← Späť na vyhľadávanie
Súdny dvor Európskej únie·25.5.2000

C-356/99

ECLI:EU:C:2000:291

Súd
Súdny dvor Európskej únie
IČS
61999CC0356

OPINION OF MR SAGGIO — CASE C-356/99

O P I N I O N OF ADVOCATE GENERAL SAGGIO delivered on 25 May 2000 *

1. By an action registered on 23 September Facts 1999 and served on the defendant on 6 October 1999, the European Commis- sion applied to the Court of Justice under Article 181 of the EC Treaty (now Arti- cle 238 EC), seeking an order that Hitesys SpA, a limited company incorporated according to Italian law (hereinafter 'Hitesys'), should repay to it the sum paid The contract entered into by the parties to Hitesys by the Commission by way of an advance for carrying out the research project provided for in a contract in that connection, which was unilaterally termi- nated by the Commission due to alleged non-performance by the defendant. Speci- 2. On 7 December 1993 the European fically, the Commission sought on the Economic Community, represented by the abovementioned ground payment to it by Commission, entered into contract JOU2- Hitesys of EUR 132 500 by way of capital CT93-0417 ('the contract') with a group of together with interest in the amount of companies comprising Irvin Elettronica Spa EUR 61 032.8 (calculated at the annual ('Irvin'), as 'coordinator', Zentrum fur rate of 8.25%) in respect of the period from Sonnenenergie- und Wasserstoff-Forschung 8 January 1994 to 8 September 1999, that ('ZSW') and the Department of Chemical is to say a total amount of EUR 194 443.7, Engineering and Applied Chemistry of the together with EUR 30.364 in respect of University of Aston (hereinafter 'Aston'). interest for each further day's delay until The subject-matter of the contract was the settlement. The Commission also sought an technological research and development order for costs against Hitesys. project described in the work programme in Annex I to the contract, entitled 'Advanced biomass pyrolysis for electricity production using electron beam irradia- tion', financed by Community contribu- tions within the 'Non-nuclear energy — JOULE II (1991-1994)' programme, * Original language: Italian. adopted by the Council of the European

I-9518

COMMISSION V HITESYS

Communities in its decision of 9 September coordinator, that is to say Irvin, who would 1991. 1 then transfer the appropriate shares to the other companies in the group (ZSW and Aston).

3. Under Article 2.1 of the contract, the abovementioned research project was to be completed within a period of 18 months from the first day of the month following signature of the contract. Since the contract was signed in December 1993 work com- 5. However, as regards the obligations menced on 1 January 1994, with the result assumed by the other parties, Article 1.4 that the research was to be completed by stipulated that the coordinator was to 30 June 1995. assume overall responsibility for liaison between the contracting undertakings and the Commission. Therefore it assumed, inter alia, the obligation concerning sub- mission of all documentation relating to the 4. The obligations assumed by the Com- contract. More specifically, as from the mission are described in Article 4 of the operative commencement date, Irvin had to contract. It is stated therein that the submit a progress report every six months Commission undertook to finance the describing the activity carried out and the research according to an agreed plan which results obtained by all the contractors. In provided for an advance payment of ECU addition a final technical report, in respect 200 000 and subsequent periodic pay- of the whole project, was to be submitted ments. Under Article 5 thereof, the pay- within two months of completion of the ments following the first payment were to project. Irvin also had to present the cost be made every 12 months after the opera- statements as mentioned above. In accor- tive commencement date, that is to say as dance with Article 5 of the contract, Irvin from 1 January 1994, on presentation by had to present a cost statement every 12 the coordinator of a financial statement of months after the operative commencement the costs actually incurred and a technical date and a final cost statement within three progress report. The Commission under- months of termination of the work. The took to make those payments within two other contractors had to submit their months of approval of the aforementioned reports to the coordinator who was to statement and report. Finally, the possibi- append them to his own. lity was provided for of withholding 10% of the total contribution, which was to be released after approval by the Commission of all the reports provided for in the contract, and, in particular, the final report on all costs incurred. Also under Article 4, all payments were to be made to the 6. Under Article 1.2. the annexes formed 1 — Council Decision 91/484/EEC of 9 September 1991 an integral part of the contract, in particu- (OJ 1991 L 257, p. 37). lar Annex I concerning the 'work pro-

I - 9519

OPINION OF MR SAGGIO — CASE C-356/99

gramme' and Annex II containing the Gen- on reasonable technical or economic eral Conditions. grounds.

