← Späť na vyhľadávanie
Súdny dvor Európskej únie·25.1.2001

C-77/99

ECLI:EU:C:2001:56

Súd
Súdny dvor Európskej únie
IČS
61999CC0077

OPINION OF MR ALBER — CASE C-77/99

OPINION OF ADVOCATE GENERAL ALBER delivered on 25 January 2001 1

I — Introduction dant l'), NCC Siab Bau GmbH, a company under German law (hereinafter: 'Defen- dant 2'), and Esbensen Consulting Engi- neers, a company under Danish law (here- 1. This dispute concerns the reimbursement inafter: 'Defendant 3'). Under the preamble of an advance paid by the Commission as to the contract, the three contractors 3are part of the Thermie Programme. 2Reim- jointly and severally liable. In addition, bursement is demanded because the con- Defendant 1 assumed the role of 'coordi- struction project of the joint and several nator' under Article 1.4 of the contract. defendants, subsidised by the Commission, was not implemented, as the land in question could not be acquired.

3. The contract provisions relevant to these proceedings read as follows: I I — Facts and legal background

A — The contract between the parties 'Article 1 — Subject of the contract

2. On 15 September 1992 the European Community, represented by the Commis- sion, concluded Contract No BU/1048/91 as part of the THERMIE programme with Oder-Plan Architektur GmbH, a company under German law (hereinafter: 'Defen- 1.1 The contractors undertake to execute the work described in Annex I, titled 1 — Original language: German. 2 — Council Regulation (EEC) No 2008/90 of 29 June 1990 concerning the promotion of energy technology in Europe 3 — This refers to the three defendant companies Oder-Plan, (Thermie programme), OJ 1990 L 185, p. 1). Siab and Esbensen under the contract.

I - 7356

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

O D E R H A U S — PASSIVE SOLAR Article 3 — Financial contribution by the ENERGY IN AN INNOVATIVE OFFICE Community BUILDING (hereinafter referred to as "the project").

3.2 The Commission shall contribute 1.4 The coordinator shall assume overall responsibility on behalf of the contractors for submitting all written documents to the Commission and for communications between the contractors and the Commis- — 30% of the allowable costs (exclusive sion. All general communications from the of VAT) of the project in accordance Commission to the contractors, and vice with Articles 8 and 19 to 28 of versa, shall pass through the coordinator. Annex II, subject to a limit of ECU 233 100.

Article 2 — Duration

2.1 The project shall have a duration of 47 months, starting on 01/06/1992 (herein- Article 4 — Payments by the Commission after referred to as the "work commence- ment date") and ending on 30/04/1996 (hereinafter referred to as the "work com- pletion date"), in accordance with the schedule set out in Table 1 of Annex I. 4.1 The Commission shall make its pay- ments in ECU as follows:

2.2 The Commission shall be informed immediately of any delays in implementing the project. The contractors or the Com- — one advance of ECU 69 930 (European mission may terminate the contract, subject Currency Unit), corresponding to 30% to the conditions set out in Article 8 of of the sum specified in Article 3.2 of Annex II. the contract;

I - 7357

OPINION OF MR ALBER — CASE C-77/99

Article 9 — Applicable law, and entry into force of the contract

4.3 The Commission shall make all pay- 9.1 This contract shall be subject to GER- ments to the coordinator, who shall be MAN law. responsible for forwarding the appropriate amounts to the other contractors without delay. The Commission shall not be held liable for any irregularities on the part of the coordinator in this connection.

Article 5 — Reports Article 10 — Annexes

5.1 The contractors shall submit to the The following annexes shall constitute Commission, through their coordinator, the integral parts of the contract: following documents (separately) at regular intervals:

Annex I Schedule of work

1 TECHNICAL REPORTS (see Arti- cle 6.1(a)l of Annex II) Annex II General conditions.'

2 FINANCIAL REPORTS (see Arti- cle 6.1(a)2 of Annex II) 4. Part B of Annex 1 to the contract consists essentially of the timetable for execution of the work, detailed technical information on the planned project, a breakdown of the estimated costs for each implementation phase, and a detailed description of the project location. Some

I - 7358

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

of its individual provisions giving a specific the energy calculations, a net floor area of description of the project are: 5 200 m2 has been used.

'Annex 1 — Part B

B.1 Aim of the project 5. Under Section B.7(a) of Annex I to the contract, the project is divided into five phases. The first phase is referred to as 'preliminary design' and its duration is The aim of the project is to implement a given as 1 June 1992 to 30 November low-energy design office building. The 1992. The second phase, 'detailed design', building has a volume of 6 200 m2 and was planned to last from 1 November 1992 20 000 m 3and is situated near the river to 30 April 1993. The subsequent phases Oder. are not relevant for the present case.

6. Table 2 on page 18 of Annex I to the contract shows the estimated costs, exclu- sive of tax, for the various phases of the project. Preliminary design is quoted as B.5 Detailed description of the project DEM 96 600, while DEM 64 400 is stated for detailed design.

This office building is designed around an integrated atrium. The building is situated 7. Pages 19 to 25 of Annex I to the contract near to the river Oder, the eastern border of contain plans showing the site and the Germany towards Poland, see Appendices dimensions of the 'Oderhaus' building. 2 and 3.

The gross floor area of the building is 6 200 8. The provisions relevant to these pro- m2, and it has a volume of 20 200 m3. For ceedings of the General Conditions con-

I - 7359

OPINION OF MR ALBER — CASE C-77/99

tained in Annex II to the contract, divided tract and shall, if necessary, take appropri- into Parts A to F, read as follows: ate measures by common agreement.

1.4 The contractors shall notify the Com- 'Part A mission, through the coordinator, of the commencement of the work under the contract and shall inform the Commission without delay of the completion or the cessation of the work, or of any event or Execution of the work circumstances liable to significantly affect the performance of the contract.

Article 1 — Progress of the work

Article 2 — Joint and several liability 1.1 The contractors shall provide the per- sonnel, facilities, equipment and materials necessary for the proper performance of the work under the contract. Where the contract is to be carried out by more than one contractor the contractors shall be jointly and severally liable to the Commission for any failure on the part of any of them to discharge their responsibil- ities. The contractors shall discharge the responsibilities of defaulting or withdraw- ing contractors to such extent as is reason- able in all the circumstances through the completion of the work under this contract 1.3 The contractors shall be responsible for by themselves or with the assistance of taking the necessary steps to obtain any third parties in accordance with Articles 3 permit or licence required for the perfor- and 8 of this Annex, unless the contract is mance of the work under the contract by terminated in accordance with Article 8 of law and regulations in force in the place or this Annex. A contractor shall not be liable places where the work is to be carried out. in respect of a defaulting contractor: Contractors shall inform the Commission immediately if they are unable to obtain any such permit or licence. The contracting parties shall jointly review the effect of this situation on the performance of the con-

I - 7360

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

(c) to make any reimbursement under Arti- reports in a single consignment (in separate cle 8.4 of this Annex if it can show to the documents), in 4 copies covering exactly reasonable satisfaction of the Commission the same period and in the two languages that it has not contributed to the default stipulated in Article 5.4 of the contract, to and has complied with Article 1.4 of this the Commission for approval: Annex.

