C-59/99
ECLI:EU:C:2001:325
- Súd
- Súdny dvor Európskej únie
- IČS
- 61999CC0059
- Zdroj
- eur-lex.europa.eu ↗
OPINION OF MR GEELHOED — CASE C-59/99
OPINION OF ADVOCATE GENERAL GEELHOED delivered on 12 June 2001 1
1. By this action brought under Article 181 gramme), provided for by Regulation of the EC Treaty, the Commission seeks (EEC) No 2008/90. 2 repayment of an advance, together with interest, as a result of the termination of a contract concluded as part of the Thermie programme. The Commission terminated the contract on the ground that the defen- dants had failed to fulfil their contractual 3. Two annexes form an integral part of the obligations. contract. Annex I concerns the technical and financial specifications. Annex II sets out the general conditions ('the general conditions').
I — Contents of the contract 4. Under Article 2(1) of the contract, the duration of the project was to be 36 months with effect from 1 January 1993, and MPR, 1ST and KTG ('the contractors') undertook to carry out the work referred 2. On 17 December 1992, the Commission to in Annex I of the contract in accordance entered into a contract with Manuel Pereira with the timetable set out therein. Roldão e Filhos Lda., established in Portu- gal ('MPR'), Instituto Superior Técnico, also established in Portugal ('1ST'), and King, Tandevin & Gregson (Holdings) Ltd, established in the United Kingdom ('KTG'). The contract concerned a financial contri- 5. MPR was appointed as the project bution by the Commission to a project coordinator. Under Article 1(4) of the con- entitled 'Low Emissions — Low Cost tract, the coordinator assumed responsibil- Melting Tank for Superior Lead Crystal' ity for liaising between the Commission ('the contract'). The contract, numbered IN and the contractors. The coordinator was 90/91 PO/UK, was concluded within the also required to send to the Commission, framework of the promotion of energy on behalf of the contractors,the documents technology in Europe (Thermie pro- 2 — Council Regulation (EEC) No 2008/90 of 29 June 1990 concerning the promotion of energy technology in Europe 1 — Original language: Dutch. (Thermie programme) (OJ 1990 L 185, p. 1).
I - 8500
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
more particularly specified in the contract. 9. The contract contained a series of provi- For example, under Article 5(1) of the sions under which the contractors were contract, the coordinator was required to required to provide information. Pursuant supply the Commission with half-yearly to the first sentence of Article 2(2), the progress reports containing information Commission had to be informed of any about the technical and financial situations. delay in the performance of the contract. That obligation is further specified in Under Article 1(4) of the general condi- Article 6(1 )(a) of the general conditions. tions, the coordinator was required to inform the Commission, on behalf of the contractors, of the date of commencement of work on the project under the contract and also to inform it without delay of completion or cessation and of any event or circumstance liable to affect significantly 6. Pursuant to Article 4(1) of the contract, the performance of the contract. the Commission was to finance the project in accordance with a programme provid- ing, in particular, for the payment of an advance of ECU 357 813.
10. Under the second sentence of Arti- cle 2(2) of the contract, the Commission was entitled to terminate the contract in the circumstances set out in Article 8 of the 7. Under the first sentence of Article 4(3) of general conditions. Article 8(2)(d) of the the contract, the Commission was to make general conditions provides, in particular, all payments to the coordinator, who was that where a contractor fails to fulfil one of responsible for transferring the appropriate its obligations, the Commission may, after sums directly to each of the contractors. giving notice in writing on the defaulting Furthermore, under the second sentence of party requiring it to perform its obligations, that provision the Commission could not, terminate the contract if the contractor is under any circumstances, be held liable for still in breach of its obligations one month any failure by the coordinator to comply with that obligation. after receipt thereof, except where non- performance occurs for reasonable and justifiable technical or economic reasons.
8. The first sentence of Article 17(2)(a) of the general conditions provided that the 11. Under the first sentence of Article 2 of Commission was to pay the advance within the general conditions, the three contrac- two months of signature of the contract by tors are jointly and severally liable to the all the parties. Under the second sentence of Commission for any failure by any of them Article 17(2)(a), the advance was to be to discharge their responsibilities. The last used for the purposes set out in the sentence of this article also provides that a contract. contractor is not liable in respect of a
I-8501
OPINION OF MR GEELHOED — CASE C-59/99
defaulting contractor to make any reim- 15. On 22 February 1993, the Commission bursement under Article 8(4) of the general paid an advance of ECU 357 813 to MPR, conditions, if it can show to the reasonable in its capacity as project coordinator. This satisfaction of the Commission that it has sum was transferred to bank account not contributed to the default and has number 2702410/000/001 (Banco Fonsecas complied with Article 1(4) of the general & Burnay, Leira). conditions.
12. If the contract is terminated under 16. On 20 September 1993, the Commis- Article 8(2)(d), Article 8(4) of the general sion carried out a technical audit and conditions provides that the Commission investigation at MPR's premises. may require reimbursement of all or part of its financial contribution under the con- tract. The Commission may also claim interest from the date on which the con- tractor received the financial contribution.
