← Späť na vyhľadávanie
Súdny dvor Európskej únie·24.2.2000

C-16/98

ECLI:EU:C:2000:99

Súd
Súdny dvor Európskej únie
IČS
61998CC0016

OPINION OF MR JACOBS — CASE C-16/98

OPINION OF ADVOCATE GENERAL JACOBS delivered on 24 February 2000 *

1. The issue in this case concerns the basis The relevant provisions of the Directive for calculating the value of a works con- tract in order to determine whether the Community provisions on procurement procedures apply. Specifically, where con- tracts for work on electricity supply and street lighting networks are to be carried 2. The Commission alleges a failure to out in a number of localities within the fulfil the obligations laid down by Arti- same overall administrative area, are all or cle 4(2), Article 14(1), (10) and (13) and any of them to be aggregated for the Articles 21, 24 and 25 of the Directive. A purposes of Council Directive 93/38 1 number of the definitions given in Arti- ('the Directive') when, although awarded cles 1 and 2 are also relevant. by separate local authorities, they are supervised and coordinated by a single agency set up by those authorities to provide technical and administrative sup- port, when the content of the contracts is largely identical for each type of network and similar as between them, when the work is to be carried out over the same 3. Article 1(1) defines, inter alia, 'public period and when the invitations to tender authorities' as 'the State, regional or local are all published simultaneously? authorities, bodies governed by public law, or associations formed by one or more of such authorities or bodies governed by public law'. Under Article 2(1), the Direc- tive is to apply to 'contracting entities which: (a) are public authorities ... and exercise one of the activities referred to in paragraph 2; ...'. Those activities include the provision or operation of fixed net- works intended to provide a service to the * Original language: English. 1 — Council Directive 93/38/EEC of 14 June 1993 coordinating public in connection with the production, the procurement procedures of entities operating in the transport or distribution of electricity, or water, energy, transport and telecommunications sectors, OJ 1993 L 199, p. 84. the supply of electricity to such networks.

I-8318

COMMISSION V FRANCE

4. Article 4(2) provides: 'Contracting enti- In particular, where a supply, work or ties shall ensure that there is no discrimina- service is the subject of several lots, the tion between different suppliers, contrac- value of each lot shall be taken into account tors or service providers.' when assessing the value referred to in paragraph 1. Where the aggregate value of the lots equals or exceeds the value laid down in paragraph 1, that paragraph shall apply to all the lots. However, in the case of works contracts, contracting entities may 5. Article 14 provides: derogate from paragraph 1 in respect of lots the estimated value net of VAT for which is less than ECU 1 million, provided that the aggregate value of those lots does not exceed 20% of the overall value of the lots. '1. This Directive shall apply to contracts the estimated value, [net] of VAT, for which is not less than:

13. Contracting entities may not circum- vent this Directive by splitting contracts or (c) ECU 5 000 000 in the case of works using special methods of calculating the contracts. value of contracts.'

6. Articles 21, 24 and 25 of the Directive fall within Title IV, 'Procedures for the award of contracts'. Article 21(1) provides that calls for competition are to be made by means of a notice drawn up in accordance 10. The basis for calculating the value of a with one of the annexes to the Directive, works contract for the purposes of para- which is to be published in the Official graph 1 shall be the total value of the work. journal of the European Communities (the "Work" shall mean the result of building 'OJEC') in accordance with Article 21(5). and civil engineering activities, taken as a The relevant annex in the present case is whole, which are intended to fulfil an Annex XII, which lists in detail the infor- economic and technical function by them- mation to be provided. Under Arti- selves. cle 24(1), contracting entities which have

I-8319

OPINION OF MR JACOBS — CASE C-16/98

awarded a contract are to communicate the all referred to together as the 'local enti- results of the awarding procedure to the ties') set up a syndicat départemental, now Commission within two months of the known as the Syndicat Départemental award, again by means of a notice drawn d'Électrification de la Vendée or by its up in accordance with one of the annexes acronym 'SYDEV'. 3 The local entities did (in the present case Annex XV), to be not thereby cease to exist, but SYDEV took published in the OJEC in accordance with over responsibility for certain of their tasks. Article 24(2). Under Article 25(1), con- It appears from documents produced by the tracting entities must be able to supply French Government that SYDEV's compe- proof of the date of dispatch of both of the tences were governed at the material time above types of notice. Article 25(5) prohi- (1994-95) by an arrêté préfectoral (prefec- bits publication in any other way before toral order) of 3 October 1960, although notices are dispatched to the Office for the relevant provisions were subsequently Official Publications of the European Com- modified (in 1997). munities.

8. Under Article 1 of the 1960 arrêté préfectoral, SYDEV's objects were to include: Facts

7. In the French département of Vendée, '(1) joint exercise of the rights conferred on various municipal authorities have formed local authorities by statute or regulation as syndicats intercommunaux (joint municipal regards the production, transport, distribu- groupings) for the purpose of administering tion and use of electrical energy, in parti- their electricity supply networks. 2 In 1950, cular under the Law of 8 April 1946 on the all of those syndicats intercommunaux and nationalisation of electricity and gas, and two individual municipalities (hereinafter of all the responsibilities conferred on the member syndicats and municipalities;

2 — Although the legal framework has not been explained to the Court by either the Commission or the French Government, it appears that the normal situation in France, governed principally by Laws of 15 June 1906 and 8 April 1946, is that local authorities are responsible for electricity supply within their areas, in respect of which they grant conces- sions, on standard terms, to the national corporation Électricité de France (EDF), which enjoys a near-monopoly in the production and supply of electricity in that country. (2) joint organisation of the services which See, for example, J. Bergougnoux and W. Varoquaux, they are to provide in order to ensure the 'Caractéristiques du service public de l'électricité', Cahiers juridiques de l'électricité et du gaz (CJEG), 1987, Librairies Techniques, Paris, p. 811; P. Sablière, 'Le nouveau modèle de cahier des charges pour la concession à Electricité de France de la distribution publique d'électricité', CJEG, 3 — This type of arrangement appears to be the norm in France: 1993, p. 1; P. Sablière, 'Le nouveau cahier des charges type see the Opinion of Madame Devillers, Commissaire du de la concession du réseau d'alimentation générale en gouvernement, in SIEP c/État et SDE, Cour administrative énergie électrique', CJEG, 1995, p. 87. d'appel de Nantes, 17 September 1997, CJEG, 1998, p. 398.