(a) Intermediate reports:

Article 4 — Agreements between contrac- tors

1. An intermediate report ("HALF- YEARLY TECHNICAL REPORT") setting Nothing contained in any agreement out the progress of the work (from the between the contractors themselves or Work Commencement Date), resources between the contractors and third parties employed, the results obtained, economic shall affect the obligations of the contrac- aspects, deviations from the original work tors to the Commission under the present plan during the report period and the levels contract. of cooperation in respect of work under the contract.

2. A statement of expenditure ("HALF- YEARLY FINANCIAL REPORT") during Article 6 — Reports the reporting period....

Submission of reports

6.2 Contractors shall submit promptly to the Commission, through the coordinator, any information it may require regarding 6.1 Contractors shall, from the Contract performance of the work programme spe- Signature Date, submit the following cified in the contract.

I-7361

OPINION OF MR ALBER — CASE C-77/99

8.4 Subject to... , if the contract is termi- nated pursuant to Article 8.2... (d) the Commission may require the reimburse- ment of all or part of its financial contribu- tion.

Article 8 — Termination of contract

Interest may be added from the date on which payments were received by the contractor at the rate applied by the European Monetary Cooperation Fund for its operations in ECU increased by 2 percentage points, such rate being pub- 8.2 The Commission may terminate the lished in the Official journal of the Eur- opean Communities on the first working contract: day of each month.

8.5 Where the contract is being performed by more than one contractor the Commis- sion may determine not to terminate the contract under Article 8.2, but only the (d) in the event of non-performance by one participation of the contractor to which the or more of the contractors, except for aforesaid termination provisions apply, reasonable and justifiable technical or upon such terms and conditions for such economic reasons, of any of their contractor as the Commission considers to obligations after giving notice in writ- be reasonable. Unless there are reasonable ing by recorded delivery or registered grounds for not proceeding with the con- post to the contractors requiring per- tract, the Commission shall terminate only formance of the obligations and the the participation of such defaulting con- contractors are still in breach of their tractor. obligations one month after the receipt thereof;

I - 7362

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

Article 12 — Competent court shall be used for the purpose of this contract.

The Court of Justice of the European Communities shall have sole jurisdiction in respect of any dispute concerning the contract.

Article 19 — Allowable costs

Without prejudice to Article 23, allowable costs shall include only actual costs borne by each of the contractors after the Work Article 17 — Payment of Commission Commencement Date and which are contribution expressly necessary for the performance of the work under the contract. Allowable costs may include all or any of the follow- ing category of costs:

— labour

17.2 The financial contribution of the Commission shall be paid in instalments as follows unless otherwise specified in the — overheads contract:

— travel and subsistence (a) a single sum specified in Article 4 of the contract shall be paid by the Commission as an advance payment within two months of the signature by all parties of the contract. This advance — durable equipment

I - 7363

OPINION OF MR ALBER — CASE C-77/99

— consumables Article 27 — Other costs

Any other additional costs not falling — data processing within any of the aforesaid categories may be charged to the contract only with the consent of the Commission.

— external services »

— other costs in accordance with Arti- cle 27 of this Annex.

B — Joint and several liability under Ger- man law

9. Joint and several liability is governed in German law by Paragraphs 421 et seq. of the Bürgerliches Gesetzbuch (BGB) (Ger- man Civil Code). 4 Article 25 — External services

Paragraph 421 of the BGB (Joint and several debtors) provides:

'Where performance is owed by a number of persons, such that each person under- Subject to Article 3 of this Annex costs of associated contracts, subcontracts and ser- vices shall be allowable costs as external 4 — Law of 18 August 1896 (RGBL. p. 195, BGBl. III p. 400-2), services. as last amended on 27 June 2000.

I - 7364

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

takes to effect performance in full but the C — The conduct of the contracting par- creditor may only demand performance ties, in particular the correspondence con- once (joint and several debtors), the cred- ducted with the Commission itor may, at his discretion, demand perfor- mance from each creditor in whole or in part. All the creditors remain liable until performance has been effected in full.'

10. The Commission was aware when the contract was concluded that the site for the project had not yet been acquired by the defendants. In November 1992 it paid an advance of ECU 69 930 to Defendant 1 in its capacity as coordinator.

Paragraph 425 of the BGB (Effect of other events) provides:

11. On 29 July 1994 the Commission sent a questionnaire to Defendant 1, enquiring about the status of work on the 'Oderhaus' project. Defendant 1 filled in this question- naire and returned it to the Commission on 28 September 1994.

'(1) Events other than those set out in Paragraphs 422 to 424 shall only operate for and against that joint and several debtor whom they affect, unless the contractual relationship provides otherwise. 12. As the defendants subsequently failed to submit any of the half-yearly reports which should have been produced under Article 5 of the contract, in conjunction with Article 6 of Annex II to the contract, the Commission notified them by registered post of 20 January 1995 with acknowl- edgement of receipt that they were in default as regards the submission of reports (2) This shall apply in particular to termi- under Article 2 of the contract and Arti- nation, default, fault, impossibility of per- cle 8 of Annex II to the contract, demand- formance affecting a joint and several ing that the contractors comply with this debtor, prescription and its interruption contractual obligation within two months and suspension, unification of the claim of receipt of the letter. Failing this, the with the debt, and final judgments.' Commission would terminate the contract

I - 7365

OPINION OF MR ALBER — CASE C-77/99

and demand reimbursement of the financial subsidy under the Thermie programme. subsidy plus interest. The letter was The consequent efforts on the part of the addressed to each of the three contractors. contractors to investigate alternative loca- tions to the land originally envisaged and to revise the project in the light of this were described. In particular, these efforts neces- sitated negotiations with the respective owners and with the authorities involved, 13. By letter of 27 March 1995, Defen- studies regarding the acquisition of the land dant 1 informed the Commission that the and its suitability for building, and funda- project could no longer by implemented for mental revisions of the energy engineering economic reasons, as it had not proved and the design of the project. The report possible to acquire either the land origin- disclosed total costs amounting to DEM ally envisaged for the Oderhaus or an 282 790. According to the breakdown, alternative plot, and stated that a break- these costs were incurred as part of the down of the costs incurred so far would be revision of the original design concept and sent shortly. the redesign work caused by the planned change of location.

