← Späť na vyhľadávanie
Súdny dvor Európskej únie·31.5.2001

C-416/98

ECLI:EU:C:2001:301

Súd
Súdny dvor Európskej únie
IČS
61998CC0416

OPINION OF MR LÉGER — CASE C-416/98

OPINION OF ADVOCATE GENERAL LÉGER delivered on 31 May 2001 1

1. In these proceedings, pursuant to an referred to above, I shall set out the legal, arbitration clause under Article 181 of the factual and procedural background and the EC Treaty (now Article 238 EC) which is submissions of the parties only to the extent contained in a contract for the provision of strictly necessary for my reasoning. For a financial assistance entered into in 1985 2 fuller exposition of these matters, I would with Nea Energeiaki Technologia EPE, 3a invite the parties to refer to the report for company governed by Greek law, the the hearing which has been provided to Commission of the European Commu- them. nities 4 claims that the Court should order NET to refund all the financing which it has received, together with contractual and statutory interest. The Commission's claim is based on Article 9 of the Contract and Article 147 of the Greek Civil Code. 5

I — Legal context

2. Does the fact that one party to a contract failed to inform the other party that its financial position at the time when an arrangement for settlement was proposed The Contract did not allow it to honour the terms of the settlement amount to deception in Greek law? That is in substance the legal question referred for the Court's determination. 4. Under Article 1 of the Contract and paragraphs 1 and 2 of Annex 1(A) thereto NET undertook to carry out the project 'Kea Island', whose objective was: 3. As the dispute is of a private nature and its resolution concerns only the two parties

1 — Original language: French. 2 — Hereinafter 'the Contract'. — the installation of a 300 kW wind 3 — Hereinafter 'NET' or 'the defendant'. 4 — Otherwise referred to as 'the applicant'. energy converter on a Greek island no 5 — Hereinafter 'the Civil Code'. later than 1 January 1986;

I - 1760

COMMISSION v NEAENERGIAKI TECHNOLOGIA

— a two-year demonstration, starting on contract the Commission may serve notice 1 January 1986, that the system by registered post with acknowledgement worked; of service. If on the expiry of one month following such service the Contractor is still in breach of its obligations, the Com- mission may terminate the contract without further formality. The contract may also be — the handing over of the system to the terminated where, in order to obtain the users for commercial exploitation at financial assistance, the Contractor has the end of that period, namely on made false statements and may be held 1 April 1988. responsible for them. In both cases the Contractor shall immediately repay to the Commission the amount of the financial assistance received by it, plus interest from the end of the period of one month referred to above. The rate of interest shall be the 5. Article 3 of the Contract sets the amount European Investment Bank 6rate in force of the financial assistance to be provided by on the date of the Commission decision to the Community at 40% of the actual cost grant financial assistance to the project.' of the project, as verified and accepted by the Commission, subject to a cap of GRD 46 000 000, exclusive of value added tax.

8. Article 9 of the Contract provides: 6. Under the first two subparagraphs of paragraph 1(a) of Annex II(I) to the Contract, the Commission undertook to pay NET an advance of GRD 13 800 000, corresponding to 30% of the maximum amount of the financial assistance, within 30 days of the signing of the contract. 'The present contract may be terminated by These provisions also state that the advance either party on giving two months' notice if and the interest earned are to be used only it would serve no further purpose to con- for the purpose of the project. tinue with the work programme set out in Annex I, for example because a technical or economic failure of the project is to be anticipated, or because the estimated costs of the project have been too far exceeded. 7. Article 8 of the Contract provides: In that event, the Commission may request full or partial repayment of the amounts paid as financial assistance, plus interest from the date of termination of the contract, if the programme in so far as it

'In the event of non-fulfilment by the Contractor of an obligation under this 6 — Hereinafter 'the EIB'.

I - 1761

OPINION OF MR LÉGER — CASE C-416/98

was implemented has produced results 11. According to Article 157 of the Civil which can be exploited commercially. The Code, '[t]he right to seek annulment shall rate of interest shall be the [EIB] rate in be extinguished two years after the legal force on the date of the Commission act. If the error, deception or threats have decision to grant financial assistance to continued after the act, the period of two the project. Repayment shall be made in years shall commence on the day on which accordance with paragraphs II.1and II.2 of that situation ceases. In any event, no Annex II.' action for annulment shall be admissible more than 20 years after the act.'