Article 8.4 then provides that, in the event of termination by the Commission for non- Article 8 of the General Conditions, enti- performance by the other parties, the tled 'Termination of Contract', provides at Commission may require the reimburse- paragraph 1 thereof that the contractors, ment of amounts of its financial contribu- that is to say the entities carrying out the tion actually paid to such extent as may be research, may terminate the contract uni- 'fair' and 'reasonable' given the nature and laterally by giving two months notice to the amount of the work carried out and its Commission if they consider that no further usefulness in terms of the overall pro- purpose will be served by continuing the gramme. Such amount may then be work for technical reasons or due to a increased in respect of late payment, calcu- change in the exploitation potential of the lated at the rate applied by the European results. Under Article 8.2(a) of the General Monetary Cooperation Fund for operations Conditions, the Commission may terminate in ECU increased by two percentage points, the contract, for the same reasons and from the date of receipt of payment by the giving the same notice. In those circum- contractor. stances, if the Commission considers that the reasons for early termination put for- ward by the contractors are well founded, they have the right to reimbursement of costs incurred; while, if there is no agree- 7. Finally, Article 12 of the General Con- ment on this point, they shall have the right ditions contains the arbitration clause, to reimbursement only of the costs which confers on the Court of Justice sole 'accepted by the Commission'. jurisdiction in respect of any dispute con- cerning the contract, and under Article 11 thereof, Italian law is the applicable law of the contract.

Article 8.2(d) concerns termination of the contract for non-performance. It provides that, in the event of non-performance by one or more of the contractors, the Com- Conduct of the contractors mission may consider the contract to be terminated if, after giving one month's notice in writing requiring that the party or parties in default carry out the contrac- 8. Under the terms of the contract, the tually agreed research, the breach of con- Commission on 8 December 1993 ordered tract continues to exist and is not justified payment to Irvin of the amount of

I - 9520

COMMISSION V HITESYS

ECU 200 000 by way of an advance (see would seek repayment of the advance Annex 2 to the application). payment and negotiate directly with another company in the group concerning the transfer to it of the role of coordinator.

9. During 1994, only a few months after work under the contract had commenced, 11. Subsequently, by letter of 27 July 1995, Irvin was on the verge of bankruptcy due to (see Annex 6 to the application), the Com- severe financial difficulties, caused by the mission requested Hitesys to forward to it failure of the majority shareholder (Offi- the documents relating to the progress of cine Galileo) following the liquidation of the work as provided for in the contract, the public body EFIM. For that reason, it that is to say the second technical report, changed the structure of the company concerning progress for the period from during the same year and became Hitesys. June to December 1994, the final report That company superseded Irvin in the and the cost statement for the period from performance of the contract, with the result 1 January 1994 to 30 June 1995. In the that all the obligations imposed on Irvin by same letter the Commission reserved the the contract, including those relating to the right to seek reimbursement of the advance duties of coordinator, and in particular, the after examination of the aforementioned submission of technical and financial documents. reports, were assigned to Hitesys. For its part, the Commission accepted this amend- ment to the contract by letter of 19 August 1994 (see Annex 4 to the application).

12. Subsequently, by letter of 3 September 1996 (see Annex 7 to the application), the Commission stated that the failure to forward the documents requested and to reply to the various reminders demonstra- 10. However, Hitesys did not fulfil its ted that Hitesys had not carried out any obligations correctly. In fact, in a fax to work relating to its contractual obligations Hitesys dated 21 February 1995 (see and, that consequently, under Arti- Annex 5 to the application) the Commis- cle 8.2(d) of the General Conditions, it sion complained that the first progress considered the contract terminated and, report was highly unsatisfactory and, con- accordingly, requested the reimbursement sequently, asked Hitesys to suspend all of the advance payment made to Hitesys of work and contact the Commission in order ECU 132 500. That amount, as shown in to negotiate the transfer to another com- debit note No 96005952 issued by the pany in the group the tasks of coordinating Commission and appended to the applica- the project and administering the funds of tion (see Annex 8), corresponded to the the project. In the same fax, the Commis- difference between the contribution of sion also stated that, in the absence of a ECU 200 000 paid by the Commission reply by 15 March 1995, the Commission to the coordinator and the amounts of

I - 9521

OPINION OF MR SAGGIO — CASE C-356/99

ECU 55 000 and ECU 12 500 paid by the takings were endeavouring to complete the coordinator to the other two companies tasks which they had undertaken, and forming the group of contractors. presented the final report which was accepted by the Commission in February 1997.