17. On 20 October 1993, the Commission sent a letter to MPR, which was copied to IST and KTG, stating that MPR had failed to fulfil its contractual obligations. As a 13. Under Article 9(1) of the contract it is result of its investigation of 20 September governed by Portuguese law. Under Arti- 1993, the Commission established that cle 12 of the general conditions, the Court work on the project had still not been of Justice of the European Communities commenced. Moreover, MPR had failed to has sole jurisdiction in respect of any inform the Commission, in accordance dispute concerning the contract. with Article 2(2) of the contract, that there had been a delay in carrying out the project. The Commission went on to observe that, contrary to Article 17(2)(a) of the general conditions, the advance payment had been used for purposes other than those set out in Annex I to the contract. In view of the fact that MPR had failed to fulfil its contractual obliga- I I — The facts tions, the letter contained the notice of termination of the contract referred to in Article 8 of the general conditions. The Commission stated that if MPR did not repay the advance payment into the 14. The contract was signed by MPR on account at the Banco Fonsecas & Burnay 17 December 1992, by 1ST on 21 Decem- in Leira, it would terminate the contract ber 1992, and by KTG on 8 January 1993. without further notice.
I - 8502
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
18. In reply, MPR sent a letter to the period Article 8 of the contract would be Commission which was received on applied with immediate effect. 7 December 1993. In the letter, MPR denied that the contract had not yet been commenced, stating that 1ST and KTG had already carried out work on the project. Any delay, MPR claimed, was due to late payment of the Commission's financial contribution and to unforeseeable circum- 21. By a letter dated 14 June 1994, MPR stances, about which MPR claims the requested the Commission, in light of a Commission had been fully informed. The number of special circumstances, to post- coordinator also stated that it was agree- pone the decision communicated in the able to the possibility of studying alterna- letter of 16 May 1994. MPR stated that it tive ways of ensuring continuance of the intended to carry out a project which was contract as part of an amended plan. MPR part of the restructuring of 'Indústria was willing to exchange ideas in this Portuguesa de Cristais', which was to begin respect with the Commission in Brussels. one month later. MPR also stated that it was also undergoing a restructuring phase. MPR went on to say that, in the meantime, KTG had become insolvent and that it would therefore have to look for a new partner.
19. In a letter dated 11 January 1994, which was copied to 1ST and KTG, the Commission agreed to discuss continuation of the project, provided that MPR submit- ted a bank certificate to prove that the 22. In a letter dated 7 July 1994, which advance payment was available in the was addressed to MPR and 1ST, the Com- aforementioned bank account. mission stated that, to its regret, the contractors had failed to submit the bank certificate which it had requested on 16 May 1994. Nevertheless, in the light of the financial prospects which the restruc- turing of the project would create, and of the possible introduction of a new partner, the Commission agreed, exceptionally, to 20. It emerges from a letter to the three postpone its earlier decision to terminate contractors dated 16 May 1994 that, by the contract pursuant to Article 8. It this date, the Commission had not yet granted a further time-limit, which was to received the bank certificate confirming expire on 31 December 1994. In the that the advance payment had been trans- interim, the contractors were required to ferred back into the aforementioned bank provide the Commission with full details of account. The Commission granted the three the existing difficulties. The Commission contractors a final extension of one month stated that if it was not possible to guar- to return the advance payment. The Com- antee performance of the project after mission stated in the same letter that if no 31 December 1994, the contract would be bank certificate was submitted during that terminated with immediate effect.
I - 8503
OPINION OF MR GEELHOED — CASE C-59/99
23. According to the Commission, MPR obligation. On 18 March 1997, MPR and IST did not act upon the letter of 7 July received the demand by registered post. 1994. On 4 July 1997, the Commission again requested repayment of the advance. In the same letter, the Commission stated that it would take legal action to recover the monies advanced.
24. On 7 June 1995, the Commission noti- fied MPR and IST in writing of its decision to terminate the contract, in line with the notice it had given in the letter of 7 July 1994. In the letter of 7 June 1995, the 27. On 16 February 1999, the Commission Commission observed that: (i) the advance had still not received a reply from the payment was not available in the appro- contractors. priate bank account; (ii) work on the project had still not commenced; and (iii) there was no information or guarantee regarding the execution of the project. The Commission stated that termination would take effect two months following receipt of the letter. I I I— The procedure and the claims of the parties
25. On 11 November 1995, the Commis- sion sent MPR a demand for payment, requesting reimbursement of the advance 28. The Commission's application was payment of ECU 357 813. Since, by received by the Court of Justice on 22 Feb- 17 October 1996, that sum had still not ruary 1999. been transferred, the Commission then sent MPR a reminder in which it called for the advance payment to be reimbursed imme- diately.
