← Späť na vyhľadávanie
Súdny dvor Európskej únie·12.7.2001

C-500/99

ECLI:EU:C:2001:415

Súd
Súdny dvor Európskej únie
IČS
61999CC0500

CONSERVE ITALIA v COMMISSION

OPINION OF ADVOCATE GENERAL ALBER delivered on 12 July 2001 »

I — Introduction for various investments may be recovered in its entirety or whether it must be reduced only by the amount to which the incorrect information relates.

II — Legal framework

1. The present appeal proceedings against a judgment of the Court of First Instance dismissing an application for annulment concern the contesting of a decision by 2. The provisions referred to in paragraphs which the Commission withdrew in 1996 7 to 11 below are of particular relevance to financial aid granted from the Guidance this case. The other legal provisions serve Section of the EAGGF in 1990. Together primarily to provide an overall view and a with the Italian authorities, the Commis- schematic classification. sion found that some of the payments for which aid had been granted had been made before the date on which the Commission received the application for aid and there- fore EC financial aid for that purpose could not, as a rule, be granted under the applicable provisions of Community law. 3. Conserve Italia's application for aid (in The applicant at first instance claimed that 1988) was made pursuant to Regulation the expenditure could, nevertheless, have (EEC) No 355/77. Regulation (EEC) been deemed to be eligible for assistance No 2515/85 specifies the information since it was incurred during the six months which the application must contain and preceding the date on which application the supporting documents which must be was made. The dispute also concerns enclosed therewith. Commission working whether, where the applicant provides document Vl/1216/86 stipulates in detail partially incorrect information, aid granted the conditions of eligibility for aid under Regulation No 355/77 and lays down other requirements and practices relating to the 1 — Original language: German. grant of such aid.

I - 869

OPINION OF MR ALBER — CASE C-500/99 P

4. Regulation No 355/77 was replaced by 7. Article 19(2) provides that: Regulation (EEC) No 4256/88 as part of the coordination of the different Structural Funds (EAGGF, European Regional Deve- lopment Fund and European Social Fund) carried out in 1988. However, the repeal of Regulation No 355/77 took effect only '... the Commission may decide ... to sus- with the entry into force of Regulation pend, reduce or discontinue aid from the (EEC) No 866/90 on 1 January 1990. Fund 3 ...

— if the project has not been carried out as planned, or 5. For its part, Regulation (EEC) No 4256/88 relates only to the EAGGF and must be read in conjunction with Regulation No 4253/88 which lays down general rules for the management of all — if certain of the conditions laid down structural funds. have not been fulfilled ...

(1) Council Regulation (EEC) No 355/77 of 15 February 1977 on common measures to improve the conditions under which agricultural products are processed and The Commission shall recover any sums the marketed2 payment of which was not or is no longer justified.'

(2) Commission Regulation (EEC) 6. Articles 1(3), 2 and 6(1)(a) of this No 2515/85 of 23 July 1985 on appli- regulation stipulate which projects may be cations for aid from the Guidance Section funded from the Guidance Section of the of the European Agricultural Guidance and EAGGF, and for what purpose. Guarantee Fund for projects to improve the

2 — OJ 1977 L 51, p. 1. 3 — Emphasis added.

I-870

CONSERVE ITALIA v COMMISSION

conditions under which agricultural and fish products are processed and marketed 4

B.1. Measures to be totally excluded 8. Under Article 1(1) of this regulation, applications for aid made by virtue of Regulation No 355/77 must contain the information specified in the annexes. The supporting documents specified therein must be attached to them. Under point 5.3 of the application to be completed by the applicant, a cross must be placed in the appropriate box to indicate whether the applicant undertakes not to start work on the project before the application reaches the Guidance Section of the EAGGF. 5. Work or measures begun before the According to the explanatory notes relating application was submitted, with the excep- to this point, projects begun before the tion of the following: application reaches the Commission cannot qualify for aid.

(a) ... (3) Working document VI/1216/86 on the determination of the maximum possible aid from the Guidance Section of the EAGGF under Council Regulation (EEC) No 355/77 (b) the purchase of machinery, equipment and building materials, including metal frames and prefabricated elements (order and supply), provided that their assembly, installation, incorporation, 9. The relevant passages of the working and on-site work in the case of building document read as follows: materials, did not take place before the application for aid was submitted;

'I. Measures to be excluded from calcu- lation of the minimum possible aid (c) the cost of purchasing equipment and machinery temporarily installed for test purposes before the application was 4 — OJ 1985 L 243. p. 1. submitted;

I - 871

OPINION OF MR ALBER — CASE C-500/99 P

(d) ... (4) Council Regulation (EEC) No 4253/88 of 19 December 1988 laying down provi- sions for implementing Regulation (EEC) No 2052/88 as regards coordination of the activities of the different Structural Funds between themselves and with the oper- Measures (a) and (b) are eligible while ations of the European Investment Bank measures under (c) and (d) are ineligible and the other existing financial instru- but do not render the project itself inad- ments 5 missible. Any other measure or work begun before the application concerning the pro- ject is submitted renders the project inad- missible.

10. Article 15(2) of this regulation provides that:

12. The costs of hiring equipment and investments financed by a leasing arrange- '2. Except as provided for in Article 33 ... ment. For example: hire costs for the use of expenditure may not be considered eligible tetra-pack machinery; projects financed for assistance from the Funds if incurred partially or totally by a leasing arrange- before the date on which the corresponding ment. application reaches the Commission.

These investments may be eligible, how- ever, if the hire-purchase agreement pro- vides that the beneficiary will become However, for the part-financing of projects owner of the equipment or measures and aid schemes, expenditure may 6 be involved within five years of the date of deemed to be eligible for assistance from the granting of the aid. This period is the Funds if incurred during the six months reduced to four years for projects financed preceding the date on which the Commis- from 1985 onwards. sion received the corresponding appli- cation.'' 7

5 — OJ 1988 L 374, p. 1. 6 — Emphasis added. ...' 7 — Emphasis added.

I-872

CONSERVE ITALU v COMMISSION

11. Article 24 bears the heading 'Reduc- (5) Council Regulation (EEC) No 4256/88 tion, suspension and cancellation 8 of of 19 December 1988 laying down provi- assistance'. It provides that: sions for implementing Regulation (EEC) No 2052/88 as regards the EAGGF Guid- ance Section 10

12. Article 10 of this regulation provides '1. If an operation or measure appears to that: justify only part of the assistance allocated, the Commission shall conduct a suitable examination of the case in the framework of the partnership, in particular requesting that the Member State or other authorities '1. The Council, acting on a proposal from designated by it to implement the operation the Commission in accordance with the submit their comments within a specified procedure laid down in Article 43 of the period of time. Treaty, shall by 31 December 1989 decide upon the forms of and the conditions for the Fund contribution to measures to improve the conditions under which agri- cultural [and] forestry ... products are pro- cessed and marketed ...

2. Following this examination, the Com- mission may reduce or suspend 9 assistance in respect of the operation or measure concerned if the examination reveals an 2. With effect from the date of entry into irregularity and in particular a significant force of the Council Decision referred to in change affecting the nature or conditions of paragraph 1, Council Regulation (EEC) the operation or measure for which the No 355/77 is hereby repealed. Commission's approval has not been sought.