9. Article 13 of the Contract states that all 12. Under Article 249 of the Civil Code, disputes concerning the validity, interpre- '[t]he limitation period for claims is 20 tation or application of the Contract are to years, unless otherwise provided'. be referred to the Court of Justice of the European Communities. Article 14 pro- vides for the contract to be governed by Greek law. 13. Article 345 of the Civil Code provides:

'In the case of pecuniary debts, the creditor Greek Law shall be entitled, after notice of default has been served, to claim default interest as prescribed by law or by the legal act concerned without having to prove loss. A 10. Article 147 of the Civil Code states: creditor who also proves other actual damage shall also be entitled to claim in respect thereof, save as otherwise provided by law.'

'Any person who is induced by deception to make a declaration of intent shall be entitled to seek annulment of the act. In 14. Article 346 of the Civil Code states: the event of a representation made to another person, if the deception is attribu- table to a third party, annulment may be sought only if the addressee of the repre- sentation or any other person directly acquiring rights as a result of that repre- 'A person from whom a pecuniary debt is sentation knew or should have known of due shall, even if not formally placed in the deception.' default, be liable to pay interest at the

I - 1762

COMMISSION v NEA ENERGIAKI TECHNOLOGIA

statutory rate as from the date of service of 17. In response to these various requests, judicial process to enforce payment of the NET invariably indicated that the works debt due.' were about to commence. It did not send the documents asked for by the Commis- sion.

I I — Facts

18. By letter of 22 February 1989, the 15. In accordance with the terms of the Commission advised NET that it had Contract, on 16 July 1985 the Commission decided to apply Article 8 of the Contract paid NET an advance of GRD 13 800 000 and that NET accordingly had a period of in respect of financial assistance which it one month in which to fulfil its obligations, had undertaken to provide. failing which the Contract would be ter- minated.

16. Having established that none of the phases of the project which were provided for by the Contract had been implemented, the Commission called upon NET on numerous occasions over the period from the date of signature of the Contract until 19. After the expiry of this period, on 1988: 17 May 1989 the Commission made out a recovery order. Since the order had no effect, NET was served with formal notice by registered letter of 23 January 1990, requiring the debt to be repaid within 15 days. — to comply with its obligations:

— to commence the works contemplated in the Contract, and 20. NET responded to the Commission's letter of 22 February 1989 by letters dated 26 June and 21 September 1989, in which it gave reasons as to why it had not been — to send to it the report on the progress possible for the project to succeed and of the works and copies of the auth- stated that it had had to spend substantial orisations required to carry out the amounts in respect of the preparatory work project. necessary for the realisation of the project.

I - 1763

OPINION OF MR LÉGER — CASE C-416/98

21. It proposed accordingly that this III — Forms of order sought expenditure should be deducted from its debt. It requested furthermore that it be allowed to repay the sum of GRD 10 000 000 which remained available from the amounts paid by the Commission and that the Contract be terminated in accordance 25. In these proceedings, lodged at the with Article 9. Court Registry on 20 November 1998, the Commission claims that the Court should:

22. The Commission accepted NET's pro- posals and on 27 March 1990 7 it made out a recovery order for GRD 9 257 051, '— grant the application in full, together with GRD 241 500 representing bank interest, amounting in aggregate to GRD 9 498 551. Payment was to be made no later than 15 May 1990.