29. In its application, the Commission claims that the Court should:
26. By 10 March 1997, the sum had still not been transferred. By a written demand, the Commission requested payment within 15 days of receipt of the demand. The Commission indicated that with effect from (a) order the defendants to repay to the that date it would also claim interest. It applicant the sum of ECU 357 813, stated that it would take legal action if together with ECU 185 833.78 by way MPR continued to fail to discharge its of interest accrued until 1 January
I - 8504
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
1999, plus any interest accrued until IV — Pleas in law and main arguments of the date of full repayment; the parties
34. The Commission states that MPR (b) order the defendants to pay the costs. failed to perform its obligations under Article 2 of the contract, since it failed to adhere to the timetable set out in Annex I thereto. The grant of additional time-limits, in respect of which the Commission was 30. 1ST contends that the action should be under no obligation, did not alter that dismissed and that the Commission should situation. The Commission states that it be ordered to pay the costs in full. took all necessary steps to seek repayment of the advance of ECU 357 813. It then terminated the contract in accordance with Article 2 thereof and with Article 8 of the general conditions. In the Commission's view, once the time-limit indicated in its 31. MPR did not lodge a defence. Accord- letter of 4 July 1997 had expired, the ingly, on 25 June 1999, the Commission contract was terminated. applied to the Court for judgment in its favour against MPR, in accordance with the procedure for judgment by default contained in Article 94(1) of the Rules of Procedure. 35. The Commission also claims that, under Article 2 of the general conditions, the defendants are jointly and severally liable to it. That joint and several liability is 32. The application could not be served on also recognised in Portuguese law. KTG owing to the lack of information as to the correct address of that company. It appears from the case-file that this con- tractor has since become bankrupt. In a document dated 26 April 1999, the Com- mission indicated that it wished to continue 36. The Commission also relies on Arti- the proceedings against MPR and 1ST cle 4(3) of the contract. Under this provi- alone. sion, the coordinator is responsible for transferring the appropriate portion of the advance to the other contractors and the Commission cannot, under any circum- stances, be held liable for any delay by the coordinator in performing this obliga- 33. At the hearing, which was held on tion. Moreover, it follows from the recent 15 March 2001, the Commission and 1ST case-law of the Court that the joint and presented oral argument. several liability of each of the contractors
I - 8505
OPINION OF MR GEELHOED — CASE C-59/99
creates in each one of them an obligation to bute to MPR's failure to discharge its reimburse the advance if the obligations for contractual obligations. 1ST contends that which that payment constitutes the con- it regularly encouraged the coordinator to sideration are not fulfilled. 3 perform the contract. In addition, 1ST argues that it is not bound by the obliga- tions of Article 1(4) of the general condi- tions because those obligations apply exclu- sively to the project coordinator, namely MPR. Furthermore, 1ST states that it noti- 37. IST's defence is essentially founded on fied the Commission about the delays two arguments. which had arisen as a result of MPR's difficulties, in accordance with Article 1(4) of the general conditions.
38. First of all, 1ST claims that it had no knowledge of MPR's delay until it received the copy of the Commission's letter to MPR of 20 October 1993, in which the latter 40. 1ST goes on to claim that it acted in was requested to transfer the advance good faith from the pre-contractual period payment to the original bank account. 1ST through to the termination of the contract. also contends that it took all necessary 1ST states that it has been conducting steps to perform the contract, both before research for a long time and that it has and after discovering MPR's irregularities. received financial contributions from the The documents which it has submitted European Union in the past. clearly demonstrate its efforts and its commitment with regard to performance of its contractual obligations.
41. Second, as a subsidiary point, 1ST claims that in the present case the Commis- 39. In IST's opinion, the Commission also sion may not rely upon the principle of erred in seeking to recover the advance joint and several liability to require pay- payment, together with interest, from it. ment in full from each of the contractors. Even if joint and several liability were held This plea in law is founded on certain to apply in this case, 1ST cannot be held articles of the Portuguese Civil Code liable for payment of the sums in question ('CC'). 1ST interprets Article 519(1) of the since it fulfilled the requirements for CC as meaning that, where a creditor sues exemption set out in Article 2 of the all the co-debtors simultaneously, the general conditions. In the light of those applicable legal position changes from joint requirements, 1ST asserts that the facts and several liability to joint liability, prove indisputably that it did not contri- because Article 519 of the CC provides that a creditor has the right to demand the full sum from each joint and several debtor 3 — Judgment in Case C-65/97 Commission v Cascina Laura or to demand a portion of it from each of and Garibaldi [1999] ECR I-1017, paragraphs 21 to 23.
I - 8506
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
them, but that, where the creditor has it cannot be held liable for payment of sought satisfaction from one of the debtors compensation in the form of interest, through the courts, he may not sue the because the failure to repay the advance is remaining debtors for the sum he has wholly attributable to MPR. claimed from the first debtor, except where there are reasonable grounds why he is unable to obtain satisfaction from the first debtor.
45. The Commission rejects that argument. The Commission relies, in particular, on the wording of the second subparagraph of 42. According to 1ST, by suing all the Article 8(4) of the general conditions, contractors for the full amount of the debt, under which it is entitled to claim interest the Commission has waived the right to a on repayments of financial contributions, joint and several claim. Therefore, in IST's and also on recent case-law in which the opinion, the Commission cannot claim Court has upheld the obligation of the from the other debtors any amount in defaulting party to pay interest in actions excess of their share of the whole. The for the repayment of advance payments. 4 whole of the advance was paid to MPR, while 1ST did not receive any of it. Conse- quently, MPR is the only defendant from which the Commission may seek to recover the advance, together with interest.