3. Any sum received unduly and to be 3. By way of derogation from paragraph 2, recovered shall be repaid to the Commis- Articles 6 to 15 and 17 to 23 of Regulation sion. ...' (EEC) No 355/77 shall continue to apply to projects submitted by the date of entry into

8 — Emphasis added. 9 — Emphasis added. 10 —OJ 1988 L 374, p. 25.

I-873

OPINION OF MR ALBER — CASE C-500/99 P

force of the Council Decision referred to in aid from the EAGGF lodged by the paragraph 1 ... . Italian Government under Regulation No 355/77. That application had been submitted on behalf of Fedital SpA 4. ...' ("Fedital") by the Federazione Italiana dei Consorzi Agrari, an association of agricultural cooperatives which admin- 13. The Council adopted Regulation (EEC) istered a large proportion of the Italian No 866/90 of 29 March 1990 on improv- agri-foodstuffs sector until it was ing the processing and marketing con- wound up in May 1991. The aid for ditions for agricultural products 11 on the which the application was made was basis of Article 10(1) of Regulation intended to support a project for the No 4256/88. It repeals Regulation development, rationalisation and tech- No 355/77 pursuant to Article 10(2) cited nical modernisation of a Fedital estab- above. lishment in the municipality of Massa Lombarda.

14. The derogation provided for in the second subparagraph of Article 15(2) of Regulation No 4253/88 was discontinued with effect from 3 August 1993 by Council Regulation (EEC) No 2082/93 of 20 July 1993 amending Regulation (EEC) No 4253/88 laying down provisions for i m p l e m e n t i n g R e g u l a t i o n (EEC) No 2052/88 as regards coordination of the activities of the different Structural 22. While the application was being con- Funds between themselves and with the sidered Fedital sold its Massa Lom- operations of the European Investment barda establishment to Colombani Bank and the other existing financial Lusuco SpA, which the Federazione instruments.12 Italiana dei Consorzi Agrari also con- trolled, on 31 December 1989. The business name of the acquiring com- pany was then changed to "Massalom- I I I— Facts of the case barda Colombani SpA" (hereinafter "Massalombarda Colombani"). On 15. The following facts are evident from 18 October 1994 that company was the paragraphs of the judgment set out sold to Frabi SpA (which subsequently below: became Fincoserve SpA), the finance company of the group Conserve Italia Soc. Coop, ari (hereinafter "Conserve Italia"), the applicant. ...

'20. On 27 October 1988 the Commission received an application for the grant of

11 — OJ 1990 L 91, p. 1. 23. On 23 March 1990 the Commission 12 — OJ 1993 L 193, p. 20. asked Fedital to specify the nature, cost

I-874

CONSERVE ITALIA v COMMISSION

and starting and finishing dates of the 27. On 22 November 1991 the Italian work to be financed and to state authorities carried out a final inspec- whether it had been started before the tion of the work and approved it on the date on which the application was ground that it satisfied all the con- received by the C o m m i s s i o n ditions laid down in the decision to (27 October 1988). Furthermore, the grant aid. Commission asked for the balance sheet for 1988 and a copy of the contracts of sale relating to the various acquisitions made by the company.

28. Following inspections carried out jointly by the Italian authorities and the Commission in March 1993 and from 26 to 30 September 1994, the Commission found that certain pur- 24. On 17 April 1990 Massalombarda chases had been made and work car- Colombani replied that the work had ried out before the date on which the been started on 31 October 1988 and application for aid had been received completed by 30 June 1990 and and that, contrary to the copy of the attached copies of the contracts to its contract of sale relating to a Tetra Pak reply. One of them, signed on machine which had been forwarded to 22 December 1988, concerned the sale it on 17 April 1990 in response to its of a Tetra Pak packing machine. request for information of 23 March 1990, the original showed that the machine in question had already been installed at the purchaser's establish- ment, under a contract for hire, before the date on which the application was received. Furthermore, a large number 25. By decision of 29 June 1990 the Com- of delivery notes relating to machines mission granted Massalombarda acquired for the project bore a date Colombani aid amounting to ITL 2 before the date on which the appli- 002 932 326 in respect of an overall cation was received, whereas others investment of ITL 8 036 600 ("decision were missing. to grant aid").

29. By fax to the Commission of 3 November 1994 the Italian auth- 26. By decision of 18 November 1991 the orities stated that they were in favour Italian Government awarded Mass- of initiating a procedure for the dis- alombarda Colombani a grant of ITL continuance of the aid granted by the 2 008 000 000 in addition to the EAGGF in view of the serious irregu- financial aid from the EAGGF. larities that had been found.

I-875

OPINION OF MR ALBER — CASE C-500/99 P

30. On 22 May 1995 the Commission 33. The main grounds of that decision are informed Massalombarda Colombani reproduced below: and the Italian authorities of its inten- tion to initiate such a procedure and recover the amounts wrongly paid and asked them to submit their observa- tions on this. "...

Whereas the aid was granted having 31. Massalombarda Colombani submitted regard in particular to the technical its observations on 3 August and description of the planned work and 22 September 1995. It stated that it the period set aside to carry out the had in fact purchased the equipment work referred to in the file attached to before the Commission received the the application for aid and contained in application for aid, but that those the wording of the decision; purchases had been made on a trial basis. Moreover, it acknowledged that the project related to some work that was carried out before the application for aid was submitted. Following dis- cussions with officials of the competent services of the Commission on 19 January 1996, it submitted an additional statement on 27 February 1996. Whereas during [a] check it was found that certain definitive purchases had been effected and certain work carried out before the Commission received the application for aid from the benefici- ary, that is to say before 27 October 32. On 3 October 1996 the Commission 1988, and that was contrary to the adopted Decision C (96) 2760 discon- undertaking which the beneficiary tinuing the aid granted to the company entered into pursuant to the provision Massalombarda Colombani by Com- laid down on page 5 of Annex A1 to mission Decision C (90) 950/356 of Regulation ... No 2515/85 ..., in that 29 June 1990 on the grant of aid from application for aid; the EAGGF Guidance Section pursuant to Regulation No 355/77 in connection with EAGGF project No 90.41.IT.109.0 entitled "Potenziamento e aggiorna- mento tecnologico degli impianti di uno stabilimento ortofrutticolo in Whereas it was also found that a Massa Lombarda (Ravenna)" ("the contract of sale relating to a Tetra contested decision"). Pak packing machine had been falsified

I - 876

CONSERVE ITALIA v COMMISSION

to conceal the fact that it had already — in so far as may be necessary, annul been installed at the establishment any measure carried out in relation to before the date on which the appli- the contested decision, in particular the cation for aid was received; working document;

— order the Commission to pay the costs.

However, in response to a question put to it Whereas, in view of the information by the Court of First Instance, the applicant provided above, the irregularities stated that its application for the annul- found affect the conditions of the ment of any measure related to the con- project in question ...'Y tested decision, in particular the working document, was based on Article 184 of the EC Treaty (now Article 241 EC).