I - 8320

COMMISSION V FRANCE

proper operation and best possible exploi- Annonces des Marchés Publics (the official tation of their distribution of electricity; French bulletin of notices concerning public works and service contracts, the 'BOAMP') invitations to tender for a number of works contracts, 37 of which are in issue in the present case. 4The contracts in question related to extension and maintenance work (3) in general, interest and participation, to be carried out, over a period of three where appropriate, in all activities pertain- years, on existing electricity supply and/or ing to electricity and its use within the street lighting networks under the respon- framework of the laws and regulations in sibility of the members of SYDEV. All the force.' invitations to tender were published in the BOAMP on 12 January 1995.

9. Article 2 gives a non-exhaustive list of the activities in which SYDEV was to engage in pursuit of those objects. They 12. The notices to which this case relates include: representing the member authori- involve 20 of SYDEV's 23 members and, in ties; organising administrative, legal and all but three cases, there are notices for technical planning and research services; both electrification and street lighting drawing up the general inventory of the works for each member. In numerical requirements of the département and pro- terms, they thus cover some 80% of all moting the general and periodic pro- the electricity supply and street lighting grammes of works relating to electricity networks in the département. infrastructure in the communes; harmonis- ing the rates charged for electricity; enter- ing into agreements with electricity opera- tors holding a concession; and implement- ing technical and financial measures. 13. In all the notices published in the BOAMP for the 37 contracts in question, the 'awarding body' was stated to be SYDEV and tenders were to be sent to the Works Department of SYDEV at its 10. Under SYDEV's 1997 statutes, but not address, although the name of the local under the 1960 arrêté préfectoral, it is to entity concerned was to be added in each act both as 'maitre d'oeuvre' (supervisor/ case. The description of the work to be manager) and as 'maître d'ouvrage' (con- carried out on the electricity supply net- tracting authority) on behalf of its mem- works was the same in all cases: 'electrifi- bers. cation work and associated generated work

4 — The Commission refers, throughout the pre-litigation pro- cedure and in its written pleadings, to 36 contracts. Since the number of contracts notified i n the BOAMP was in excess of that number, the Court requested clarification. In 11. On 21 December 1994, SYDEV sent reply, the Commission identified the 37 contracts to which it considered the case related, and the French Government has for publication in the Bulletin Officiel des not objected to that definition of the scope of the action.

I - 8321

OPINION OF MR JACOBS — CASE C-16/98

such as, for example, civil engineering on FRF 30 000 000) were sent by SYDEV for the telephone network, civil engineering on publication in the OJEC. Although the the cable television network, the public requests for publication were sent on address system'. The work on the lighting SYDEV's headed paper, the notices bore, networks was described in all cases as: first, the name of the local entity in 'street lighting work and associated gener- question, followed by an indication that ated work such as, for example, the public the work was to be supervised by SYDEV. address system'. Again, tenders were to be sent to SYDEV at its address, with the name of the local entity to be added in each case. The six notices were published in the OJEC on 6 January 1995, 6although the information provided (identical to that published in the BOAMP) was insufficient to enable all the 14. In most of the notices published in the headings set out in Annex XII to the BOAMP, the estimated value of each indi- Directive to be completed. In each case, vidual contract over three years was below the name of the contracting entity was the threshold of ECU 5 000 000 (equiva- published as SYDEV, followed in all but l e n t , at the m a t e r i a l t i m e , to one case by the name of the relevant local FRF 33 966 540) 5for the application of entity. the Directive to works contracts. Their aggregate value was, however, FRF 609 000 000 (FRF 483 000 000 for the electrification contracts and FRF 126 000 000 for the lighting contracts). For one of the electrification contracts and 13 of the lighting contracts, the estimated value was below the threshold of ECU 1 000 000 (equivalent to FRF 6 793 308 at the material time) for the derogation in the 16. The award procedure was of a type second half of the second subparagraph of comprising three stages. First, a short list of Article 14(10) of the Directive, subject to tenderers was drawn up on the basis, it their aggregate estimated value being also appears from the records of the award less than 20% of the relevant total. procedures produced by the French Gov- ernment, of whether tenderers had pro- duced all the required certificates as to compliance with administrative require- ments and capacity to perform the work in question. Second, one of those tenderers was selected, apparently on the basis of the best offer made. Offers were in the form of 15. Five of the electrification contracts a percentage difference from the proposed were nevertheless for an estimated value list of prices, the offer representing the in excess of the ECU 5 000 000 threshold, lowest price being accepted in all the cases and notices regarding those contracts and in respect of which documents have been one other slightly below the threshold (for produced. Finally, the successful tenderer

5 — See the notice published by the Commission on 18 Decem- ber 1993, OJ 1993 C 340, p. 10. 6 — OJ 1995 S 3, pp. 211 to 213.

