C-40/98
ECLI:EU:C:2000:319
- Súd
- Súdny dvor Európskej únie
- IČS
- 61998CC0040
- Zdroj
- eur-lex.europa.eu ↗
OPINION OF MR RUIZ-JARABO — CASE C-40/98
O P I N I O N OF ADVOCATE GENERAL RUIZ-JARABO C O L O M E R delivered on 15 June 2000 1
1. By application under Article 181 of the gramme's work in the field of applied EC Treaty (now Article 238 EC), the Com- metrology and chemical analysis. 3 The mission of the European Communities, contract was for research into measuring following a breach of contract 2which it systems and instruments for products man- alleges to have been committed by TVR- ufactured from composite materials, using Tecnologie Vetroresina SpA ('the defen- filament winding technology. dant' or 'TVR'), asks the Court to order the defendant to reimburse certain sums and to pay compensation for loss and damage. 3. The following clauses of the contract are directly relevant to the proceedings:
— The duration of the project was to be I — The contract 36 months from the month following signature of the contract (from 1 Sep- tember 1991 to 31 August 1994) and any delay was to be immediately noti- fied to the Commission (Article 2). TVR was required to submit a progress 2. On 13 August 1991, the Commission, of report every six months and, upon the one part, and the defendant and Brunei termination of the project, a final University ('Brunei'), of the other, signed report detailing the results obtained Contract No 3440/1/0/187/91/6-BCR-I(30) (Article 6.1). as part of the European Economic Com- munity's Research and Development Pro-
1 — Original language: Spanish. 2 — In Iván A. Goncharov's novel, Oblómov, two characters — The Commission's financial contribu- conspire to rob Ilyá Ilyich Oblómov of his wealth, remarking: tion (up to a ceiling of ECU 584 000) 'And the agreement, the agreement we drew up!' Tarantyev boasted. was divided into an initial advance of 'But the agreement is signed: they did not trip us up there, did they?' said Tarantyev. 'That, of course, is sacred....' (Goncharov, I.A., Oblómov, translated by David Magar- 3 —Council Decision 88/418/EEC of 29 June 1988 (OJ 1988 shack, Penguin, London, 1954, pp. 356 and 357). L 206, p. 29).
I - 308
COMMISSION V TVR
ECU 230 000, followed by subsequent 230 000 to the defendant, ECU 165 000 of periodic payments to be made in which was to be transferred by the defen- respect of the cost statements. It was dant to Brunei pursuant to Article 4 of the expressly stipulated that the Commis- contract, referred to above. Brunei, how- sion would make all payments to the ever, did not receive that sum. defendant, which was to be responsible for immediately transferring the appro- priate amount to the other contractor (Article 4). 7. By letters dated 26 March and 15 April 1993, the Commission requested TVR to transfer that sum to Brunei, warning, in its 4. The parties were entitled to terminate second letter, that it would terminate the the contract on any of the grounds set out contract and demand repayment of the in Article 8 of Annex II (General Condi- advance, together with interest, if TVR tions). Specifically, under paragraph 2(d) of failed to prove, within one month, that it this article, the Commission could termi- had made the transfer. nate the contract in the event of non- performance by one or both of the con- tractors, unless there were reasonable and justifiable technical or economic reasons, if the contractor concerned was still in breach 8. On 26 May 1993, the Commission noti- one month after receipt of notice in writing fied TVR of its decision to suspend all from the Commission, sent by recorded financing of the project with effect from delivery or registered post, requiring per- that date. formance of those obligations.
5. Under Article 12 of Annex II, the Court 9. Since Brunei had still not received the of Justice of the European Communities transfer, the Commission, by letter dated has sole jurisdiction to deal with any 31 January 1994, terminated the contract dispute concerning the contract. Article 11 under Article 8.2(d) of Annex II and of the contract stipulates that it is to be required TVR to reimburse the sum of governed by Italian law. ECU 165 000, together with interest calcu- lated in accordance with Article 8.4 of that annex.
I I — Facts In a further letter of the same date, the Commission rejected both the cost state- ment provided by TVR for the period 6. On 20 September 1991, the Commission 1 September 1992 to 26 May 1993 and transferred an advance payment of ECU the consolidated cost statement.