14. None of the contractors submitted the reports in respect of which the default notice had been issued in January 1995. 16. By registered post of 12 February 1996 The Commission therefore terminated the with acknowledgement of receipt, again contract on 17 October 1995 by registered addressed to all three contractors, the post with acknowledgement of receipt, sent Commission stated that it was only pre- to each of the three contractors. As grounds pared to recognise the sum of DEM 96 600 it cited the failure to submit the reports in (corresponding to ECU 51 401) as allow- respect of which the default notice had able costs, corresponding to the maximum been issued, and the final non-implementa- subsidisable estimate for 'preliminary tion of the project. The Commission also design' in Table 2 of Annex I to the stated that the advance paid was to be contract. It declared the subsidy granted reimbursed in full, plus interest as yet to be ECU 15 420 (corresponding to 30% undetermined. of the allowable ECU 51 401), and deman- ded that the contractors repay the sum of ECU 54 510 (the difference between the advance of ECU 69 930 paid and the subsidy granted of ECU 15 420), plus interest of ECU 11 175. 15. By letter of 24 October 1995, Defen- dant 1 sent the Commission a report on the history and costs of the project until its final cancellation at the end of 1993. This revealed that because the intended site could not be acquired, the project was 17. Despite numerous demands by the abandoned immediately after the Commis- Commission accountants, no payment has sion had upheld the application for a been made by the defendants.

I - 7366

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

I I I— Procedure and forms of order sought (2) order the applicant to pay the costs of the action.

18. By application of 2 March 1999, regis- tered at the Court of Justice on 3 March 1999, the Commission brought an action, 20. Defendant 1 has not entered an appear- asking the Court to ance. The application was sent to it by registered post with acknowledgement of receipt on 9 March 1999, and the acknowl- edgement form shows that the application was delivered to the defendants on 25 March 1999. However, on 7 April (1) order the defendants jointly and sever- 1999 the registered letter with the applica- ally to pay the European Commission tion was returned to the Registry, with the EUR 54 510 plus interest in the sum of unopened envelope inscribed in handwrit- EUR 20 798.70 for the period from ing 'Please return to sender — Oder-Plan 1 January 1993 to 15 January 1999; Architektur GmbH was dissolved on 15 November 1996 — there is no longer any director named Christian Schlote.'

(2) order the defendants jointly and sever- ally to pay the European Commission interest on the principal of EUR 54 510 21. At the request of the Registrar, the at the rate used by the European Commission submitted its observations by Monetary Cooperation Fund for its letter of 20 April 1999 regarding the matter euro transactions plus two per cent as of service of the application. It stated that from 16 January 1999; and Defendant 1 was in liquidation, the pre- vious managing director having been appointed liquidator. It was still entered in the Commercial Register at the address given in the application.

(3) order the defendants jointly and sever- ally to pay the costs of the action.

22. By written application of 15 June 1999 the Commission asked the Court to give judgment by default against Defendant 1, and: 19. Defendants 2 and 3 ask the Court to

(1) order Defendant 1 to pay the European (1) dismiss the action; Commission EUR 54 510 plus interest

I - 7367

OPINION OF MR ALBER — CASE C-77/99

amounting to EUR 20 798.70 for the Rules of Procedure of the Court of Justice period from 1 January 1993 to 15 Jan- (Rules of Procedure) for giving judgment by uary 1999; default have been met.

(2) order Defendant 1 to pay the European 25. In particular, Defendant 1, as a com- Commission interest on the principal of pany which has only been dissolved but not EUR 54 510 at the rate used by the yet been removed from the Commercial European Monetary Cooperation Fund Register, can still be sued. It is still dom- for its euro transactions plus 2 percen- iciled at the same address, as a company in tage points, as from 16 January 1999; liquidation, and is represented by its former managing director as liquidator under Paragraphs 66 and 67 of the GmbHG [Law on limited liability companies]. 5

(3) order Defendant 1 to pay the costs of the proceedings.

26. In the oral proceedings the Commission argued that these conditions still obtained.

23. This application was sent to Defen- dant 1 on 21 July 1999. The registered letter was returned to the Court Registry, however, marked 'Addressee moved, address not known'. 27. The application is also well founded, on grounds analogous to those relied on with regard to Defendants 2 and 3.

IV — The arguments of the parties B — The merits of the claim against Defendants 2 and 3

A — Judgment by default against Defen- dant 1 28. Both the defendants and the applicant understand the termination regulated in

24. The Commission is of the view that the 5 — Law of 20 April 1892 (RGBl. p. 477) as amended by notice of 20 May 1898 (RGBl. p. 846, BGBl. III/FNA 4123-1); last conditions of Article 94(1) and (2) of the amended on 22 June 1998.

I - 7368

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

Article 8.2 of Annex II to the contract as a is only effective if made to each one contractually-agreed right of termination individually. within the meaning of Paragraph 346 et seq. of the BGB (the German Civil Code). 6

(2) Grounds for termination

(1) Proper notice of termination

31. The Commission relies in particular on non-performance by the contractors of the following contractual obligations set out in Article 8.2 of Annex II to the contract: 29. The Commission is of the opinion that its letter of 17 October 1995 brought the contract to an end, especially as Defen- dants 2 and 3 also received the notice of 17 October 1995. — non-implementation of the project, contrary to Article 1.1 of the contract, and

30. Defendants 2 and 3 deny that the contract was ended by the letter of — non-fulfilment of the obligation to 17 October 1995, claiming that the Com- submit reports under Article 5 of the mission has not furnished sufficient proof contract, in conjunction with Article 6 that they received the notice of 17 October of Annex II to the contract. 1995. The acknowledgement of receipt relating to Defendant 2 submitted by the Commission was not signed by the recipi- ent, and there was no acknowledgement of receipt at all as regards Defendant 3. The 32. As a defence to non-fulfilment of the notice of termination of the contract to obligation to submit reports as grounds for Defendants 2 and 3 was invalid under termination, Defendants 2 and 3 plead that Paragraph 130(1) of the BGB, as it had Defendant 1 in its role as coordinator was not been received. Moreover, under the rule solely responsible for meeting this obliga- in Paragraph 425 of the BGB, notice of tion, inasmuch as Article 1.4 of the con- termination to all joint and several debtors tract represents a special rule, derogating from the joint and several liability of the contractors laid down in Article 2 of 6 — The first sentence of Paragraph 346 (Effects of termination) reads as follows: Annex II to the contract. The breach of 'If one party to a contract has reserved the right of contractual obligations by Defendant 1 termination, upon termination each party is obliged to return any performance or consideration received.' cannot therefore be imputed to Defen- The remaining statutory provisions regarding termination are not relevant to the present case. dants 2 and 3.