I - 8322

COMMISSION V FRANCE

was to be given orders to carry out specific electrification and lighting contracts for items of work over the three-year period. three of the local entities on whose behalf an invitation to tender (for the electrifica- tion contract) was published in the OJEC. They do not indicate whether any 'non- local' firms submitted tenders (no addresses are given), but it is possible to see that: (i) all the records are presented in an identical format and bear SYDEV's name at the top; 17. Notices concerning the award of the 37 (ii) the general terms of the invitations to contracts with which this case is concerned, tender state that 'the work will be carried including the six published in the OJEC, out on the territory of the Syndicat, the were published in the BOAMP on 29 Sep- exact specification of the works to be tember 1995, the 'body which awarded the constructed ["des ouvrages à construire"] contract' being identified in each case as being communicated in due course by SYDEV. No notice concerning the award of SYDEV to the contractor chosen'; (iii) the any of them was ever sent for publication in members of the boards which opened and the OJEC. In all cases, the notices show decided on the tenders were different for that a firm with a local address was the different local entities (a representative awarded the contract. However, at least of SYDEV being present on some, though some of the successful tenderers were in not all, occasions) and tenders were opened fact large undertakings with branches on different days or at different times; (iv) throughout France; four of the same names the lists of tenderers are similar, though not were also successful tenderers for similar identical, for the three local entities and for contracts in Dordogne cited by the Com- the two types of contract for each of them; mission in its application. In 10 of the 17 and (v) the offers of each individual ten- cases where both electrification and light- derer for the same type of work in different ing work was to be carried out for the same localities were not always identical. local entity, the same tenderer was awarded both contracts, in three cases one of the contracts was shared with another tenderer and in the remaining four separate con- tracts were awarded to different tenderers. Overall, there were 10 successful tenderers for the 37 contracts, their 'success rate' ranging from a single shared contract to eight full contracts and two shared con- tracts, and from FRF 6 000 000 to FRF Procedure 114 000 000 plus a share of FRF 48 000 000.

19. On 17 January 1996, its attention having been drawn to the possibility that the above procedures infringed Community 18. The French Government has produced law, the Commission sent the French records of the award procedure for the Republic a letter of formal notice alleging

I - 8323

OPINION OF MR JACOBS — CASE C-16/98

that separate lots had been treated as Analysis separate contracts, that two -thirds of those contracts had not been notified in the OJEC and that an inappropriate procedure had been used. On 7 April 1997, following the French Government's denials, the Com- mission sent a reasoned opinion under Applicability of the directive Article 169 of the EC Treaty (now Arti- cle 226 EC) alleging that: (i) inaccurate information of the volume of work had been given, thus discriminating against tenderers from other Member States; (ii) a 21. The contracts in issue were advertised single programme of works had been split and awarded in early 1995. From the on geographical and technical pretexts in Court's judgment in Case C-311/96 Com- order to avoid publication of a number of mission v France,7 it is clear that the lots in the OJEC; (iii) the concepts of Directive had not been transposed in contracting entity, association of contract- France at that time, but it is not disputed ing entities, lots and contracts had been that the relevant authorities should have misapplied; and (iv) the procedure used was complied with it or that the Commission is not provided for in the Directive. entitled to bring an action concerning an individual instance of failure to comply with a directive which has not yet been implemented. 8

The alleged infringements

20. On 22 January 1998, the Commission 22. The Commission makes two basic brought the present action, in which it claims. First and foremost, it claims that seeks a declaration that 'in the procurement SYDEV separated on both technical and procedure issued by the Syndicat Départe- geographical pretexts what was for the mental d'Electrification de la Vendée in De- purposes of the directive a single works cember 1994 for the award of contracts for contract into a number of smaller con- electrification and street lighting work, the tracts, thereby avoiding for the most part French Republic failed to fulfil its obliga- the requirement of publication in the tions under Articles 4(2), 14(1), (10) and OJEC, misleading potential tenderers as to (13), and also under Articles 21, 24 and 25, the true scope of the work and making it of Directive 93/38/EEC'. The Commission and the French Republic presented oral argument at the hearing on 16 November 7 — [1997] ECR I-2939. 8 — See Case C-431/92 Commission v Germany [1995] ECR 1999. I-2189, paragraphs 19 to 23 of the judgment.

I - 8324

COMMISSION V FRANCE

appear considerably less attractive for other of the six calls for competition which were than local firms to submit a tender, to the published, I do not consider it necessary or disadvantage in particular of tenderers appropriate for the Court to make a from other Member States. Secondly, it declaration as regards failure to supply asserts that the notices of invitation to proof of the date of dispatch in accordance tender sent for publication in the OJEC with Article 25(1) of the Directive. Nor were incomplete and no notices of the was there any infringement of Article 25(5) awards were ever sent. in respect of the notices which were sent, since the documents produced to the Court establish that they were dispatched on the same day to the OJEC and the BOAMP.

Failure to provide certain details and to send notices of awards Scope of the allegation relating to separate treatment of the contracts

23. The French Government does not, essentially, dispute the second claim, which relates to failure to comply with Articles 21 25. The main issue is whether the contracts (as regards the missing information which should have been aggregated for the pur- should have been provided in the notices poses of Article 14(10) and/or whether which were sent to the OJEC), 24 and 25 of their separation constituted illegitimate the Directive. 9It admits that the informa- splitting, contrary to Article 14(13), lead- tion sent was incomplete and that no ing in either case specifically to a failure to notices of the awards were sent. It is thus publish notices in the OJEC where such undisputed that, by failing to provide full notices should have been published under details in accordance with Annex XII in Article 21. respect of the six calls for competition published in the OJEC and by failing to communicate details of the award of those contracts, the French Republic failed to fulfil its obligations under Articles 21(1) and 24(1) and (2) of the Directive. 26. In the French Government's view it was correct to treat them all as separate con- tracts for separate works.