I - 309
OPINION OF MR RUIZ-JARABO — CASE C-40/98
At the same time, the Commission notified defendant rejected that calculation and Brunei of its decision to terminate the requested a review of the contract. contract.
13. On 13 August 1993, the Commission 10. On 24 February 1994, TVR sent the instructed Ernst & Young to carry out an Commission a new consolidated cost state- audit of the first contract year (the period ment, followed, at the Commission's from 1 September 1991 to 31 August request, by additional documentation 1992). which it submitted on 15 March 1994.
14. On 8 September 1994, Ernst & Young 11. By letter dated 6 April 1994, the Com- delivered their audit report. The auditors mission advised TVR that the information stated that they had found no evidence to it had supplied was not sufficient to justify show that ECU 165 000 had been trans- its consolidated cost statement. However, it ferred to Brunei. With regard to the labour accepted the revised cost statement in costs, the auditors stated, first, that the respect of the first project year and partially amount of working time notified to the accepted the travel costs for the second Commission was lower than the amount project year. shown in TVR's books and, second, that the defendant had calculated the labour costs for 1992 using the 1991 rates, so that the actual costs could be taken to be higher than those contained in the statement.
12. Using those figures, the Commission calculated TVR's costs to be ECU 37 386, 50% of which (ECU 18 693) was to be borne by the Community in accordance with Article 3.2 of the contract. Therefore, By way of conclusion to their report, Ernst in July 1994, the Commission claimed from & Young stated that, in their opinion, apart TVR reimbursement of the difference from the sum which should have been between that sum and its share of the transferred to Brunei, the costs submitted advance (ECU 65 000), that is to say, ECU were in accordance with those contained in 46 307. In a letter dated 26 July 1994, the TVR's books and with the contract terms.
I-310
COMMISSION V TVR
15. On 30 September 1994, the Commis- law is applicable, the duty to make restitu- sion transferred ECU 165 000 to Brunei, tion contained in Article 1458 4 of the Civil after verifying the accuracy of the costs it Code only takes effect where termination had claimed and the work it had carried of the contract, on the ground of a breach out under the contract. by one of the parties, has been declared by a court. Since the Commission has not requested the Court of Justice to terminate the contract for breach by the defendant, it cannot claim reimbursement of the sums paid under the contract. 16. By letter to the defendant dated 22 June 1995, the Commission made a formal demand for reimbursement of ECU 203 775, including the sum which should have been transferred to Brunei (ECU 165 000), together with interest, and also 19. In its reply, the Commission asserts, ECU 46 307 to cover the difference first, that it acted in accordance with the between the work actually carried out by procedure laid down in the contract for TVR under the contract and the advance terminating it on the grounds of non- paid to it by the Commission on 20 Sep- performance. Therefore, the contract has tember 1991. already been terminated automatically and there is no need to seek a declaration to that effect from the Court of Justice.
17. Since no response was forthcoming from TVR, the Commission brought the present action before the Court of Justice, The Commission goes on to refer to the seeking an order that the defendant repay case-law of the Corte Suprema di Cassa- the sum of ECU 211 307, plus interest, and zione (Supreme Court of Cassation) con- pay ECU 20 000 by way of compensation cerning Article 1453 of the Italian Civil for loss and damage, in addition to the Code on the termination of contracts. The costs of the proceedings. Commission claims that, according to that case-law, there is no requirement that the intention to terminate a contract for non- performance be expressly formulated in an action before the court, since such an intention may be inferred from other actions which, although having a different
III— Admissibility of the action 4 — The defence erroneously cites Article 1958. Article 1458 of the Italian Civil Code provides: 'Termination of the contract on the ground that it has been breached shall have retroactive effect vis-à-vis the parties, except in the case of contracts whose performance is continuous or periodic, where termination shall not affect activities already per- formed. Termination, even where it has been expressly 18. TVR claims that the action should be agreed, shall not adversely affect the rights acquired by third parties, save as regards the effects of the lodging of the declared inadmissible because, as Italian action for termination of the contract.'