VI — Proceedings before the Court of First The Commission contended that the Court Instance and its judgment of First Instance should

16. On 23 December 1996 Conserve Italia brought an action against the Commis- — declare inadmissible the claim for sion's decision. annulment, in so far as may be necess- ary, of the working document;

It claimed that the Court of First Instance should — as for the remainder, dismiss the action as unfounded;

— annul the contested decision; — order the applicant to pay the costs.

I - 877

OPINION OF MR ALBER — CASE C-500/99 P

17. Conserve Italia based its action on the eligibility of the project is governed various infringements of rules of law relat- by that provision. ing to the application of the EC Treaty and in particular Article 15(2) of Regulation No 4253/88, paragraphs 5 and 12 of point B.1 of the working document, and Article 24(2) of Regulation No 4253/88. In the context of those pleas it complained in particular that the Commission failed to 44. The terms "expenditure" and "in- observe the principles of legality of pen- curred" in the second paragraph of alties, the protection of legitimate expec- that article ... suggest that account tations and proportionality and that it has must be taken of the date of payment misused its powers. Finally, the applicant for the purchases or work, or at least also put forward a plea alleging infringe- the date of invoicing. ment of essential procedural requirements on the ground that insufficient reasons were stated for the contested decision.

45. In this case all the payments were made after the date on which the application for aid was received by the Commis- sion (27 October 1988), all the invoices (1) Plea alleging infringement of bear a date after the commencement of Article 15(2) of Regulation No 4253/88 the operation, which the applicant gives as 1 October 1988 in its originat- ing application, and no delivery note was drawn up more than six months before that date. Consequently, all the 18. According to the contested judgment, expenditure at issue is eligible. Conserve Italia made the following sub- missions in that respect:

46. Furthermore, the beneficiary never '43.The applicant submits that the con- made any false declarations as to the dition contained in point 5.3 of the date of the purchases or the work. The "Explanatory notes for each heading" transactions carried out before the date in Annex A to Regulation No. on which the Commission received the 2515/85, whereby "projects begun application of aid (in particular the before the application reaches the contract for the hire of the Tetra Pak Commission cannot qualify for aid", machine) were not covered by defini- must be construed in the light of tive contracts but only by preliminary Article 15(2) of Regulation No 4253/88 relationships or contracts subject to a because the Commission decision on condition having suspensory effect.

I - 878

CONSERVE ITALIA v COMMISSION

47. Finally, the defendant failed to observe It follows that the instructions con- the principle of the protection of legit- tained in the aid application form, in imate expectations by discontinuing particular those relating to the under- the aid at issue on the basis of criteria taking which the applicant must enter other than those referred to in into when submitting his application, A r t i c l e 15(2) of R e g u l a t i o n examined in the light of point 5.3 of No 4253/88 ...'. the "Explanatory notes for each head- ing" in Annex A to that regulation ..., have binding force identical to that of the provisions of the regulation to which the models and explanatory notes are annexed (see, to this effect, 19. In that regard the Court of the First the judgment of the Court of First Instance stated: Instance in Joined Cases T-551/93, T-232/94, T-233/94 and T-234/94 Industrias Pesqueras Campos and Others v Commission [1996] ECR II-247, at paragraph 84). Moreover, '59.... Article 19(2) of... [R]egulation the company Massalombarda Colomb- [No 355/77] states that the Commis- ani entered, by its signature, into an sion may decide to suspend, reduce or express, solemn and unequivocal per- discontinue aid "if the project has not sonal undertaking not to start work on been carried out as planned" and "if the project before receipt of the appli- certain of the conditions laid down cation for aid by the EAGGF Guidance have not been fulfilled". Section. Since that undertaking was accepted by the Commission, it became part of the measure granting the aid and is imbued with the legal force of that measure. The condition relating to the point in time to which the under- 60. That provision does not state what taking refers, which, amongst other those conditions are but refers things, makes for legal certainty and expressly to the "financial or other helps to further equal treatment of conditions laid down for each project". applicants for aid, constitutes a "con- It follows that all the conditions laid dition laid down" within the meaning down for each project, irrespective of of Article 19(2) of Regulation whether they are technical or financial No 355/77 and failure to comply with or whether they lay down a time-limit, it therefore means that the project are covered by that expression. financed has not been carried out as planned.

61. Article 1(1) of Regulation No 2515/85 provides that "[a]pplicationsfor aid from the EAGGF Guidance Section ... 62. However, that undertaking — as pre- shall contain the information and scribed in the aid application form and documents specified in the Annexes." entered into by the beneficiary when he

I - 879

OPINION OF MR ALBER — CASE C-500/99 P

submits his application — does not 65. Even if it were necessary to accept the refer to a six-month period before the argument that the undertaking must be application is received. It is therefore interpreted in the light of Article 15(2) necessary to consider whether, as the of Regulation No 4253/88, the cri- applicant claims, the entry into force of terion to be taken into consideration Article 15(2) of Regulation No 4253/88 for determining the date from which on 1 January 1989 amended the under- the work may be started is that set out taking so as to allow expenditure to be in the first subparagraph of that provi- incurred during the six months preced- sion, unless otherwise indicated by the ing the date on which the Commission Commission. receives the application.

66. It is therefore necessary to ascertain the 63. It is clear from the first subparagraph date to be taken into consideration for of Article 15(2) of Regulation determining whether the work was No 4253/88 and the term "may" in started before receipt by the Commis- the second paragraph thereof that, as a sion of the application for aid, bearing general rule, expenditure is eligible in mind the undertaking entered into at only if incurred after the date on which the time the application for the aid at the Commission received the cor- issue was submitted. In particular, it is responding application. It is only in necessary to consider whether, as the exceptional cases that the Commission applicant claims, that date is the date has the power to consider expenditure on which the initial purchases or sub- eligible if it was incurred during the six sidised work were paid for or, possibly, months preceding the date on which the date on which they were invoiced. the Commission received the appli- cation.

67. The conclusion of contracts, even sub- ject to a condition having suspensory 64. By the decision to grant aid ... the effect, as part of a supported invest- Commission approved the application ment project has a decisive effect on the containing the personal undertaking manner in which it is carried out. Such not to start work on the project before contracts therefore constitute a meas- receipt of the application for aid, with- ure executing a project. Accordingly, it out specifying that it intended to use is their conclusion which determines the power provided for in the second the date on which work is started for paragraph of Article 15(2) of Regu- the purposes of the undertaking lation No 4253/88. entered into by the beneficiary.

I-880

CONSERVE ITALIA v COMMISSION

68. The applicant does not deny that the 71. Applicants for, and beneficiaries of, aid contracts relating to the machines are required to satisfy themselves that which are covered by the supported they are submitting to the Commission project were concluded before the date reliable information which is not liable on which the Commission received the to mislead it, otherwise the system of application for aid. controls and evidence set up to deter- mine whether the conditions for grant- ing aid are fulfilled cannot function properly. In the absence of reliable information projects which do not fulfil the conditions required could become the subject of aid. It follows that the obligation on applicants for, 69. Consequently, the beneficiary acted in and beneficiaries of, aid to provide breach of the undertaking, entered into information and act in good faith is in the application form, not to start inherent in the EAGGF aid system and work on the project before that date. It essential for its effective functioning. follows that the condition laid down in the decision to grant aid was not fulfilled and that the project was not carried out as planned.