24. However, in view of the admission that no notices were sent other than in respect 27. The Commission considers that for the purposes of the Directive they should have been treated as lots of the same overall 9 — See paragraph 6 above. works contract and not separately, whether

I - 8325

OPINION OF MR JACOBS — CASE C-16/98

on a geographical basis (separate contracts the ECU 5 000 000 threshold in only one for each local entity) or on a technical basis case — in which a notice was in fact (separate contracts for electrification and published in the OJEC for the electrifica- lighting). tion contract (FRF 30 000 000) and the lighting contract was for less than ECU 1 000 000 and 20% of the total for the local entity. Thus, if it were to be found that there were justifiably separate con- tracts for each local entity, but that the separation between electrification and 28. There are three possible configurations lighting was not justified, the infringement in the Commission's allegation: that the would be confined to the failure to publish electrification and lighting work should calls for competition for lighting work for have been treated as a whole for each local the five remaining local entities where entity but not for the département, that all notices of the electrification contracts were the electrification work and all the lighting published and where the lighting contracts work should have been treated as two were worth more than ECU 1 000 000. separate wholes for the whole département, or that all the work of both types should have been treated as a single whole for the whole département. The remaining possi- bility is, of course, that argued for by the French Government.

31. If, on the other hand, all the contracts 29. Of the 37 notices with which this case for the département were aggregated in is concerned, five were for an estimated each category (if separation were justified value of over ECU 5 000 000, those five on technical but not on geographical and one more (all for electrification con- grounds), both categories would be well tracts) were in fact published in the OJEC above the ECU 5 000 000 threshold. One and 14 (all but one of which were for electrification contract (for FRF 6 000 000) lighting contracts) were for amounts below would then have been exempt from the ECU 1 000 000. need for publication by being under the threshold of ECU 1 000 000 and 20% of the total for electrification. Those of the lighting contracts which fall below the threshold total more than 20% of the total for lighting, but up to six of them could be exempted before that percentage (some 30. If the electrification and lighting con- FRF 25 000 000) was reached. Thus, if tracts had been aggregated for each local separation were justified on technical but entity separately (if separation were justi- not geographical grounds, the infringement fied on geographical but not technical would concern 12 electrification contracts grounds) the value would have risen above and 12 lighting contracts.

I - 8326

COMMISSION V FRANCE

32. Finally, if all the contracts in both 35. It might be thought that those provi- categories were aggregated together for sions of Article 14(10) and Article 14(13) the département (if separation were unjus- express the same rule in different terms. I tified on either technical or geographical consider, however, that they should be grounds), then all 14 under the ECU distinguished. 1 000 000 threshold would be exempt from the need for publication because they would amount to less than 20% of the aggregate total. The infringement would thus concern 12 electrification contracts but only 5 lighting contracts. 36. Article 14(10) sets out purely objective criteria on the basis of which it may be determined whether the Directive applies. The term 'work' is defined and it is the total value of that work, arrived at where necessary by aggregating the values of any lots into which it may be divided, which 33. It is therefore necessary to look at both determines the need to comply with the types of separation because the effects of provisions of the Directive. the three possible approaches to aggrega- tion would be different.

37. Article 14(13), on the other hand, introduces a subjective element. It speaks of 'circumventing' the Directive by specific types of conduct, namely splitting contracts or using special methods of calculating Article 14(10) and Article 14(13): aggrega- value. That wording implies a degree of tion and splitting intent in the conduct adopted. Circumven- tion, like the equivalent concepts used in other language versions, involves deliberate conduct rather than a fortuitous escape. Both the splitting of contracts and the use of special methods of calculation require 34. It will be recalled that Article 14(1) some intention on the part of the splitter or provides that the Directive is to apply to calculator. works contracts for an estimated value of at least ECU 5 000 000. Under Arti- cle 14(10), where work is the subject of several lots, it is the aggregate value of all the lots which is to be taken for the purposes of Article 14(1). Article 14(13) provides that contracting entities may not 38. It is also true, however, that Arti- circumvent the Directive by splitting con- cle 14(13) of Directive 93/38 appears to tracts. contrast with the equivalent provision

I - 8327

OPINION OF MR JACOBS — CASE C-16/98

(Article 6(4)) of Directive 93/37, 10 adopted 41. Has the Commission established that on the same day, which provides: 'No work the contracts in issue would normally have or contract may be split up with the been treated as a whole by the relevant intention of avoiding the application of entities but were deliberately separated to this Directive' (my emphasis). Nevertheless, circumvent the application of the Direc- I consider that the difference is not signifi- tive? cant; the import is the same and there is no indication of any will on the part of the legislature to remove the element of intent from the prohibition. Had that been the case, a more neutral wording would cer- tainly have been chosen. It may be noted in this connection that the Commission's 'Guide to the Community rules on public 42. I consider that it has not. works contracts', produced in response to a request by the Court, states of the prohibi- tion in Directive 93/37 that it 'catches any splitting which is not justified on objective grounds and is thus solely designed to circumvent the rules laid down in the Directive'. 43. On the contrary, no evidence has been put forward that the practice of SYDEV or the various local entities was any different in relation to the contracts in issue in the present case from what it would otherwise have been. The documents produced by the 39. I thus take the view that a breach of French Government are consistent with its Article 14(13) cannot be established in the contention that the course followed was the absence of intent. normal one in Vendée and no evidence to the contrary has been submitted by the Commission. At the hearing, the French Government made the point that, had there been any intention to circumvent the Directive, an effort would have been made to do so more discreetly. 40. Article 14(13), moreover, prohibits the 'splitting' of contracts. That concept, in addition to emphasising the element of intent, presupposes the existence of a contract which would, in the normal course of events, have been treated as a single whole but which has been — abnor- mally — divided into separate contracts. 44. The Commission's references to prac- tices followed in two other départements are of no particular relevance in that 10 — Council Directive 93/37/EEC of 14 June 1993 concerning regard, in the absence of evidence of any the coordination of procedures for the award of public works contracts, OJ 1993 L 199, p. 54. consistent practice systematically applied