I -311
OPINION OF MR RUIZ-JARABO — CASE C-40/98
object, contain an implied application for 21. In the Commission's view, the contract termination. 5 The Commission states that was terminated by application of the ter- the Corte Suprema di Cassazione has held, mination clause contained therein. in particular, that the intention to terminate Although the defendant has not claimed a contract may be contained by implication that that clause was invalid, I consider that in an action whereby one of the parties to a number of observations are called for in the contract seeks an order that the other that regard. party, who is in default, is to reimburse the sums he was paid when the contract was signed. 6
For those reasons, and despite the fact that A. Validity of the contractual termination it considers it to be superfluous on the clause ground that the application for a declara- tion that the contract has been terminated is, in any event, implicit in its action for 22. Termination clauses are governed by reimbursement of the sums paid and for Article 1456 of the Italian Civil Code, 9 compensation for damage, the Commission which allows the contracting parties to requests the Court of Justice to declare that agree expressly that the contract will be the contract has in fact been terminated. automatically terminated should there be a breach of a specified obligation. According to the case-law of the Corte Suprema di Cassazione, two conditions must be satis- 20. In Commission v SNUA, 7to which I fied in order for one party to be entitled to shall refer later, the Court dismissed a terminate the contract unilaterally by rely- similar plea of inadmissibility after con- ing upon a termination clause: the clause in firming the validity of the Commission's question must be valid and responsibility unilateral termination of a contract. 8In the for the breach must be attributable to the light of that case-law, it is appropriate to other party. examine whether, in the present case, the contract between the Commission and TVR was automatically terminated on the ground of non-performance by the defen- dant. 23. With regard to the first requirement, the Corte Suprema di Cassazione has interpreted Article 1456 of the Italian Civil 5 —Judgment of the Corte Suprema di Cassazione of 15 July Code as meaning that, in order to be valid, 1980, No 4591. 6 — Judgements of the Corte Suprema di Cassazione of 4 Octo- a termination clause must refer to specified ber 1976, No 3217; 15 July 1980, No 4591; and 22 Feb- obligations arising under the contract, and ruary 1992, No 1908. 7 — Case C-69/97 Commission v SNUA [1999] ECR I-2363. 8 — That is not the only case in which the Court has adjudicated on a claim for reimbursement of sums paid and for compensation for damage brought by the Commission, 9 — Article 1456 provides: 'The parties to the contract may despite the fact that the latter had failed to seek a prior expressly agree that the contract will be terminated if a declaration that the contract had been terminated on the specified obligation has not been performed in accordance ground of non-performance by the other party: see Case with the rules set out. If such a situation arises, the contract C-334/97 Commission v Comune di Montorio al Vomano will be terminated automatically when the party concerned [1999] ECR I-3387 and Case C-65/97 Commission v notifies the other party that he intends to invoke the Cascina Laura and Gariboldi [19991 ECR I-1017. termination clause.'
I-312
COMMISSION V TVR
that clauses referring generally to non- law, was drafted in different terms and performance of all the obligations con- provided that 'the Commission may uni- tained in the contract are to be regarded as laterally terminate the contract in the event 'stylistic clauses' and, as such, inopera- of the contractor's non-performance of any tive. 10 Those stylistic clauses do not allow of its obligations thereunder, in particular if the parties to terminate the contract uni- it fails to comply with the stipulations laterally; they must apply to the courts made in Clause 4.3 thereof...'. 11 The latter instead. condition led the Court of Justice to take the view that the termination clause satis- fied the requirement laid down by the Corte Suprema di Cassazione that the obligation must be specified in order for 24. So, in the light of the case-law of the Article 1456 of the Italian Civil Code to Corte Suprema di Cassazione, the termina- apply. tion clause in the contract between the Commission and TVR could be regarded as a stylistic clause. In fact, as I have already pointed out, the Commission reserved the right to terminate the contract if one or both of the contractors breached any of its 27. None the less, the defendant contended obligations. that, as the Commission had acknowl- edged, the breach of contract was due to force majeure, with the consequence that it could not incur any blame and that an express termination clause which was sub- 25. Nevertheless, I believe that, pursuant to ject to the condition that one of the parties the case-law of the Court of Justice, the should be held responsible for non-perfor- contract between the Commission and mance could not in any event be relied TVR can be exempted from the require- upon as against it. ment that the obligation whose breach could lead to unilateral termination must be specified.
