← Späť na vyhľadávanie
Súdny dvor Európskej únie·17.2.2000

C-13/99

ECLI:EU:C:2000:91

Súd
Súdny dvor Európskej únie
IČS
61999CC0013

TEAM V COMMISSION

OPINION OF ADVOCATE GENERAL JACOBS delivered on 17 February 2000 *

1. This is an appeal against a judgment 1of Europe, is the framework within which the the Court of First Instance dismissing an European Community channels economic action for damages by TEAM Sri, an Italian aid in order to implement measures inten- engineering consultancy company. The ded to support the process of economic and damage was allegedly suffered as a result social reform under way in those countries. of, first, a decision by the Commission annulling a tendering procedure for a feasibility study for the modernisation of a railway junction in Warsaw and, sec- ondly, the subsequent restricted invitation to tender for another such feasibility study.

3. Article 3(2) of Regulation No 3906/89 provides as follows:

Background and procedure before the Court of First Instance

'Account shall be taken, inter alia, of the preferences and wishes expressed by the recipient countries concerned in the choice 2. The PHARE programme, based on of measures to be financed pursuant to this Council Regulation (EEC) No 3906/89 of regulation.' 18 December 1989 on economic aid to the Republic of Hungary and the Polish Peo- ple's Republic 2 and subsequently extended to other countries of Central and Eastern

* Original language: English. 1 — Case T-13/96 [19981 ECR II-4073. 2 — OJ 1989 L 375, p. 11; as amended by Council Regulations (EEC) No 2698/90 of 17 September 1990 (OJ 1990 L 257, 4. Article 23 of the General Regulations for p. 1), No 3800/91 of 23 December 1991 (OJ 1991 L 357, Tenders and the Award of Service Contracts p. 10), No 2334/92 of 7 August 1992 (OJ 1992 L 227, p. 1), No 1764/93 of 30 June 1993 (OJ 1993 L 162, p. 1) and financed from PHARE/TACIS Funds, in the No 1366/95 of 12 June 1995 (OJ 1995 L 133, p. 1). version thereof applicable at the material

I - 4673

OPINION OF MR JACOBS — CASE C-13/99 P

time in the present case, 3 provides as follows:

'Annulment of the tendering procedure 3. In the event of annulment of any tender procedure, Tenderers who are still bound by their tenders shall be notified thereof by the Contracting Authority. Such Tenderers shall not be entitled to compensation.' 1. The Contracting Authority may, prior to awarding the contract, without thereby incurring any liability to the Tenderers, and notwithstanding the stage in the procedures leading to the conclusion of the contract, either decide to close or annul the tender 5. On 13 June 1995 the Commission issued procedure in accordance with para- a restricted invitation to tender for a graph 2, or order that the procedure feasibility study for the modernisation of be recommenced, if necessary, on a railway junction in Warsaw on the E-20 amended terms. line ('the June invitation to tender') to be financed in the context of PHARE Project PL 9406 (1994 Transport Infrastructure Programme). That invitation to tender was sent to, amongst others, TEAM and Cen- tralne Biuro Projektowo-Badawcze Budow- 2. A tender procedure may be closed or nictwa Kolejowego (Kolprojekt) (herein- annulled in particular in the following after 'Kolprojekt'), a Polish public-owned cases: company providing railway engineering consultancy services. Having formed a consortium to take part jointly in the procedure, with Kolprojekt acting as the lead tenderer, the two undertakings sub- mitted their tender.

(d) if exceptional circumstances render 6. By fax of 16 November 1995, the Com- normal performance of the tender mission informed the tenderers that the procedure or contract impossible; invitation to tender had been cancelled due to the introduction of new objectives and modified terms of reference ('the contested 3 — Set out in paragraph 4 of the judgment of the Court of First Instance. decision').