I - 7369

OPINION OF MR ALBER — CASE C-77/99

33. In this connection, Defendants 2 and 3 (3) Obligation to reimburse also claim that under Article 8.5 of Annex II to the contract, the Commission should have considered terminating only the participation of the defaulting contrac- tor, instead of terminating the contract for all contractors. 36. The Commission is of the view that the contractors are under an obligation to reimburse the advance as joint and several debtors. Defendants 2 and 3 cannot plead the exclusion of their joint and several liability by Article 2(c) of Annex II to the contract. They have neither shown that they have not contributed to the presence of the grounds for termination, nor com- 34. In relation to non-implementation of plied with their duty of information the project constituting grounds for termi- towards the Commission under Article 1.4 nation, in the view of Defendants 2 and 3 of Annex II to the contract. the conditions laid down in Article 8.2(d) of Annex II to the contract have not been met. Under these, before terminating the contract the Commission must call upon the contractors to fulfil their contractual obligations. In its letter of 20 January 1995, however, the Commission merely 37. Further, Defendants 2 and 3 cannot demanded fulfilment of the contractual avoid their obligation to reimburse by obligation to report. Since there was no pleading the defence of loss of the enrich- prior reminder regarding non-implementa- ment under Paragraph 818(3) of the BGB. tion of the project, termination cannot be Paragraph 812 et seq. of the BGB, in effectively based on this breach of contract. particular the defence of loss of the enrich- ment, do not apply to termination of a contract and its subsequent discharge. 7

38. Defendants 2 and 3 are of the view that they are not jointly and severally liable 35. Defendant 2 also claimed in the oral under Article 2(c) of Annex II to the con- proceedings that under the division of work set out in Table B.4 of Annex I to the contract, its contractual obligations only 7 — The first sentence of Paragraph 812 (Principle) (1) of the applied to the 'Construction 1' and 'Erec- BGB reads as follows: 'A person who obtains something from another person by tion' phases of the project. Defendant 2 way of performance or in some other way at their expense, cannot therefore be held liable for the non- without legal basis therefor, is bound to restore it to that person.' implementation of the project in the prior Paragraph 818(3) (Extent of the enrichment claim) reads: 'The obligation to restore or make restitution of the value 'Engineering/design' phase. does not apply if the recipient is no longer enriched'.

I - 7370

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

tract. They are neither to blame for the DEM 96 600, or EUR 51 401. The project failure to comply with the obligation to never advanced beyond the initial planning report, nor were they properly informed by phase, described in Table 2 of Annex I to Defendant 1 as to the progress of the the contract as 'Preliminary Design'. The project. Moreover, payments were only costs shown in the breakdown in the report made to Defendant 1. by Defendant 1 of 24 October 1995 are therefore also only allowable up the max- imum amount of DEM 96 600, as stipu- lated in Table 2 of Annex I. Further costs are not allowable, because they relate to a 'completely new design concept' that no longer had anything to do with the original 39. Any liability that may exist at all arises project in respect of which the Commission in their view only under the provisions of had concluded the contract. In the view of Paragraph 812 et seq. of the BGB regarding the applicant, problems and questions con- unjustified enrichment. Consequently, in nected with the acquisition of the land fall the absence of permanent enrichment they entirely within the area of risk borne by the are in accordance with Paragraph 818(3) of defendants. Consequently, the amount to the BGB under no obligation to reimburse. be repaid by the defendants under Arti- The limitation of the claim for reimburse- cle 3.2 and the first indent of Article 4.1 of ment to that of permanent enrichment is the contract amounts to EUR 54 510 (the due in the present case to the fact that the difference between the advance paid of payment received was intended from the EUR 69 930 and the allowable sum of 30% outset to be passed on to a third party, of EUR 51 401, namely EUR 15 420). namely a subcontractor, under Article 25 of Annex II to the contract. Defendant 2 merely received DEM 20 000 of the advance paid to Defendant 1, which was insufficient even to cover the costs of the outside services it bought in; accordingly, it has been impoverished to that extent. Defendant 3 never received any payment 41. Defendants 2 and 3, on the other hand, at all from Defendant 1, and accordingly are of the view that the Commission has had at no time been enriched by the calculated the allowable costs incorrectly. advance paid to Defendant 1. Costs were incurred in respect of not only the 'preliminary design', but also the 'detailed design'. The maximum amount of allowable costs under Table 2 of Annex I to the contract is therefore DEM 161 000 (DEM 96 600 plus DEM 64 400). (4) The calculation of the allowable costs

42. Moreover, the Commission was aware 40. The Commission is of the view that the at the time it concluded the contract that allowable costs of the project amounted to the land originally envisaged for the project

I - 7371

OPINION OF MR ALBER — CASE C-77/99

had not yet been acquired by the defen- tract, the first report should have been dants. In the view of Defendants 2 and 3, submitted in January 1993, whereas the the resulting problems fall therefore not first time the applicant drew attention to only within their area of risk, but also the failure to fulfil the obligation to report within that of the Commission. Since it was in January 1995. If Defendants 2 and 3 paid the advance despite knowing of the had known earlier of the failure by the status of the planning, it must have coordinator to fulfil its duties under the expected to have had to finance the costs contract, they would have exerted influence of any redesign of the project. on it and could have disclosed the failure of the project in 1993; and had the Commis- sion reacted earlier, the advance paid would not have been completely used up. By waiting two years the Commission had failed to monitor the subsidy and thereby 43. Consequently, Defendants 2 and 3 are breached its duty of care towards Defen- claiming an a d d i t i o n a l g r a n t of dants 2 and 3. EUR 25 129.50 and therefore a matching reduction in the applicant's claim.

(5) Contributory fault on the part of the Commission (6) The interest claimed

44. The applicant is of the opinion that Defendants 2 and 3 cannot plead contrib- utory fault on the part of the Commission. 46. The Commission is claiming interest on Since Defendants 2 and 3 both failed to the reclaimed sum as from 1 January 1993, discharge their own contractual obliga- the final amount of which, for the final tions, their argument that the Commission time period starting on 16 January 1999, tolerated non-fulfilment of the obligation still has to be calculated in accordance with to submit reports for too long is in breach Article 8.4(2) of Annex II to the contract. of good faith and thus immaterial.

45. Defendants 2 and 3 are of the view that the Commission must bear a large portion 47. Defendants 2 and 3 plead as a precau- of the blame as regards both the amount of tionary measure that under Paragraph 197 the interest accrued, and the intervening of the BGB the claim for interest, at least up insolvency of Defendant 1. Under the con- to and including 1994, has lapsed. I - 7372

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

48. In the view of the Commission, the 52. Under Article 94(2) of the Rules of claim for interest has not lapsed. The claim Procedure, before giving judgment by could not made before the reimbursable default the Court need only check whether costs were fixed by letter of 12 February the applicant's claims appear to be well 1996. founded. Consequently, only a plausibility test need be carried out as regards Defen- dant 1. As regards Defendants 2 and 3, however, the merits of the action need to be examined in full. Since the Commission's claims in the action are identical in all three 49. In the oral proceedings, Defendants 2 instances, it is appropriate to examine the and 3 also claimed for the first time that merits of the action against Defendants 2 interest could not be claimed, if at all, after and 3 before considering the application for 12 February 1996, since the Commission judgment by default against Defendant 1. had expressly asked in its letter of 12 Feb- ruary 1996, which finally quantified the reimbursement demanded, that no money be transferred before an appropriate demand was made by the Accounting Officer. No further interest could therefore accrue from that time onwards. A demand for payment had never been made by the A — Merits of the action against Defen- Commission's Accounting Officer to dants 2 and 3 Defendants 2 and 3.

(1) The claim for reimbursement

50. The Commission regards this defence as too late and therefore to be dismissed. Moreover, Appendices K10 to K12 of the application show that the Commission 53. The claim for reimbursement presup- demanded reimbursement on several occa- poses effective termination of the contract sions after May 1996. by the Commission.