28. The Court of Justice did not accept that contention and held that it could be 26. In Commission v SNUA, cited above, inferred from the termination clause in the the termination clause in the contract contract that the ability to terminate auto- between the Commission and the defen- matically was not conditional upon the dant, which was also governed by Italian existence of fault on the part of the contractor, but instead depended solely upon the non-performance of certain con- 10 — By way of example, see the judgements of the Corte tractual obligations, regardless of their Suprema di Cassazione of 23 May 1985, No 3119 (Rep. Giur. it., Obbligazioni e contratti, 393) and 2 June 1990, cause or origin. No 5169 (Rep. Giur. it., Obbligazioni e contratti, 447). The views of Italian civil lawyers appear to be in harmony on this point; see, for example, Mosco, L., La risoluzione del contratto per inadempimento, Casa editrice Dort. Eugenio Jovene, Naples, 1950, pp. 196-201, and Sacco, 11 — Emphasis added. Clause 4.3 of the contract dealt with the R. and De Nova, G., Trattato di diritto civile, Unione periodic reports which the contractor undertook to send to Tipografico — Editrice Torinese, Turin, p. 624. the Commission.
I-313
OPINION OF MR RUIZ-JARABO — CASE C-40/98
The Court of Justice added: 'Whilst it is requirement of responsibility for the breach true that the case-law of the Corte Suprema of contract may also be applied to the di Cassazione requires that, in order to requirement which Italian law imposes on bring express termination clauses which are termination clauses, namely that the obli- subject to Article 1456 of the Italian Civil gations to which they apply must be Code into effect, it must be possible to specified. attribute responsibility for non-perfor- mance to the contractor in default, the fact remains that, under Article 1322 of the Code, the parties' right freely to determine the terms of the Contract within the limits set by the law is recognised as forming part of the principle of freedom of contract.
It does not therefore preclude the parties to a contract from deciding to insert therein a termination clause which is not subject to 31. Therefore, it can be deemed that, by the condition that the contractor must be availing themselves of the principle of responsible for non-performance, by way freedom of contract recognised in Arti- of derogation from the usual format of cle 1322 of the Italian Civil Code, and contracts under Italian law.' 12 having regard to the particular nature of the relations between the Commission and the undertaking to which it makes a financial contribution, 13 the parties freely
29. The Court of Justice took the view that agreed in the contract that any breach by it was clearly the parties' intention to make TVR of its contractual obligations would provision for specific methods of terminat- entitle the Commission to terminate the ing the contract given, inter alia, the contract unilaterally, regardless of the particular nature of relations between the applicable provisions of Italian law. The Community and the company in receipt of clarity and precision with which the con- funding and the Commission's ability in tract lays down the procedure for and the practice to monitor implementation of the consequences of unilateral termination by work schedule, which to a large degree the Commission in the event of non-per- depended on the reports which the con- formance by TVR support that view, parti- tractor was required to submit to it under cularly when the principle of contractual Clause 4.3 of the contract. The Court held, therefore, that the Commission was justi- fied in relying on the termination clause in 13 — In that regard, it is interesting to note the view of Professor Draetta, who argues that contracts between the Commu- the contract to terminate the contract nity and private individuals should be deemed interna- tional contracts, in respect of which Italian case-law allows automatically. the parties to agree that provisions, including compulsory provisions, of the national law of one of the parties, or of the lex fori, are not to apply (such as, for example, the provisions of Articles 1341 and 1342 of the Italian Civil Code, dealing with express consent to unfair clauses) (Draetta, U., 'Corte di Giustizia C.E_E_ e contratti internazionali: l'art. 181 del Trattato di Roma,' Diritto del commercio internazionale, Giuffrè, Milan, 1989).
