← Späť na vyhľadávanie
Súdny dvor Európskej únie·23.3.2000

C-337/98

ECLI:EU:C:2000:156

Súd
Súdny dvor Európskej únie
IČS
61998CC0337

COMMISSION V FRANCE

OPINION OF ADVOCATE GENERAL JACOBS delivered on 23 March 2000 *

1. In this case, die Commission alleges a undertakings or on the basis of special or failure by the French authorities to comply exclusive rights granted by a competent with the Community rules governing the authority of a Member State (Article 2(1) use of negotiated procedures for the con- and (2)(c)). clusion of procurement contracts by entities operating in the water, energy, transport and telecommunications sectors, in a spe- cific instance where a negotiated procedure was followed without a prior call for competition. The main issue is whether those rules applied to the procedure in 3. It provides for three types of procedure question; the French Government disputes whereby such entities may award contracts the Commission's contention that they in the fields covered: open, restricted and were in force at the material stage of that negotiated procedures. These are defined in procedure. If the rules were applicable, it Article 1(7) as follows: must be determined whether the conditions were met for a derogation from the obliga- tion to issue a call for competition.

'(a) in the case of open procedures, all interested suppliers, contractors or ser- vice providers may submit tenders;

The relevant Community legislation

(b) in the case of ... restricted procedures, only candidates invited by the contract- 2. Council Directive 93/38 1 applies to ing entity may submit tenders; contracting entities operating, biter alia, public transport networks either in their capacity as public authorities or public

* Original language: English. 1 — Council Directive 93/38/EEC of 14 June 1993 coordinating (c) in the case of negotiated procedures, the procurement procedures of entities operating in the the contracting entity consults suppli- water, energy, transport and telecommunications sectors, OJ 1993 L 199, p. 84. ers, contractors or service providers of

I - 8379

OPINION OF MR JACOBS — CASE C-337/98

its choice and negotiates the terms of may be executed only by a particular the contract with one or more of them'. supplier, contractor or service provider;

4. Under Article 4(2): 'Contracting entities shall ensure that there is no discrimination between different suppliers, contractors or ...' service providers.'

5. Article 20(1) provides: 'Contracting entities may choose any of the procedures described in Article 1(7), provided that, 7. In accordance with Article 45, Member subject to paragraph 2, a call for competi- States were to adopt the measures necessary tion has been made in accordance with to comply with the provisions of Directive Article 21' (which indicates the forms to be 93/38 and to apply them by 1 July 1994. used in notices of calls for competition and prescribes that they are to be published in the Official Journal of the European Com- munities).

8. Article 45 also provided that Directive 6. However, under Article 20(2): 'Con- 90/531 2— which contained3 provisions tracting entities may use a procedure with- identical for present purposes to those of out prior call for competition in the fol- Directive 93/38 cited above — should lowing cases: cease to have effect as from the date on which the latter was applied by the Mem- ber States. Member States had been required to comply with Directive 90/531 by 1 January 1993. 4Prior to that directive, procurement procedures in the 'utilities' sectors had not been subject to Community regulation.

2 — Council Directive 90/531/EEC of 17 September 1990 on the procurement procedures of entities operating in the water, (c) when, for technical or artistic reasons energy, transport and telecommunications sectors, OJ 1990 L 297, p. 1. or for reasons connected with protec- 3 _ In Articles 1(6), 4(2), 15(1) and (2)(c) and 16. tion of exclusive rights, the contract 4 —Article 37(1) and (2).

I - 8380

COMMISSION V FRANCE

The relevant French legislation (2) when requirements can be met only by [work or supplies] which, by reason of technical necessity, substantial preli­ minary investment, special plant or equipment or know-how, can be con­ 9. The rules governing public procurement tracted out only to a specific contractor in France are contained principally in the or supplier; Code des Marchés Publics (Public Procure­ ment Code, hereinafter also 'the Code').