I - 4674

TEAM V COMMISSION

7. On 4 December 1995 the Commission Court of First Instance, claiming that that issued, 'on behalf of the Government of Court should annul both the Commission Poland', a new restricted invitation to decision contained in the letter of tender for a feasibility study for the mod- 16 November 1995 and the contested invi- ernisation of the Warsaw railway node on tation to tender, award them compensation the E-20 TEN line ('the contested invitation for the damage suffered and order the to tender'). The shortlist of undertakings Commission to pay the costs. invited to submit tenders included the applicant but not Kolprojekt. The terms of reference issued with the contested invitation to tender, however, stated, under the heading 'Staff and local participation', 10. By fax of 28 May 1996, the Ministry of that the successful tenderer would be Transport and Maritime Economy of the required to work with Kolprojekt and that Republic of Poland asked the Commission the budget allocated for the participation of to withdraw the Warsaw railway junction the latter company was to be 25% of the study from the PHARE PL 9406 pro- financial offer. The terms of reference gramme and to replace it with other urgent appear to be otherwise identical to those railway projects. It pointed out that the issued with the June invitation to tender. tendering procedure had been suspended for several months and that the study could not be undertaken. The ministry also mentioned external factors relating to the planned modernisation of the junction, in particular the improvement of the Warsaw- Terespol section of the E-20 railway line and new priority pre-investment activities 8. By fax of 21 December 1995, the head for another line. of the relevant Commission unit announced that, in response to questions and remarks from several tenderers pointing to a lack of clarity in the terms of reference as regards available data, data collection and the involvement of the Polish institutions, the 11. By letter of 3 June 1996, the Deputy Commission would clarify the matter with Director-General of DG IA informed the the Polish authorities with a view to issuing Polish ministry that the Commission had more precise terms of reference during acceded to its request. He further explained January and setting a new deadline for the that, since there was no longer any reason submission of bids. The fax stated that the to proceed with the invitation to tender for submission of bids was, in the meantime, the study, the Commission had decided to deferred and the deadline postponed. annul the whole procedure on the basis of Article 23(2)(d) of the General Regula- tions.

12. By letter of the same date, the Director 9. On 26 January 1996, the applicant and of the relevant Directorate informed the Kolprojekt brought proceedings before the applicant and Kolprojekt of the Polish

I - 4675

OPINION OF MR JACOBS — CASE C-13/99 P

ministry's request and of the Commission's paragraphs 68 to 79 of the judgment. In consequent decision to annul the whole brief that Court made the following points. tendering procedure on the basis of Arti- cle 23(2)(d) of the General Regulations.

16. First, 6 the Court held that the charges and expenses incurred by a tenderer in 13. By order of 13 June 1997, the Court of connection with his participation in a First Instance (Fourth Chamber), in tendering procedure could not in principle response to an application by the Commis- constitute loss capable of being remedied sion, ruled that there was no longer any by an award of damages since, first, need to give a decision on the application Article 23 of the General Regulations for annulment and reserved for the final applicable to the tender procedure provided judgment its decision on the admissibility for contracting authorities to close or annul of the claim for damages. 4 the tendering procedure without incurring liability for compensation, and, secondly, the Instructions to Tenderers forming part of the June invitation to tender provided that the contracting authority was not bound to accept the lowest offer or to 14. By order of 8 May 1998, 5the Presi- award any contract. dent of the Fourth Chamber of the Court of First Instance, having been informed by the applicants in the reply that Kolprojekt wished to withdraw from the present proceedings, ordered the latter's name to be removed from the Court register. 17. Next, 7the Court examined the ques- tions of illegality and causation, since Article 23 could not apply if a tenderer's chances of being awarded the contract had been affected by an infringement of Com- munity law in the conduct of the tendering procedure. It noted that TEAM had not shown any such infringement of Commu- The judgment of the Court of First Instance nity law and that in any event the cause of the loss of chance of award was the with- drawal from the PHARE PL 9406 pro- gramme of the feasibility study (and the acceptance of that withdrawal by the 15. The substance of the ruling of the Commission pursuant to Article 3(2) of Court of First Instance is contained in Regulation No 3906/89), which TEAM

4 — Case T-13/96 TEAM and Kolprojekt v Commission [1997] ECR II-983. 6 — Paragraphs 69 to 71. 5 — Not published in the European Court Reports. 7 — Paragraphs 72 to 75.

I - 4676

TEAM V COMMISSION

had not shown to be either contrary to purposes of its judgment. 10 The Court did Community law or caused by the conduct not however rule on the objection of alleged against the Commission. inadmissibility raised by the Commission with regard to those documents.