V — Assessment
43. In its reply, the Commission argues that there is a reasonable ground in this case, namely the fact that it is unable to recover the advance from MPR, which became 46. Article 39 of the Rules of Procedure insolvent on 26 April 1999. 1ST rejects this provides that an application must be served argument, stating that, in its opinion, it was on the defendant. The Commission's appli- submitted out of time and must therefore cation was not served on KTG. Conse- be ruled inadmissible. quently, the requirement of notification was not fulfilled and the action against KTG must accordingly be ruled inadmissi- ble. The Commission itself has indicated that it has abandoned the action against KTG and that it only wishes to proceed 44. Finally, as regards the payment of against MPR and 1ST. I will therefore interest, 1ST relies on Article 520 of the confine my assessment to those parties. CC. Under this provision, the responsibility for restitution falls only to the jointly and severally liable debtor to whom the non- 4 — Cases C-172/97 Commission v SIVU and Hydro-Réahsa nons [1199] ECR I-3363 a n d C - 3 3 4 / 9 - Commission v performance is attributable. 1ST states that Montuno [1999] ECK I-3387.
I - 8507
OPINION OF MR GEELHOED — CASE C-59/99
47. The differences in the factual and legal payment order in favour of MPR, dated circumstances warrant a separate examina- 22 February 1993, for the sum of tion of MPR and 1ST in this Opinion. ECU 357 813 in favour of MPR, which was credited to bank account number 2702410/000/001 (Banco Fonsecas & Bur- nay, Leira). Consequently, in accordance with Article 17(2)(a) of the general condi- tions, the advance was transferred within the time-limit of two months from 8 Jan- uary 1993, this being the date on which A — MPR KTG, as the last contractor, signed the contract.
48. It appears from the evidence adduced by the Commission that the application was lawfully served on MPR. Pursuant to Article 39 of the Rules of Procedure, the application was served on 1 April 1999 by 51. Under Article 8(2) of the general con- registered post with an acknowledgement ditions, the Commission is entitled to of receipt on Mr Carlos Manuel Bueri terminate the contract unilaterally if any Alves Antero, who had signed the contract of the conditions stipulated therein are met. on behalf of MPR in his capacity as In its correspondence with the contractors, managing director. However, MPR failed the Commission did not specify exactly to lodge a defence within the time-limit laid which of the grounds stipulated in Arti- down in Article 40(1) of the Rules of cle 8(2) it was relying on. However, from Procedure. Consequently, the Court of the way it is worded, there can be no Justice is required to give judgment by reasonable doubt that the Commission's default, in accordance with Article 94(1) of first letter of formal notice of 20 October the Rules of Procedure. 1993 referred to the ground for termination contained in Article 8(2)(d) of the general conditions.
49. Since there are no doubts as to the admissibility of the action against MPR, the Court must examine, under Arti- cle 94(2) of the Rules of Procedure, whe- 52. Under Article 8(2)(d) of the general ther the Commission's claims against this conditions, the Commission may terminate party are well founded. the contract if (i) one of the contractors has failed to perform any of its obligations, (ii) the defaulting contractor is given notice in writing to remedy the non-performance, (iii) the non-performance continues one month after receipt of the letter of formal 50. It has been established that the advance notice, and (iv) the non-performance is not payment was indeed made to MPR. The justified by reasonable technical or eco- Commission has submitted a copy of a nomic grounds.
I - 8508
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
53. In my opinion, the four requirements denied that performance of the contract have been fulfilled in this case. had not yet commenced during that first phase, stating that 1ST and KTG had already carried out work. In its letter, MPR did not deny that it had not actually commenced work on the project itself. 54. With regard to the performance of Furthermore, by citing force majeure rea- contractual obligations, in its letter of sons and by suggesting to the Commission 20 October 1993, the Commission refers that they search together for alternative to two provisions which MPR allegedly ways of ensuring that the contract contin- failed to fulfil, namely, Article 2(2) of the ued, MPR essentially acknowledged its contract and Article 17(2)(a) of the general breach of its obligations. conditions.
55. The Commission claims, first of all, that MPR omitted to inform it of the delay 58. In all other respects, there is nothing in in carrying out the project, which it was the case-file which suggests that MPR, in its required to do under Article 2(2) of the capacity as coordinator of the project, contract. This claim appears to me to be discharged its obligation under Article 5(1) well founded. of the contract, in conjunction with Arti- cle 6(1) of the general conditions, to pro- vide the Commission with half-yearly pro- gress reports containing information about the technical and financial situations. Nor 56. According to the timetable set out in does the case-file contain any evidence to Table 1 of Annex I to the contract, during prove that the Commission received sub- the period from January 1993 to September stantive information from the coordinator 1993 inclusive, work was to be carried out regarding the progress of the project by any on the section of the project entitled 'design other means. In my opinion, besides not and basic engineering'. In addition, accord- complying with the obligation to provide ing to a table contained on page 3 of information contained in Article 2(2) of the Annex I, this section of the project was to contract, MPR also failed to fulfil the be carried out in Marinha Grande, the obligation under Article 5(1) of the con- location of MPR's registered office. It can tract, read with Article 6(1) of the general be inferred from the above that MPR conditions, to submit reports. should already have carried out work in performance of the contract during the first phase of the project.