— order the defendant to refund to the Commission the total financial con- tribution which it received from the Community, on the basis that the 23. This amount was not paid by NET, settlement which the Commission notwithstanding numerous demands made agreed to is considered to be invalid as achieved by fraudulent means, that by the Commission. is to say the Court should order the defendant to refund the entire amount of the principal debt of GRD 13 800 000, together with interest under the provi- sions of the Contract amounting to GRD 24 382 218 up until service of this application, namely a total amount 24. On 29 May 1998, NET informed the of GRD 38 182 218, and additionally Commission that it was unable to pay the default interest payable under Greek sums claimed. It furthermore disclosed that legislation from service of this appli- it had been in liquidation for a considerable cation on the defendant until the full period. It sought further time and proposed discharge of its debt, or otherwise that the Commission should accept pay- interest calculated on the basis of the ment of GRD 4 000 000. rate set by the [EIB] in respect of the period from the lodging of this appli- cation until the defendant has fully 7 — Otherwise referred to as 'the settlement of 27 March 1990'. discharged the debt;

I - 1764

COMMISSION v NEA ENERGIAKI TECHNOLOGIA

— in the alternative, order the defendant — order the applicant to pay its costs, to refund to the Commission the including lawyers' fees.' amount arising under the abovemen- tioned settlement, namely GRD 9 498 551, together with interest owed on the principal amount (GRD 9 257 051), which under the provisions of the Contract amounts to interest of GRD 14 643 006 up until service of this application, that is to say a total amount of GRD 24 141 557, IV — The Commission's principal claim and also the statutory interest provided for by Greek legislation from service of this application until the full discharge of the defendant's debt, or otherwise interest on the basis of the rate set by the [EIB] in respect of the period from the lodging of this application until the Arguments of the parties defendant has fully discharged the debt;

27. The Commission claims that it accepted NET's proposed settlement as a result of the latter's assertions that it had at — order the defendant in each case to pay its disposal the sum of GRD 10 000 000. the Commission's legal costs including This amount represented, according to the fees of its authorised lawyers.' NET, the balance of the advance of GRD 13 800 000 received by it. The acceptance of the proposal was furthermore subject to the condition subsequent, which although implied was none the less clear and indis- putable, that the said sum be actually 26. NET contends that the Court should: remitted.

'— dismiss the application in its entirety; 28. The Commission relies on NET's com- munication of 29 May 1998 in support of its claim. It submits that it follows there- from that at the time when NET was presenting its proposal for settlement it — in the alternative, order it to pay to the plainly did not intend to repay part of the applicant the sum of GRD 3 986 545, advance received but that its sole aim was without interest; to deceive the Commission in order to

I - 1765

OPINION OF MR LÉGER — CASE C-416/98

delay its obligations to make repayment and had to be found. 8It follows that the and ultimately to gain a reduction in its decision to terminate the Contract under debt. As part of this strategy, NET Article 9 is not subject to the condition, refrained from informing the Commission implied or otherwise, that the sum in that it had been put into liquidation. question be paid.

32. NET also submits that, should the 29. The result of the above is, in the Court find that the Commission was Commission's submission, that its accept- induced by deception to accept the pro- ance of NET's settlement proposals and the posal set out in its letters of 26 June and corresponding reduction in the amount 21 September 1989, the right to challenge owed to the Community are void. The the agreement on grounds of deception is Commission considers itself to have been time-barred. It invokes Article 157 of the the victim of deception on NET's part, Civil Code, which states that the right to within the meaning of Article 147 of the seek annulment is extinguished after a Civil Code. It accordingly requests that the period of two years. arrangement be declared null and void and that the defendant be ordered to repay to it the whole of the advance paid, namely GRD 13 800 000, together with contrac- tual interest and statutory default interest.

Analysis

30. NET denies that the agreement was Greek positive law — Article 147 of the entered into as a result of deception on its Civil Code part.

33. For there to be deception within the meaning of Article 147 of the Civil Code, 31. It argues that its 'willingness to repay' two conditions must be met. First, there the sum of GRD 10 000 000 expressed in must have been action or subterfuges which its letter of 26 June 1989 indicated only its were dishonest. Secondly, the perpetrator wish to comply with the terms of the must have acted with specific intent. Contract, as it understood them to apply and as it believed they could be imple- mented. This money was not available to it 8 — Pages 12 and 13 of the defence.

