C-433/97
ECLI:EU:C:1999:133
- Súd
- Súdny dvor Európskej únie
- IČS
- 61997CC0433
- Zdroj
- eur-lex.europa.eu ↗
IPK V COMMISSION
OPINION OF ADVOCATE GENERAL MISCHO delivered on 11 March 1999 *
1. The present case concerns aid of ECU project and by 31 October 1993 at the 530 000 which the Commission granted to latest. The declaration stipulated that the support a project to create a database of latter date was a compulsory time-limit in information on ecological tourism in Eu- the context of the budgetary rules of the rope, known as 'Ecodata', proposed by the Communities. Finally, the declaration sta- appellant, the undertaking IPK-München ted that failure to observe the time-limits GmbH (hereinafter 'IPK'). laid down for the submission of reports and necessary documents would amount to a renunciation of the right to payment of the balance of the aid.
2. The appellant submitted the project on 22 April 1992 following a call for propo- sals published by the Commission in the Official Journal on 26 February 1992. 1 By 3. The declaration was signed by the a letter of 4 August 1992, the Commission appellant on 23 September 1992 and informed the appellant that its project had lodged at the Commission on 29 September been accepted, and submitted to it a 1992. The first instalment of the aid was 'declaration by the beneficiary of the aid' not, however, paid to the appellant upon (hereinafter 'the declaration'), which con- receipt by the Commission of the signed tained the conditions under which the aid declaration. On 18 November 1992, the was granted. The declaration stipulated in Commission sent the appellant a new particular that 60% of the amount of the declaration. On the basis of that new aid would be paid, by the Commission, on declaration, which had the same content receipt of the declaration duly signed by the as that annexed to the letter of 4 August appellant, and that the balance would be 1992, the first instalment of the aid was paid once the Commission had received paid in January 1993. and accepted the reports on the perfor- mance of the project. These reports com- prised, first, an interim report to be sub- mitted within three months of the project commencing and, secondly, a final report, accompanied by accounts, to be submitted within three months of completion the 4. By letter of 23 October 1992, the Com- mission informed the appellant that it assumed that the project had commenced * Original language: French. on 15 October 1992 at the latest and that it 1 — OJ 1992 C 51, p. 15. expected, therefore, to receive the interim
I - 6797
OPINION OF MR MISCHO — CASE C-433/97 Ρ
report by 15 January 1993. In the same investigations concerning the matters for letter, the Commission also asked the which he had been responsible. The dis- appellant to submit two additional interim ciplinary procedure resulted in the dismis- reports by 15 April and 15 July 1993, sal of Mr Tzoanos. In contrast, no irregu- respectively. Lastly, it repeated that the larities were revealed by the internal inves- final report was to be presented by tigation concerning the administrative pro- 31 October 1993 at the latest. cedure which had resulted, in August 1992, in the grant of aid to the Ecodata project.
5. On 24 November 1992, Mr Tzoanos, 7. Having failed to reach an agreement Head of Division within DG XXIII, invited with Studienkreis für Tourismus, in March the appellant and the undertaking 01- 1993 the appellant and the undertakings Pliroforiki to a meeting, which took place whose participation was envisaged in the in the absence of the two other partners in initial proposal, namely Innovence, Tour- the project. According to the evidence of consult and 01-Pliroforiki, negotiated an the appellant, which the Commission does agreement on the structure of the project not, as such, dispute, Mr Tzoanos sug and, in particular, the distribution of tasks. gested at that meeting that 01-Pliroforiki This agreement was formally concluded on should be responsible for the majority of 29 March 1993. the work and that the majority of funds be allocated to that undertaking. The appel lant was also asked to agree to the parti cipation in the project of a German under taking, Studienkreis für Tourismus, which had not been mentioned in the proposal for the project but was already involved in an 8. The appellant submitted an initial report ecological tourism project known as 'Eco- in April 1993, a second report in July 1993 trans'. That participation was further dis- and a final report in October 1993. It also cussed, in particular, at a meeting at the invited the Commission to a presentation of premises of the Commission on 19 Febru- the work which had been carried out. That ary 1993 during which the Commission presentation took place on 15 November continued to press for the inclusion of 1993. Studienkreis für Tourismus in the project.