13. In the absence of any response from Hitesys, the Commission sent it a request for payment on 17 July 1997 (see Annex 9 to the application). By a letter of 25 Sep- 15. By a letter of 6 February 1998 tember 1997 (see Annex 10 to the applica- (Annex 12 to the application) the Commis- tion), Hitesys informed the Commission sion confirmed to Hitesys that it was that it had been faced with serious technical seeking reimbursement, stating that the and financial problems inherited from Irvin contract had been terminated on 30 June and that this had prevented it from pro- 1995, and that the company had not gressing with the research forming the fulfilled its contractual obligations since it subject-matter of the contract, and that had not produced the requisite reports therefore 'it was impossible to obtain within the periods provided for in the satisfactory technical results'. In the same contract and, in addition, had not replied letter, Hitesys stated that its technical to the reminder letters and faxes. In con- experts were drawing up a technical-eco- sequence, the Commission stated that it nomic report on the results obtained by could not take into account any of the costs Irvin in order 'to determine whether there set out by Hitesys in the annex to its were any possibilities of continuing the abovementioned letter of 17 December research' and that this report would be sent 1997, with a view to a possible reduction to the Commission by 31 October 1997. In in the amount claimed. those circumstances, it asked that any action against it for the recovery of the advance payment be suspended.

16. By letter of 20 April 1998 (see Annex 13 to the application), Hitesys sent On 17 December 1997 Hitesys sent the to the Commission its technical report, the Commission 'a report on the costs incurred text of which was not however produced. by the company in connection with carry- ing out the programme' and expressed the hope that this document could 'demon- strate the basic honesty' with which it had tackled the programme despite the eco- nomic and financial difficulties. 17. By letter of 14 July 1998 (see Annex 14 to the application) the Commission con- firmed its claim for reimbursement, stating again that Hitesys had not complied with the periods contractually stipulated for the 14. Meanwhile, as the Commission states submission of reports on its research and in its action, the other contracting under- that the documentation sent with the letter

I - 9522

COMMISSION V HTTESYS

of 20 April 1998 did not enable the Com- mentioned Article 94 of the Rules of Pro- mission 'to amend the initial claim for cedure. reimbursement'.

Proceedings Substance

18. The Commission's action was regis- 20. Since as mentioned above, the defen- tered at the Court Registry on 23 Septem- dant did not defend this action, and since ber 1999. It was served on Hitesys on the necessary preconditions are satisfied, 6 October 1999 which, however, lodged no the proceedings are being conducted in defence. Thereupon, the Commission accordance with the special forms and with requested the Court, by letter of 10 January the special evidentiary rules proper to this 2000, to grant the form of order sought in type of case. In that connection it should be its application, in accordance with Arti- recalled that, under Article 94 of the Rules cle 94(1) of the Rules of Procedure. of Procedure of the Court, if the defendant does not defend an action, the applicant may apply to the Court for judgment by default and has the right to obtain a judgment in accordance with the form of order sought if the application in that regard 'appears well founded'. It is there- fore clear from the wording of this provi- Admissibility sion that the judicial appraisal of the adequacy of the evidence in regard to the merits of the claim in this type of proce- dure, in order to be able to uphold the 19. The action is admissible. On 6 October grounds invoked by the applicant, is gen- 1999 it was duly served by post on Hitesys, erally less rigorous than is required in an in accordance with Article 94(1) of the ordinary case, in which both parties are Rules of Procedure of the Court. In addi- present and state their own case; this is so tion, the applicant, by letter of 10 January because it is reasonable to assume that this 2000, requested the Court to grant the appraisal may be conducted on the basis of form of order sought by it. It follows that the documents without, as a general rule, the default on the part of Irvin-Hitesys there being any need to call for production must be deemed attributable to a choice of any document which may be considered made by that company and not to a failure relevant to the decision. The essentially to institute proceedings between the parties summary nature of this assessment is and that, consequently, the present pro- justified and offset by the right of the ceedings are conducted in the form of a unsuccessful defendant in default to apply judgment by default, as defined in afore- for the judgment by default to be set aside