59. Second, in the letter of 20 October 57. In its letter which was received by the 1993, the Commission alleges that MPR Commission on 7 December 1993, MPR used the advance payment for purposes
I - 8509
OPINION OF MR GEELHOED — CASE C-59/99
other than those set out in the contract, 63. Third, the non-performance cannot be contrary to Article 17(2)(a) of the general regarded as justified on technical or eco- conditions. In the correspondence which nomic grounds. Despite the fact that MPR ensued between MPR and the Commission, stated in its letter of 14 June 1994 that it in particular the letters of December 1993 was undergoing internal restructuring, a and June 1994, that fact is not disputed. reason of this kind cannot be relied on since Although the Commission regularly urged it relates to circumstances specific to the MPR to transfer the advance back to the company concerned and not to technical or original bank account, MPR did not com- economic problems relating to execution of ply with that request. In my opinion, the research project. 5 therefore, it follows that the claim that the provision in question was breached is also well founded.
64. Consequently, I deduce from the case- file that, in its letter of 7 June 1995, the Commission acted correctly in deciding to 60. As to the other three requirements for terminate the contract unilaterally, in termination of the contract, it is sufficient accordance with Article 8 of the general to make the following observations. conditions.
61. First of all, in the letters of 11 January 65. Pursuant to the second subparagraph of 1994 and 7 July 1994, the Commission Article 8(4) of the general conditions, inter- gave MPR ample opportunity to perform est may be charged from the date of receipt the contract. It can be inferred from the of the advance at the rate applied by the case-file that MPR did not avail itself of European Monetary Cooperation Fund for that opportunity. its transactions in ECU published on the first working day of each month, plus two percentage points. In its letter to MPR of 10 March 1997, the Commission indicated that it would claim interest on the advance as from 15 days following the date of receipt of the letter, which was 18 March 1997. The Commission now claims the sum 62. Second, the Commission also did more of ECU 185 833.78 by way of interest until than merely comply with the one-month 1 January 1999, plus interest accruing until notice period, by stating in its letter of the date of full repayment. The Commis- 7 June 1995, addressed to all the contrac- tors, that the decision to terminate the contract would not take effect until two 5 — See the judgment in Case C-356/99 Commission v Hitesys months following receipt of that letter. [2000] ECR I-9517, paragraph 22.
I - 8510
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
sion specified the said sum of ECU are to act jointly and severally within the 185 833.78 in an annex to the application. meaning of Article 2 of the general condi- The case-file contains no evidence which tions. Under Article 2, the contractors are would call into question that the sum is jointly and severally liable to the Commis- well founded. 6 sion for failure by any one of them to perform the contractual obligations.
66. Therefore, the Commission's claims are well founded and comply with the require- ments of Article 94(1) of the Rules of Procedure, with regard to the claim for repayment by MPR of the advance of ECU 357 813, received on 22 January 1993, 69. Therefore, it is perfectly clear that, with together with interest. respect to the Commission, all the contrac- tors undertook to guarantee that all the obligations under the contract would be discharged by each of them. By signing the contract, the contractors freely accepted that the risk of failure by one of them to fulfil the contract, irrespective of the rea- B — IST son, could not be relied upon against the Commission.
67. The question whether the Commis- sion's action against 1ST is well founded must be analysed in the light of the provisions of the contract, of IST's actual behaviour and of the provisions of Portu- guese civil law governing joint and several liability. 70. As I have already pointed out, my view is that MPR, in its capacity as coordinator and contractor, failed to perform its obliga- tions as such under the contract. In my opinion, MPR breached, in particular, 68. It is not disputed that the contract Article 2(2) and Article 5(1) of the con- makes the three contractors jointly and tract, and Article 17(2)(a) of the general severally liable for its performance. This is conditions, with the result that the Com- absolutely clear from the actual wording. mission was entitled to terminate the The preamble provides that the contractors contract under Article 8 of the general conditions. In this case, it has been estab- lished that the Commission is entitled to 6 — IST also disputes the total amounts of the advance and the sue MPR and the other contractors jointly interest. and severally for the non-performance by
I-8511
OPINION OF MR GEELHOED — CASE C-59/99
MPR. The payment of the advance to MPR 73. In order to fulfil the first requirement, created in IST an obligation to reimburse IST must have reasonably been able to that advance in the event that the obliga- convince the Commission that it did not tions for which it constituted the consid- contribute to MPR's failure to fulfil the eration were not fulfilled. 7 contract.