In 30. To my mind, the same criteria used by fact, the contract between the Commission and TVR, and the Court of Justice in relation to the in particular Annexe II thereto, bears all the hallmarks of what is known in international commerce as a self- regulatory contract, in which the parties set out in detail the rules applying to performance and termination (termi- nation by default) of the contract (see Bianchi, M. and 12 — Commission v SNUA, cited in footnote 7 above, paragraph Saluzzo, D., I contratti internazionali, lì Sole 24 Ore,
23. Milan, 1997).
I - 314
COMMISSION V TVR
good faith to which the Commission refers B. The defendant's breach of the contract in its reply is taken into account. 14
33. In its defence, TVR asserts that, of the ECU 230 000 which the Commission transferred to the Istituto Bancario San Paolo, Turin, ECU 65 000 was paid into the defendant's own account and ECU 165 000 transferred directly by the bank to Brunei. 32. It is now appropriate to ascertain However, owing to lack of information whether the breach of which the defendant relating to the beneficiary (the name of its is accused — namely failure to transfer to bank and details of its current account), Brunei the sum of ECU 165 000 — actu- that sum never came into Brunei's posses- ally occurred and whether the Commission sion and TVR's efforts to discover what complied with the procedure laid down in had happened to it were fruitless.
The the arbitration clause. defendant adds that, on 31 October 1993, its relationship with the bank concerned broke down completely and it commenced 14 — In order to complete this analysis, I feel it is appropriate to litigation over the bank's disproportionate point out that, in my view, the Commission's unilateral interest charges. The defendant states that termination of the contract could also be deemed to be valid under Article 1454 of the Italian Civil Code. That it would be appropriate for the Commis- provision allows for one of the parties to the contract to give the other party, who is in default, written notice sion to request information from the Isti- requiring performance of its obligations within a reason- tuto Bancario San Paolo concerning the able period, and to warn that upon expiry of that time- limit the contract will be terminated automatically. For a whereabouts of the abovementioned pay- contract to be terminared unilaterally under Article 1454, the following conditions must be satisfied: performance ment and to demand reimbursement of that must be demanded in writing; the party making the sum which, it adds, 'the Istituto has prob- demand must stipulate a specific and reasonable time-limit to the other party, which in principle must not be less than 15 days; ana the intention to terminate the contract should ably retained by reason of the proceedings the party on notice fail to perform its obligations within between it and TVR.' the stipulated time-limit must be expressly stated. Under Italian law, the court confines itself in such cases to confirming whether the abovementioned conditions have been satisfied, whether the responsibility for non-perfor- mance is attributable to the defendant, and whether, as opposed to the procedure where termination is based on an express clause, the non-performance may be defined as significant for the purposes of Article 1455 of the Italian
Civil Code. As in the case of termination clauses, the judgment will declare, rather than effect, termination of the contract, since termination will already have taken place de jure, provided that the abovementioned circum- stances are all present. 34. Given the terms of the contract, under To my mind, the request contained in the Commission's letter to the defendant of 15 April 1993 satisfies all the which TVR was required to transfer to the formal conditions laid down in Article 1454 of the Italian other contracting party the sums it received
Civil Code. Likewise, it must be deemed in the present case that the requirement that responsibility for non-perfor- from the Commission for that purpose, mance be attributable to the party in default is also satisfied. Finally, with regard to the significance that the there has clearly been a breach. In objective breach attributed to TVR held with regard to the general terms, it is a fact that the ECU 165 000 structure of the contract, there is no doubt whatsoever that the obligation to transfer the sum in question to the co- transferred by the Commission to TVR, contractor, representing Brunei University's remuneration for the work it had carried out under the contract, must be which TVR was required to transfer imme- regarded as an essential obligation, breach of which could diately to Brunei, was not transferred to give rise to unilateral termination of the contract by the
Commission. Brunei. It was TVR's responsibility to effect
I-315
OPINION OF MR RUIZ-JARABO — CASE C-40/98
the transfer and non-performance of that of Annex II thereto, which I shall discuss obligation cannot be excused by how well below, to my mind there is no doubt that or badly a third party (a bank), to which the Commission scrupulously complied TVR entrusted the transfer on its own with that procedure. The written notice initiative, carries out the task which it has was sent to the defendant by recorded been given. delivery on 15 April 1993. In it, the Commission requested TVR to remedy its non-performance of the contract within one month and warned that, should it fail to do so, the contract would be terminated under the termination clause. Since the 35. The person responsible for transferring defendant did not comply with the notice the sum of money, vis-à-vis both Brunei and within the stated time period, the contract the Commission, was TVR. If, for its part, was automatically terminated. Moreover, TVR used the professional services of a despite the fact that the termination clause bank in order to carry out the transfer and did not contain any such obligation, the was then, at the worst, defrauded by the Commission confirmed that it had termi- bank, it is not thereby relieved of its nated the contract in a subsequent letter obligation both to the Commission and to dated 31 January 1994. Brunei. TVR can claim compensation for damage from the bank, in such form as it considers appropriate, but it is not entitled to shelter behind non-performance by a third party, a stranger to the main contract, to justify the objective breach of its own obligations to the parties to the contract.