I - 9523

OPINION OF MR SAGGIO — CASE C-356/99

since the (deferred) proceedings between receipt of the notice. A slightly different the parties at that stage allows that unsuc- rule is laid down in the General Conditions cessful party to exercise the rights of the for termination of the contract by the defence, including production of docu- contractors: they may terminate the con- ments deemed relevant to the decision, if tract unilaterally, on giving the Commis- applicable. sion two months notice, if they consider that for technical or economic reasons continuation of the research serves no further purpose. An analogous right is also afforded to the Commission under the contract. That being the case, it must be determined whether, in the present case, the claim for the repayment of the advance 'appears' to be well founded on the basis of the documentation produced by the plaintiff. I consider that this question must be answered in the affirmative, for the follow- ing reasons. The consequences of termination of the contract with regard to the possible pay- ment for research work carried out before termination are very different depending on whether termination occurs in the circum- 21. In its action the Commission contends stances referred to in Articles 8.1 and that Hitesys did not fulfil its obligations 8.2(a) of the General Conditions or in under the research contract and states that, Article 8.2(d) thereof. In the former case, in those circumstances, it took the initiative the contractors are entitled to reimburse- of terminating the contract and requesting ment of costs incurred if the Commission repayment of the advance. considers their reasons to be well founded and 'accepts' the costs stated by them. However, in the second case, that is to say if termination is due to non-performance by one or more contractors, the Commission can request repayment of amounts already It should be noted that the General Condi- paid to such extent as it deems it 'fair' and tions expressly give the Commission the 'reasonable'. It must therefore be ascer- right to terminate the contract unilaterally tained which of the two situations is if it considers that continuation of the applicable in this case. research serves no further purpose, or if one or more of the contractors fails to fulfil his obligations. That is provided for in Article 8.2(a) and (d) of the General Con- ditions under which, as has already been noted, in such a situation, the Commission can consider the contract terminated, after giving notice to the parties to fulfil their 22. In order to clarify this matter it is obligations, provided that the breach of necessary to refer to the correspondence contract still subsists one month after between Hitesys and the Commission. It

I - 9524

COMMISSION V HITESYS

will be recalled that the research work was 23. I do not believe that it can be seriously to have been completed by Irvin-Hitesys by doubted that the overall conduct of Irvin- 30 June 1995 and that the coordinator Hitesys, as is apparent from the aforemen- (Irvin-Hitesys) was under an obligation to tioned correspondence, essentially consti- submit a progress report to the Commis- tutes a more or less total breach of its sion every six months concerning progress obligations under the contract. As regards of the work and the results obtained with the submission of technical reports and regard to the activity carried out by all the statements, in particular, it appears that companies in the group, periodic cost Irvin-Hitesys sent the first report six statements corresponding to the progress months later than the date scheduled in of the works, the final cost statement and a the contract (that is apparent from the fax final technical report. from the Commission of 21 February 1995) and that on 27 July 1995, that is when the final date had already passed for completion of the research, it had not by then submitted the technical reports for the period from June to December 1994, or the final technical report, or the cost state- ments for the period from 1 January 1994 to 30 June 1995. In addition, Hitesys acknowledged in its letter of 17 July 1997 to the Commission that it could not It may be inferred from the correspondence progress with the research work provided exchanged between the Commission and for in the contract and was unable to reach Irvin-Hitesys that the company did not satisfactory results. Only in December fulfil the aforementioned obligations. That 1997, following further reminders from is clear in particular from: (a) the fax of the Commission, did Hitesys submit a 21 February 1995, in which the Commis- report on the costs incurred by the com- sion complained of the unsatisfactory pro- pany in carrying out the research pro- gress of the work and asked Irvin-Hitesys gramme and subsequently in its letter of to suspend all work; (b) the letter of 20 April 1998, the final technical report. 3 September 1996, in which the Commis- sion stated that it considered the contract to be terminated and sought reimbursement of the advance payment; (c) the letter of 17 July 1997 in which Irvin-Hitesys acknowledged that it could not progress with the research work in question and was unable to achieve satisfactory technical results; (d) the letter of 6 February 1998 in which the Commission confirmed that the contract had been terminated on 30 June 1995, and held the company 24. It should be added that, as the Com- responsible for not fulfilling its obligations mission observes, a further breach of con- since it had not produced the reports tractual obligations is constituted by the required by the contract within the periods fact that Hitesys did not ask for an laid down therein and did not reply to the extension to the contract in due time, as various reminders from the Commission. allowed by Article 1.7 of the General