10. Article 104(1) of the Code requires negotiated contracts to be preceded by a ...' call for competition. Article 104(11) con­ cerns exceptions for which no call for competition is needed. The text applicable at the material times in the present case provides, in so far as is relevant:

11. During the relevant period, France had 'Negotiated contracts may be entered into not transposed Directive 93/38. 5However, without a prior call for competition when Directive 90/531 appears to have been only one specific contractor or supplier is transposed by Law No 92-1282 of capable of carrying them out. 11 December 1992 6and Decree No 93- 990 of 3 August 1993. 7Article 2 of the latter contains an exhaustive list of cases where a procedure may be used without a prior call for competition, and item 4 on that list reproduces the terms of Arti­ cle 15(2)(c) of Directive 90/531, which This applies in the following cases: were identical, as regards contractors and suppliers, to those of Article 20(2)(c) of Directive 93/38.

5 — Sec the judgment in Case C-311/96 Commission v Brance [1997] ECR I-2939. ( 1 ) when requirements can be met only by 6 —journal Officici de la République française (JORľ) 1992, [work or supplies] which necessitate p. 16952. That Law essentially lays down the entities and activities covered, with the detailed rules governing pub­ recourse to a patent, a licence or licity and procedures to he adopted by subsequent decree exclusive rights held by a single con­ (see Article 1 ). Article 9 states that its provisions were to he applicable as from I January 199V tractor or supplier; 7 — Published on 10 August 1993; JORF 1993, p. 11266.

I-8381

OPINION OF MR JACOBS — CASE C-337/98

Factual background say a tram or light railway network. On 26 October 1989, its committee voted, inter alia, to confirm previous decisions to provide a reserved-track network, to opt for the 'VAL' automatic light railway system, to seek government funding and 12. Briefly stated, this case concerns a to authorise consultations with a view to lengthy process to award a contract for awarding a contract for drawing up pre- the construction of an urban light railway liminary specifications. The report on line. The relevance of the different stages in which that vote was taken stated that the that process lies essentially in determining VAL system was produced by the two whether it comprised a single, uninter- companies Matra (Matra Transport, now rupted award procedure or whether a apparently known as Matra Transport second procedure was commenced at a International) and Alsthom (GEC Alsthom relatively late stage of the overall process. Transport). The contract for drawing up That issue is relevant in turn when deter- preliminary specifications was, it was sta- mining the applicability of the Community ted at the hearing, later awarded to and rules to one of the initial steps in the performed by Matra. procedure leading to the final award.

15. From the minutes of its committee 13. Public transport in the conurbation of meeting of 19 July 1990 it appears that Rennes in France is the responsibility of a Sitcar, having previously issued an invita- joint grouping of all the constituent muni- tion to tender for 'civil engineering work cipalities, the Syndicat intercommunal des and equipment not linked to the system' transports collectifs de l'agglomération and selected the successful tenderer, agreed rennaise ('Sitcar'), which apparently comes on that date that the 'contrat d'ensemblier' under the authority of the District Council (turnkey contract, that is to say a contract for the conurbation ('the District Council'). for the complete work to the point of Decisions are taken by the District Council readiness for operation) for the 'system and or by Shear's committee, composed of equipment linked to the system' would be delegates from the various municipalities. awarded to Matra once a guaranteed guide The transport service is actually managed price had been determined. by the semi-public company 'Semtcar'.

14. From 1984 onwards, Sitcar investi- 16. In a report read to the committee at its gated ways of improving the service by meeting on 12 July 1991, concerning the creating a 'reserved-track' system, that is to contract for civil engineering and equip-

I - 8382

COMMISSION V FRANCE

ment not linked to the system, the chair- complete system, including not only track, man of Sitcar stated that negotiations with control post and train sets, but also secur- Matra were not yet complete but would ity, workshop, power-supply and track lead to the conclusion of a turnkey con- equipment, together with spare parts and tract. staff training.

17. In response to a request from the Court, the French Government has pro- 20. However, that stage had not been duced a letter from Matra to Sitcar, dated reached without political opposition. A 9 July 1991 and apparently received on 'Comité pour une alternative au VAL' had 12 July 1991 (though perhaps too late to be been set up in 1991 and most of the mentioned in the report delivered on that relevant resolutions had been opposed by date). That letter appears to accompany a a minority. In addition, the ecological file containing Matra's proposal for the movement 'Rennes Verte' had applied to 'system' portion of the work on the first the Tribunal Administratif (Administrative VAL line in Rennes. It confirms a guaran- Court), Rennes, to have the Prefect's teed price of FRF 987 000 000 or, with declaration of public interest set aside. On certain possible modifications to the pro- 16 February 1994, that court annulled the gramme, of FRF 953 200 000, both declaration on the ground that the preli- excluding tax and at January 1991 prices. minary inquiry was incomplete as regards analysis of certain required criteria.