18. The Court then turned to the damage allegedly resulting from the non-award of the contract, 8holding that, since the appli- cant had no certainty of securing the The grounds of appeal relating to alleged contract, the damage was not real and procedural infringements by the Court of existing but future and hypothetical. As for First Instance the alleged harm to its image, there was no causal link between unlawful conduct on the part of the Commission and the damage 21. TEAM's first two grounds of appeal allegedly resulting therefrom. may be subsumed under this one head. The grounds comprise allegations that, in its treatment of the two documents referred to above, the Court of First Instance commit- ted infringements of its Rules of Procedure 19. The Court accordingly dismissed the which adversely affected TEAM's interests. claim for damages as unfounded. 9

20. The Court also ruled on two docu- The history of the two documents in ments on which TEAM sought to rely at question the hearing: a letter dated 21 August 1995 from the Ministry of Transport and Mari- time Economy of the Republic of Poland to the Commission and a confidential version 22. By written question sent on 11 May of the minutes of a meeting held in Brussels 1998 the Court of First Instance requested on 13 September 1995 between represen- the Commission, pursuant to Article 64 of tatives of the Commission and of the its Rules of Procedure, to produce before Ministry concerning the evaluation of the 20 May 1998 the minutes, notes and tenders submitted in the context of the memoranda relating to the contested deci- invitation to tender of 13 June 1995. The sion and the contested invitation to tender, Court ruled that the documents were together with the correspondence irrelevant for the purposes of determining exchanged between the Commission and the dispute; they were therefore not taken the Polish authorities between 13 June and into consideration by the Court for the 4 December 1995 concerning the conduct of the two invitations to tender in question.

8 — Paragraphs 76 and 77. 9 — Paragraph 78. 10 — Paragraph 79.

I - 4677

OPINION OF MR JACOBS — CASE C-13/99 P

On 20 May 1998 the Commission sent the tender evaluation report (which had recom- documents to the Court under cover of a mended TEAM and Kolprojekt) and the letter submitting that they were not rele- outcome of the tender procedure and vant to the proceedings and were in any indicated that, if the Polish authorities event confidential, and accordingly wished to proceed with PHARE financing requested the Court not to put them on of the study, a new evaluation would have the file or communicate them to the to take place. The letter of 21 August 1995 applicant without hearing its further obser- expressed surprise at that view and sought vations. On 4 June 1998 the Court of First clarification from the Commission, while Instance returned the documents to the acknowledging that the final decision con- Commission and asked it to produce a non- cerning selection of the successful tenderer confidential version. The Commission was for the Commission. replied to that request by letter of 5 June 1998, stating that it was not for the Commission to provide the documents belonging to the Polish Government or authorities, sending the other documents duly expurgated of all confidential material and repeating its view that the documents were in any event irrelevant to the proceed- ings.

25. The minutes of the meeting of 13 Sep- tember 1995, convened with a view to clarifying the Commission's position, record the Commission's view that the two equally economically most advanta- 23. The Court forwarded the documents to geous offers were those presented by under- TEAM on 12 June 1998. They included a takings other than TEAM, with TEAM in letter dated 21 August 1995 from the third place. An Annex gives detailed rea- Ministry of Transport and Maritime Econ- sons for that view, supported by a table omy of the Republic of Poland to the awarding percentage points to all five Commission and a non-confidential version tenderers for various criteria. of the minutes of a meeting held in Brussels on 13 September 1995 between represen- tatives of the Commission and of the Ministry concerning the evaluation of the tenders submitted in the context of the invitation to tender of 13 June 1995.

26. At the hearing on 25 June 1998, TEAM 24. The letter of 21 August 1995 was in requested that the two documents should response to a letter from the Commission be put on the Court file. The. Court of First dated 11 August 1995 in which the Com- Instance refused that request, finding that mission stated that it could not endorse the the documents were irrelevant.

I - 4678

TEAM V COMMISSION

Summary of the arguments ments were relevant for a correct assess-' ment of at least two elements of the application, namely the illegality of the Commission's conduct and the decisive role 27. TEAM notes that it first asked the played by the Commission in changing the Court of First Instance to request the tender procedure and preventing its con- Commission to produce all relevant min- tinuance. utes of meetings and correspondence in its application lodged on 26 January 1996, two and a half years before the Court's formal request was made. TEAM submits that the conduct of the Court of First Instance is a manifest infringement of its right to a fair hearing, since the decision to request production was taken after exces- sive delay when it was no longer in a 30. Finally, TEAM states that the Court position to submit written observations and gave no reasons for its decision that the had little time to use the documents for the documents were irrelevant, which is in purposes of the hearing. itself sufficient to invalidate its judgment.