36. I therefore conclude that there was a breach of contract and that responsibility for it can be attributed to the defendant. 38. For the reasons given, it is my view that the contract between the Commission and TVR was automatically terminated under the termination clause contained therein. Pursuant to the case-law of the Court of Justice to which I have already referred, the defendant's plea of inadmissibility should C. Delivery of notice under the termination be rejected, since, as the contract has clause already been terminated, the Commission is entitled to claim reimbursement of the sums it paid and compensation for damage without first being required to bring a 37. As regards the procedure for termina- formal action for termination of the con- tion of the contract set out in Article 8.2(d) tract.
I - 316
COMMISSION V TVR
IV — Substance of the claim B. Reimbursement of part of the advance
42. The Commission also seeks reimburse- ment of ECU 46 307, representing the difference between TVR's actual costs and A. Reimbursement of the sum which was the advance of ECU 65 000 it received from not transferred to Brunei the Commission.
39. The Commission requests the Court to 43. In calculating this amount, the Com- order TVR to reimburse the advance of mission accepted the following items from ECU 165 000 which it received in its the statement of expenditure submitted by capacity as co-ordinator of the project TVR: and which it should have transferred to Brunei.
— ITL 46 675 000 in respect of labour costs;
40. The considerations which I have set out in points 34 to 36 above will permit me to be brief on this point. TVR must be held liable for failing to transfer the advance of — ITL 3 270 538 (for the period 1 Sep- ECU 165 000 to Brunei and the arguments tember 1991 to 3 August 1992) and it has made in its defence cannot be ITL 5 092 963 (for the second contract accepted. year) in respect of travel expenses;
— ITL 2 396 031 in respect of consum- 4 1 . I therefore believe that this part of the ables; action is justified and that the Court may allow the Commission's claim, since the latter, in order to comply with its obligation to Brunei, had to make a second payment of ECU 165 000, which on this occasion it — ITL 623 391 in respect of other costs; paid directly to the university. 15 and
15 — Under Article 2(1) of Council Regulation (EC) No 1103/97 of 17 June 1997 on certain provisions relating to the introduction of the euro (OJ 1997 L 162, p. 1), as regards the amount of the principal sum and the — ITL 11 667 000 in respect of over- interest, all referencesto the ecu are to be replaced by a reference to the euro at a rate of one euro to one ecu. heads.
I-317
OPINION OF MR RUIZ-JARABO — CASE C-40/98
These items come to ITL 69 724 923 in all, 46. The defendant asserts in the rejoinder of which the Commission is liable to pay that the Commission has adduced no 50%, that is to say, ITL 34 862 461, which evidence whatsoever that the working time is equal to ECU 18 693. Since the amount was 'exaggerated'. To my mind, however, of the advance previously made was the main question is whether TVR justified ECU 65 000, the difference comes to ECU sufficiently its calculation of the labour 46 307. costs.