18. On 15 February 1993, the Prefect of Ille-et-Vilaine, the département in which Rennes is situated, issued a declaration of 21. As a result, by letter of 30 March 1994, public interest in respect of the first line of the Minister for Infrastructure, Transport the VAL light railway network. That and Tourism informed the Chairman of the declaration was a precondition for pro- District Council that government funding, ceeding with the project, in particular for although still in principle available, could making expropriations. not be provided until the administrative procedure had been recommenced and completed as required by that judgment.

19. On 30 March 1993, the District Coun- cil approved the turnkey contract negoti- ated by Semtcar with Matra for FRF 966 420 000, excluding tax, at January 22. On 22 September 1995, the District 1993 prices, and authorised its signature. Council passed two linked resolutions. The contract was for the supply of a First, it voted to withdraw its previous

I - 8383

OPINION OF MR JACOBS — CASE C-337/98

resolution of 30 March 1993 approving the 1993 and it could not be deemed inexistent contract with Matra and authorising its on the ground that it was neither signed nor signature by Semtcar, 'that resolution not notified; it was a completed document, having been implemented even inchoately having been the subject of negotiation and and having become redundant'. The report having been approved by the District on the basis of which the vote was taken Council. stated that government authorisation had not been granted within the necessary time, thus affecting the terms of performance of the contract, in particular as regards dead- lines. 25. On 4 October 1996, the Prefect issued a new declaration of public interest and government funding consequently became available. As a result, the District Council voted on 22 November 1996 to 'approve the terms of the draft negotiated contract to 23. Second, the District Council requested be concluded with the company Matra Semtcar to 'resume detailed negotiation/ Transport International for the work on finalisation ["reprendre la mise au point"] the system and equipment linked to the of the contract with Matra' within the system' and authorised Semtcar to sign the framework of the provisional budget for contract. the operation and to submit it anew to the District Council for approval.

24. In a letter dated 29 July 1996 to two Procedure councillors hostile to the project, who had challenged an alleged refusal to communi- cate the 1993 turnkey contract for the 'system' portion of the VAL line, the Chairman of the District Council stated, 26. Following a complaint submitted to it inter alia, that the contract could not be in late 1996 — apparently by councillors communicated because it had never hostile to the VAL project — the Commis- existed, having been neither signed by the sion requested clarification from the French competent authority nor forwarded to the Republic, which replied, essentially, that Prefect, and that the withdrawal of the the contract had been awarded in 1989, resolution approving it called into question before the entry into force of Directives the very existence of the project. The 90/531 or 93/38, and that Matra was the decision embodied in that letter was, how- only company able to meet the require- ever, subsequently set aside by a judgment ments and had already made substantial of the Tribunal Administratif of 16 July investments. The Commission sent the 1997, which held, inter alia, that the French authorities a letter of formal notice existence of the contract was attested by in June 1997. Considering the reply to that the terms of the resolution of 30 March letter unsatisfactory, it then sent a reasoned

I - 8384

COMMISSION V FRANCE

opinion under Article 169 of the EC Treaty indeed concluded) at a much earlier date, (now Article 226 EC) concluding that the and that it is the date of commencement provisions of Directive 93/38 had been which must be decisive when determining infringed and requiring the French Govern- whether the Community rules were applic- ment to comply with the opinion within able. In response to the latter point, the two months. In its reply dated 12 June Commission argues that, although the date 1998, the French Government maintained of commencement may be taken into its position. consideration, an unreasonable length of time must not elapse, as it did here, before the actual award of the contract. The French Government submits in the alter- native that, if the Commission's main contention is accepted, the conditions for application of the derogation were in any 27. The Commission brought the present event met. action on 14 September 1998. It seeks a declaration that, as a result of the resolu- tion of 22 November 1996 awarding Matra the turnkey contract for the Rennes District light railway project, the French Republic failed to fulfil its obligations under Directive 93/38, and in particular Articles 4(2) and 20(2)(c) thereof. The 29. In those circumstances, although the specific infringement to which the Com- main issue to be decided is whether a new mission refers is a failure to issue a prior procedure was commenced on 22 Septem- call for competition in order to avoid ber 1995, it is helpful to clarify the context discrimination between undertakings. first by considering the more general issue of the applicability of newly-introduced Community rules to procedures already under way. I shall then examine the main issue of the date of commencement of the procedure. Finally, I shall consider whether the conditions for application of the dero- gation may have been met. Analysis