9. By letter of 30 November 1993 the Commission informed the appellant that it 6. A few days after the meeting on 19 Feb- considered that the final report showed that ruary 1993, the Ecodata project case was the work completed by 31 October 1993 withdrawn from Mr Tzoanos. A disciplin- did not satisfactorily correspond with what ary procedure was subsequently initiated was envisaged in the appellant's proposal of against Mr Tzoanos, together with internal 22 April 1992. The Commission therefore
I - 6798
IPK V COMMISSION
refused to pay the outstanding 40% of the 14. The appellant claims that the Court ECU 530 000 which it had proposed for the should: project.
(1) set aside the Court of First Instance's 10. Since it considered that it had suffered judgment of 15 October 1997 in Case serious loss as a result of the Commission's T-331/94 and annul the Commission's decision not to pay the second instalment decision of 3 August 1994 to refuse to of the aid which had been granted to it by pay the second instalment of the aid the letter of 4 August 1992, the appellant granted to the appellant by its letter of brought an action seeking to have the 4 August 1992; aforementioned decision set aside.
(2) in the alternative, set aside the afore 11. The appellant raised two pleas in law mentioned judgment of the Court of before the Court of First Instance. The first First Instance and refer the case back to alleged infringement of the principles of that court; legal certainty and the protection of legit imate expectations. The second plea alleged that the decision was based on inadequate reasoning. (3) order the Commission to pay the costs.
12. By its judgment of 15 October 1997, 2 the Court of First Instance dismissed that 15. The Commission claims that the Court action. should:
13. By application lodged at the Registry of (1) dismiss the appeal; the Court of Justice on 22 December 1997 the appellant has brought an appeal against the aforementioned judgment of the Court of First Instance.
(2) order the appellant to pay the costs of 2 — Case T-331/94 IPK ν Commission [1997] ECR II-1665. the proceedings.
I - 6799
OPINION OF MR MISCHO — CASE C-433/97 Ρ
The appeal ified. The remark in question, which is contained in the minutes of the 19 Febru- ary 1993 meeting drawn up by the Com- mission, reads as follows:
16. In support of its appeal the appellant relies on six pleas in law, of which I shall 'The proposal did not make clear where the examine initially the second, third and information for the network was to be fourth pleas. derived from, but the Commission would prefer that this information is drawn from all member states; the latter, however, was not a formal obligation.' In those circum- stances, the appellant holds the view that the Court of First Instance should have examined whether there had been infringe- ment of the principle of the protection of legitimate expectations or of the principle of estoppel. Thus, the appellant contends, The second plea since the Commission agreed to modifica- tion of the conditions for grant of the aid, those principles prevent it from now criti- cising the appellant for failing to comply with the initial conditions under which the aid was granted. 17. The second plea alleges 'infringement of the obligation to state reasons, and failure to take into consideration Mr Tzoa- nos' remarks of 19 February 1993'. 19. The Commission considers, first, that this plea is in fact raised against the finding of fact by the Court of First Instance that the project had been only partially com- pleted, and that it therefore, must be rejected as inadmissible.
18. The appellant contends that the Court of First Instance erred in failing to take into consideration remarks by Mr Tzoanos made in the course of a meeting attended 20. I do not share that view. The plea under by representatives of the Commission, the examination concerns in fact the issue four partners in the project and Studien whether the disputed remarks were capable kreis für Tourismus, to the effect that the of modifying the conditions under which Commission agreed that the project should the aid was granted. The question whether cover only four Member States instead of or not the conditions in question were 12. It considers these remarks to be satisfied, and in particular whether the evidence that the project had been mod- project was completed, given those condi-
I - 6800
IPK V COMMISSION
tions, can only be addressed thereafter. The 24. Such an argument goes to the substan- substance of the conditions to be satisfied tive issue, which is that of determining the must first be determined before it can be legal effect, if any, of the remarks in decided whether or not they were fulfilled. question.