28. TEAM further submits that an even more serious infringement of its right to a fair hearing was committed when the Court of First Instance refused to take the two 31. The Commission notes that two years documents into consideration: the Court and ten months elapsed between lodging of decided essential questions for the exercise the application before the Court of First by TEAM of its right to a fair hearing, such Instance and delivery of its judgment. It as the relevance and confidentiality of the draws attention, however, to the unusual documents, without giving TEAM the features of the case — namely that the opportunity to express its point of view. Court was being asked to rule on facts Moreover in finding, without giving rea- occurring after the start of proceedings, sons, that the documents were irrelevant that TEAM quantified its damages claim and in thus refusing to take them into only in its reply lodged on 8 October 1997 consideration, the Court committed serious (one year and ten months after the start of procedural errors. proceedings), and that it was not until that same date that the Court was notified of Kolprojekt's wish to discontinue its claim. The Court accordingly could not have had a precise idea of the situation before the close of the written procedure, namely at 29. TEAM adds that the Court distorted the end of November 1997. In those the evidence by concluding that that evi- circumstances, it cannot be maintained that dence had no relevance for the purpose of the measures of inquiry of May 1998 the proceedings: on the contrary, the docu- indicate excessive or unjust delay.

I - 4679

OPINION OF MR JACOBS — CASE C-13/99 P

32. As for the Court's alleged failure to give before the Court of First Instance may be a reasons for not taking the documents into ground of appeal. 1 3In this case, however, consideration, the Commission submits there is nothing to support the allegation of that paragraph 79 of the judgment, intro- unreasonable delay in ordering production duced by the words 'In view of the fore- of the documents. It was not until the order going' and therefore to be read in conjunc- of the Court of First Instance of 13 June tion with paragraphs 12, 11 73, 74 and 75, 1997 that the Court decided to postpone clearly shows the logic behind the Court's ruling on the Commission's objection of decision. inadmissibility until it ruled on the sub- stance of the claim for damages. In the following month the Commission, in its defence lodged on 16 July 1997, referred to the existence of a notarial deed by which Kolprojekt's representatives revoked the powers of attorney granted to their lawyers (who also acted for TEAM), noting that they had asked those lawyers to cease any Analysis actions in the name of Kolprojekt. That deed was subsequently annexed to TEAM's reply lodged on 8 October 1997. In its order of 8 May 1998 the Court of First Instance stated that that must be regarded 33. TEAM complains essentially that the as a discontinuance of proceedings within Court of First Instance (i) ordered the the meaning of Article 99 of its Rules of production of documents with excessive Procedure, and accordingly removed the tardiness; (ii) decided questions — namely name of the applicant Kolprojekt from the the relevance and confidentiality of the register. Three days later the Court of First documents — which were relevant to Instance made its first request for relevant TEAM'sright to a fair hearing without documents to the Commission. In the hearing TEAM; (iii) wrongly refused to circumstances outlined above, the lapse of take the documents into consideration, time between TEAM's application and that distorting the evidence by concluding that first request cannot be regarded as unrea- they were not relevant; and (iv) gave no sonable or excessive. reasons for that conclusion.

34. Although measures of internal organi- sation of the Court of First Instance cannot 35. As for the complaints about the in general be reviewed by the Court of approach of the Court of First Instance to Justice, 12excessive duration of proceedings deciding on the relevance and confidenti- ality of the documents, the Court of Justice has repeatedly stressed that it is for the 11 — Which summarises the fax from the Polish Ministry of Transport asking the Commission to withdraw the study from the PHARE programme: see paragraph 10 above. 12 — Case C-173/95 P Hogan v Court of Justice [1995] ECR 13 —Case C-185/95 P Baustahlgewebe v Commission [1998] I-4905, paragraph 15 of the order. ECR I-8417.

I - 4680

TEAM V COMMISSION

Court of First Instance alone to assess the letter and the non-confidential version of value to be attached to items of evidence the minutes nearly two weeks in advance of adduced before it and that that appraisal the hearing; moreover by its own admission does not, save where the sense of the it had in the mean time obtained its own evidence has been distorted, constitute a copies of the two documents, presumably point of law which is subject to review by including the confidential version of the the Court of Justice. 14 There is nothing in minutes, which is annexed to its appeal. the judgment of the Court of First Instance to suggest that that Court distorted the sense of the evidence.