28. The Commission's case is, essentially, that the procedure in issue was initiated on 22 September 1995, that at that date the conditions for the application of the dero- Directive 90/531 and Directive 93/38 gation contained in Article 20(2)(c) of Directive 93/38 were not met and that by failing to issue a call for competition the French authorities thus infringed that direc- tive. The French Government maintains 30. In so far as they are relevant to the that the procedure was commenced (and present case, the rules contained in Direc-

I - 8385

OPINION OF MR JACOBS — CASE C-337/98

tive 90/531 and in Directive 93/38 are sion — or indeed any transitional provi- identical; the changes introduced by the sions — nor is there any reason to con- latter merely extend them to cover con- clude that their purpose requires any form tracts for services, as well as for works and of retroactive effect. supplies. The Commission, however, seeks a declaration of failure to fulfil obligations in respect of Directive 93/38 alone.

33. The Court has also recognised the principle that amending legislation applies, unless otherwise provided, to the future consequences of situations which arose 31. Consequently, any finding that the under the previous legislation. 9 provisions of Directive 90/531 were brea- ched during the period when they were applicable but Directive 93/38 was not applicable would be ultra petita. None the less, I consider it useful to bear both directives in mind when analysing the 34. Those principles, however, do not situation in this case. directly resolve the question of the immedi- ate application of new rules to a procedure already under way at the date by which they were to be transposed. The measures necessary to comply with the provisions of Directive 90/531 should have been applied from 1 January 1993 and those of Direc- tive 93/38 from 1 July 1994 at the latest.

Applicability of the directives to a proce- dure already commenced

35. Although in a different legislative con- text, a similar question of application of new Community rules to procedures 32. The general principle is that, in the already under way has been examined by absence of a clear provision and unless the the Court in several cases involving Direc- purpose to be achieved so demands, legis- tive 85/337 10 on environmental impact lation is not to be interpreted as having a retroactive effect. 8 In this case, neither of the directives contains any such provi- 9 — See, for example, Case 125/77 Koninklijke Schoîten-Honig v Hoofdproduktschap voor Akkerbouwprodukten [1978] ECR 1991, paragraph 37 of the judgment, and the recent judgment of 29 June 1999 in Case C-60/98 Butterfly Music 8 — See, for example, Case 88/76 Exportation des Sucres v v CEMED, paragraph 24, together with the case-law cited Commission [1977] ECR 709, paragraph 17 of the judg- there. ment, Case C-368/89 Crispoltoni [1991] ECR 1-3695, 10 — Council Directive 85/337/EEC of 27 June 1985 on the paragraphs 17 and 20, and Case C-244/95 Moskof v EOK assessment of the effects of certain public and private [1997] ECR 1-6441, paragraph 77. projects on the environment, OJ 1985 L 175, p. 40.

I - 8386

COMMISSION V FRANCE

assessments, which also contains no transi- applicable to subsequent stages of proce- tional provisions. The Court has held that dures already under way at the date of the obligations imposed by that directive must deadline for their transposition into apply to a consent procedure commenced national law. The Court's approach in the after the deadline for their transposition environmental impact assessment cases into national law but before that transposi- cited above may have been influenced by tion was actually effected. 11 In order to the consideration that it could not be determine whether the directive rules apply, determined with certainty at what stage in for reasons of legal certainty the sole a procedure the assessment required by the criterion must be whether the application directive should take place, whereas the for consent was formally lodged before or commencement of the procedure by the after the deadline for transposition. 12 The lodging of a formal application was a directive was designed to cover projects clearly ascertainable event. likely to require a long time to complete, so that complex procedures already initiated under national law and situations already established should not be affected by it. 13