(a) Effective notice of termination V — Opinion

51. The Court has jurisdiction to decide the 54. The letter from the Commission of case under Article 12 of the contract. 17 October 1995 could constitute delivery

I - 7373

OPINION OF MR ALBER — CASE C-77/99

of an effective notice of termination. It did respect of all the debtors must first be in fact reach Defendant 1, as confirmed by rejected. The principle of individual effect letter of 23 October 1995. Defendants 2 embodied in Paragraph 425 of the BGB and 3, on the other hand, deny having only applies, according to the express received this letter. wording of the first subparagraph of this provision, 'unless the contractual relation- ship provides otherwise...'. In the present case Article 1.4 of the contract provides a rule derogating from the individual effect by means of the appointment of a coordi- 55. Although the acknowledgement of nator, which represents a specific individual receipt submitted by the Commission in agreement that takes priority. respect of Defendant 2 bears the postmark of the relevant post office at Fürstenwalde, dated 23 October 1995, the 'Date and Signature of Recipient' field is unsigned. The Commission therefore has not furn- ished proof of receipt of the letter by Defendant 2. Contrary to the view of Defendant 3, the Commission has in its reply provided an acknowledgement of receipt signed by Defendant 3 on 3 November 1995. Proof of receipt by 58. Furthermore, whether the termination Defendant 3 of the letter of 17 October of the contract can still be regarded as a 1995 therefore has been furnished. 'general communication' or whether it is a particular communication that has to be received by all the defendants to be effec- tive, can ultimately be left open: if receipt of the letter by Defendant 1 is held to be insufficient, then lodging of the action by the Commission, in which it states that it 56. As regards Defendant 2, it remains to no longer wishes to be bound by the be examined whether receipt of the letter contract, constitutes notice of termination by Defendant 1 can be imputed to Defen- to Defendant 2. Notice of the application dant 2 under Article 1.4 of the contract. has incontestably been received by Defen- That would reflect its role as coordinator. dant 2. However, this presupposes that the letter of 17 October 1995 is a 'general communica- tion' for the purposes of Article 1.4 of the contract.

57. In this connection, the arguments of Defendants 2 and 3 that Paragraph 425 of 59. It can therefore be held that the Com- the BGB prevents such an 'overall effect' of mission has given effective notice of termi- receipt by Defendant 1 being valid in nation to Defendants 2 and 3. I - 7374

COMMISSION v ODER-PLAN' ARCHITEKTUR AND OTHERS

(b) Existence of grounds for termination would be entitled to repudiate the contract as against all the contractors. None the less, the defences of Defendants 2 and 3 are examined below as they are of importance in relation to subsequent remarks concern- ing the joint and several liability of the contractors. 60. The question remains as to whether the Commission was entitled to terminate. It relies on two main grounds for termination, namely non-fulfilment of contractual obli- gations, and non-implementation of the project. 63. The obligation to report of all the defendants arises from the contract, and from Annex II to the contract. Articles 5.1 and 5.4 of the contract, and Article 6.1 of Annex II to the contract, consistently refer to 'the contractors' in connection with the 61. Under Article 8.2(d) of Annex II to the production and submission of reports, and contract, the Commission may terminate never to one of them, or to the 'coordina- the contract if one contractor fails to fulfil tor', alone. It follows from Article 1.4 and its obligations. It is undisputed that the Article 5 of the contract that the 'coordi- defendants have neither submitted the nator' is only responsible for presenting or technical and financial reports due to the forwarding the reports. These are purely Commission under Article 5, nor imple- organisational provisions that have no mented the project as a whole. Conse- effect on the duties to produce reports. In quently, at least two contractual obliga- view of this unambiguous wording, the tions have been breached. view of Defendants 2 and 3 that the contractual obligation to report was solely the responsibility of Defendant 1 is uncon- vincing. Rather, the duty to fulfil this obligation was incumbent upon all defen- dants equally. The breach of the obligation to report can therefore be imputed to (i) Non-fulfilment of the obligation to Defendants 2 and 3 as their own breach report of contract.

62. The assertion by Defendants 2 and 3 64. For these reasons, the defence of that Defendant 1, in its role as coordinator, Defendants 2 and 3 that the Commission was the sole and exclusive incumbent of the should have terminated only the participa- obligation to report, is irrelevant, as a tion of Defendant 1 in the contract, as result of Article 8.2(d) of Annex II. Even opposed to the contract as a whole, is also if only Defendant 1 was in breach of its unsuccessful. Firstly, there are grounds for obligation to report, the Commission terminating the contract as regards Defen-

I - 7375

OPINION OF MR ALBER — CASE C-77/99

dants 2 and 3 due to their own breaches of 27 March 1995. Moreover, at no time did contract. Secondly, Article 8.5 of Annex II the defendants state that they still intended to the contract places any partial termina- to implement the Oderhaus' project. A tion of the contract within the discretion of notice to implement the project issued the Commission: 'Unless there are reason- between March 1995, the time of becoming able grounds for not proceeding with the aware of the grounds for termination, and contract...'. In view of the failure at the end October 1995, the time of the notice of of 1993 of the project that was the subject termination, would therefore no longer of the contract, reasonable grounds existed have achieved its objective under the rule for terminating the contract as a whole in Article 8.2(d) of Annex II to the con- with regard to all contractors. tract, namely that of enabling the contrac- tors to discharge their contractual obliga- tions and thus avoid the consequences of termination of the contract. A prior notice for fulfilment of the contractual obligations would therefore seem superfluous. (ii) Non-implementation of the project

67. The defence pleaded by Defendant 2 in 65. It is also undisputed that the defendants the oral proceedings, that it was not subject did not implement the 'Oderhaus' project, at the time of the failure of the project to but abandoned it at the end of 1993. any contractual obligation non-fulfilment Defendants 2 and 3, however, allege there of which could have represented grounds has been an error of procedure as regards for termination, is not valid. As already this ground for termination, inasmuch as discussed, non-fulfilment of the contractual the Commission did not demand perfor- obligation by one of the contractors is mance from them before terminating the sufficient grounds for termination against contract. all the contractors (see point 61 et seq. above). Furthermore, under Article 1.1 of the contract, all the contractors undertook to implement the Oderhaus' project. According to Article 2.1 of the contract, the project was commenced on 1 June 1992. Consequently, from that time 66. A prior written notice from the Com- onwards all three contractors were subject mission to remedy the breach is indeed a to an obligation to implement the project. basic precondition for exercising the right Table B.4 of Annex I to the contract gives of termination under Article 8.2(d) of no grounds for assuming that the obliga- Annex II to the contract. However, in the tions of the different contractors were present case it must be borne in mind that limited in time to the individual phases of the definitive failure of the project had the project. If such an internal agreement existed since the end of 1993, whereas the had been intended, it cannot be cited in Commission only learned of its abandon- opposition to the Commission, as it is not ment in the letter from Defendant 1 of clearly apparent.