47. It is clear from the documents before the Court that, on 30 November 1993, 44. The response to this claim contained in TVR submitted a cost statement in respect the defence is very unclear, since it merely of the second contract year. 17 The Com- states that the audit report from Ernst & mission rejected that statement in a letter Young shows that the labour costs calcu- dated 31 January 1994, on the ground, lated by TVR are wholly consistent with inter alia, that at a meeting held in Brussels the work undertaken and with the amount on 15 March 1993 it had agreed with the charged. The defence goes on to say that, contractors that, with effect from that date, according to that report, the charge made certain work provided for in the contract for labour was lower than it should have would no longer be funded and that the been because it was based on the rate for contractors should confine themselves to 1991, rather than 1992, the year in which completing the feasibility assessment. 18 the work was actually carried out. There- The Commission therefore requested the fore, the defendant argues, the second part defendant to submit details of the work of the claim is clearly unfounded. undertaken during the periods 1 September 1992 to 15 March 1993 and then from the latter date up to termination of the contract on 26 May 1993, so that it could ascertain whether that agreement had been complied with.
45. To my mind, Ernst & Young's report is of little use when it comes to deciding on this part of the Commission's claim. In fact, the audit only covers the first contract year 48. The defendant replied to that letter on (1 September 1991 to 31 August 1992), 24 February 1994, submitting a consoli- whereas the disagreement between the dated cost statement covering the entire parties centres on expenditure incurred in duration of the contract but failing to the second year (1 September 1992 to 26 May 1993). 16 17— Neither the Commission nor, surprisingly, the defendant has seen fit to lodge this statement at the Court. 18 — This time it is the Commission which has acted surpris- 16 — At the hearing, the Commission's Agent explained that the ingly in failing to lodge the minutes of this meeting at the audit was confined to the first contract year because, at the Court. However, a memorandum from Brunei, lodged by time it was requested, the only cost statements which had the defendant, confirms, at length, the Commission's been received from TVR related to this period. assertion.
I-318
COMMISSION V TVR
provide the information requested by the ing the second contract year. Therefore, it is Commission. The latter therefore repeated my view that the Commission was entitled its request in a letter dated 10 March 1994. to reject the figure submitted by TVR and that this claim should also be allowed.
49. On 15 March 1994, the defendant sent a further document to the Commission, in C. Interest which it provided details of the travel costs for the second year but no information relating to labour costs. For that reason, the Commission, in a letter dated 6 April 1994, informed TVR that, in respect of the 51. Under Article 8.4 of Annexe II to the second year, it had decided to accept only contract, in the event of termination, the the travel costs and not the labour costs, in Commission should receive not only reim- respect of which the defendant had failed to bursement of advance payments it has supply the information requested. The made but also interest on those amounts, defendant expressed its disagreement with to be added from the date on which that decision in a letter dated 26 July 1994, payments were received by the other party but once again failed to provide further to the contract. The rate of interest is the details of the labour costs for the second rate applied by the European Monetary contract year. Cooperation Fund for its operations in ECU, increased by two percentage points, such rate being published on the first working day of each month.
50. In order to adjudicate upon this claim by the Commission, the Court must refer to 52. Therefore, the Commission seeks inter- the documents submitted by the parties. est on the amount of ECU 211 307 (being Those documents contain no indication at the sum of ECU 165 000 paid to TVR for all that the defendant, in spite of the transfer to Brunei and ECU 46 307 repre- repeated requests it received from the senting the difference between the advance Commission, 19 provided sufficient infor- and the costs proved by TVR) at the rate of mation regarding the work performed dur- 12% from 21 December 1991, 20 which comes to ECU 69.47 per day. The defen-
19 — Under the heading 'Justification of Costs', Anicie 36.4 of Annexe II to the contract provides that each contractor is 20 — The Commission calculates that TVR received the advance to provide any details reasonably required by the Commis- three months after the payment order (which is dated sion for its management of the contract. 20 September 1991).
I - 319
O P I N I O N OF MR RUIZ-JARABO — CASE C-40/98
dant submits no claim in that regard, but submit, in the appropriate conditions, merely states that the primary obligation to the periodic reports. 22 make reimbursement is not enforceable.
— The Commission was obliged to instruct a firm of auditors to undertake 53. Since, in my view, TVR must repay the a financial review of TVR's work. abovementioned sum to the Commission, by way of a primary obligation, it follows that the secondary obligation to pay the corresponding interest — which was expressly agreed — also applies. 21 — The Commission has been unable to enjoy the possible advantages provided for in Article 19 of Annexe II to the contract, concerning the exploitation of information or patents acquired as a result of the research it funded.