38. Such a consideration need not apply where new rules come into effect at an identifiable stage in a sequence of steps making up a complete procedure. What can be excluded, however — in line with the 36. If that reasoning is transposed to the requirement of legal certainty to which the present case, the result is that the rules Court has referred — is any 'application' contained in Directives 90/531 or 93/38 of such rules to stages of a procedure which cannot apply to procurement procedures have already been completed. Indeed, commenced before the dates from which unless such stages were already in compli- they should have been applied. ance with the new rules, the only way in which they could be brought into compli- ance would be by repeating them, requiring a recommencement of the whole procedure in cases where the initial stages are in issue — and that intention cannot be attributed to the Community legislature in the absence of a clear indication. 37. However, I would not necessarily exclude, as a general rule, the possibility that certain provisions of a directive may be

11 — Case C-396/92 Bund Naturschutz iu Bayern and Others [1994] ECR I-3717, paragraphs 18 to 20 of the judgment. 12 — Case C-431/92 Commission v Germany (1995] ECR 39. In either event, whether the rules in the I - 2189, paragraph 32 of the judgment. 13 — Case C-81/96 Burgemeester en Wethouders ran Haarlem· directives can apply to subsequent stages of merhede en Spaarmvonde and Others v Gedeputeerde procedures already under way or not, I Staten van Noord-Holland [1998] ECR I-3923, para- graphs 23 aud 24 of the judgment. conclude that they cannot have any effect

I - 8387

OPINION OF MR JACOBS — CASE C-337/98

on stages completed before the dates on original procedure was completed well which they were to be applied. before 1 July 1994, when the period for transposition of Directive 93/38 expired, and even before 1 January 1993, by which date the provisions implementing Directive 90/531 were to be brought into force.

40. In the specific context of a Community procurement directive not transposed within the period prescribed, that conclu- sion is consistent with the Court's ruling in 42. The issuing of a call for competition Tögel, 14 that 'Community law does not must be prior to the commencement of require an awarding authority in a Member negotiations. Here, it is clear that negotia- State to intervene ... in existing legal situa- tions had already commenced by 19 July tions ... where those situations came into 1990 at the latest — prior to even the being before expiry of the period for adoption of Directive 90/531 — and had transposition'. Although that ruling con- been substantially completed by 9 July cerned a situation in which the contract 1991. Agreement was reached by itself had been concluded before, but for a 30 March 1993. Indeed, at the hearing, period extending beyond, that date, the the Commission appeared to accept that if principle is in my view of general applica- the contract had been carried out as tion: it applies to whatever and however approved on the latter date the Community many stages of a procurement procedure procurement rules would not have been have been completed before expiry of the infringed. period for transposition.

43. However, the Commission's case is based on the premiss that the original procedure outlined above came to an end Applicability of the directives in the present on 22 September 1995 and that a new case procedure was then commenced. France, on the other hand, contends that there was no such conclusion and recommencement but a single continuing procedure delayed at one stage by an administrative hitch. 41. It is clear from the evidence before the Court that the stage at which a call for competition might have been issued in the

14 — Case C-76/97 Tögel v Niederösterreichische Gebietskran- kenkasse [1998] ECR I-53J7, paragraph 54 of the 44. The question to be answered is thus: judgment. what were the effects of the withdrawal of

I-8388

COMMISSION V FRANCE

the resolution approving the 1993 contract 47. As for the significance of the resolution and of the decision to resume detailed requesting Semtcar to 'reprendre la mise au negotiations with Matra? point' of the contract, the Commission sees it as clear evidence of the commencement of a new procedure, the French Govern- ment as a resumption and continuation of the original procedure. The contract approved on 22 November 1996 is invoked by both parties in support of their posi- tions: the Commission claims it diverges in substantial respects from the 1993 con- 45. The contract approved on 30 March tract, whereas the French Government 1993 was, it appears, never signed. The asserts that it was substantially the same, Court has been presented with various the only differences being the choice of a arguments as to whether a binding award marginally different model as a result of was none the less made at that date or at an technical developments in the intervening earlier stage when agreement was reached period and an updating of the price. on terms. The Commission considers that the award was made on 30 March 1993, there having been no final, unconditional agreement prior to that date. The French Government argues that Matra had acquired a right to the contract by its firm commitment as to price on 9 July 1991. 48. The Commission's action is brought in respect of the procedure leading to the award of the contract approved for signa- ture on 22 November 1996. What is at issue is whether that award was the out- come of the original procedure or whether the latter had come to a close on or before 22 September 1995. 46. We have also heard conflicting views on whether, assuming there was such an award, the contract was rendered void by the withdrawal of the resolution approving it. The Commission argues that the with- drawal meant, in French administrative 49. Directive 93/38 lays down certain law, that the resolution was deemed never requirements to be observed before, during to have existed. The French Government and following the 'award' stage of a asserts that the position was simply that, procedure but does not specify how it is until a new declaration of public interest to be determined when that award has was issued and the funding conditional taken place. This is understandable. The thereupon released, it was impossible to Community procurement directives do not sign the contract with Matra; a binding effect a complete harmonisation of proce- decision to award the contract to that dures but lay down requirements to be company had none the less been taken observed where specified criteria are met, and remained in existence unless and until in particular as regards the value of the a competent court should decide otherwise. contract. All other applicable rules, includ-