25. It must be emphasised, however, that 21. It flows from this that, in alleging that the plea under examination here is not a the Court of First Instance failed to give response touching on the merits of the case, adequate reasons as regards whether the but concerns the statement of reasons by conditions under which the aid was granted the Court of First Instance. had been modified, the appellant is advan- cing a plea concerning the consequences in law of the disputed remarks, and not a plea concerning the finding in fact by the Court of First Instance that the initial conditions 26. In this regard, it must be observed that under which the aid was granted had not the Court of First Instance did not give a been met. detailed reply to the argument set forth by the appellant. The Court of First Instance referred to the matter of whether or not the geographical extent of the database was adequate only in the following terms:
22. The appellant's plea could, admittedly, lead to a conclusion that the conditions under which the aid was granted had been 'As regards the appellant's observation of modified and that, as a result, the Court of the conditions under which the aid was First Instance's finding of fact that the granted, as defined above, it should be initial conditions had not been satisfied was noted that as at 31 October 1993, the work irrelevant. This, quite clearly, does not intended to extend the system to the amount to questioning the content of the regions and Member States other than finding itself. The Commission's assertion those covered by the pilot phase of the that the claim is inadmissible therefore does project had not been carried out.' 3 not stand up in this instance.
27. The appellant can, indeed, reasonably deduce from this, as the only possible 23. The latter contends, moreover, that the implication, that the Court of First Instance remarks in question carry no legal weight rejected its argument that the conditions and merely suggest that the appellant under which the grant was made had been proposed partial performance which did not at all entitle it to the full amount of the financial assistance envisaged. 3 — Paragraph 41 of the contested judgment.
I - 6801
OPINION OF MR MISCHO — CASE C-433/97 Ρ
modified, since the Court confined itself to ification of which it had previously examining whether the initial conditions accepted. were satisfied.
28. The words which the Court of First 32. I therefore consider the appellant's Instance used, however, do not afford the second plea to be well founded. appellant, nor, furthermore, the Court of Justice, called upon to exercise its review function, the slightest possibility of identi fying the grounds on which the Court of First Instance rejected the appellant's argu ment on this point. The third plea
29. It is true that the appellant explicitly set forth its argument based on Mr Tzoanos' 33. By its third plea, the appellant contends remarks only at the reply stage, in response that the Court of First Instance based itself to the Commission's defence. on inaccurate facts.
30. This consideration is, however, of no 34. The appellant points out that the Court relevance whatsoever in determining whe of First Instance, at paragraph 48 of its ther the Court of First Instance complied judgment, stated that '[t]he appellant with its obligation to give reasons for waited until March 1993 before starting rejecting the plea in question. Nor, indeed, discussions with its partners concerning the did the Court of First Instance declare it to distribution of tasks with a view to com be inadmissible. pleting the project'. That this statement is wrong is, according to the appellant, dis cernible even from evidence before the Court.
31. Given all the foregoing, it must be concluded that the Court of First Instance did fail to give reasons sufficient in law for rejecting the appellant's argument seeking to show infringement of the principle of the 35. The Commission considers this plea to protection of legitimate expectations and of be inadmissible since, in its view, it the principle of estoppel, consisting in the amounts to questioning a finding of fact fact that the Commission is now allegedly by the Court of First Instance which is, requiring compliance with conditions mod moreover, evident and beyond all dispute.
I - 6802
IPK V COMMISSION
36. According to settled case-law, a finding granted until 13 March to settle the matter of fact by the Court of First Instance of the sharing of tasks. cannot, prima facie, be reopened on appeal. There is, however, an exception to this principle where the finding is vitiated by a manifest error of assessment. This occurs, in particular, where a finding of fact by the Court of First Instance is contradicted by 40. One could argue that, since it related to the case documents. 4 participation by a third party undertaking, this second meeting was not part of any negotiations 'with its [the appellant's] part ners', to use the Court of First Instance's own words. 37. So, it can be seen from those docu ments that, in November 1992 and Febru ary 1993, the appellant attended meetings held first and foremost to decide funda mental aspects concerning the distribution of tasks between the various participants in 41. It seems to me incontrovertible, how the project. ever, that, since negotiations on participa tion by a third party undertaking concerned the distribution of tasks relating to a specific project and, consequently, of funds which were themselves fixed, they necessa rily fall within the ambit of distribution 38. The first meeting thus addressed the between the original partners. distribution of tasks between the appellant and the Greek undertaking 01-Pliroforiki, and was followed by at least one commu nication in writing by the appellant in January, regarding the distribution of tasks. 42. The documents submitted to this Court therefore clearly show that there were negotiations on the distribution of tasks in the context of the project which involved 39. The purpose of the February meeting the appellant and which took place prior to was essentially to define the terms of March 1993, the date taken into account participation of an undertaking by the by the Court of First Instance. name of 'Ecotrans', which did not feature in the appellant's proposal, but which the Commission wished to have participate in the project. The minutes of the meeting stated, furthermore, that the appellant was 43. The fact that these meetings were convened, it would appear, at the initiative 4 — See, for example, the judgment of the Court of Justice in Case C-136/92 Ρ Commission ν Brazzelli Lualdi [1994] of the Commission and not of the appel ECR I-1981. lant, does not at all alter the fact that they
I - 6803
OPINION OF MR MISCHO — CASE C-433/97 Ρ
did take place and that the appellant 48. The appellant sets forth a series of attended them, and therefore took part in arguments on this point. negotiations on the distribution of tasks.