38. Finally, TEAM argues that the Court of First Instance gave no reasons for conclud- 36. With regard more specifically to the ing that the documents were not relevant. argument concerning confidentiality, it is Although it is true that the Court of First for the Court of First Instance, and more Instance is subject to the general principle particularly the Chamber to which the case which places on every court the obligation has been assigned, to rule on procedural to state the reasons on which its decisions issues raised by the parties and in particular are based, by indicating in particular the on questions connected with the commu- reasons which led it not to uphold a nication between parties of secret or con- complaint expressly raised before it, 16 that fidential documents. 15 Moreover and in principle does not mean that the Court of any event, the Court of First Instance saw First Instance must give reasons for every the confidential versions and excluded decision on procedural and evidential mat- them as irrelevant: since, as indicated ters: the principle requires the Court to above, that decision is unreviewable on respond to all the pleas in law raised before appeal, it seems to me that no separate it but not necessarily to address all .addi- point of appeal relating to the confidenti- tional arguments. 17 In particular the Court ality aspect subsists. is not obliged to give reasons for every assessment of evidence: such assessments are, as indicated above, findings of fact not decisions of law.

37. With regard to the arguments directed to TEAM's right to a fair hearing, it is clear that TEAM had the opportunity to address the two documents. It received both the 39. TEAM's grounds of appeal relating to the alleged procedural infringements by the 14 — See for example Case C-362/95 P Blackspur DIY and Others v Council and Commission [1997] ECR I-4775, paragraph 29 of the judgment. 1 5 — J o i n e d Cases T-134/94, T-136/94, T-137/94, T-138/94, 16 — Case C-283/90 P Vidrányi v Commission [1991] ECR T-141/94, T-145/94, T-147/94, T-148/94, T-151/94, I-4339, paragraph 29 of the judgment. T-156/94 and T-157/94 NMH Stahlwerke and Others v 1 7 — Vidrányi, paragraph 31 of the judgment; see also the Commission [1997] ECR II-2293, paragraph 41 of the Opinion of Advocate General Van Gerven in Case C-68/91 order. P Moritz v Commission [1992] ECR I-6849, paragraph 7.

I - 4681

OPINION OF MR JACOBS — CASE C-13/99 P

Court of First Instance are accordingly charges and expenses incurred in partici- unfounded. pating in the tender, independently of the actual or potential outcome of the proce- dure for awarding the contract. That prin- ciple is based on the idea that the tenderer has at least a chance of obtaining the contract and that it is precisely in view of that chance that he incurs expenses linked to drawing up his tender offer. The Court The grounds of appeal relating to the Court of First Instance distorted TEAM's argu- of First Instance's interpretation of TEAM's ments on damage, completely ignoring the arguments legal principles relied on, and thus com- mitted a serious error of law.

40. TEAM submits that on two points the Court of First Instance incorrectly inter- preted the arguments set out in the appli- cation and thus erroneously assessed their legal implications: the first point concerns the loss allegedly suffered and the second 42. The Commission responds that the concerns causation. Court did indeed examine the claim for loss of chance of award, concluding that that loss was due not to any infringement of Community law by the Commission but to an act of the Polish Government, namely withdrawal of the study. That was further- more accepted by TEAM in its reply before the Court of First Instance, where it stated The concept of the damage to be compen- that the Polish authorities' decision to sated withdraw the study, far from extinguishing the damage pleaded, made it irremediable. The Court moreover found that TEAM had not shown that the Commission had 41. TEAM first criticises the Court for infringed Community law. stating that the loss pleaded by it, in particular the non-award of the contract, could be compensated only if it had a right to the contract. TEAM notes that it stressed in its written and oral pleadings that the damage of which it complains was not the failure to obtain the contract but was caused by a different legal situation. It is 43. TEAM's appeal on this ground is in my well established that, where there is irregu- view inadmissible. In its application before larity in a tender offer, a participant who the Court of First Instance, TEAM breaks has complied with the prescribed procedure down its damages claim into (i) charges and may seek compensation both for the loss of expenses, (ii) loss resulting from the non- chance of award of the contract and for the award of the contract and (iii) damage to

I - 4682

TEAM V COMMISSION

its image. That formula is repeated in its by the contracting institution to make response lodged on 8 August 1996 to the irreversible investments in advance and Commission's application to strike out and thereby to go beyond the risks inherent in its reply lodged on 8 October 1997 and in... making a bid, [so that] non-contractual is borne out by the quantifications of the liability may be incurred on the part of the damages claim set out in both those Community', in the words of the Court of documents. Thus before the Court of First First Instance in Embassy Limousines Sc Instance it appears that TEAM was indeed Services v Parliament. 19 I accordingly see seeking damages for not obtaining the no reason to interfere with the conclusion contract. A party may not put forward for of the Court of First Instance to the effect the first time before the Court of Justice a that TEAM has not shown any infringe- plea in law which it has not raised before ment of Community law by the Commis- the Court of First Instance. 18 That ground sion. of appeal is accordingly inadmissible.