I - 8328

COMMISSION V FRANCE

throughout France. 11 Nor is it relevant obligations thereunder. The examination of whether, as the Commission alleges, com­ that provision will, therefore, be crucial in mon sense may dictate that electricity my analysis. supply and street lighting work should be dealt with together — a matter which I shall examine more fully in the context of Article 14(10) — unless it is established that they were deliberately separated in defiance of such an approach. And com­ mon sense is often an elusive guide. Identity of the contracting entity

47. First, however, it is necessary to con­ sider a matter debated at some length 45. For an allegation of breach of Arti­ between the parties: is it significant whe­ cle 14(13) to be successful, it would be ther there was, for the purposes of Com­ necessary to establish an intent to circum­ munity law, a single contracting entity vent the provisions of the Directive, possi­ (SYDEV) or a number of separate con­ bly on the basis of a departure from what tracting entities (SYDEV's members, the would otherwise have been the practice. local entities)? No specific evidence of either has been produced by the Commission, nor in my view can they be inferred from the circum­ stances as a whole, which I shall analyse in greater detail below. I thus consider that the Court should not find that in this instance 48. The French Government's point of view the French Republic has failed to fulfil its is, essentially, that it is impossible to obligations under Article 14(13) of the separate the question of the unity of the Directive. work involved from that of the unity of the contracting entity; there cannot be a single work where there are separate contracting entities. It has thus argued, vigorously, that each local entity was a separate contracting entity (a maître d'ouvrage in French law) whereas SYDEV was legally incapable at 46. None of the foregoing, however, the material time of acting other than as a detracts from the possibility that the provi­ technical supervisor, manager and coordi­ sions of the Directive should have applied nator of the different works (as maître on objective grounds in accordance with ď œuvre). Article 14(10) thereof and that the French Republic may have failed to fulfil its

11 — Indeed, it may be noted that the notices of award of contracts for the département of Dordogne produced with the application m fact show that, in addition to the 49. The Commission, after appearing to procedure to which the Commission refers, separate seek to refute that argument, asserting that procedures were followed simultaneously for the northern, north-eastern and south-western parts of the département. the true contracting entity was SYDEV in

I - 8329

OPINION OF MR JACOBS — CASE C-16/98

all cases, stated in response to a question at and ECU 1 000 000 for works contracts) the hearing that the identity of the con- are clearly designed to deal with that tracting entity was not in its view an concern. In order to ensure, though, that essential factor in the application of Arti- those thresholds are effectively observed, cle 14(10) of the Directive, the aggregation there are provisions to prohibit deliberate requirement in which could apply also to circumvention (Article 14(13)) and to avert contracts awarded by a number of different a possible failure to apply them if a single contracting entities, provided that they overall works project is subdivided on were for a single 'work' within the meaning other — and possibly otherwise legiti- of that provision. mate — grounds (in Article 14(10)).

52. The aim is thus to ensure that under- takings in other Member States have the 50. I agree with that latter view. opportunity to tender for contracts or bundles of contracts which, on objective grounds of estimated value, are likely to interest them. Whether such contracts are to be awarded by one contracting entity or by several is not a significant factor in that context. There may well be legitimate reasons, administrative or other, for con- 51. The definition of 'work' in Arti- tracts for portions of a single works project cle 14(10) makes no reference to the iden- to be awarded separately by different tity of the contracting entity and it is logical entities, but that will not seriously reduce that it should not. The aim of the Directive, the interest which the whole project is as is clear from its preamble, its provisions likely to represent for an appropriately and the surrounding context of other qualified undertaking in another Member Community public procurement legisla- State. One might imagine, for example, tion, is to open up the market to Commu- work to be carried out on a road passing nity-wide competition in the areas to which through the territories of different local it relates. The principal means which it authorities each having administrative employs for that purpose are the require- responsibility for a section of highway. ments that standard procedures must be The aim of the Directive would not be used, that calls for competition must be achieved if its application were to be published at Community level and that excluded on the ground that the estimated there must be no discrimination between value of each section was only ECU tenderers. However, no purpose would be 3 000 000. served, and a great deal of unnecessary administrative work would be generated, if those requirements were to apply to all contracts, regardless of their value and of the likelihood that they would interest potential tenderers from other Member 53. It is true that the definition of a works States. The thresholds (of ECU 5 000 000 contract in Article 1(4) of the Directive

I - 8330

COMMISSION V FRANCE

specifies that it is a contract concluded by Article 14(10): a single 'work' or several? 'one of the contracting entities referred to in Article 2' (my emphasis), which might suggest that for the purposes of Article 14 each works contract must be concluded with a separate entity. However, Article 2 refers to 'contracting entities' in the plural, 55. The crucial point to be decided is classifying them in two basic categories, whether the contracts awarded separately those which are public authorities or under- for electrification and street lighting work takings and those which are not. It thus by each of the local entities formed a single seems more probable that the definition in 'work' ·— or a number of larger 'works' Article 1(4) is intended to refer to contract- aggregated either geographically or techni- ing entities of one of the types referred to in cally — for the purposes of the Directive Article 2. Moreover, as the Commission and should thus have been treated together. has pointed out, the definition of 'public authorities' includes 'associations formed by one or more of such authorities', which means that a contracting entity need not be a single public authority and need not be the body which actually concludes the contract. It is clear also that the criterion 56. A 'work' is defined in Article 14(10) as of the 'total value of the work' in Arti- 'the result of building and civil engineering cle 14(10) is not the value of a single activities, taken as a whole, which are contract, or the provision would be self- intended to fulfil an economic and techni- defeating. On the basis of those considera- cal function by themselves'. This is not a tions, I suggest that too much significance particularly precise definition, nor is any should not be attached, for the purposes of specific help to be found in the guidelines Article 14, to the use of the singular in produced by the Commission. As one Article 1(4). commentator has put it, 'identifying a single work should be like defining the proverbial elephant: awarding authorities will know one when they see it'. 12 In the present case, however, the Court is called upon to provide some guidance on how to recognise an elephant.