I - 1766

COMMISSION v NEA ENERGIAKI TECHNOLOGIA

34. As regards the first condition, under the entered into the contract even if there had settled case-law of the Greek courts, any been no fraudulent conduct. conduct liable to create or reinforce an incorrect impression or perception of real- ity through misrepresentation or the con- cealment of facts or only partial disclosure of facts constitutes deception. The obli- gation to disclose certain facts or provide 37. Lastly, under Greek law deception is the other party with certain information not presumed but must be proved by the depends on the type of contract, the party who claims to be a victim of it. requirements of good faith in the relations between the parties, morally sound conduct and bilateral contractual practice. In com- mercial transactions and particularly where a commercial risk is to be assumed, the obligation to provide information on the financial status of either party is greater Applicability of Article 147 of the Civil than usual. Code to the present proceedings

38. The Commission claims that the settle- 35. As far as the second condition is ment of 27 March 1990 is void. It submits concerned, the perpetrator's intention con- that its acceptance was obtained as a result sists of fraudulent intent on his part, that is of the defendant's false representation as to to say the knowledge or, at least, the its financial situation. NET indicated that it awareness that his conduct is misleading, retained GRD 10 000 000 from the and of acceptance of the consequences of amounts advanced by the Community, the deception. The concept of deception and accordingly that it was in a position accordingly excludes negligence, even seri- to repay this sum to the Commission. The ous negligence, on the perpetrator's part. Commission further contends that NET concealed important facts, such as the winding up proceedings commenced against it.

36. In order for a legal act to be annulled by reason of deception, case-law also requires that there be a causal link between the perpetrator's untruth and the sub- 39. According to the Commission, these sequent act. The legal act cannot be facts, which were known to the defendant annulled and the perpetrator of the decep- at the time when it proposed the arrange- tion may be released from any responsibil- ment, were intentionally concealed. The ity if he shows that the deception did not Commission claims that it would never influence the contractual intent of the have accepted the proposal if these facts victim and that the victim would have had been brought to its attention.

I - 1767

OPINION OF MR LÉGER — CASE C-416/98

40. The defendant accepts that it did not inferred from the efforts which it made to have the sum which it proposed to remit to obtain a reduction in the amount of its the applicant available to it at the time indebtedness, as evidenced by the arrange- when it proposed the settlement. 9 ment for settlement that it proposed to the Commission on 26 June 1989. According to NET, there would have been no point in its striving to obtain this reduction in the amount of its indebtedness to the Commis- sion if it had had no intention at all to 41. Given the very wide meaning of the repay the sums due from it. concept of deception in Greek positive law, which it should be remembered provides that any conduct liable to create or rein- force an incorrect impression or perception of reality may amount to deception, it is my view that the fact that NET lied about the sums available to it and which it proposed to remit to the applicant means that it may be concluded that the act of deception is present in this case. 44. It must be found that the allegations made by the Commission are not substanti- ated by any matter or prima facie evidence supporting the conclusion that NET found itself in a financial position which made the repayment that it proposed in its letter of 42. According to the Commission, the 26 June 1989 completely illusory or fraudulent nature of NET's conduct may impossible. No information is given as to be deduced from the fact that it did not the date on which NET suspended pay- have the sums which it proposed to remit to ments. Nor has the Commission produced the Commission available to it at the time any accounting documents which would when it was attempting to obtain the prove that, for example, at the time when Commission's agreement to a reduction of the proposal for settlement was made, NET its debt. The Commission submits that the did not have any debts which it could misrepresentation of NET's financial pos- recover from a third party or any credit ition would be enough to prove that NET facility. did not intend to make the repayment agreed to by it.

43. NET categorically denies that it did not intend to honour its debts. On the contrary, its wish to fulfil its obligations may be 45. It follows from the above that the Commission has not proved that NET acted with fraudulent intent. Article 147 9 — Ibid. of the Civil Code is therefore inapplicable.

