a single document signed by all the parties.
57. Admittedly, one might be justified in thinking that, if Balkom had had any objections to that withdrawal, of which it cannot have been unaware because it was 60. However, even if, as Balkom claims, on headed by Mr Van Balkom, who was also the basis of German legal literature, the director of VBS, it would have expressed conditions for DF's withdrawal remain them. However, there is no need at all to debatable in view of the nature of the embark on that line of reasoning, which contract, I do not think that it can be would imply that shared management pre- inferred from failure to notify DF of the vailed over the existence of two separate Commission's decision to terminate the legal persons, since we have the letter, contract that that termination was invalid which could not be more explicit, from vis-à-vis Balkom. the Commission to Balkom, dated 9 March 1993, in which withdrawal by DF, and also by VBS, is presented as an established fact, a letter which followed discussions in which Mr Van Balkom took part, on behalf of Balkom, and which provoked no nega- 61. In order for Balkom to be able to rely tive reaction from Balkom. on failure to comply with a formal require- ment, it would be necessary for it to be able to show that its rights and interests have been prejudiced. However, the only com- pany which could, if the lawfulness of its 58. One may assume that, at that time, withdrawal were challenged, rely on such when execution of the project appeared to prejudice, in view of the joint and several be in jeopardy, Balkom would have reacted liability provided for in the contract, would strongly to a letter stating that it agreed to be DF. the withdrawal of two partners if that agreement had not been given.
62. It appears, however, that DF stated in 59. I believe, therefore, that we can infer the clearest possible manner that it was from the various letters I have just men- impossible for it to continue the contractual tioned, read in the light of Paragraph 157 relationship and it therefore waived its of the BGB, according to which contracts right to be treated by the Commission as are to be interpreted on the basis of the a party to the 1990 contract, so it would
I - 1105
OPINION OF MR MISCHO — CASE C-l J6/97
certainly not have been in a position to 66. Such an interpretation would, more- complain to the Commission for not having over, be incompatible with that clause, notified it of the termination. which gives each of the parties the option to terminate the contract 'where the pro- g r a m m e of w o r k set out in Annex I becomes inoperative by reason, in particu- lar, of a foreseeable technical or economic failure or an excessive overrun on the costs 63. I therefore consider that, in view of the of the project in relation to the estimates'. developments in the contractual relation- On that basis, the fact of the programme of ship between 1990 and 1994, the Commis- work becoming inoperative cannot be trea- sion's termination of the contract was ted merely as an overrun on the ,costs in lawful from the formal point of view. relation to the estimates, as Balkom would have it.
67. Next, once this objection by Balkom has been dismissed, I think there is no need Justification for termination of the contract to go into long explanations as to how we might legitimately consider, contrary to Balkom's arguments, which seem to me to be lacking in good faith, that the following 64. Was that termination justified, how- constituted foreseeable economic failure: a ever? I think, once again, that Balkom's project which was due to be completed in objections carry little weight. Balkom states 1993 was still, in 1994, at a stage where that the concept of economic failure refer- very little had been done; of the three red to in Clause 9 of the contract must be undertakings initially associated, there understood in relation to an annex to the remained only one which, despite its contract relating to economic and technical efforts, had not been able to find new risks. partners and which itself stated that it was unable to continue providing the funding required to carry on with the project; and, in addition, the administrative permission on which progress to the second phase depended had still not been obtained in 65. It turns out, however, that the provision spite of legal action. in question, Point 4.1 of Annex I, is essentially descriptive. It refers to the amount of investment required for the execution of the project and states the limit of the financial commitment entered into 68. It is difficult to envisage more patent by the three undertakings contracting with failure. It is all the more reason to be the Commission. It could not in any way be amazed, yet again, that the Commission regarded as providing a definition of fore- did not terminate the contract sooner or seeable economic failure within the mean- exercise sooner its option to withdraw ing of Clause 9 of the contract. under Clause 8 of the contract, with much
I-1106
COMMISSION V VAN BALKOM
harsher consequences for the other con- to the Commission in 1992, should be tracting parties, or, at least, take cognisance taken into account, so that the amount sooner of that certain failure, but instead claimed by the Commission would fall to extended time-limits which it had itself be reduced. previously described as mandatory.
72. It was not evident from the file that the 69. In any event, I consider that, when the Commission had clearly adopted a position Commission terminated the contract, that on the second financial report. In its reply, termination was fully justified under the the Commission had explained that it had terms of the contract. taken action on that report ('den 2. Finanz- bericht beschieden') by setting for Balkom, by letter of 9 March 1993, a time-limit expiring on 31 December 1993 for obtain- ing administrative permission and by informing Balkom that the Commission would not make any further payments until that date. However, it is one thing to The amount of reimbursement sought suspend payments, but quite another to state that nothing more is owed.
70. Is the Commission thereby justified in claiming reimbursement of an overpayment which it fixes at EUR 251 649, the euro having replaced the ecu in the interim? The 73. Furthermore, the Commission had, in Commission arrived at that sum by taking an unofficial note of 20 January 1994, as expenditure incurred by the other con- planned to acknowledge the 'Engineering' tracting parties, which entitled them to phase at the level of DEM 1 127 800, on financial assistance, only the expenditure it condition that the corresponding documen- accepted when it approved the first finan- tary evidence be available ('falls entspre- cial report. chende Nachweise vorliegen').