49. It relies, first, on the contractual nature 44. Similarly, the observation put forward of its relationship with the Commission. In by the Commission that IPK may not have its view, the latter set 15 October 1992 as demonstrated all the initiative and effi the starting date for the project, which it ciency that circumstances seemed to was proposed would last fifteen months. require, does not at all alter the fact that, The Commission was not therefore entitled well before March 1993, it had already unilaterally to set 31 October 1993 as the taken part in negotiations on the distribu date for completion. This would be an tion of tasks. infringement of the principles of the law of contract.
45. The Court of First Instance's finding 50. The Commission maintains, on the that the appellant waited until March 1993 other hand, that the appellant is merely before starting those discussions is, there repeating a manifestly erroneous assertion fore, contradicted by the documents before which had already been rejected at the time the Court and vitiated by manifest error. of the proceedings before the Court of First Instance.
46. The third plea must therefore also be upheld. 51. The Commission disputes, in particu lar, the interpretation which the appellant seeks to give to the Commission's letter of 23 October 1992, in which it informed the appellant that '[f]or the purposes of this exercise all projects are deemed to start by 15 October'.
The fourth plea
52. I share the Commission's conclusion 47. IPK considers that the Court of First that, contrary to what the appellant asserts, Instance erred in law in taking 31 October one cannot deduce from the content of this 1993 as the deadline for delivery of the letter that the Commission had decided to final report. postpone the starting date of the project.
I - 6804
IPK V COMMISSION
That letter does not in fact refer to the to interference by the Commission. The 15 October date unconditionally, qualify- latter therefore, in the appellant's view, ing it as it does with the phrase 'for the infringed the principle of good faith and purposes of this exercise', namely, for committed an abuse of rights by requiring 'monitoring' purposes. the appellant to comply with a deadline which its own conduct rendered impossible to meet.
53. Furthermore, and most significantly, the same letter states that the date on 57. According to the appellant, the Court which the Commission expected the final of First Instance misdirected itself as to the report was indeed still 31 October 1993. significance of these principles by finding that it was the appellant which had to prove that the conduct of Commission officials had prevented it from engaging in proper cooperation with its partners before March 1993. 54. The appellant cannot therefore rely on that document to infer an intention by the Commission to modify the deadline, what- ever doubts the reference to 15 October may, admittedly, have aroused. One must 58. It is necessary to determine, therefore, take the view, in consequence, that the whether the Court of First Instance was Commission could not have unilaterally right to adjudge, at paragraph 48 of its modified the terms of the 'contract', and it judgment, that: is not even necessary to examine whether the relationship between the Commission and the appellant was in fact contractual in nature.
'Even though the appellant has provided some evidence that one or more officials of the Commission did interfere in the project between November 1992 and February 55. Other arguments which the appellant 1993, it has not established at all that this adduces under this plea are, however, more interference prevented it from engaging in persuasive. proper cooperation with its partners before March 1993.'
56. It explains that the delay in launching 59. The appellant states that, by requiring the project was due, on the one hand, to the it in this way to prove a negative, proof late payment of the aid, and, on the other, which in practice is impossible to furnish,
I - 6805
OPINION OF MR MISCHO — CASE C-433/97 Ρ
the Court of First Instance rendered mean facie evidence that actions by the Commis ingless the limits, which the prohibition on sion, the occurrence of which was men the abuse of rights imposes on the Com tioned by that court, had a detrimental mission. effect on the running of the project.