72. The fact that, in this case, the infor- mation relating to the date on which work was started was concealed or presented in such a way as to mislead the Commission constitutes breach of that obligation and, consequently, of 70. The applicant's submission that the the applicable rules. relevant date is the date of payment, or at least the date of invoicing, cannot be upheld. It is doubtful that the beneficiary of the aid could have thought that no start had been made on the work on the project before the invoices had been drawn up or paid. 73. Accordingly, there is no valid ground Even assuming that the beneficiary had for charging the defendant with an no fraudulent intent, it must at the very infringement of Article 15(2) of Regu- least have had doubts as to its inter- lation No 4253/88. pretation of the undertaking not to start work on the project before the Commission had received the appli- cation for aid. In such circumstances it was for the beneficiary to inform itself of the significance of the undertaking required, not only so as not to commit 74. Since the complaint alleging breach of itself lightly but also to avoid any risk the principle of the protection of legit- of misleading the Commission. imate expectations is based on the

I - 881

OPINION OF MR ALBER — CASE C-500/99 P

premiss that Article 15(2) of Regu- it were not intentional, is at the very lation No 4253/88 has been infringed least the result of gross negligence. and the argument which the applicant derives from the alleged infringement of that provision is unfounded for the reasons set out above, it must also be rejected. 77. Contrary to the contention of the applicant, that irregularity could have affected the amount of the aid. The purpose of Regulation No 355/77, as is clear from its title, the fourth recital in — Falsification of a contract for the its preamble and the provisions under purchase of a packing machine Title II, is to improve the conditions under which agricultural products are processed and marketed. Improvement is determined by comparing the situ- ation which is intended to result from the measure financed with that which 75. The applicant acknowledges that the existed before the project was started. copy of the contract for the sale of a Since work on that project may not Tetra Pak packing machine forwarded start before the Commission receives to the Commission in response to a the application for aid, improvement request for information did not show, must be assessed in relation to the as the original did, that the machine in situation prior to that date. However, question had been installed at the it is possible that the definitive pur- beneficiary's establishment pursuant chase of a packaging machine, which to a contract for hire ... by the date has already been installed, under a on which the Commission received the contract for hire, at the establishment application for aid. of the undertaking receiving the aid, may not constitute such an improve- ment. The applicant has in any event failed to show that the purchase of the machine would bring about improve- ment in the conditions under which the 76. The beneficiary of the aid should have agricultural products in question are assumed that complete information processed and marketed. concerning the contract in question was essential to enable the Commission to exercise its powers correctly, par- ticularly as it had requested the rel- evant information. Consequently, the beneficiary should have forwarded a 78. It cannot be inferred from the working copy that was consistent with the document that the irregularity in ques- original of the contract in question (see tion has no effect. First, even assuming paragraph 71 above). The forwarding that paragraph 5(b) of point B.1 of the of a document that was not a true copy working document relates to machines of that contract constitutes a manifest of the type at issue, it applies, on any and serious irregularity which, even if view, only to machines which were not

I -882

CONSERVE ITALIA v COMMISSION

installed before the application for aid of Regulation No 4253/88 was not appli- was submitted, which is not the case cable in this case since the irregularities here. Second, paragraph 12 of point found did not affect the conditions of the B.1 of the working document provides operation. In the alternative, it contended that investments financed by leasing that Article 24(2) did not provide for the are eligible only where the contract possibility of discontinuing the aid, but stipulates that the beneficiary will only for the possibility of reducing or become the owner of the equipment suspending it. Consequently, the contested financed during the four years follow- decision was unlawful because it had no ing the date on which the aid is legal basis. granted. In this instance the contract for hire contained no clause stipulating a transfer of ownership within such a period.

21. In that regard the Court stated as follows in its judgment:

'90. As is clear from paragraphs 69 and 72 to 76 above, the beneficiary of the aid did not carry out the project as planned 80. It follows from all the foregoing that and certain of the conditions laid down the pleas alleging infringement of were not fulfilled. Article 19(2) of Article 15(2) of Regulation No 4253/88 Regulation No 355/77 allows the Com- and paragraphs 5 and 12 of point B.1 mission to suspend, reduce or discon- of the working document must be tinue aid which has been granted rejected.' beforehand where the project has not been carried out as planned or certain conditions laid down have not been fulfilled. Consequently, that provision constitutes a sufficient legal basis for the adoption of the contested decision.

(2) The legal basis for the discontinuance of the aid and the alleged infringement of Article 24(2) of Regulation No 4253/88 91. The infringements found by the Court at paragraphs 69 and 72 to 76 above constitute irregularities within the meaning of Article 24(2) of Regulation 20. Before the Court of First Instance No 4253/88. It follows that that provi- Conserve Italia submitted that Article 24(2) sion is also applicable in this case.

I - 883

OPINION OF MR ALBER — CASE C-500/99 P

92. Although the wording of Article 24(2) (3) Proportionality of the discontinuance does not expressly provide for the of the aid possibility for the Commission to adopt a measure to cancel assistance, the fact remains that it is entitled "Reduction, suspension and cancel- 22. Lastly, Conserve Italia submitted that lation of assistance". Where there is a the contested decision was disproportion- discrepancy between the wording of a ate. Since the irregularities complained of provision and the title thereof, both did not result in any discrepancy between must be construed in such a manner the project approved and the operation that all the terms employed serve a carried out and did not stem from any useful purpose. Having regard, first, to fraudulent intent or an effort to obtain that rule of interpretation and, second, financial assistance greater than the to the existence of another provision, amount of the investments made, they did also applicable to the aid in question, not justify the discontinuance of the aid at which provides for the possibility of issue. discontinuing aid from the EAGGF in certain circumstances (Article 19(2) of Regulation No 3 5 5 / 7 7 ; . . . ) , A r t i c l e 2 4 ( 2 ) of R e g u l a t i o n No 4253/88 must be construed as 23. In that regard the Court ruled as meaning that all the terms employed follows: by the legislature, in particular the word "cancellation" in the title of that provision, serve a useful purpose. That article must therefore be construed as meaning that it allows the Commission '101. It is settled case-law that by virtue of to discontinue aid from the EAGGF in that the principle of proportionality the event of an irregularity, in particu- laid down in the third paragraph of lar where a significant change to the Article 3b of the EC Treaty (now operation affecting its nature or the Article 5 EC) the measures adopted conditions governing its execution is by Community institutions must not involved, for which the Commission's exceed what is appropriate and prior approval has not been sought. necessary for attaining the objective pursued ...

102. The Court of Justice has held, fur- thermore, that where the evaluation of a complex situation is involved, 93. Since the existence of a legal basis which is the case with respect to the empowering the Commission to dis- common agricultural policy, the continue aid has been established, the Community institutions enjoy a wide complaints alleging infringement of the measure of discretion (see, to this principle of legality of penalties and a effect, in particular Case 29/77 misuse of powers cannot succeed.' Roquette [1977] ECR 1835, at para-

I-884

CONSERVE ITALIA v COMMISSION

graph 19). In reviewing the legality of beneficiaries of, aid of reliable infor- the exercise of such discretion, the mation which is not liable to mislead Court must confine itself to examin- the Commission is essential for the ing whether it discloses a manifest proper functioning of the system of error or constitutes a misuse of controls and evidence set up in order powers or whether the institution to determine, in particular, whether has clearly exceeded the limits of its the condition that work on the pro- discretion ... ject is not to be started before the Commission has received the appli- cation for aid has been fulfilled.