71. None of the above is altered in any respect by either IST's defence, in which it states that it was unaware that the advance 74. The Commission alleges that in the had been paid until October 1993, or by months immediately following the signa- that party's claim that it did not receive any ture of the contract, 1ST acted negligently in portion of the advance from MPR. Speci- that, in its capacity as a contractor, it was fically in relation to the advance payment, unaware of certain facts relevant to the the second sentence of Article 4(3) of the project, and because some time passed contract expressly provides that the Com- before agreement was reached between mission cannot be held responsible for any the contractors as to how the project was failure by the coordinator to transfer to the to be executed. However, at the hearing the other contractors their share of the monies Commission acknowledged that IST acted advanced. in good faith when it entered into the contract. Nor does the Commission dispute that 1ST had a great deal of interest in carrying out the project. Nevertheless, to my mind it is more significant that IST subsequently submitted several letters and a 72. Under the contract, 1ST has only one fax, which are dated, respectively, 25 Jan- means of avoiding being held jointly and uary 1993, 19 February 1993, 22 June severally liable for reimbursement of the 1993 and 20 July 1993, from which it advance payment. The final sentence of emerges that 1ST regularly encouraged Article 2 of the general conditions provides MPR to continue executing the project that a contractor is not jointly and severally and to discharge its contractual obligations. liable for the reimbursement of financial A letter from MPR to IST, dated 13 June contributions which have been received 1994, also demonstrates that, at least until from the Commission, within the meaning that date, 1ST was entitled to believe that of Article 8(4) of the general conditions, if MPR intended to continue with the project. it can prove, to the reasonable satisfaction of the Commission, that it did not contri- bute to the default and that, in addition, it has complied with Article 1(4) of the general conditions. It must therefore be examined whether 1ST fulfilled those requirements in the present case. 75. In my opinion, IST has thus succeeded in reasonably convincing the Commission that it did not contribute to MPR's failure 7 — In this regard, see the judgment in Commission v Cascina Laura and Garibaldi, cited in footnote 3, paragraph 23. to perform its obligations.
I - 8512
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
76. The second requirement of the last 79. In my view, with regard to the fore- sentence of Article 2 of the general condi- going, three events were crucial for 1ST: its tions concerns the obligation to provide receipt of the Commission's two letters of information contained in Article 1(4) of the 20 October 1993 and 7 July 1994, and the general conditions. expiry of the time-limit of 31 December 1994, within which the contract was required to be performed and which was laid down by the Commission in the second of the two letters.
77. IST's contention that it cannot be regarded as bound by that obligation to 80. The first event was the receipt of the provide information on the ground that it Commission's letter of 20 October 1993, applies exclusively to the coordinator is which was addressed to all the contractors founded, in my opinion, on an erroneous and in which the Commission noted that interpretation of the aforementioned provi- work on the project had still not been sion. The first part of Article 1(4) of the commenced and that MPR had used the general conditions provides that the coor- advance payment for inappropriate pur- dinator, on behalf of all the contractors, has poses. a duty to notify the Commission when work on the project begins. The second part of the same clause also provides that each contractor must inform the Commis- sion without delay of the completion or the cessation of the work or of any event or 81. 1ST does not dispute the fact that circumstances liable significantly to affect between 1 January 1993, the date on which the performance of the contract. Accord- the period for performance of the contract ingly, this latter obligation, which is set out began to run, and receipt of the letter of in Article 1(4) of the general conditions, 20 October 1993, it took no steps to also applies to IST. inform the Commission about the delay which had arisen in executing the project. 1ST contends that until the latter date it too had been unaware of MPR's problems. IST claims that, during the period in question, it merely encouraged MPR to execute the project properly. According to 1ST, during that period, it expressly asked MPR whe- ther the Commission had paid the advance, 78. I am of the opinion that IST has failed to which MPR replied in the negative. to establish, by means of the evidence it has submitted, that it fulfilled that obligation. In order to have done so, it would have needed to prove that it had immediately notified the Commission about the difficul- ties which had arisen in executing the 82. In my opinion, it is clear that at that project. point IST ought immediately to have con¬
I-8513
OPINION OF MR GEELHOED — CASE C-59/99
tacted the Commission. As a result of its 86. First of all, IST claims that it contacted own experience with MPR, it should have the representative of the D G XVII for the been clear by then that there would be a Thermie programme at the State Energy delay in carrying out the project. Moreover, Board in Portugal, namely Ms Virginia 1ST might have had doubts about MPR's Correia. IST informed her about the delays assertion that the Commission had still not which had been caused by MPR and asked paid the advance provided for in the her to bring pressure to bear on MPR to contract. Had this been the case, the reimburse the advance payment. IST also Commission would have been in breach attempted to find a new partner for the of its obligations under Article 17(2) (a) of project, with the assistance of the State the general conditions. Energy Board.