54. I therefore take the view that, as 57. One possibility is to start from the regards a possible infringement of Arti- purpose of the rules laid down in the cle 14(10) of the Directive in the present Directive. As I have stated, that aim is case, it is not necessary to decide whether there were a number of separate contract- ing entities or a single contracting entity in 12 — Adrian Brown, 'Getting ro Grips with Aggregation under the EC Public Procurement Rules', Public Procurement the form of SYDEV. Law Review 1993, p. 69, at p. 72.

I-8331

OPINION OF MR JACOBS — CASE C-16/98

essentially to ensure that undertakings interpreted in the light of its aims, the throughout the Community enjoy the criterion here is specific. It is to the opportunity to compete for contracts intended economic and technical function exceeding a certain fixed threshold value that we must look, rather than to the way above which it is likely to be economically in which the work may be seen by potential profitable to do so. Since in several tenderers. instances contracts for both electrification and street lighting work were awarded to the same tenderer in different localities — from which it may be deduced that, in theory, a single contractor could have performed all the work of both kinds throughout the département — and since 59. I take the criterion set out in Arti- seven of the ten successful tenderers were cle 14(10) to mean that the boundary awarded contracts totalling considerably between work which must be aggregated more than ECU 5 000 000, it would seem for the purposes of the Directive and work logical that tenderers from other Member which may legitimately be treated sepa- States should have been given an opportu- rately lies between bundles of contracts nity to compete. At the hearing, the Com- which, as regards their intended objective, mission argued that the requirement to share a common economic and technical treat a number of contracts as forming a function and those which do not. single 'work' and to publish them in the OJEC arises when the contracts are so linked that a Community undertaking is likely to regard them as a single economic operation and to wish to tender for the whole, as it claims was the case here. 60. The Commission's position is, essen- tially, that the work to be done in the present case formed a multiannual electri- fication programme covering the whole of Vendée and thus had a single economic and technical function. It stresses that the work descriptions are identical within each cate- gory and similar as between categories, with all the work to be carried out over the same period within the same geographical and administrative area. The concept of a 'work' cannot be confined in a case such as the present to that of a specific structure or 58. However, I do not consider that to be construction. the correct approach. Article 14(10) refers to the economic and technical function which the contracted activities are intended to fulfil by themselves and not to the interest which a potential tenderer may have in being fully informed, even though one of the overall aims of the Directive is to 61. The French Government contends that protect and further that interest. Although separate improvement and extension the provisions of the Directive should be operations on a number of independent

I - 8332

COMMISSION V FRANCE

networks cannot be regarded as forming a invitation to tender published by the bodies single 'work' intended to fulfil a single equivalent to SYDEV in two other French economic and technical function. It con- départements (Calvados and Dordogne) in siders that, in the absence of a specific 1995. The French Government emphasises structure or construction, it is for the that the work on the electricity supply contracting entity to define its needs and network is essentially underground, thus determine the identity of the 'work'. In whereas the street lighting work is essen- the present case, each local entity defined tially above ground, and that the two types its own needs in respect of its own net- of work fall under different headings ('civil works, independently of any hypothetical engineering' and 'installation' respectively) overall 'work'. in the NACE classification as set out in Annex XI to the Directive. At the hearing, it suggested that work on the street lighting networks might not fall within the scope of the Directive at all, since those networks do not involve the production, supply, trans- 62. Neither of the parties has provided the port or distribution of electricity u but Court with a very full description of the rather its consumption for the benefit of networks involved. However, it appears the public. from what has been said by the French Government, and not denied by the Com- mission, that the local entities are respon- sible for individual low-voltage electricity supply networks radiating from transfor- mer substations and serving consumers within their areas; that those networks are interconnectable; and that the street light- ing networks, controlled by the individual local entities, are powered from those electricity supply networks. 64. Of those considerations, I consider only the last to be significant. It highlights — even without there being any need to consider that street lighting falls entirely outside the scope of the directive — the distinction which may legitimately be — Electrification and street lighting: tech- drawn, in terms of intended economic and nical considerations technical function, between the two types of network. An electricity supply network is intended, technically, to transport elec- tricity from a supplier to individual end- consumers who, economically, must pay that supplier for what they consume. A street lighting network provides lighting in 63. The Commission stresses that the public places. It is itself an end-consumer of description of both types of work (electri- fication and street lighting) includes work on the public address system and that both 13 — See Article 2(2) of the Directive, cited in paragraph 3 types of work were included in the same above.

I - 8333

OPINION OF MR JACOBS — CASE C-16/98

the electricity delivered to it by the elec- offer a single contract for work on both tricity supply network. The authority pro- types of network determine whether, in viding the service must itself assume the principle, such civil engineering activities, cost — recovering it, presumably, from the taken as a whole, are intended to fulfil a population served through some such single economic and technical function. means as local taxation rather than on the basis of any individual benefit derived.

67. It is thus unnecessary to decide for the purposes of this case whether street lighting falls within the scope of the Directive or not, an issue which has in any event not been properly debated before the Court. If it does not, however, then clearly there can 65. It is thus clear, in my view, that an be no question of aggregating such work electricity supply network and a street with electrification work for the purposes lighting network are intended to fulfil of the Directive. different economic and technical functions. That being so, I do not consider that work to maintain, improve and/or extend net- works of the two different types, whether in the same area or not, can be treated together as a single 'work' for the purposes 68. I conclude that it was not necessary to of Article 14(10) of the Directive. aggregate the values of the electrification and lighting contracts for the purposes of the Directive, whether for the département as a whole or for each local entity. The question remains, however, whether the contracts should have been aggregated for the whole département for either category individually.