103. Furthermore, the Court of Justice has held that the infringement of obli- gations whose observance is of fun- damental importance to the proper functioning of a Community system may be penalised by forfeiture of a right conferred by Community legis- lation, such as entitlement to aid (see, 105. At the hearing the applicant acknowl- to this effect, Case C-104/94 Cereol edged, first, that the work had been Italia [1995] ECR I-2983, at para- started before the Commission had graph 24, and the case-law cited received the application for aid in the therein). sum of ITL 1 780 663 116 and, second, that the irregularity relating to the contract for the sale of the Tetra Pak packing machine involved a sum of ITL 470 000 000. A total of 104. As has been pointed out at paragraph ITL 2 250 663 116 was thus involved. 77 above, the purpose of Regulation Since the aid granted from the No 355/77 is to improve the con- EAGGF was ITL 2 002 932 326 and ditions under which agricultural the overall investment was ITL 8 036 products are processed and marketed, 600 000, the irregularities com- improvement being assessed by com- plained of therefore represent 112% paring the situation which was of the aid and 28% of the investment. intended to be the result of the The fact that the applicant failed to operation funded with that which comply with its undertaking not to existed before the commencement of start work on the project before the project. It also follows from the receipt of the application for aid by seventh recital in the preamble to the Commission, failed to inform the Regulation No 355/77 that the legis- Commission of this and, in response lature sought to lay down an effective to a request for information, for- control procedure in order to ensure warded a copy which was not con- that beneficiaries comply with the sistent with the original of the conditions laid down when the contract for the sale of a machine EAGGF aid is granted. It follows referred to in the subsidised project from paragraph 71 above that the constitutes a serious breach of funda- submission by the applicants for, and mental obligations.

I-885

OPINION OF MR ALBER — CASE C-500/99 P

106. Although the circumstances of this 109. Consequently, the applicant has case differ from those which the failed to show that the discontinu- Court of First Instance had to con- ance of the aid was disproportionate sider in the case which gave rise to the in the light of the infringements judgment in Industrias Pesqueras committed and the objective of the Campos and Others v Commission, legislation at issue.' cited at paragraph 61 above, it was reasonable for the Commission to take the view that any measure other than discontinuance of the aid might constitute an invitation to commit fraud. Beneficiaries might be tempted to supply false information or to conceal certain information in order to increase artificially the amount of V — Appeal and appraisal investment eligible for financing, so that greater financial aid from the Community could be obtained, their risk being confined to having that aid reduced only by the amount of the 24. In its appeal lodged on 22 December investment which did not fulfil a 1999 the appellant puts forward four condition governing the grant of the grounds of appeal: aid.

— infringement of the second indent of the s e c o n d s u b p a r a g r a p h of Article 19(2) of Regulation No 355/77; 107. Furthermore, the applicant's argu- ment that the discontinuance of the aid is disproportionate, on the ground that Fedital but not the applicant itself can be held responsible for the irregularities complained of, must be rejected since the applicant assumed — infringement of the second subpara- Fedital's rights and obligations fol- graph of Article 15(2) of Regulation lowing the successive purchases No 4253/88; referred to at ... above.

— misinterpretation of Article 24(2) of Regulation No 4253/88 and paragraph 5 of point B.1 of working document 108. ... V1/1216/86;

I - 886

CONSERVE ITALIA v COMMISSION

— breach of the principles of propor- is concluded specified as the date to be tionality and non-discrimination. taken into consideration.

27. Conserve Italia considers that taking (1) Ground of appeal alleging infringement account of the date of payment is also of the second indent of the second sub- compatible with point 5.3 of Annex A to paragraph of Article 19(2) of Regulation Regulation No 2515/85, which merely No 355/77 makes clear that projects begun before the application reaches the Commission are ineligible for aid. However, it does not specify when a project is to be regarded as having been started. (a) Submissions of the parties

28. In this context it complains of breach (i) Conserve Italia of the principle of the protection of legit- imate expectations. The point of reference for the appellant and the Commission was working document VI/1216/86 in accord- ance with which the acquisition of 25. The appellant denies that it failed to machinery is permitted before the date on fulfil certain of the conditions laid down. It which the Commission receives the appli- complains of the, in its view, incorrect cation. interpretation of the expression 'work is started'. The date to be taken into con- sideration is not the date on which the Tetra Pak machine was ordered or a contract was concluded, as the Court of First Instance concluded at paragraph 67 of the contested judgment, but rather the date 29. As regards the Tetra Pak machine, on which the goods and services were paid Conserve Italia acknowledges that it had for. been already been installed on its premises, pursuant to a contract for hire, by the time the application was submitted. However, it considers, firstly, that this is not ruled out by the Commission working document, and in particular is not incompatible with 26. The view of the Court of First Instance paragraph 12 of point B.1. Secondly, the is not supported by Commission working subsequent acquisition of ownership did in document VI/1216/86. At no point in this fact help improve the conditions under document is the date on which the contract which the agricultural products in question

I-887

OPINION OF MR ALBER — CASE C-500/99 P

are processed and marketed as the subsidy However, this is not relevant to the appeal conditions required, contrary to the proceedings since the Court can rule only assumption of the Court of First Instance on points of law. Conserve Italia has not at paragraph 77 of the contested decision. claimed that the Court committed an error in law in its appraisal of the evidence. Therefore, in that regard the appeal is in fact inadmissible.

(ii) Commission

33. Finally, working document VI/216/86 is, under paragraph 5 of point B.1 thereof, applicable only to machinery which has not 30. By contrast, the Commission considers been installed at the relevant establishment that the Court of First Instance's interpre- before the date on which the application tation of Article 19(2) of Regulation was received. Moreover, paragraph 12 of No 355/77 is correct. Work on a project point B.1 excludes hired machinery from starts when the contracts are concluded. If any form of aid. Consequently, in this the relevant date were the date on which regard too the contested decision is not the agreed work was paid for, the bene- vitiated by an error in law. ficiary of the subsidy could easily manipu- late that date simply by delaying payment despite the fact that it was due.

(b) Appraisal

31. As regards the Tetra Pak machine, it concurs with the Court of First Instance that the forwarding of a copy which was not consistent with the original of the 34. Under the first paragraph of Article 51 contract constitutes a serious irregularity. of the EC Statute of the Court of Justice, an For the management of financial resources appeal may be brought only on the grounds to function properly, it is essential that of a lack of competence of the Court of information submitted to it be complete First Instance, a breach of procedure before and correct. it which adversely affects the interests of the appellant and the infringement of Community law by the Court of First Instance.