I - 9525

OPINION OF MR SAGGIO — CASE C-356/99

Conditions, even though it was aware of determining the amount which it could the delays which were building up. claim back. It should be noted that, under Article 8.4 of the General Conditions, the Commission, in assessing whether to request the reimbursement of all or only part of the advance, must have regard 'to the nature and results of the work under- taken and its use' under the Community programmes.

25. Since these are the facts which appear from the documents, it was reasonable, it seems to me, for the Commission to consider Hitesys to be in breach of contract 26. The many instances of non-perfor- with all the consequences which that entails mance which are discernible from the under the General Conditions of the con- conduct of Irvin-Hitesys are clearly such tract. It is true that in its fax of 21 February as to justify termination of the contract. In 1995 the Commission did not invoke its action the Commission relies in that Article 8.2(d) of the General Conditions, connection on the allegedly mandatory which concerns termination by the Com- nature of the deadlines laid down in the mission for non-performance; nor, in that contract for submission of the various fax, does it mention Article 8.2(a) thereof, reports. It is inferred that mere failure to which allows termination of the contract observe these deadlines amounts to non- for technical reasons or if it is impossible to performance of the contract warranting exploit the results of the research, but unilateral termination under Article 8.2(d) purely and simply points out to Irvin- of the General Conditions. I cannot agree Hitesys that it should cease all activity in with this argument. Under Italian law, the relation to the research project. In the same period of time allowed for performance is way, it should be noted that in the letter of considered of the essence when the con- 27 July 1995, the Commission informed tracting parties specifically so agree or Hitesys unequivocally that it considered the when it is implicit in the nature and contract to have been terminated on purpose of the contract. 2In this case there 30 June 1995 and requested repayment of is no such indication in the contract, nor the advance. The fact that, in the same are there any factors to support the view letter, the Commission also asked Hitesys that those deadlines may be implied as to produce the technical and financial being of the essence of the contract because reports does not seem to me capable of of the type of activity. On this point the supporting a different conclusion, that is to Commission, in support of its interpreta- say that in this case the contract was tion of the contract, states that failure to terminated not for non-performance but observe the scheduled dates 'may contri- on one of the grounds set out in Article 8.1 bute to altering... the outcomes of the of the General Conditions: those reports are in fact documents to which the Com- mission was entitled to have regard in 2 — See Civil Cassation 2 December 1997, No 8233.

I - 9526

COMMISSION V HITESYS

collateral research and technological devel- way of an advance payment. In those opment activities... mentioned as related circumstances the subsequent submission and supplementary in the technical report by Hitesys of the technical and financial relating to the project in Annex I' to the reports could not constitute performance of contract. However, the reference in ques- the contract since once the contract is tion seems to me to be too imprecise to be terminated, it is treated as never having able to support the inference that the existed. deadlines are of the essence, a matter which requires to be reflected in the clear con- sensus of the contracting parties.