I - 7376

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

68. Accordingly, it must be found that both Defendants 1, 2 and 3 are joint and several the non-fulfilment of the obligation to debtors, and reference is made to Article 2 report and the non-implementation of the of Annex II for the details. Under the first project entitled the Commission to termi- sentence of Article 2 of Annex II to the nate. contract, the defendants are in principle all liable as joint and several debtors for the discharge of all contractual responsibilities. An exception to joint and several liability is provided for in Article 2(c) only when the (c) Legal consequences as regards the obli- following cumulative conditions are met: gation to reimburse

69. The question thus arises of the obliga- tion to reimburse of Defendants 2 and 3. — the contractor can show to the reason- able satisfaction of the Commission that it has not contributed to the default of the other contractor, and

(i) Existence of the claim for reimburse- ment

(aa) Joint and several liability — the contractor has complied with its notification obligations under Arti- cle 1.4 of Annex II to the contract.

70. The defence of Defendants 2 and 3 to the claim for reimbursement of the Com- mission under Article 8.4 of Annex II to the contract is that the obligation to report and the obligation to acquire the land were 72. None of these conditions for exemption incumbent solely upon Defendant 1, but from liability appears to be met in the not upon them. Reimbursement therefore present case. As already stated above, the cannot be claimed from them. breaches of contract founding the termina- tion, consisting of non-submission of reports and non-implementation of the project, are the responsibility of all three contractors equally. It is therefore irrele- 71. After naming the individual contrac- vant whether Defendants 2 and 3 have tors, the contract stipulates on page 1 that contributed to the fault of Defendant 1.

I - 7377

OPINION OF MR ALBER — CASE C-77/99

73. Moreover, it should be noted that they Defendant 1 was passed on to subcontrac- did not inform the Commission of the final tors. From a legal point of view, it should abandonment of the project at the end of be pointed out here that as a basic princi- 1993. They have therefore also breached ple, the right to claim reimbursement in their obligation under Article 1.4 of association with the termination of a con- Annex II to the contract, so that the second tract is not limited to any enrichment still condition for exemption from liability for enjoyed, and that Paragraph 818(3) of the Defendants 2 and 3 is not met either. Their BGB is in principle not applicable. 8 defence based on the position of Defen- Although agreement may be reached that dant 1 as 'coordinator' is consequently the first sentence of Paragraph 346 of the unsound. BGB shall not apply, so that the obligation to reimburse is limited to any permanent enrichment, no such agreement is included in the contract concluded between the Commission and the defendants.

74. They also plead that the Commission made payments to Defendant 1 only, for which reason only the latter should be liable to reimburse. 77. Consequently, the most that could exist here is an implied agreement. However, in the present case no such agreement can be inferred from the defendants' having to pass on the advance to third parties (such as 75. However, this defence is also unsuc- subcontractors), as Defendants 2 and 3 cessful. Under Article 4.3 of the contract, claim. The implied consequence, namely the Commission cannot be held responsible that with a rule of this kind the person for irregularities by the coordinator in liable to reimburse should be allowed to connection with the forwarding to the avail himself of the defence in Para- other contractors of monies paid. Payment graph 818(3) of the BGB, is only admissible to Defendant 1 does not therefore release in exceptional circumstances. 9 Defendants 2 and 3 from their obligation to reimburse.

78. In the present case, the explicit rule in (bb) Unjust enrichment Article 8.4 of Annex II to the contract contradicts any such limitation of the

8 — Cf. Kaiser, in Staudinger, Kommentar zum Bürgerlichen Gesetzbuch [Commentary on the German Civil Code], Vol. II, 13th ed. (Berlin 1995), Paragraph 346, section 22; Heinrichs, in Palandt, Bürgerliches Gesetzbuch ¡German 76. Defendants 2 and 3 finally plead the Civil Code], 58th ed. (Munich 1999), Paragraph 346, section 3. defence of loss of the enrichment. Any 9 — Cf. Kaiser, in Staudinger, Paragraph 346, section 31; Hein- money that Defendant 2 did receive from richs, in Palandt, Paragraph 346, section 5.

I - 7378

COMMISSION v ODER PLAN ARCHITEKTUR AND OTHERS

obligation to reimburse. It states that pages 19 to 25 of Annex I to the contract reimbursement is unconditional, and above consist of layout plans specifying both the all, independent of the use to which the precise location and the scope of the project advance is put. In addition, the costs for construction work. Under Article 27 of services provided by subcontractors are Annex II to the contract (see above, only one of the possible kinds of allowable point 8), additional costs can only be costs under Article 19 of Annex II to the charged to the project with the consent of contract. Accordingly, the payment of sub- the Commission. contractors was neither the only possible use of the money received, nor was it in the foreground of the contract. An exceptional agreement to avoid the rule in the first sentence of Paragraph 346 of the BGB cannot therefore be implied in the present circumstances. Defendants 2 and 3 are consequently liable to reimburse the 80. This shows that the advance was paid advance. by the Commission in respect of a quite specific project and definite costs incurred in connection with it. The contract gives no indication to support the theory of the defendants that the subsidy may be used for other locations without the express consent of the Commission. (ii) Amount of the reimbursement claim

(aa) Calculation of the allowable costs 81. The fact that when the Commission concluded the contract it knew that the land for the project had not yet been acquired makes no difference to the out- come, since the contract makes no provi- 79. As regards the amount of the reimburse- sion for the costs of redesigning the project, ment claim, firstly the question of the or for a new design concept for a different allowable costs is disputed by the parties location. Furthermore, under Articles 1.1 to the proceedings. Under Article 19 of and 1.3 of Annex II to the contract, the Annex II to the contract, the only costs defendants were responsible for providing allowable are those expressly necessary for the necessary facilities and materials, and the performance of the work under the for obtaining any permits or licences contract concluded between the parties. required for the performance of the work This work is designated in Article 1.1 of (see above, point 8). Obstacles associated the contract as the 'Oderhaus — Passive with this fall therefore not within the area solar energy in an innovative office build- of risk of the two sides to the contract, ing' project, and described in detail in but — contrary to the view put forward by Annex I to the contract (see above, point 4, Defendants 2 and 3 — within that of the and Annex II, Section B.5). In particular, defendants alone.