I - 1768

COMMISSION v MEA ENERGIAKI TECHNOLOGIA

V — The Commission's alternative claim accordance with Article 346 of the Civil Code from the date of service of the application until it has fully discharged the debt, or otherwise to pay default inter- est at the EIB rate in respect of the period from the lodging of the application until it has fully discharged the debt. Arguments of the parties

46. In the alternative, should the Court hold that the acceptance by the Commis- sion of the settlement of 27 March 1990 is valid and binding on the Community, the Commission claims that NET is bound to 49. NET accepts that it is indebted to the repay the amount which this arrangement Commission and the validity of the settle- requires, namely GRD 9 498 551, together ment of 27 March 1990, but submits that with interest under Article 9 of the the amount of the expenditure incurred in Contract and statutory default interest. connection with the contract for financial assistance is greater than the figure declared by it to the Commission in its letters of 26 June and 21 September 1989. It explains that the expenditure declared and subsequently approved by the Com- mission, in connection with the settlement 47. The Commission submits that, as pro- of 27 March 1990, corresponded to the vided in the settlement of 27 March 1990, figures set out in its tax returns but not to the contract to provide financial assistance the contractual position. It states, however, entered into by the parties was terminated that it is unable to furnish proof of the under Article 9 of the Contract. This clause additional expenditure to which it refers. expressly provides that the Commission may request full or partial repayment of the amounts paid as financial assistance, together with interest from the date when the Contract is terminated. The clause also states that the rate of interest is the EIB rate in force on the date of the Commission decision to grant financial assistance to the project. 50. NET also submits that, if the Court were to grant one of the Commission's claims, the rate of interest should be that of the EIB. It challenges the Commission's claim for statutory default interest. Accord- ing to NET, as default interest was not 48. The Commission further claims that provided for by the parties, it cannot be NET must be ordered to pay statutory ordered to pay such interest on the basis of default interest on the whole of its debt in Article 346 of the Civil Code.

I - 1769

OPINION OF MR LÉGER — CASE C-416/98

Analysis from the date of termination of the contract. This article also provides that the rate of interest is the EIB rate in force on the date of the Commission decision to grant financial assistance to the project. 51. Under the settlement of 27 March 1990 the parties agreed both on the prin- ciple that NET owed a pecuniary debt and the amount owed by NET and the interest payable. 56. In judgment 272/1994 10 the Areios Pagos (Greek Supreme Court of Cassation) held that the statutory rate of interest under Article 346 of the Civil Code is a secondary one, arising only when the parties have not agreed on a rate of interest under the 52. Since NET's claim seeking amendment contract. On the other hand, where the of the sum payable by it is without parties have agreed on a contractual rate, justification it should be rejected. the judgment provides that that rate is to prevail over the statutory rate in all cases, including where the contractual rate is lower than the statutory one.

53. It follows that the settlement of 27 March 1990 must be held to be valid and must be applied. 57. The provisions of the contract expressly state the rate of default interest which applies in the present case.

54. I therefore propose that the Court should order the defendant to pay the Commission the amount owing under the 58. Accordingly, the Commission's claim settlement of 27 March 1990, namely GRD based on the provisions of the contract 9 498 551. must be allowed and NET ordered to pay default interest as provided for in the Contract.

55. As regards the claim for payment of contractual and statutory default interest on the whole amount owing, Article 9 of 59. I accordingly propose that the Court the Contract expressly provides that the should order NET to pay the sum of GRD Commission may request full or partial repayment of the amounts paid as financial assistance, together with default interest 10 — NoB 1995, p. 57, NOMOS database.

I - 1770

COMMISSION v NEA ENERGIAKI TECHNOLOGIA

9 498 551, together with interest calculated 60. Under Article 69(2) of the Rules of by reference to the EIB rate in force on the Procedure of the Court, the unsuccessful date of the Commission decision to provide party is to be ordered to pay the costs if financial assistance to the 'Kea Island' they have been applied for in the successful project, for the period from the date of party's pleadings. As the Commission has termination of the Contract until the applied for such an order against NET and defendant has fully discharged the debt. the latter is unsuccessful, it should be ordered to pay the costs.

Conclusion

61. For the reasons set out above, I propose that the Court should order Nea Energeiaki Technologia EPE, a company governed by Greek law, to:

— pay the Commission of the European Communities the amount resulting from the settlement of 27 March 1990, namely GRD 9 498 551, together with interest calculated by reference to the European Investment Bank rate in force on the date of the Commission decision to provide financial assistance to the Kea Island project, for the period from the date of termination of the Contract until the defendant has fully discharged the debt;

— bear the costs.

I - 1771

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-416/98 – Súdny dvor Európskej únie | AI Pravnik