44. In any event, that ground of appeal is unfounded. As TEAM itself notes, damage Erroneous test of causation for loss of chance of award of the contract could arise only where the conduct of the procedure was irregular. As is apparent from paragraph 69 of the judgment of the Court of First Instance, under Article 23(1) of the General Regulations the contracting authority may, before awarding the con- tract and without incurring any liability to the tenderers, either decide to close or 45. TEAM submits that the Court wrongly annul the tendering procedure or order that applied the test for determining causation: the procedure be recommenced, if neces- the judgment proceeds on the basis that the sary, on amended terms. As the Court of damage pleaded was due not to any illegal First Instance indicates, such a provision act or conduct on the part of the Commis- would not validate conduct by the Com- sion but rather to the autonomous with- mission in conflict with the principles of drawal of the project by the Polish autho- legal certainty and the protection of legit- rities. That is wrong, TEAM suggests, for imate expectations. However, there is noth- two reasons: first, the damage pleaded is ing to suggest any infringement of those due to the Commission's acts and conduct principles in this case. There is no evidence, in administering the tender procedure, and for example, that TEAM was 'encouraged is unrelated to the decisions subsequently taken by the Polish authorities, and

18 — Case C-136/92 P Commission v Brazzelli Lualdi and Others [1994] ECR I-1981, paragraph 59 of the judgment. 19 — Case T-203/96 [1998] ECR II-4239.

I - 4683

OPINION OF MR JACOBS — CASE C-13/99 P

secondly, in any event those decisions were tender, were added at the express request of caused wholly or partly by the illegal the Polish Government. The Commission conduct of the Commission. seeks to distinguish Embassy Limousines, where the conduct of the Parliament was found to have created legitimate expecta- tions such as to give rise to non-contractual liability; in any event, in that case the Court of First Instance stated that the costs connected with the preparation of the bid must be borne by the undertaking which 46. TEAM argues on the basis of Embassy had chosen to participate in the procedure Limousines 20 that the Commission acted since it in no way followed from the mere unlawfully in refusing to endorse the fact that an undertaking had the right to recommendation of the Evaluation Com- take part in a tendering procedure that its mittee. The Court should accordingly have tender would be accepted, 2 1and that the concluded that the damage pleaded (both applicant was not justified in claiming loss of chance and costs and expenses) was compensation for its loss of profit since the direct consequence of the Commission's that would result in giving effect to a acts and had nothing to do with the Polish contract which had never existed. 22 That Government's subsequent decision. More- principle applied a fortiori in this case, over, since the delay in awarding the since the contract not only had never contract — due solely to the Commission's existed but could no longer exist since the unlawful conduct — was a fundamental Polish Government had withdrawn the reason contributing to the Polish authori- project. ties' decision to withdraw the project, the Court's conclusion that the withdrawal was in no way attributable to the Commission's alleged conduct appears not to be justified.

48. There are two separate but related 47. The Commission states that the inclu- aspects to this ground of appeal. First, sion in the contested invitation to tender of there is the argument that the damage the obligation on the successful tenderer to pleaded is due to the Commission's illegal work with Kolprojekt and the provision acts and omissions and not to the Polish that the budget allocated for the participa- Government's decision to withdraw the tion of that company was to be 25% of the study, as found by the Court of First financial offer meant that it was substan- Instance. Secondly, there is the argument tially different from the June invitation to that that decision was in any event sub- tender. Those amendments, which signifi- stantially prompted by the Commission's cantly altered the economic content and the illegal conduct. working methods of the project subject to

21 — Paragraph 75 of the judgment. 20 — Cited in note 19. 22 — Paragraph 96 of the judgment.

I - 4684

TEAM V COMMISSION

49. In my view the findings of the Court of as stated above there is nothing to suggest First Instance as to causation are findings of that the Commission acted unlawfully. fact and as such unreviewable on appeal. Even if that were not the case, and even if the damage pleaded or the Polish autho- rities' decision was a consequence of the Commission's conduct of the tender proce- dure, I do not consider that the outcome 50. It follows that none of the grounds of would or should have been different since appeal can be upheld.

Conclusion

5 1 . Accordingly in my opinion the Court should:

(i) dismiss the appeal;

(ii) order TEAM to pay the costs.

I - 4685

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-13/99 – Súdny dvor Európskej únie | AI Pravnik