87. However, the Commission has stated that no such 'representative of the DG 83. In any event, after it received the XVII' ever existed and that Ms Virginia Commission's letter of 20 October 1993, Correia is probably a national civil servant there can be no doubt that 1ST was aware who represents Portugal on a committee set of the Commission's complaints about up as part of the Thermie programme. MPR and of MPR's failure to discharge According to the Commission, Ms Virginia its contractual obligations. Correia had no authority whatsoever to represent the Commission, either in a general sense or in connection with the contract. At the hearing, 1ST did not dispute this point but stated that it had assumed that Ms Virginia Correia would pass on the information to the appropriate 84. I consider that the second important Commission officials. moment for 1ST occurred when it received the Commission's letter of 7 July 1994 in which, in the light of special circumstances, the Commission allowed MPR and 1ST a further opportunity to fulfil their contrac- tual obligations by 31 December 1994. 88. In my view, IST's argument is implau- sible and is wholly inadequate to discharge the contractors' obligation under the con- tract to inform the Commission should problems arise.
85. 1ST has attempted to demonstrate that between receiving the letters of 20 October 1993 and 7 July 1994, it contacted the Commission on two occasions and 89. Second, 1ST has submitted a list of the informed the latter about the problems names of five officials who, it claims, work which had arisen. for the DG XVII of the Commission and
I-8514
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
whom it purportedly contacted by tele- 92. Between the beginning of July 1994 phone during the period in question. 1ST and the end of December 1994, it should states that during those conversations it have been clear to 1ST that the Commis- indicated that it wished to continue the sion's patience had run out with respect to project in Portugal after MPR had reim- the performance of the contract and that bursed the monies advanced. 31 December 1994 was the final deadline for saving the project. If the project could not be saved, termination of the contract would be unavoidable. By that stage, it should have been obvious to 1ST that MPR had become an untrustworthy partner and an unreliable project coordinator. MPR had 90. I find this evidence too flimsy. In the failed to fulfil its contractual undertakings absence of specific additional details, it is and the monies advanced by the Commis- doubtful that the information which it is sion had not been used for the purposes laid claimed was provided would have clarified down in the contract. While, in the pre- sufficiently the actual problems which had ceding period, 1ST, in accordance with its arisen in the execution of the project. contractual obligations, and in particular Furthermore, 1ST does not dispute the with the fact that it was jointly and Commission's contention that one of the severally liable, should already have five officials no longer worked for the DG informed the Commission by registered XVII, which does not reinforce the plausi- post about the status of the work under bility of its claim to have contacted the said the contract, that requirement was perhaps officials. In addition, it appears quite clear even more important during the period that 1ST should have made written record now in question. In its letter of 7 July 1994, of the problems which had arisen and the Commission also expressly required the should have notified them to the Commis- contractors to inform it about possible sion in a registered letter. The obligation to problems. provide information, in the first sentence of Article 2(2), in conjunction with the exemption clause, together with IST's joint and several liability, mean that IST had a duty to observe such a formality. 93. However, 1ST has completely failed to demonstrate that, during the second half of 1994, it informed the Commission about the difficulties which had arisen. It did not even attempt to do so. 91. Therefore, IST has been unable to prove convincingly that, during the period from the end of October 1993 to the beginning of July 1994, it informed the Commission about the problems which had arisen. Nevertheless, in its letter of 7 July 94. Subsequently, by a letter dated 7 June 1994, the Commission gave the contractors 1995, the Commission informed 1ST that the opportunity to discharge their obliga- the contract had in fact been terminated. tions by 31 December 1994. IST distanced itself from the conduct of
I-8515
OPINION OF MR GEELHOED — CASE C-59/99
MPR only in a letter dated 17 July 1995. In 97. In the alternative, 1ST contends that, that letter, 1ST drew the Commission's under Portuguese law, the Commission attention to its active contribution to the cannot claim in this case that 1ST is jointly project, stated that it had never received and severally liable in order to obtain an any financial contribution from MPR and order against 1ST for repayment of the attributed full blame for the failure of the advance, together with interest. project to the latter.
98. In this regard, we must first of all mention Article 8(4) of the general condi- 95. As a result of the foregoing, I conclude tions, which does not limit the sum which that between October 1993 and July 1995, may be claimed — jointly and severally — 1ST did not inform the Commission with- to the amount of the advance, but instead out delay about the problems which had provides that the Commission is entitled to arisen in executing the project, which it was claim interest from the date on which MPR bound to do under the final sentence of received the advance payment. Article 2 of the general conditions, in conjunction with Article 1(4) of the general conditions. Thus, 1ST did not make use of the opportunity to exonerate itself vis-à-vis the Commission and to avoid being held jointly and severally liable by means of a reply, such as the one it provided in its letter of 17 July 1995, in which it clearly 99. Consequently, it must be observed that explained the problems which had arisen Portuguese law does not, as such, preclude and the reason behind them, and demon- debtors from being held jointly and sever- strated how it had taken all reasonable ally liable, as is provided for by the contract steps to fulfil its contractual obligations. in the case of the contractors, and particu- Such a reaction would have been all the larly by Article 2 of the general conditions. more natural in view of the fact that 1ST claims to be a professional contractor which had already acquired the necessary experience in other projects financed by the European Union.