32. Moreover, Conserve Italia failed to show that the acquisition of ownership of the machine has improved the conditions under which the agricultural products in 35. Conserve Italia is not raising a point of question are processed and marketed. law in claiming that the acquisition of

I-888

CONSERVE ITALIA v COMMISSION

ownership of the Tetra Pak machine has project before the date on which the indeed brought about an improvement in Commission received the application. the conditions under which the agricultural Therefore, the Court concluded that a products in question are processed and 'condition laid down' within the meaning marketed, contrary to the assumption of of Article 19(2) of Regulation No 355/77 the Court of First Instance. In particular, it had not been fulfilled. does not complain of any error in law in the appraisal of the evidence by the Court. Therefore, this plea must be dismissed as inadmissible.

38. The Court of First Instance established that the Commission received the appli- cation for aid on 27 October 1988. This was before 1 January 1990, the date on 36. An error in law in the interpretation of which Regulation No 866/90 came into Article 19(2) of Regulation No 355/77 force pursuant to Article 24 thereof. There- could have been committed if the Court fore, under Article 10(3) of Regulation of First Instance failed to determine cor- No 4256/88, Articles 6 to 15 and 17 to rectly the scope of the purported 'condition 23 of Regulation No 355/77 apply to the laid down', that is to say the time at which application. That is because Regulation work on the project started. No 866/90 is the legal act referred to in Article 10(1) of Regulation No 4256/88 on whose entry into force Regulation No 355/77 will be repealed pursuant to Article 10(2) of Regulation No 4256/88.

37. In its examination of the conditions relating to the application of Article 24 of Regulation No 4253/88 and its consider- ation of the extent to which an 'irregular- ity' with the meaning of that provision had been committed, the Court of First Instance 39. Articles 6 to 15 and 17 to 23 of found that work on a project starts when Regulation No 355/77, which are con- the contracts are concluded. 13 The con- sequently applicable to Conserve Italia's clusion of the contracts before 27 October application, lay down no provision con- 1988, the date on which the Commission cerning the date on which work on a received the application for the aid, 14 was project starts. However, Regulation incompatible with the undertaking, which No 2515/85 was adopted on the basis of Conserve Italia entered into in its appli- Article 13(5). It stipulates the information cation for aid, not to start work on the which must be provided when applying for aid from the EAGGF. In accordance with Annex A, Part One — Beneficiary (A 1), 13 — Paragraph 67 of the contested judgment. the applicant under point 5.3 must place a 14 — Sec paragraph 20 of the contested judgment. cross in the appropriate box to indicate

I - 889

OPINION OF MR ALBER — CASE C-500/99 P

whether it undertakes not to start work on by the Commission, the Court of First the project until the application is received Instance concluded that a 'condition laid by the Guidance Section of the EAGGF. down ' [Auflage] within the meaning of The 'Explanatory Notes and Instructions Article 19(2) of Regulation No 355/77 had for Completion of Applications' state that not been fulfilled. 15 projects begun before the application reaches the Commission cannot qualify for aid.

43. The term 'Auflage' is translated in the French version of the provision as 'con- 40. It is clear from those Explanatory ditions imposées', in English as 'conditions Notes that only measures undertaken after laid down', and in Spanish as 'condiciones the application has been received may be exigidas'. These language versions indicate funded. However, they say nothing about that the term 'Auflage' is to be understood the date from which work on a project as meaning the conditions laid down by the starts. decision to grant aid. However, the under- taking pursuant to point 5.3 of Annex A to Regulation No 2515/85 is not a condition which is expressed only at the time the aid is approved, but a condition which must already be fulfilled on the date when the application is submitted. Therefore, it is 4 1 . Furthermore, the Court of First more a 'Bedingung' [condition] than an Instance did not determine the relevant 'Auflage' [obligation attached] in the ter- date by reference to these provisions. minology of German administrative law. Instead, it stated as follows at paragraph 67 of its judgment: 'The conclusion of contracts, even subject to a condition having suspensory effect, as part of a supported investment project has a decisive effect on the manner in which it is carried out. Such contracts therefore constitute a 44. However, for the purposes of the measure executing a project. Accordingly, present proceedings the question may ulti- it is their conclusion which determines the mately be left open as to the extent to date on which work is started for the which the condition is an 'Auflage', as the purposes of the undertaking entered into by Court of First Instance contends, 16 or a the beneficiary.' 'Bedingung', which is the requirement for the grant of aid, since Conserve Italia does not contest the classification of the obli- gation as an 'Auflage'. Instead, the appeal

15 — See paragraphs 61 and 69 of the contested judgment, cited 42. Since Conserve Italia concluded above. contracts before receipt of the application 16 — Paragraph 61 of the contested judgment.

I - 890

CONSERVE ITALIA v COMMISSION

is directed at the finding that this 'Auflage' (order and supply 17), provided that or 'Bedingung' has not been fulfilled. What their assembly, installation, incorpor- is at issue is the fact that the date on which ation, and on-site work in the case of the contracts were concluded is taken as the building materials, did not take place date on which work was started. Fur- before the application for aid was thermore, the legal consequence is the submitted; same. Aid is not possible where there is failure to satisfy either an 'Auflage' or a 'Bedingung'.

45. As has already been stated, neither Regulation No 355/77 nor Regulation No 2515/85 contain any criterion for resolving the question raised in this case. It is therefore necessary to consider whether (d) ... or not Commission working document VI/1216/86 reveals anything in favour of the appellant.

Measures (a) and (b) are eligible while measures under (c) and (d) are ineligible 46. In accordance with paragraph 5 of but do not render the project itself inad- point B.1 of the working document (see missible. Any other measure or work begun point 9 above), work or measures begun before the application concerning the pro- before the application was submitted in ject is submitted renders the project inad- particular are to be excluded, with the missible.' exception of the following:

'... 47. Thus, paragraph 5 of point B. 1 specifi- cally takes account of order or supply. Therefore, it may be inferred that where the date of order and the date of delivery differ, the former must be taken as the reference point. However, an order is normally placed by concluding a contract. Con- (b) the purchase of machinery, equipment and building materials, including metal frames and prefabricated elements 17 — Emphasis added.

1-891

OPINION OF MR ALBER — CASE C-500/99 P

sequently, working document VI/1216/86 50. In accordance with paragraph 12 of clearly assumes that work on a project point B.l of the working document the starts when a contract placing orders is following are also to be ineligible for aid: signed and not when payment is made. 'The costs of hiring equipment and invest- ments financed by a leasing arrangement. For example: hire costs for the use of tetra-pack machinery; projects financed partially or totally by a leasing arrange- ment. These investments may be eligible, however, if the hire-purchase agreement provides that the beneficiary will become 48. This assessment is based on the above- owner of the equipment or measures mentioned consideration of the Court of involved within five years of the date of First Instance that the conclusion of a the granting of the aid. This period is contract as part of a supported investment reduced to four years for projects financed project — as cited above at paragraph from 1985 onwards.' 41 — 'has a decisive effect on the manner in which it is carried out. Such contracts therefore constitute a measure executing a project.'