64. According to generally accepted prin ciples on the subject, this prima facie 60. It is true that, by obliging the appellant evidence, far from being of no conse to prove the impossibility of any coopera quence, as the Court of First Instance tion with its partners, the Court of First appeared to believe, has the effect, on the Instance required it to prove a negative. contrary, of reversing the burden of proof.
65. Once the appellant produced evidence making it possible to think that the alleged 61. What seems to me more conclusive, conduct of members of the Commission however, is the fact that the Court of First staff may have impacted on the smooth Instance itself found that the appellant had running of the project, it fell to the provided evidence of interference by Com Commission, then, to bear the burden of mission officials in the management of the proving that, despite the conduct in ques project. What is more, it even went so far as tion, the appellant remained fully able to to describe as 'disturbing' the manner in manage the project in a satisfactory man which this interference occurred. ner.
66. This is indeed true since, apart from the 62. I consider, therefore, that it was incum evidence indicated by the Court of First bent on the Court of First Instance to draw Instance, the appellant also relies on the from this finding what seem to me to be the fact, which is not disputed, that, for a inevitable conclusions as regards the bur project which was supposed to last 15 den of proof. months and end in October 1993, the Commission did not pay the first instal ment of the aid at issue until January 1993.
63. Thus, the appellant, in my view, by 67. I therefore consider that the Court of providing the evidence to which the Court First Instance erred in law in requiring the of First Instance referred, furnished prima appellant to prove that the conduct of
I - 6806
IPK V COMMISSION
Commission officials had prevented it from 72. In view of the foregoing, I cannot but cooperating with its partners. propose that the Court should set aside the judgment of the Court of First Instance. Given that the evidence before the Court sets out the case in full, the Court of Justice can, in my view, give judgment on the matter. 68. However, the conclusion reached by the Court of First Instance as regards the burden of proof led it to find, at paragraph 48 of the judgment under appeal, that the appellant could not level blame against the Commission for causing the delay in the completion of the project. Substance
73. The appellant relies on the following arguments to seek annulment of the con- 69. Since the Court of First Instance relied tested decision. on this finding, even if it did not state precisely why it considered it to be foun- ded, it must be concluded that the position of the appellant was altered and that the plea alleging infringement of the law relat- 74. It considers that the Commission con- ing to the burden of proof must be upheld. tracted an undertaking to pay to it the funds envisaged in the context of the decision to grant the aid and that none of the arguments advanced by the Commis- sion enable it to avoid this obligation. 70. It is therefore unnecessary to examine the appellant's arguments to the effect that the Court of First Instance infringed the rules on evidence and failed in its duty to investigate the matter by rejecting the 75. In particular, the appellant points out, appellant's request for production of docu- first, that the Commission's powers of ments by DG XXIII, whilst at the same control were confined merely to monitoring time finding against it in relation to the utilisation of the funds, and that the burden of proof. Commission's assertions as regards this utilisation, are, in its view, easily refuted.
71. Since these three pleas must, in my 76. Given the imperative restrictions on the view, be upheld, there is no need to Commission's powers of control under the examine the others. rules on aid, the Commission was not, to
I - 6807
OPINION OF MR MISCHO — CASE C-433/97 Ρ
the appellant's understanding, entitled to fact that the project was incomplete as at refuse to make the payment on the ground 31 October 1993, and, according to the of material shortcomings affecting the Commission, that is the only relevant project. criterion to determine whether or not the balance of the aid is payable since, by signing the aid declaration, the appellant undertook to complete the project by that date, on pain of renouncing the right to 77. What is more, according to the appel that payment. lant, even on the assumption that the Commission could, in theory, have relied on such arguments, they are, in the present case, unfounded.
82. It should be observed that the decision to grant the aid was notified to the appellant by letter of 4 August 1992. The 78. Lastly, the appellant contends that, latter was invited to sign and return the even if the work ultimately carried out declaration by the beneficiary annexed to had to be found to differ from the initial the letter, to enable the payment to take proposal, the obligation to pay the balance place. would remain none the less.