I - 8389

OPINION OF MR JACOBS — CASE C-337/98

ing those which determine the stage at have brought the original procedure to an which a contract is awarded or concluded, end. However, on the Commission's own takes effect or becomes binding, will be argument, the withdrawal of that resolu- found in national law. Since the Court is tion means that it is deemed never to have not competent to rule on matters of French existed. Thus, it seems inevitable, the law, a number of hypotheses will have to be original procedure must be deemed not to considered. have been terminated. In those circum- stances, the negotiations in 1995 and 1996 could qualify as a continuation of that procedure.

50. When considering those hypotheses, however, it must be borne in mind that in proceedings against a Member State for a declaration of failure to fulfil an obligation, it is incumbent on the Commission to prove 53. If a procedure is concluded by a that the obligation has not been fulfilled separate award and that award is made and to place before the Court the informa- when, say, firm agreement is reached tion necessary to enable it to determine between the contracting entity and the whether that is so. 15 future contractor, so that approval by the elected body, whilst essential for other reasons, does not affect the existence of that award, 16 then it would seem to follow that withdrawal of that approval can like- wise not affect the existence of the award, 51. Three possibilities may be envisaged although presumably there must be some when considering when the original proce- new approval before the contract can take dure was brought to an end: it may have effect. In those circumstances the award, if been concluded by the approval of the made before 30 March 1993, would have contract by the District Council on remained in existence after 22 September 30 March 1993, by an award at some 1995, since the only measure withdrawn on earlier stage, perhaps when firm agreement that date was the resolution approving the had been reached, or by some later event. contract and authorising its signature, and could have been subsequently approved anew by the resolution of 22 November 1996.

52. If approval by an elected body is necessary and a procedure is concluded by the decision approving the contract and authorising its signature, then the resolu- tion of 30 March 1993 would appear to 54. If the original procedure was not con- cluded either on or before 30 March 1993,

15 — See, most recently, the judgment of 25 November 1999 in Case C-96/98 Commission v France, ECR I-8531, para- 16 — Cf. the judgment of the Tribunal Administratif of 16 July graph 36. 1997 referred to in paragraph 24 above.

I - 8390

COMMISSION V FRANCE

then it must have been concluded by some account of an agreed updating of the later event. The withdrawal of the resolu- administrative specifications, confirmed tion of 30 March 1993 could not, in that that its tender negotiated in early 1993 hypothesis, have been that event. If the would be maintained until 30 September procedure were to have been terminated by 1996. Those two documents are strong the withdrawal of a decision, it would have evidence, not refuted by the Commission, had to be one actually constituting the that negotiations were in fact resumed procedure — such as the decision to carry shortly after 22 September 1995 on the out the project, to seek a supplier for a light basis of everything that had gone before. In railway system or to negotiate with Matra. that context, the contracting entity could No such decision was withdrawn. In that hardly be expected to remain irrevocably case, the contract approved on 22 Novem- burdened with an outdated model as a ber 1996 would appear to be the outcome result of forced delays, whatever their of the original procedure, to the initial cause, and both the change of model and stages of which the Community rules could the updating of the price seem wholly not apply. legitimate adjustments. The Commission having provided no evidence of any greater 'substantial difference' between the two, I consider that the contract approved on 22 November 1996 may legitimately be regarded as the outcome of a continuation of the earlier negotiations and/or a permis- 55. However, the conclusions I have set out sible refinement of the agreement reached in those three hypotheses are all dependent at the earlier stage. on a further element: it must be established whether the negotiations conducted in 1995 and 1996 were in fact a continuation of those which took place prior to 1993 and/or concerned merely a permissible refinement of the agreement reached at the earlier stage or whether, on the con- trary, they represented a new departure.