66. That conclusion is not outweighed by the other considerations put forward by the Commission. The fact that a public address system is mentioned in both types of — Electrification: technical and geographi- invitation to tender, as 'associated gener- cal considerations ated' work, does not imply a single eco- nomic or technical function. Different parts of a public address system may be carried by electricity supply ducts and by street lighting masts, so that work on either network may generate work on that sys- 69. It appears 14 that each local entity is tem, without affecting the economic or responsible for the electricity supply net- technical functions of the networks them- selves. Nor does the fact that some other contracting entities may have chosen to 14 — See note 2 and paragraph 62 above.

I - 8334

COMMISSION V FRANCE

work in its area, although the networks are place, time and action. All the electrifica- interconnected and the electricity is sup- tion contracts in issue were for work to be plied by the national corporation EDF. The done within the same département over the Commission stresses the geographical con- same period, bearing the same general tiguity of the networks, the simultaneity of description and subject to the same techni- the work programmes, the identical nature cal control. There is no suggestion that of the work descriptions and the overall there was work of the same nature to be coordination by SYDEV. The French Gov- carried out at the same time over any wider ernment emphasises above all that each area — covering neighbouring départe- local entity entered into a separate contract ments or regions, or even the whole for its own network. national network. In particular, it is implausible that any such work would have come under the supervision of SYDEV. Had that been the case, however, then it could indeed have been argued that all such work constituted a single 'work' for the purposes 70. That latter consideration, I have con- of the Directive. And in that case, I cluded, 15 is not relevant to the question of consider, the conclusion would be not the determining whether there was a single reductio ad absurdum which the French 'work' for the purposes of the Directive. Government seeks to establish but rather Indeed, the present situation would appear that all the invitations to tender would have comparable to the example which I have had to be notified in the OJEC. cited of a public highway passing through the territories of several local authorities. Although, for administrative reasons, the different local entities have responsibility for the low-voltage supply networks within their areas, those interconnectable net- works taken as a whole are intended to fulfil a single economic and technical function: the conveyance and sale to con- sumers of electricity produced and supplied by EDF. 72. The fact that the contracts are for a series of separate operations to be carried out at different points in time and space (within the same period of time and the same geographical area) does not mean that 71. It is true that, as the French Govern- they should not be regarded as a single ment has pointed out, that reasoning would 'work'. If that reasoning were followed, apply to the whole of the national electri- each operation would be a separate 'work', city supply system. However, I agree with and not even the French Government has the Commission that the 'work' in the suggested that such should be the case. On present case is clearly circumscribed by the contrary, a series of operations to be what one might call the three unities — of carried out within a specified period on a group of networks having a shared eco- nomic and technical function must itself be 15 — See paragraphs 51 to 54 above. regarded as intended to fulfil a shared

I - 8335

OPINION OF MR JACOBS — CASE C-16/98

economic and technical function. In that — Street lighting: technical and geographi- connection, it may be recalled that the cal considerations terms of the 1960 arrêté préfectoral 16 refer to the 'general inventory of the require- ments of the département — a wording which tends to confirm that conclusion.

75. I find it more difficult to apply the same reasoning to the work to be carried out on 73. I thus reach the view that all the the street lighting networks. It is certainly electrification contracts in issue formed a true that the economic and technical func- single 'work' within the meaning of Arti- tion of each individual network is the same cle 14(10) of the Directive. Their values as that of all the others, but I do not should have been aggregated for the pur- consider that they thereby share a common pose of determining whether calls for function. competition should have been published in the OJEC. Six such calls were in fact published, and one other contract was for an estimated value lower than ECU 1 000 000 and 20% of the total, thus qualifying for a derogation in accordance with the second subparagraph of Arti- cle 14(10). The failure to publish notices of the remaining 12 contracts, however, all 76. Whilst we have not been given any for estimated values above that threshold specific account of how street lighting is and totalling somewhat over ECU organised in Vendée, I think it not unrea- 26 000 000, constituted an infringement sonable to assume that the networks are of the Directive. independent of each other, as the French Government says. Since street lighting is an activity which consumes electricity, for which each local entity responsible must pay, there would not appear to be any purpose in interconnection, in contrast to the situation as regards the electricity net- 74. That infringement involved a failure to work, which is a supply system with a comply with not only Article 14(1) and single supplier. Each network is likely to be (10) of the Directive, as regards the calcu- supplied from a separate point on the lation of the value of the work, but also electricity supply system, enabling the con- Article 21(1) and (5), because notices were sumption of each local entity to be deter- not drawn up and sent for publication in mined. Lighting is, moreover, generally the OJEC, and Article 25(5), because confined to built-up areas. Where such notices were published in the BO AMP. areas are separated by open countryside, as may well be predominantly the case in a largely rural département such as Vendée, 16 — Cited in paragraph 9 above. the different networks are unlikely to be

I - 8336

COMMISSION V FRANCE

contiguous. Different local entities may, Article 4(2): discrimination between con- furthermore, take quite different approa- tractors ches to street lighting: some may seek to provide as generous a service as possible, whereas others may wish to save rate- payers' money by providing a strict mini- mum.