79. In support of its argument the appellant 83. The appellant signed and returned the asserts, in particular, that the delay in declaration on 23 September 1992 — not, implementing the project was caused by moreover, indicative of any great prompt the Commission's conduct which, it claims, ness on the part of an undertaking in 'greatly hindered and disrupted its work'. receipt of Community aid. As apparent from paragraph 19 of the Commission's rejoinder submitted to the Court of First Instance, the letter was registered in the incoming correspondence section of D G 80. The Commission is therefore not enti XXIII on 29 September 1992 and allocated tled, the appellant argues, to rely on the to Mr Tzoanas. Nothing then happened for 31 October 1993 deadline, which its own two months. The Commission explains in actions rendered impossible to meet, and it detail the reasons for this inaction, which it was legitimate for the appellant to believe attributes exclusively to the deliberate that the performance of the project and behaviour of the official concerned. In therefore the deadline had been postponed. November, the appellant contacted the Commission to enquire about payment of the first instalment. As from that moment, as the Commission continues to explain, the payment procedure was set in motion 81. The principal justification which the and the payment was made in January Commission gives for its decision lies in the 1993, on an unspecified date.
I - 6808
IPK V COMMISSION
84. Three months had therefore already as has been seen, was in fact made only in elapsed since the date on which IPK January. returned its duly signed acceptance declara- tion, and the undertaking had not received the first instalment, which was, however, under the provisions of that declaration, to be paid as soon as the Commission received the signed declaration.
88. As has already been seen in relation to the fourth plea of the appeal, the Commis- sion and the appellant dispute, in particu- lar, the interpretation to be given to a letter 85. It should be observed, furthermore, sent by the Commission on 23 October to that this declaration, on a literal interpre- all undertakings in receipt of aid under the tation of which the Commission's argument programme in question. The Commission rests, made reference both to the project stated in that letter that '[f]or the purposes proposal submitted by the appellant, which of this exercise, all projects are deemed to explicitly proposed that the project would start by 15 October', and that it therefore take fifteen months, and to the 31 October expected the first interim report by 15 Jan- 1993 deadline for its completion. uary 1993. The letter pointed out that final reports had to be submitted on 31 October 1993.
86. It is true that the call for proposals stipulated that the projects selected would last a year.5 The Commission did, none the less, accept the appellant's proposal, includ- ing the express reference to the 15-month project period. 89. In the specific context of the appellant's project, the meaning of this document is unclear. Given the fact that, as has been seen, the Commission agreed that the project would take fifteen months, should one understand therefore that this letter postponed the project starting date to 87. The declaration made perfect sense in 15 October 1992, in which case the com- August 1992, when it was sent to the pletion date should logically have been put appellant for acceptance. It no longer made back to 15 January 1994. Or should one sense, on the other hand, when the Com- lay emphasis on the last sentence and, mission eventually made the first payment accordingly, understand that the deadline due under that declaration. That payment, remained 31 October 1993, in which case the project should have been deemed to have started on 1 August 1992, that is, five 5 — OJ 1992 C 51, p. 15. months before payment of the aid and even
I - 6809
OPINION OF MR MISCHO — CASE C-433/97 Ρ
before the appellant had returned the was in a position to take the work forward declaration ? regardless, using its own resources.
90. In any event, in the circumstances described above, the Commission could 94. This is all the more so given that, in the not reasonably consider that the time-limit period subsequent to the appellant sending initially envisaged remained totally unal the declaration, there were numerous inter tered. It could not, thus, hold the under ventions by staff of the Commission, as the taking in receipt of the aid to a literal latter admits. These interventions sought, reading of the condition laid down at as applicable, to influence the distribution paragraph 5 of the aforementioned declara of tasks, and therefore of funds, between tion (deadline of 31 October 1993) whilst the undertakings which were partners in being able, for its part, to avoid with the project, or, even, to promote inclusion impunity enforcement of the payment con of an additional undertaking, not initially ditions laid down at paragraph 2 of the envisaged in the proposal submitted by the same document (payment on receipt of the appellant. It is not disputed that this was signed and dated declaration). still happening at the meeting of 19 Febru ary 1993, which has already been men tioned (paragraph 5 above).