I - 7379

OPINION OF MR ALBER — CASE C-77/99

82. The letter from Defendant 1 of discovered the state of the work before the 24 October 1995 shows that the original insolvency of Defendant 1 occurred. The project was abandoned immediately after letter from Defendant 1 of 27 March 1995 confirmation of the application documents shows that on 29 July 1994 the Commis- by the Commission, and that the defen- sion sent a questionnaire relating to the dants made efforts from then on to find an state of the work to Defendant 1, who alternative project location. The break- returned it to the Commission on 28 Sep- down of the costs claimed by the defen- tember 1994. Defendant 1 was not actually dants shows likewise that they were in- dissolved for reasons of insolvency until curred in respect of the change of location 1996. envisaged, and relate to the revision of the original design concept and the changes in project planning. However, neither the contract nor its annexes makes any provi- sion for such costs, and consequently in the absence of express consent by the Commis- 85. Nor can this defence by Defendants 2 sion, they are not allowable. The defence and 3 succeed on legal grounds. The that the allowable costs have been calcu- Commission is not under the duty of care lated too low by the Commission is there- towards Defendants 2 and 3 that the latter fore to be rejected. presume. Firstly, the contract and its annexes do not include any express duty of care or supervision on the part of the Commission. There is merely a obligation on the defendants under Article 5 of the (bb) Possible contributory fault on the part contract, and Article 6 of Annex II to the of the Commission contract to produce the appropriate reports and send them to the Commission, without any corresponding duty of control or to issue notices on the part of the Commis- sion. 83. Finally, Defendants 2 and 3 plead a 'predominant contributory fault' on the part of the Commission as a defence to the reimbursement claim. The Commission is claimed to have had a duty of care 86. Any breach of a duty of care on the towards the defendants, in that as early as part of the Commission would therefore at the beginning of 1993 it should have issued the outside have to be founded on provi- a notice regarding the non-fulfilment of the sions of public law, or the fundamental obligation to report, and demanded reim- principle of good faith. bursement of the advance at a time when Defendant 1 was still solvent.

87. It is possible that there was a breach of 84. However, this defence fails already on budgetary regulations. The Commission is the facts. The Commission had already required under budgetary regulations to I - 7380

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

monitor whether subsidies it grants are Commission to comply with its unwritten used properly. However, this duty of the duties of care and protection towards them, Commission under public law does not give must be rejected. The argument represents rise to any protective effect for the defen- unacceptable and inconsistent conduct on dants. The purpose of the material regula- the part of the defendants. A party in tions is not to protect recipients of sub- flagrant breach of contract cannot assert sidies, such as Defendants 2 and 3, against that the other party should have acted in their partners in a contract who receive the good faith and solicitously towards it. The subsidies on their behalf, such as Defen- debtor cannot rely on the fundamental dant 1. Instead, the budgetary regulations principle of good faith as a defence against serve the general interest in proper employ- a claim directed against it, if it has itself not ment of public funds. As observance of acted in good faith and has thereby caused those regulations was in no way made a the claim against it to be raised late. 11 part of the contract concluded between the parties those public-law duties of the Com- mission cannot found any duty of care towards Defendants 2 and 3.

90. The lateness in raising the claim for reimbursement is due primarily to the fact 88. Finally, the exercise of a right may be that the Commission only became aware of inadmissible under the principle of good the non-implementation of the project in faith if in so doing the beneficiary of that March 1995. To that extent the defen- right infringes duties of cooperation, clar- dants breached their obligation, under ification and/or protection ancillary to the Article 1.4 of Annex II to the contract, to contract. Under this principle, both the inform the Commission without delay of debtor and the creditor in a contractual the abandonment of the project. The relationship are required jointly to create defence of Defendants 2 and 3 that they the preconditions for performance of the were unaware of the breach by Defen- contract and remove impediments to per- dant 1 and consequently had no possibility formance, and to inform each other, with- of exerting any influence is again immater- out being so requested, of any circum- ial here, as the obligation to report is an stances of significance.10 individual obligation incumbent upon Defendants 2 and 3, as stated above.

89. Even if in the present case one were to consider that there was negligence on the part of the Commission in tolerating non- fulfilment of the obligation to report for two years, the defence of Defendants 2 and 91. Informed by the same considerations, 3 that this amounts to failure by the the argument that the exercise of this right by the Commission is in bad faith due to

10 — Cf. Heinrichs, in Palandi, Paragraph 242, section 23 et seq. 11 — Cf. BGHZ 254,7, 52 e t seq.

I-7381

OPINION OF MR ALBER — CASE C-77/99

forfeiture of the rights by waiting too long Under Article 8.4(2) of Annex II to the is also to be dismissed. A right becomes contract, the Commission may claim inter- forfeit if the beneficiary does not exercise it est from the time the defendants received for a prolonged period of time, and the the payment. It is not disputed that the party liable may rely, and indeed has relied, advance was paid by the Commission in upon the inference, drawn from the overall 1992, and the Commission is asking for conduct of the beneficiary, that the latter interest only as from 1 January 1993. The will not exercise the right in future either. claim is therefore in accordance in that However, a 'confident expectation' of this respect with the contract concluded nature may not arise if the debtor has between the parties and is therefore well himself not acted in good faith. 1 2In this founded. instance, Defendants 2 and 3 were in breach of their own obligations to report.

92. The outcome is therefore that the Commission is entitled to a reimbursement claim in the sum of EUR 54 510 against Defendants 2 and 3 as joint and several debtors. 95. As regards the question until when the interest accrues, Defendants 2 and 3 have argued in the oral proceedings that interest can only be claimed from them, if at all, until 12 February 1996. However, this is not convincing. Under Article 8.4(2) of (2) The claim for interest Annex II to the contract, in the event of a claim for reimbursement interest may be claimed from the time of receipt of the payment. There are no other provisions regarding a claim for interest. The interest claimed here is precisely not interest for late payment, which ceases to accrue when 93. As well as reimbursement, the Com- payment is made, and it is therefore mission is also claiming interest. immaterial as regards the period in respect of which interest can be claimed that the Commission initially asked in its letter of 12 February 1996 that no payments be made then. Besides, it was open to Defen- dants 2 and 3 to repay the sum owed, 94. The calculation of the amount of despite the Commission's letter of 12 Feb- interest depends on the time from when ruary 1996. The request by the Commis- interest is payable, and for how long. sion not to transfer anything for the time being was made for purely internal admin- istrative reasons. It did not prevent the 12 — Cf. BGHZ 25, 47, 52 et seq. defendants from making repayment, and

I - 7382

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

the Commission was not in default as issuing of an invoice, even if the latter regards the acceptance of payment. specifies the sum involved for the first time. 14

96. Finally, it must be pointed out that the Commission has asked the defendants for payment on several occasions since May 1996. Although these letters were addressed only to Defendant 1, Defen- dants 2 and 3 cannot prevent receipt of the claims being imputed to them, as they 99. Under Article 8.4 of Annex II to the were addressed to the coordinator. contract, the Commission may demand not only reimbursement of the subsidy, but also interest from the time when the prescrip- tion period starts to run, namely that of termination of the contract. The disputed claim for interest could therefore in the 97. The amount of interest for the indivi- present case have been raised at the time of dual periods of time is not disputed by termination of the contract. This was Defendants 2 and 3. effected, as has already been discussed, by the letter from the Commission of 17 Octo- ber 1995, which was received by Defen- dant 1 on 23 October 1995, and by Defen- dant 3. Whether 3 November 1995 or a later date, namely the bringing of the action 98. However, the defendants also plead the on 3 March 1999, is to be taken as the defence of prescription. Interest claims are relevant time in relation to Defendant 2, subject to a prescription period of four can be disregarded here. The only conse- years under Paragraph 197 of the BGB. quence of this would be that the prescrip- Under the first sentence of Paragraph 201 tion period would have started to run even of the BGB and the first sentence of later. It can therefore be assumed that the Paragraph 198 of the BGB, the prescription earliest time when the claim for interest period starts to run at the end of the year in could have been raised was 17 October which the claim arose, that is to say, the 1995. The prescription period therefore time when the claim was raised for the first began on 31 December 1995 and under time and could be enforced by means of an Paragraph 209(1) of the BGB was effec- action. This in turn is governed by the time tively interrupted by the bringing of the when performance was due, i.e. the time action on 3 March 1999, in other words when the creditor could demand pay- before the end of the prescription period on ment. 13 On the other hand, it is not 31 December 1999. The defence of pre- necessary for the claim to have been scription against the claims for interest quantifiable then. The start of the prescrip- cannot therefore succeed. The interest tion period is therefore independent of the claimed by the Commission is due in full.