57. I thus reach the view that it has not been established that the original procedure was concluded at an earlier stage in any of 56. In that regard, the language used in the the three possible hypotheses, so that the second resolution of 22 September contract approved on 22 November 1996 1995 — "reprendre la mise au point" — may be regarded as the conclusion of that is highly indicative of both a resumption procedure, at the commencement of which and a refinement of negotiations. More- Community procurement rules did not over, the French Government has produced apply to contracts awarded by entities a letter from Matra to Semtcar dated operating public transport networks. Con- 30 November 1995, stating that Matra sequently, the fact that no prior call for had examined the impact of readjusting competition was issued cannot constitute the timetable for the project and, taking an infringement of those rules.

I - 8391

OPINION OF MR JACOBS — CASE C-337/98

The derogation in Article 20(2)(c) of Direc- because more than one undertaking could tive 93/38 have provided a VAL system or equivalent. It produces letters from Alsthom and another undertaking — ANF Industrie, of the Bombardier Eurorail group — to the opponents of the VAL system, dating from 58. I shall nevertheless consider in the 1995, 1996 and 1997, which it claims alternative the hypothesis that a new pro- indicate that those undertakings would cedure was commenced after the expiry of have been able at that time to submit bids the period allowed for transposition of in conformity with the specifications. The Directive 93/38. In that event, the question derogation could therefore not apply at the would arise whether, as the French Gov- time of the resolution of 22 November ernment argues, the criteria in Arti- 1996. At the hearing, the Commission cle 20(2)(c) were met. argued that it was not required to prove that other undertakings could have provi- ded equivalent systems but merely that a call for competition was required in order to establish whether that was so.

59. It may be noted here that, although critical of Article 104(II) of the French Public Procurement Code, the Commission does not seek any declaration of failure to fulfil obligations with regard to the inclu- sion in that provision of a derogation on the basis of substantial prior investment. Nor, in its defence, does France seek to rely on that article; it argues, rather, that the Community derogation applied. That aspect may thus be ignored, and it is also irrelevant for present purposes whether there may be any contradiction between 61. The French Government considers that Article 104(II) of the Code and Article 2(4) the conditions for the derogation were met of Decree 93-990, implementing Directive as regards both 'technical reasons' and 90/531. 17 The question to be answered is: 'reasons connected with protection of was there a breach of Article 20(2)(c) of exclusive rights'. The basic elements and Directive 93/38 as a result of conduct after certain essential parts of the VAL system 1 July 1994? were protected by 11 patents and one design registered by Matra in France between 1975 and 1993, each with a validity of 20 years, the majority of them being extended to other Member States. Only two of them expired during the 60. The Commission submits that there relevant period, in 1995. The name 'VAL' should have been a call for competition was registered by Matra as a trade mark in 1987. In 1996, Alsthom stated to Semtcar that it could not meet the terms specified as 17 — See paragraphs 10 and 11 above. regards deadlines and previous construe-

I - 8392

COMMISSION V FRANCE

tions. A system proposed by Alsthom for identical in substance or closely compar- Toulouse would not receive type certifica- able to Article 20(2)(c) of Directive tion until the year 2006, whereas the 93/38. 20 It has held that such provisions, Rennes system was to start operating in 'which authorise derogations from the rules November 2001. No other undertakings intended to ensure the effectiveness of the were in a position to provide a system rights conferred by the Treaty in relation to meeting the specific requirements of the public works contracts, must be interpreted Rennes project, nor has the Commission strictly and that the burden of proving the produced any evidence that they were. existence of exceptional circumstances jus- tifying a derogation lies on the person seeking to rely on those circumstances'. 21

62. The evidence before the Court is thus not unequivocal, and its assessment depends largely on the burden and standard of proof.