79. The Commission's argument here is essentially that, by wrongly publishing only a selection of the invitations to tender in the OJEC, the French authorities placed ten- derers from other Member States at a disadvantage since such tenderers, being unaware of the total value of the work and the extent to which it might interest them, 77. It is true that the above considerations would either decide not to compete or are largely conjectural with regard to the allow for proportionately higher fixed costs specific circumstances of the present case. and thus submit less attractive bids than However, the French Government has undertakings having gleaned fuller knowl- stressed the mutual independence of the edge of the scope of the work from the individual networks, and the Commission BOAMP. The French Government, has produced no evidence to the contrary. although it relies principally on its denial In particular, there is no evidence of any of any artificial splitting, asserts that there unifying economic factor such as might be was no discrimination between tenderers, provided by, for example, a uniform system who were all required to bid a percentage of local taxation throughout the départe- difference from the estimated value of ment to pay for the cost of the lighting. different categories of work with a view to carrying out specific items of work to be determined in the future.

78. I thus consider that the Commission has not established the existence of a 80. Since Article 4(2) prohibits discrimina- shared economic and technical function tion specifically between 'suppliers, con- within the meaning of Article 14(10) of tractors or service providers', it might be the Directive and that it was not necessary wondered whether it extends also to dis- to aggregate the values of all the street crimination between tenderers or, a for- lighting contracts in order to determine tiori, potential tenderers (since we have not whether the Directive was applicable, even been informed that any undertaking from assuming that street lighting falls within the another Member State in fact submitted scope of the Directive. any tender in this case).

I - 8337

OPINION OF MR JACOBS — CASE C-16/9 8

81. I consider that it does. For one thing, Article 4(2) of Directive 90/531, 18 the the terms 'supplier', 'contractor' and 'ser- direct and almost identically-worded pre- vice provider' are not defined in the Direc- decessor of Article 4(2) of the present tive, whereas 'tenderer' is defined in Arti- Directive. Although the Court described cle 1(6) as 'a supplier, contractor or service the principle as that of equal treatment provider who submits a tender'. The term between tenderers, I consider that, by its 'contractor' is thus not used in the Directive very nature, it must apply also to those who in the sense of one who has been awarded a may be discouraged from tendering because contract but in the wider sense of one who they have been placed at a disadvantage. aspires to be awarded a contract.

82. Indeed Article 4(1) — and it is worth noting that Article 4 is the first substantive provision in the Directive, defining to a certain extent the scope of what follows —· requires contracting entities to comply with the Directive 'when awarding... contracts, or organising design contests'. The juxta- position of 'awarding' and 'organising' 84. That being so, and in view of the suggests that the term 'awarding' too must conclusion I have reached regarding the be taken as embracing the whole procedure failure to aggregate the electrification con- rather than just its final stages, and I tracts, I consider that the Commission has consider that Article 4(2) must have the established a breach of Article 4(2) of the same scope. Directive. Regardless of whether in this case tenderers from other Member States would in fact have been attracted — given the obvious desirability of a local establish- ment and the risk that they might be awarded only a portion of the total work, thus possibly compromising their calcula- tions as to fixed costs — they were pre- vented from taking a decision on a proper 83. The Court has, moreover, held the basis because full information of the whole principle of equal treatment to be inherent 'work' was not published in the OJEC as it in the original Community directive on should have been. Tenderers consulting the public works contracts 17 and embodied in BOAMP, however, who will have been

17 — Council Directive 71/305/EEC concerning the coordina- tion of procedures for the award of public works contracts, 18 — Council Directive 90/531/EEC of 17 September 1990 on OJ, English Special Edition 1971(11), p. 682, as amended the procurement procedures of entities operating in the by Article 1(6) of Council Directive 89/440/EEC of 18 July water, energy, transport and telecommunications sectors, 1989, OJ 1989 L 210, p. 1; see Case C-243/89 Commis- OJ 1990 L 297, p. 1; see Case C-87/94 Commission v sion v Denmark [1993] ECR I-3353, paragraph 33 of the Belgium [1996] ECR I-2043, paragraphs 51 and 52 of the judgment. judgment.

I - 8338

COMMISSION V FRANCE

predominantly French, had fuller informa- Costs tion at their disposal.

86. Since, in my view, the Commission has established breaches of the Directive in 85. However, with regard to the six calls respect of the failure to publish all the for competition actually published in the required details of the electrification con- OJEC, the information published in the tracts in the OJEC but has failed to OJEC was the same as that published in the establish a breach of Article 14(13) or any BOAMP, so that the failure to communi- breach in respect of the lighting contracts in cate all the information required by Arti- issue, I consider that, in accordance with cle 21(1) of the Directive read in conjunc- Article 69(3) of the Rules of Procedure, the tion with Annex XII thereto did not entail parties should each be ordered to pay their any discrimination. own costs.

Conclusion

87. In view of all the foregoing considerations, I consider that the Court should:

( 1 ) declare that, by failing, in the course of the procurement procedure issued by the Syndicat Départemental d'Électrification de la Vendée in December 1994 for the award of contracts for electrification work:

— to publish a call for competition in the Official Journal of the European Communities for 12 contracts each with an estimated value exceeding ECU 1 000 000 and forming part of a single work within the meaning of

I - 8339

OPINION OF MR JACOBS — CASE C-16/98

Article 14(10) of Council Directive 93/38/EEC, the French Republic failed to fulfil its obligations under Article 4(2), Article 14(1) and (10), Article 21(1) and (5) and Article 25(5) of that directive;

— to provide full details in accordance with Annex XII to Directive 93/38/ EEC in respect of six calls for competition published in the Official Journal of the European Communities, the French Republic failed to fulfil its obligations under Article 21(1) of that directive;

— to communicate details of the award of all the contracts, the French Republic failed to fulfil its obligations under Article 24(1) and (2) of Directive 93/38/EEC;

(2) dismiss the remainder of the application;

(3) order the parties to bear their own costs.

I - 8340

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-16/98 – Súdny dvor Európskej únie | AI Pravnik