13 —Cf. BGHZ 55,340, 341. 14 —Cf. BGHZ 79, 176, 178.

I - 7383

OPINION OF MR ALBER — CASE C-77/99

B — Application for judgment by default (1) Capacity of Defendant 1 to be a party against Defendant 1 to an action

102. According to Article 9.1 of the con- tract, the contract is subject to German law, and the question of the capacity of Defen- dant 1 to be a party to an action must 100. By application of 15 June 1999, the therefore be decided under German law, Commission asked for judgment by default according to which Oder-Plan GmbH is against Defendant 1. Under Article 94(1) capable of being a party to an action unless of the Rules of Procedure the application is it has ceased to exist as a legal person. A well founded if the Commission's action company ceases to exist when liquidation is has been properly raised. Doubts may exist complete and its cessation has been entered in this regard inasmuch as service on in the Commercial Register. A company Defendant 1 of the application is question- which has merely been dissolved, however, able. continues to be capable of being a party to an action and an action can therefore be brought against it. 15

103. The notarially-authenticated extract of 4 June 1999 from the Commercial Register of the Charlottenburg District 101. The application was notified to Court submitted by the Commission shows Defendant 1 by registered post with that Oder-Plan GmbH was dissolved by acknowledgement of receipt, in accordance decision of the District Court on with the first sentence of Article 39 and 14 November 1996, in accordance with Article 79(1) of the Rules of Procedure. Paragraph 1 of the Löschgesetz (Cancella- Doubts as to whether proper service was tion Act) of 9 October 1934. 16 The com- effected exist inasmuch as the envelope containing the application was returned to the Registry bearing the inscription '... 15 — Cf. Lutter, Hommelhoff, GmbH-Gesetz, 15th ed. (Cologne Oder-Plan Architektur GmbH was dis- 2000), paragraph 60, section 9, paragraph 74, sec- solved on 15 November 1996 there is no tions 17, 6. 16 — This was repealed with effect from 1 January 1999. Its longer any director named Christian regulatory content is now contained in the newly-intro- Schlote.' The question of the capacity of duced subparagraphs 5 and 7 of Paragraph 60 of the GmbHG in conjunction with Paragraph 141a of the FGG. Defendant 1 to be a party to an action Cf. for the legal position after the Löschgesetz e.g. Rasner, in Rowedder, Fuhrmann et al., GfiibH-Komtnentar therefore arises. (Munich 1985), the appendix on Paragraph 60.

I - 7384

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

pany has not yet ceased to exist, however. office on 23 July 1999. By letter of Accordingly, Defendant 1 is capable of 26 October 1999 the date of the oral being party to an action. proceedings was set as 6 December 2000. This letter was also effectively served on Defendant 1 by being lodged at the post office.

(2) Further conditions for the procedure for judgment by default

104. The application was notified to Defendant 1 in accordance with the first sentence of Article 39 and Article 79(1) of the Rules of Procedure, by registered post with acknowledgement of receipt. This was properly effected at the address stated by the Commission. In the absence of indica- tions to the contrary in the Commercial 106. Judgment by default may be granted Register, it must be assumed that Defen- under Article 94(1) and (2) of the Rules of dant 1, as a company in liquidation, Procedure if no defence is lodged in the remains domiciled at the same address proper form within the time prescribed and and is represented by its former director the applicant's claims appear to be well as liquidator under Paragraphs 66 and 67 founded. The first condition is met: the of the GmbHG. The acknowledgement of defendant has not entered an appearance as receipt shows that the application was regards either the original application or received on 25 March 1999 and was thus the application for judgment by default. properly served. The fact that Defendant 1 returned the envelope containing the appli- cation to the Court Registry a few days later cannot invalidate service once effected. On balance, it must therefore be concluded that the application was prop- erly served and the action was thus prop- erly initiated.

105. In the absence of the appointment of any person authorised to accept service at the place where the Court has its seat, the 107. As regards whether the Commission's application for judgment by default was application is well founded, reference may also properly served under Articles 79, be made to the discussion above. The claim 40(1), 39, and 38(2) of the Rules of against Defendant 1 is as well founded as Procedure by being lodged at the post the claims against Defendants 2 and 3. The

I - 7385

OPINION OF MR ALBER — CASE C-77/99

application for judgment by default should VI — Costs therefore be granted.

109. Under the first sentence of Article 69 (2) of the Rules of Procedure, the unsuc- cessful party shall be ordered to pay the costs if they have been applied for in the 108. However, Defendant 1 may apply for successful party's pleadings. Since Defen- the judgment by default to be set aside dants 1, 2 and 3 have been unsuccessful under Article 94(4) of the Rules of Proce- and the Commission has applied for costs, dure, in which case the Court would then the defendants should be ordered to pay have to decide on the matter. costs.

V I I — Conclusion

110. On the basis of the above discussion, it is suggested that the Court rule as follows:

A — Judgment by default against Defendant 1

(1) Defendant 1 is ordered, as joint and several debtor with Defendants 2 and 3, to pay the European Commission EUR 54 510, plus interest in the sum of EUR 20 798.70 for the period from 1 January 1993 to 15 January 1999.

(2) Defendant 1 is ordered, as joint and several debtor with Defendants 2 and 3, to pay the European Commission interest on the principal of EUR 54 510 as

I - 7386

COMMISSION v ODER-PLAN ARCHITEKTUR AND OTHERS

from 16 January 1999, at the rate charged by the European Monetary Cooperation Fund for its euro transactions plus 2 percentage points.

B — Judgment against Defendants 2 and 3

(1) Defendants 2 and 3 are ordered with Defendant 1, as joint and several debtors, to pay the European Commission EUR 54 510, plus interest in the sum of EUR 20 798.70 for the period from 1 January 1993 to 15 January 1999.

(2) Defendants 2 and 3 are ordered with Defendant 1, as joint and several debtors, to pay the European Commission interest on the principal of EUR 54 510 as from 16 January 1999, at the rate charged by the European Monetary Cooperation Fund for its euro transactions plus 2 percentage points.

C — Costs

The defendants shall bear the costs of the action jointly and severally.

I - 7387

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-77/99 – Súdny dvor Európskej únie | AI Pravnik