49. This view is supported by the following consideration. If the date on which pay- ment was made were taken into consider- 51. According to the findings of fact of the ation, the applicant could determine inde- Court of First Instance, which cannot be pendently the date on which work on a reviewed in the appeal proceedings, the project was started. There would no longer conditions in paragraph 12 of point B.1 be any direct link between the investment were not fulfilled. The contract for hire, by and the aid from the EAGGF. The invest- virtue of which the Tetra Pak machine had ment would go ahead in any event. How- already been installed on the premises of ever, when the application is received by Conserve Italia before the application was the Commission the institution knows submitted, did not fulfil the conditions set which measures are envisaged and can take out in that provision. 18 Since this rule corrective action if necessary. It is not able constitutes a derogation, it must, according to do so if the contracts necessary for the to the settled case-law of the Court, 19 be implementation of the investment project interpreted strictly and therefore cannot have already been concluded and thus support the view of Conserve Italia. fundamental decisions on the investment to be made have already been taken. The effective use of aid requires that work on 18 — See paragraph 78 of the contested judgment. the project and the conclusion of contracts 19 — In respect of this principle of interpretation see, for be started only when the application for aid example, Case C-358/97 Commission v Ireland [2000] ECR I-6301, paragraph 52, and Case C-216/97 Gregg has been received by the EAGGF. [1999] ECR I-4947, paragraph 12.

1-892

CONSERVE ITALIA v COMMISSION

52. For these reasons, no legal objection disregard this provision. All the expendi- may be raised to the Court's finding that ture in question was incurred during the six the conclusion of contracts determines the months preceding the date on which the date on which work is started. Therefore, Commission received the application. the first plea must be rejected. Contrary to the Court's finding at para- graph 63 of the contested decision, this provision does not grant the Commission a measure of discretion as regards which expenditure is to be considered eligible. 'May' does not mean that the Commission 53. In light of the foregoing, the complaint has discretion and that its silence must be which Conserve Italia derives from the interpreted as refusal. Instead, the provi- protection of legitimate interests must like- sion enables undertakings to take swifter wise be dismissed. Paragraph 5 of point B.1 action and to adapt their facilities more of the working document confirms the view easily. that the date on which the contracts are concluded, and not the date of payments made, determines the date on which work is started on an investment project.

(ii) Commission

(2) Ground of appeal alleging infringement of the second subparagraph of Article 15(2) of Regulation No 4253/88 (see paragraph 14 above) 55. By contrast, the Commission observes that the Court of First Instance had already ruled out the application of Article 15 of Regulation No 4253/88 because the Com- (a) Submissions of the parties mission had not indicated that it intended to rely on this provision. Moreover, that derogation is intended merely to make it easier for the Member States to make the transition from the old to the new rules resulting from the reform of the Structural (i) Conserve Italia Funds. At any rate, this possible deroga- tion, which had existed since 1 January 1989, was removed from 3 August 1993 as a result of an amendment to Article 15 by Regulation No 2082/93. Furthermore, the Commission points out that — irrespec- 54. Conserve Italia complains that the tive of whether Article 15(2) of Regulation Court of First Instance was wrong to No 4253/88 can, in principle, be applied to

I - 893

OPINION OF MR ALBER — CASE C-SOO/99 P

the present case — Conserve Italia under- mission discretion and how far it is took, in its application for aid, not to begin required to fund expenditure incurred dur- the work until the application had been ing the six months preceding the date on received by the Commission. which the application was received.

(b) Appraisal 59. The wording of the provision initially indicates that the Commission does have discretion. The term 'may' normally grants the authority concerned discretion. If the legislature had intended to impose an 56. The second ground of appeal raises the obligation on the Commission to finance question as to whether or not the Court of all expenditure incurred in this period, it First Instance was right to rule out appli- would have opted for the expression 'must cation of Article 15(2) of Regulation be funded'. No 4253/88 to the aid applied for. The central issue is the meaning of the word 'may' in the second subparagraph under which expenditure may be deemed to be eligible for assistance if incurred during the six months preceding the date on which the application was submitted. 60. This interpretation is confirmed by the scheme of the provision. The first subpara- graph establishes the principle that expen- diture incurred before the date on which the application reaches the Commission cannot as a rule be funded. This reiterates a 57. The Court of First Instance dismissed principle which already applies under application of this provision on the ground Regulation No 355/77, read in conjunction that the Commission had not indicated that with Regulation No 2515/85, as discussed it intended to use the power granted to it. 20 above in connection with the consideration It is not evident that the judgment is of the first ground of appeal. Therefore, for vitiated by an error in law in this regard. these reasons too, the view put forward by Conserve Italia must be dismissed.

58. However, it is uncertain as to how far the second subparagraph of Article 15(2) of Regulation No 4253/88 grants the Com- 61. The Commission also points to the spirit and purpose of the provision which is closely linked to the history of the regu- 20 — Paragraph 64 of the judgment. lation. It is intended to make it easier for

I-894

CONSERVE ITALIA v COMMISSION

the Member States to make the transition discretion as regards the recognition of from the previous system of managing the expenditure incurred during the six months Structural Funds to the new system for preceding the date on which the application coordinating the activities of the different for aid was received. Furthermore, no Structural Funds as between themselves misuse of powers is evident. Therefore, and with the operations of the European the second ground of appeal must also be Investment Bank and the other existing rejected. financial instruments. Consequently, the second subparagraph of Article 15(2) con- stitutes a transitional provision. This is confirmed by the fact that it was repealed by Regulation No 2082/93 which entered into force on 3 August 1993. The pro- visional nature of the regulation also indi- cates that the legislature did not intend to (3) The ground of appeal alleging misinter- establish a circumscribed system of man- pretation of Article 24(2) of Regulation agement. No 4253/88 and paragraph 5 of point B.1 of working document VI/1216/86

62. Conserve Italia's claim that the purpose (a) Submissions of the parties of the provision is to enable the applicant undertakings to take swifter action is likewise unconvincing. This factor is already taken into account in that there is eligibility for aid from the time the Com- mission receives the application, not just (i) Conserve Italia when the applicant receives approval. The ability of undertakings to take swift action is thereby safeguarded, but at the same time the abovementioned ability of the Commis- sion to exert influence over the investment decisions set out in the application is also secured. This constitutes a sensible balance 64. Conserve Italia takes the view that of the interest in swift action on the one there is no legal basis for the contested hand, and in effective management of the decision of the Commission. The infringe- available aid, on the other. ments found concern only 28% of the financial assistance which was granted. The legal consequence provided for in Article 24(2) of Regulation No 4253/88 is a pro rata reduction of the aid, not the complete cancellation thereof. The wording of the provision provides only for a reduc- 63. Therefore, it must be held that the tion or suspension of the financial assist- second subparagraph of Article 15(2) of ance, but not complete cancellation. Con- Council Regulation No 4253/88 grants sequently, Conserve Italia considers that

I-895

OPINION OF MR ALBER — CASE C-500/99 P

the Court of First Instance interpreted the No 4253/88 must be read instead in the provision, at paragraph 92 of the contested light of Article 24(3). This provision stipu- judgment, contrary to the wording thereof. lates specifically when sums must be repaid to the Commission. 'Effet utile' could thus be given to the heading without circum- venting the wording of Article 24(2).