100. Under Article 512(1) of the CC, lia- bility is joint and several where each of the debtors is responsible for full satisfaction of the debt, which then releases all the debtors from liability. In accordance with Arti- 96. In my opinion, IST's reliance on the cle 517(1) of the CC, joint and several exemption clause in the final sentence of liability does not preclude the debtors from Article 2 of the general conditions cannot being sued jointly by the creditor. Arti- avail it. cle 519(1) of the CC provides that the
I-8516
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
creditor is entitled to seek from each debtor legal action if the advance payment is not full or partial satisfaction of the debt, reimbursed within the period laid down. irrespective of whether the share of the The judicial phase of the matter only began debtor who is sued is proportional. If the with these proceedings before the Court of creditor seeks to recover all or part of the Justice. debt from one of the debtors through the courts, he may not sue the other debtors for the amount he has claimed from the first debtor, unless that debtor is insolvent or is at risk of insolvency, or if there is some other reason why the creditor is unable to 103. Therefore, under the provisions of the recover the debt from the said debtor. contract, Portuguese law does not preclude the Commission, as the creditor, from suing the contractors jointly and severally for reimbursement of the advance, even though it had already sent letters of formal notice and demands for payment to MPR.
101. IST's argument presupposes that, by bringing a joint action against the contrac- tors, the Commission has waived the opportunity to take action against each of them jointly and severally for reimburse- 104. Finally, IST relies on Article 520 of ment of the full amount. the CC in support of its claim that it is exempt from any obligation to pay the interest owed to the Commission.
102. I consider this view to be founded on an erroneous interpretation of Arti- 105. Article 520 of the CC is worded as cle 519(1) of the CC. That article provides follows: 'If performance becomes impossi- that a creditor may seek satisfaction of the ble for a reason attributable to one of the debt from each debtor, but that the creditor obligors, they are all jointly and severally only waives the right to rely on the joint liable for the amount of the debt, however and several liability of the remaining debt- only the defaulting obligor shall be liable to ors where he has taken legal action against compensate for damage which exceeds that the first debtor. That is not the situation in amount and, if there is more than one, then- this case. On 11 November 1995, the liability shall be joint and several.' Commission sent MPR a demand for payment, which should be regarded as the initial step in bringing legal proceedings in the matter. This can also be deduced from the letters of formal notice which the Commission sent to MPR on 10 March 106. IST contends that it is not liable for 1997 and 4 July 1997. In both letters, the the payment of compensation in the form Commission gives notice that it will take of interest because it did not contribute to
I - 8517
OPINION OF MR GEELHOED — CASE C-59/99
the non-performance of the contract and liable for the non-performance is jointly because it discharged its obligation to and severally liable for payment in full of inform the Commission, pursuant to Arti- the compensation. The fact that MPR cle 2 of the general conditions. might, perhaps, be more at fault than IST for the failure to execute the contract is immaterial to the legal position vis-à-vis the Commission. The question of culpability is a matter for debate in proceedings con- cerning the contractors' reciprocal obliga- 107. It is not disputed that the interest tions. claimed by the Commission should be regarded as compensation within the mean- ing of Article 520 of the CC.
110. Article 2(1) of Council Regulation (EC) No 1103/97 of 17 June 1997 on 108. I will be brief on the subject of these certain provisions relating to the introduc- arguments put forward by 1ST. In my tion of the euro 8 provides that any refer- opinion, it can be inferred from the fore- ence to the ecu shall be replaced by a going that both MPR and 1ST contributed reference to the euro at a rate of one euro to to the non-performance and, therefore, to one ecu. the termination of the contract. In the case of 1ST, suffice it to point out that it failed to discharge its obligation, under Article 2(2) of the general conditions, to inform the Commission within an appropriate period about the delays in executing the contract. 1ST can also be said to have permitted the amount of interest owed to increase. 1ST must have been aware of MPR's problems VI — Costs from an early stage and, in any event, from August 1995, when the Commission finally terminated the contract, it must have known that the contract provided that the Commission was entitled to recover the 111. Under Article 69(2) of the Rules of advance, together with interest, from each Procedure the unsuccessful party is to be of the contractors. ordered to pay the costs. Since the Com- mission applied for an order for costs against both MPR and 1ST, and since the pleas put forward by both those parties have been dismissed, MPR and 1ST must be ordered jointly and severally to pay the 109. Even on the supposition that 1ST did costs. not receive any advance, in such a situa- tion, as the final section of Article 520 of the CC provides, each contractor who is 8 — OJ 1997 L 162, p. 1.
I-8518
COMMISSION v PEREIRA ROLDÃO & FILHOS AND OTHERS
V I I— Conclusion
112. I propose that the Court should:
(1) Order Manuel Pereira Roldão e Filhos, Lda. by default to pay jointly and severally to the Commission of the European Communities the sum of EUR 357 813, together with EUR 185 833.78 by way of interest to 1 January 1999, plus interest accrued until the date of full payment.
(2) Order Manuel Pereira Roldão e Filhos, Lda. by default to pay jointly and severally the costs of the proceedings.
(3) Order Instituto Superior Técnico to pay jointly and severally to the Commission of the European Communities the sum of EUR 357 813, together with EUR 185 833.78 by way of interest to 1 January 1999, plus interest accrued until the date of full payment.
(4) Order Instituto Superior Técnico to pay jointly and severally the costs of the proceedings.
I-8519