D. Compensation for damage
— By entering into a contract with a party 54. Last, the Commission requests the which did not honour its commitments, Court to order TVR to pay compensation the Commission has suffered a loss of for the damage suffered by reason of its credibility in the eyes of all those with a non-performance, which, in the Commis- potential interest in entering into a sion's view, is the following: contract with it.
— A number of its officials spent a large 55. The Commission contends that the number of hours monitoring the defen- overall sum to compensate for this damage dant's activities and requesting it to amounts to ECU 20 000, although the Court may calculate it differently using the option provided in Article 1226 of the 21 — In answer to a question I asked at the hearing, the Italian Civil Code, which provides that defendant's representative stated that he agreed with the Commission's interpretation that the second subparagraph of Article 8.4 of Annexe II to the contract provides for a fixed rate of interest in the event of termination of the contract. Since the parties are in agreement on this point, 22 — The Commission calculates that 56 working hours have there is no need to analyse the question in greater detail, been lost in this way. Using the rate of ECU 52 per hour, although I believe that the wording of this clause might the total amount works out at ECU 2 912 (although the perhaps allow a different interpretation. application cites the incorrect figure of ECU 2 925).
I - 320
COMMISSION V TVR
where the exact amount of the loss cannot (b) There can be no 'loss of credibility' vis- be proved it is to be determined by the à-vis third parties as a result of one court according to equitable principles. party to a contract, such as the one in these proceedings, failing to fulfil all its obligations and causing the contract to be terminated.
56. In my view, of all those heads of claim, which are disputed by the defendant, only the second, and possibly the third, should be upheld. The other two should be rejected, since: 57. With regard to the loss of possible advantages resulting from the exploitation of information or patents acquired as a result of the research financed, there is no reason in principle why such a loss should not be assessed. However, any such advan- tages in the present case are purely hypo- thetical and the applicant has provided no information about them. The Commission refers to them in general, abstract terms (a) The hours worked by the Commis- and fails to provide any firm evidence on sion's officials during the period prior which to base even an approximate calcu- to termination of the contract cannot lation of the loss of profit. Consequently, be construed as damage, since mon- even by having resort to the equitable itoring the institution's contracts is part principles provided for in Article 1226 of of their normal workload. Viewed in the Italian Civil Code, the Court would be this way, the vicissitudes of the Com- unable to quantify the damage because it mission's and TVR's contractual rela- would be acting blindly when attempting to tionship do not appear so unusual as to do so. require a disproportionate amount of attention, to the detriment of other administrative tasks, or, as a result, to merit payment of compensation. With regard to the period following termina- tion of the contract, the Court has already held that costs incurred by the parties for the purposes of legal pro- ceedings cannot, in any event, be regarded as constituting damage dis- tinct from the burden of costs. 23 58. By contrast, sufficient evidence has been provided of the expenditure (ECU 6 610) arising from the consultancy 23 — Commission v Comune di Mortorio al Vomano, cited in contract between the Commission and footnote 8 above, paragraph 54. Ernst & Young to enable the total cost of
I-321
OPINION OF MR RUIZ-JARABO — CASE C-40/98
that contractual relationship to be deter- V — Costs mined. The defendant should be held liable for that item of expenditure in view of its evasive attitude following termination of 59. Since virtually the whole application the contract and of its failure to justify must be granted, and since the applicant much of the expenditure claimed. Further- has applied for costs, the defendant must be more, TVR does not dispute that head of ordered to pay the costs, in accordance claim, either in the defence or in the with Article 69(2) of the Rules of Proce- rejoinder. dure.
VI — Conclusion
60. In the light of the foregoing considerations, I propose that the Court of Justice should essentially grant the application and order the defendant to pay to the Commission:
— the sum of EUR 211 307, together with interest at the rate of EUR 69.47 per day from 21 December 1991 until the debt is paid in full;
— the sum of EUR 6 610 by way of compensation for damage; and
— the costs of the proceedings.
I - 322