28. It remains to be determined whether the instances of non-performance as noted above can be regarded as justified by technical or economic reasons. In fact, 27. In the present case, however, the legal under Article 8.2(d) of the General Condi- basis for termination for non-performance tions, the Commission is not entitled to is to be found in the General Conditions terminate the contract unilaterally in such a which, in Article 8.2(d), contain, as has case. It does not seem to me that there are already been seen, a specific termination any such grounds in this case. The only clause, whose scope is in accordance with explanation provided by Hitesys to justify the terms of Article 1456 of the Italian its inertia was the financial crisis of the Civil Code. In fact, under that provision, group of companies to which Irvin where a contract contains a termination belonged, but plainly a ground of this kind clause, the contract is terminated automa- cannot be invoked, because it relates in tically where the contracting party who has broad terms to the conduct of the company observed the obligations notifies the concerned and cannot therefore result in defaulting party that he intends to invoke damage to the body awarding the contract that clause. Under Article 1458 of the Civil and the other parties involved in the Code, termination has retroactive effect as research project. between the parties, which means that the basis on which the transfer of assets occurred disappears, and the obligation arises for the parties to return amounts received. 3Therefore, in the present case, once the Commission availed itself of the right conferred on it under the aforemen- tioned clause (in the letter of 27 July 1995, 29. Similarly, account should also be taken confirmed by the subsequent letter of of the fact that, as the Commission points 3 September 1996), the contractual rela- out, the justifications relied on by Hitesys tionship with Hitesys came to an end, and in its letters of 25 September 1997 and at the same time, the obligation arose for 20 April 1998 (serious economic and finan- Hitesys to return the amount received by cial crisis following the liquidation of EFIM) are not only irrelevant, for the reasons given, but reveal a further instance 3 — See Civil Cassation, 12 March 1997, No 2209. of non-performance, since Hitesys was

I - 9527

OPINION OF MR SAGGIO — CASE C-356/99

required by Article 1.4 of the General In the present case the Commission is Conditions to notify the Commission with- seeking reimbursement of the total amount out delay of any event or circumstance paid by way of advance. On this point, it likely to compromise the performance of states in its application that the documen- the contract, yet only mentioned these tation supplied does not allow 'the activ- matters in correspondence as from Septem- ities carried out to be precisely identified, ber 1997. the time taken for implementation or their functional link with the Community pro- ject' to which this dispute refers. A similar point was made by the Commission in its letter to Hitesys of 14 July 1998 (see Annex 14 to the application).

30. In those circumstances, I do not believe I consider this negative position taken by that it is open to doubt that Hitesys did not the Commission to be reasonable, in fulfil its obligations under the contract and response to the many instances of non- that the unilateral termination of the con- performance by Hitesys identified and tract by the Commission is thus justified. examined above. The delay of several years Under the General Conditions, the Com- in submitting information and also its mission is entitled in such a case to inadequacy fully justifies the line taken by repayment of the advance, which forms the administration. Moreover, Hitesys itself the subject-matter of this dispute. acknowledges this inadequacy, in particular in its letter of 25 September 1997, in which it admits that, following the liquidation of EFIM, Irvin was compelled to conclude that it was 'impossible to achieve satisfac- tory technical results'.

It has already been noted that, under the first paragraph of Article 8.4 of the General 31. In light of all the foregoing considera- Conditions, the Commission may claim a tions, I propose that the claim for reimbur- reimbursement of a smaller sum than that sement by the Commission should be paid by way of advance and, in making an upheld in full. The sum to be paid by assessment in that regard, is to take into Hitesys to the Commission in repayment of account the nature and results of the work the advance must include interest accrued carried out, and of its use and coherence in on the sum paid by way of advance, regard to the Commission's programmes. calculated from 8 January 1994 (presumed

I - 9528

COMMISSION V HITESYS

date of receipt of the advance by Hitesys) to 32. Finally, since I propose that the Com- 8 September 1999, and is to be determined mission's claim should be upheld, Hitesys in accordance with the criteria laid down in should also be ordered to pay the costs the second paragraph of Article 8.4 of the under Article 69(2) of the Rules of Proce- General Conditions, together with interest dure, in accordance with the claim on that accruing until the actual date of payment. behalf by the administration.

Conclusions

33. I therefore propose that the Court should:

(1) order Hitesys SpA to pay to the Commission EUR 132 500 by way of capital, together with EUR 61 032.8 by way of interest accrued due at the rate of 8.25% for the period from 8 January 1994 to 8 September 1999, that is to say a total amount of EUR 194 443.7, as well as EUR 30.364 by way of interest for each extra day's delay until actual payment; such amount being in connection with the financing relating to contract JOU2-CT93-0417;

(2) order Hitesys SpA to pay the costs.

I - 9529

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-356/99 – Súdny dvor Európskej únie | AI Pravnik