65. This means, I consider, that where a Member State seeks to rely on a deroga- tion, it is for the Member State to justify its 63. As I have pointed out, 18 it is for the claim and not for the Commission to prove Commission to prove its case and to place that the conditions for the derogation were the necessary evidence before the Court. not met. However, the overall burden of proof remains with the Commission; where evidence has been put forward to justify the derogation, it is up to the Commission to refute that evidence. On the totality of the evidence presented to it, the Court must be satisfied that the Commission has estab- 64. However, where a Member State relies lished its case. on a derogation from a general rule, the Court has regularly held the burden of proof to be reversed. 19 It has taken that 20 — Article 9(b) and Article 9(d) (later Article 5(3)(c)) of Council Directive 71/305/EEC concerning the coordina- approach in a number of cases concerning tion of procedures for the award of public works contracts, OJ, English Special Edition 1971(11), p. 682, and Arti- provisions of procurement directives either cle 6(1)(h) of Council Directive 77/62/EEC of 21 Decem- ber 1976 coordinating procedures for the award of public supply contracts, OJ 1977 L 13, p. 1. 2 1 — C a s e C-318/94 Commission v Germany [1996] ECR I-1949, paragraph 13 of the judgment; see also Case 18 — See above, paragraph 50. 199/85 Commission v Italy [1987] ECR 1039, paragrapli 19 — See. for example, as regards exceptions to the principle of 14, Case C-107/92 Commission v Italy [1993] ECR free movement of goods. Case C-128/89 Commission v I-4655, paragraphs 12 to 14, Case C-328/92 Commission Italy [1990] ECR I-3239, paragraph 23 of the judgment, v Spam [1994] ECR I-1569, paragraph 16, and Case and Case C-205/89 Commission v Greece [1991] ECR C-57/94 Commission v Italy [1995] ECR I-1249, para- I-1361, paragraph 9. graph 23.

I - 8393

OPINION OF MR JACOBS — CASE C-337/98

66. In the present case, the French Govern- tender if given the opportunity. In addition, ment has produced two documents indicat- Alsthom stated that several industrial ing that Alsthom would not have been able undertakings were in a position to supply to provide a light railway system to speci- a system and that a failure to allow them to fication. One is a brief letter from Alsthom compete with Matra would be anomalous to Semtcar dated 30 October 1996 (more under the current legislation. The Commis- than a year after the decision was taken to sion has also produced technical descrip- resume negotiations with Matra and less tions by ANF Industrie of automatic urban than a month before the contract with that light railway systems supplied by it in the company was finally approved) showing USA and Canada prior to 1995. that Alsthom had in fact been consulted but was unable to offer a system compatible with the infrastructure already planned within the strict timetable required or to provide as a reference an identical system 68. Those documents, I consider, ade- already in operation. The other is an quately refute the evidence produced by extract from the minutes of Sitcar's equiva- the French Government and establish that lent body in Toulouse, dated 2 March at least one other contractor could and 1998, from which it appears that for the would have responded had a call for second line of the light railway network in competition been issued in September that city Alsthom proposed a system which 1995. would be operational in 2006, whereas the Rennes line was to start operating in November 2001.

69. In those circumstances, I take the view that, if the procedure leading to the final award is held to have commenced in 67. The Commission has produced a letter September 1995, it cannot be concluded from Alsthom to one of the councillors from the totality of the evidence before the opposed to the VAL project, dated Court that for technical reasons or reasons 23 November 1995 (two months after the connected with the protection of exclusive decision to resume negotiations with Matra rights the contract could be executed only and one year before the final approval of by a particular contractor; the derogation the contract). It is clear from that letter that in Article 20(2)(c) of Directive 93/38 thus at that date Alsthom, having supplied did not apply and, by not publishing a call similar though not identical systems in the for competition in the Official Journal of past, considered itself perfectly capable of the European Communities, the French providing a fully automatic reserved-track Republic failed to fulfil its obligations system in Rennes in accordance with the under that provision and consequently also specifications and wished to submit a under Article 4(2) of the same directive.

I - 8394

COMMISSION V FRANCE

Conclusion

70. Nevertheless, on the basis of the view I have reached as to the applicability of the Community rules to the initial stages of the procedure in issue, I conclude that the Court should:

(1) dismiss the application; and

(2) order the Commission to pay the costs.

I - 8395

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-337/98 – Súdny dvor Európskej únie | AI Pravnik