91. This consideration stands up, more over, whether or not one classifies the relationship between the Commission and the beneficiary of the aid as contractual. 95. Negotiations with a view to involving Ecotrans (Studienkreis für Tourismus eV) in the project ran on, without success, until March 1993, and it was only on 29 March that an agreement on the structure of the 92. It is true, as the Commission points out, project and, in particular, the distribution that an undertaking granted aid is perfectly of tasks, was finally concluded between the able to commence work as soon as the original participants. grant decision is made, whilst awaiting the payment.
96. In those circumstances, the Commis- 93. In the present case, however, so much sion was not entitled to assume that the time elapsed that it ceased to be possible to undertaking would quite calmly use its own assume that the beneficiary undertaking resources in carrying out the project, nor
I-6810
IPK V COMMISSION
that it would be in a position to progress that sure that IPK would have worked more the work at the pace initially envisaged. quickly in any event.
97. Before the Court of First Instance, the Commission asserted that, even disregard- ing the issue of including Ecotrans, IPK The outcome of this is that we have had a failed, from the outset, to demonstrate the delay of some 5 months out of approxi- required degree of diligence. mately 14. In the circumstances I think it is most unlikely that the deadline of 31 October for completion of the contract can be achieved.
98. As to the merits of this argument, it is, however, discernible from the assessment made by the Commission director respon- sible, in an internal note of 25 February 1993 annexed to the appellant's reply, that he was aware of the fact that not all responsibility for the delay in the perfor- I would like if possible to be able to give mance of the project could be imputed to some indication before 13 March that we the appellant, and that the Commission can extend the date. Apparently, however, faced a veritable dilemma. After pointing if we do so we will loose the balance of the out that the first payment had been late, the subsidy (approximately 240 000 ECU) as director stated the following: we will not pay it in this year. This may however be preferable to forcing the part- ners to attempt to meet the deadlines which seem totally unrealistic.
'In addition it is clear that little or no work has been done on the project. Here IPK will always argue that this was due to our imposing the additional requirement of their consulting and involving Ecotrans in the project even though they did not form I would be grateful if you and RS could part of the original proposal or our sub- consider whether there is some way out of sidy-contract. There may even by some this dilemma. All that occurs to me is that justification in this point although I am not we can perhaps accept the loss of the
I - 6811
OPINION OF MR MISCHO — CASE C-433/97 Ρ
240 000 and pay that amount eventually 100. It is, on the other hand, apparent from out of next year's budget — but this will of the Commission's letter of 30 November course draw the problem that was created 1993, which sets out the grounds for the to the attention of the Management Com decision finally issued by letter of 3 August 6 mittee.' 1994, that the Commission bases its entire reasoning for refusing to pay the balance on the state of progress of the project as at 31 October 1993.
The Commission official was therefore quite evidently of the view that, in terms of fairness at least, there were grounds for 101. As regards the other considerations extending the time-limit, and that the only referred to in that letter, on which the obstacle to an extension was the annual parties expound at length, these concern nature of the credits in question. He the application of funds already paid, in the thought, however, that there might be a context of a possible decision by the technical means of circumventing the pro Commission to require their reimburse blem. ment.
99. My view is that the Commission should 102. Since the action seeks only annulment indeed have sought a solution of this kind. of the decision to refuse to pay the balance, it is not for me to examine the arguments raised in the context of a possible decision 6 — (French translation included here in the original tej requiring reimbursement.
I-6812
IPK V COMMISSION
Conclusion
103. It thus follows from the foregoing that, by considering that the project should be completed by 31 October 1993, whereas payment of the aid did not take place as soon as the acceptance declaration was received, and by continuing until as late as February 1993 to press for the list of participating enterprises to be changed, the Commission departed from its own decision to grant financial assistance. By doing so, it also infringed the principle patere legem quam ipse f ecisti and the principle of good faith. 7 Given that the Commission's defence has in my view been unsuccessful, I propose, also, that it be ordered to pay costs.
7 — Judgment in Joined Cases 43/59, 45/59 and 48/59 Von Lachmüller, Bernard Peuvrier and Roger Ehrhardt ν Commission of the European Communities [I960] ECR 463, and, especially, p. 474 et seq.
I - 6813