71. After the first hearing, it had seemed to 74. At the second hearing, the Commission me that it must be possible for the parties to stated, however, that none of the expendi- reach an agreement on whether certain of ture referred to in the second financial the expenditure detailed in the second report could be acknowledged for the financial report, which was sent by VBS following reasons.
I-1107
OPINION OF MR MISCHO — CASE C-156/97
75. In so far as that second report men- Of course my client would be willing to tioned — which was not, however, true — assist you in whatever way you require, and expenditure relating to the second phase of to forward to you copies of the financial the programme, entitled 'Production and statements you requested. For reasons Delivery', such work could have been made clear to you in the abovementioned, commenced only at the defendant's own you can understand, however, that this risk because, under Point 2.2 of Annex I to would present considerable problems for the contract, that phase could be com- my client, as my client has never been in ... menced only after completion of the appli- possession of these documents.' cation procedure for permission relating to the construction in question. It appeared expressly from the second progress report that that procedure was held up.
76. Second, the Commission told us during the second hearing that, contrary to the obligation under Clause 4.3.2 of the con- tract, no documentary evidence was inclu- 78. Since, at the hearing of 21 October ded in the second financial report, nor was 1999, the defendant was not able to prove such evidence sent subsequently, although that the documents in question had been the Commission, in its letter of termination sent, and it merely denied that they had of 16 August 1994, stated that it wished to been requested, it may be concluded that obtain documentary evidence correspond- the Commission was not given an oppor- ing to the expenditure which might be tunity properly to take action on the acknowledged ('The Commission ... would subject of expenditure incurred after the like to receive the corresponding state- first financial report. ments').
77. Finally, in a letter of 17 October 1994, appearing as Annex 7 to the application, Balkom's lawyer told the Commission the following:
79. It is very clear that the Commission, as accounting officer for public funds, cannot incur expenditure without having at its disposal supporting documentation which 'My client has always assumed that in the may be shown to the supervisory autho- past you received full financial statements rities, and in particular to the Court of from Van Balkom Seeliger .... Auditors. I - 1108
COMMISSION V VAN BALKOM
80. It is Balkom which claims to be entitled The date as from which interest becomes to a certain amount, corresponding to a payable percentage, fixed by the contract, of the expenditure incurred in performing it, and it is thus for Balkom to prove the genuine- ness of its expenditure. 85. The two parlies also disagree on the date as from which interest should become payable.
81. That burden of proof obviously goes beyond simply producing a financial report and includes the production of the financial statements on the basis of which it was 86. According to the Commission, thai- drawn up. date is clear from the third paragraph of Clause 9 of the contract, which stipulates:
82. Since the hearing has shown that there 'If an audit reveals that the amounts paid is no point in hoping for the production of by the Commission arc too high, the sum those statements, it is no longer necessary paid in error, plus interest due as from the to offer the defendant a last chance to date of ending (Abschluß) or finishing prove that its contentions are well founded (Beendigung) the work stipulated in the as regards the sums which are still owed to contract, shall be reimbursed forthwith by it and which should be deducted from the the other party to the contract.' amount claimed by the Commission.
87. According to the Commission, Balkom 83. Consequently, I can only propose that finished the first phase of the project, as the Court, in order to fix the principal stipulated in the contract, on 30 June 1991. amount owed by Balkom, accept the sum Consequently, it is as from that date, of EUR 251 649 claimed by the Commis- namely 1 July 1991, that interest should sion. be calculated.
84. That solution makes superfluous any 88. Balkom contends that the first phase of discussion on a possible right to retention the project, the engineering, was by no which Balkom might claim. means completed on 30 June 1991. At
I-1109
OPINION OF MR MISCHO — CASE C-156/97
present, Balkom is not in a position to of the BGB. That provision states that determine the date on which the engineer- interest is to be calculated as from the time ing phase was completed. In any event, by at which the debtor was given formal letter of 29 October 1992, VBS informed notice to pay. The recovery order, which the Commission that that phase was sched- was issued by the Commission on 8 Feb- uled to end on 30 September 1993. ruary 1995, fixed 30 April 1995 as the date by which Balkom should effect repayment. In that case, interest would be due as from 1 May 1995. It seems to me, however, that that solution should be rejected, since the 89. For my part, I think that one may date as from which interest due in the event accept that the expression 'finishing the of reimbursement is payable is governed by work' (Beendigung), as opposed to 'ending' Clause 9 of the contract itself. (Abschluß), refers to the time when the work actually ceased, without the project being completed. The Commission was right to try to determine that date, but it is possible that it is later than 30 June 1991. However, since Balkom itself 90. I would add, finally, for the sake of acknowledges that that date is in any event completeness, that, by relying after the first not later than 30 September 1993, it is that hearing on limitation as provided for in the date which I propose the Court should BGB, Balkom introduced a new plea in law accept. There is, admittedly, an alternative which must, as the Commission claimed, be solution, which is to apply Paragraph 284 dismissed.
Conclusion
9 1 . For all those reasons, I propose that the Court should:
(1) order Van Balkom Non-Ferro Scheiding to pay to the Commission of the European Communities the sum of EUR 251 649, plus interest on that sum as from 1 October 1993 at the percentage rates, published on the first working I-1110
COMMISSION V VAN HALKOM
day of each month, which the European Monetary Cooperation Fund charges in respect of its euro transactions;
(2) dismiss the application as to the remainder;
(3) order Van Balkom Non-Ferro Scheiding BV to pay the costs.
I - 1111