65. Furthermore, Article 24 cannot be interpreted with reference to Article 19 of Regulation No 355/77, as the Court of First Instance maintains. Firstly, Article 24, as a 68. Furthermore, Conserve Italia com- more general rule, takes precedence. Sec- plains of a breach of the principle of ondly, a legal rule which had already been equality. If all infringements of the provi- repealed by the time the contested decision sion relating to aid could be penalised by was adopted cannot be relied on to inter- the complete withdrawal of a benefit, even pret a provision in force. At paragraph 90 if, as in the present case, only 28% of the of the contested judgment the Court of First financial assistance were affected by irregu- Instance wrongly concluded t h a t larities, such a case would be treated in Article 19(2) of Regulation No 355/77 is exactly the same way as cases in which the a sufficient legal basis for the cancellation irregularities affected 100% of the aid. In of the financial assistance. This is erroneous that regard the findings at paragraph 93 of in law since at the time the contested the judgment are erroneous in law. decision was adopted, that is to say 3 October 1996, Article 19 was no longer in force, and had not been since 1993.

(ii) Commission

66. Moreover, the 'effet utile' referred to at paragraph 92 of the judgment likewise provides no argument to support the view of the Court of First Instance. The appli- 69. The Commission, on the other hand, cation of that principle of interpretation concurs with the Court of First Instance's does not justify the interpretation of a rule interpretation of Article 24(2) of Regu- contrary to its wording. lation No 4253/88 as a sufficient legal basis for the recovery of the assistance. Firstly, the provision must be read in the light of its heading and the full effectiveness of each expression used must be safeguarded. Sec- ondly, Article 19(2) of Regulation No 355/77, which is also applicable to the 67. In the view of Conserve Italia, the facts, confirms that it is possible to recover heading of Article 24 of Regulation assistance which has been granted.

I-896

CONSERVE ITALIA v COMMISSION

70. Even if a literal interpretation is placed undertakings acting in bad faith to commit on Article 24(2) of Regulation No 4253/88, abuse. If they had to fear only a reduction this provision does empower the Commis- proportionate to the irregularities found, sion to effect recovery. That is because they would still retain the remainder of the there can also be a reduction of 100% and assistance. that amounts to a cancellation.

71. By adopting Article 24(2) of Regulation 75. The Court of First Instance had no No 4253/88, the legislature merely comment to make on the criteria used to intended to replace its forerunner, not in determine the level of the reduction, that is an attempt to restrict its importance but the say on the alleged infringement of rather to extend its effectiveness (effet paragraph 5(c) of point B.1 of the working utile). document. In that regard Article 24(2) of Regulation No 4253/88 grants the Com- mission a measure of discretion. The Com- mission has to consider measures in full knowledge of all the circumstances of the specific case. 72. Furthermore, the interpretation by the Court of First Instance is consistent with the spirit of the provision. It is intended to facilitate proper, effective, and non-dis- criminatory management of the financial resources of the Structural Funds. (b) Appraisal

73. Conserve Italia's reference to Article 24(3) of Regulation No 4253/88 is devoid of any basis. The provision governs 76. By its third ground of appeal, the only the consequence of applying appellant correctly points out that the Article 24(2). The recovery of sums wording of Article 24(2) of Regulation received unduly is the logical consequence No 4253/88, which forms the legal basis of a reduction or suspension carried out for the contested decision of the Commis- under Article 24(2). sion, makes no mention of cancellation of Community assistance. However, the Court of First Instance inferred this power from the heading of Article 24 and a comparison with Article 19(2) of Regu- lation No 355/77, the forerunner of 74. As regards the proposed pro rata Article 24. It is necessary to consider reduction of the assistance, the Commis- whether or not this interpretation is vitiated sion states that this would encourage by an error in law.

I-897

OPINION OF MR ALBER — CASE C-500/99 P

77. Firstly, as regards the objection that the longer applicable by the time the contested Court of First Instance was wrong to decision was adopted on 3 October 1996. conclude that Article 19(2) of Regulation Since Regulation No 4256/88, as amended No 355/77 is applicable, it must be noted by Regulation No 2085/93, contains no that this provision could in fact no longer legal basis for the recovery of aid paid out, form a legal basis for the contested decision it was necessary to rely on the horizontal of the Commission. Under Article 10(2) of rules in Regulation No 4253/88, as Regulation No 4256/88, Regulation amended by Regulation No 2082/93. This No 355/77 was repealed on 1 January explains why the contested decision cor- 1990. It is true that, under Article 10(3), rectly cites only Article 24 of Regulation Articles 6 to 15 and 17 to 23 of Regulation No 4253/88 as a legal basis. No 355/77 continued to apply to projects submitted by 1 January 1990. To that extent, the application for aid which the applicant submitted on 27 October 1988 was also still subject to these provisions, as has already been discussed as part of the consideration of the first ground of appeal.

79. However, the Court's mistake with regard to the scope of Article 19 of Regulation No 355/77 does not establish an error in law which would justify the 78. However, the decision to recover the annulment of the contested decision. The aid was adopted on 3 October 1996. Court of First Instance also concludes that Regulation No 4256/88 had been amended Article 24 of Regulation No 4253/88 forms by Regulation (EEC) No 2085/93 21 since the legal basis for the contested decision. It 3 August 1993. The transitional rule in relied on Article 19 of Regulation Article 10 of Regulation No 4256/88 was No 355/77 only in its interpretation of not extended further. The version of Article 24. However, it is still necessary to Article 10 in force with effect from consider whether that interpretation is 3 August 1993 no longer contains a provi- possibly erroneous in law. sion concerning projects for which an application was submitted before 1 January 1990. It merely lays down a further rule concerning the release of sums for projects which were decided on before 1 January 1989. That does not include the investment project of Conserve Italia approved by decision of 29 June 1990. Article 19 of Regulation No 355/77 was no 80. As the Court of First Instance held, there is an apparent contradiction between 21 — Council Regulation (EEC) No 2085/93 of 20 July 1993 the heading of Article 24 of Regulation amending Regulation (EEC) No 4256/88 laying down No 4253/88 and Article 24(2) thereof. provisions for implementing Regulation (EEC) No 2052/88 as regards the European Agricultural Guidance and Whereas the heading speaks of 'Reduction, Guarantee Fund (EAGGF) Guidance Section (OJ 1993 L 193, p. 44). Suspension and Cancellation', Article 24(2)

I-898

CONSERVE ITALIA v COMMISSION

empowers the authority merely to reduce or ing an advantage to be withdrawn. It must suspend assistance in respect of the oper- therefore be held that the term 'cancella- ation or measure concerned. tion' in the heading of Article 24 is not to be read primarily in conjunction with the obligation to repay laid down in Article 24(3) but is at most relevant to this provision in so far as it also covers, according to its wording, repayment of the entire assistance granted. 81. The Commission proposes that this divergence between the wording of the heading and of Article 24(2) be overcome by considering that there can be a reduction of 100% and that would amount to a cancellation. That view has the advantage 83. In the context of the scheme of that it respects the wording of Article 24(2) Article 24 it should be noted that and nevertheless permits cancellation as a Article 24(1) does indeed cover the possi- result. However, it is unsatisfactory in so bility of the complete cessation of the far as it fails to answer the question why assistance. It states that the Commission the heading refers to the term 'cancellation' must conduct an examination if an oper- separately from the term 'reduction'. If the ation or measure 'appears to justify neither latter were the more comprehensive term part nor the whole of the assistance allo- and thus also covered a 'cancellation', then cated'. This indicates that the consequences it would have been logical not only to omit of the examination referred to in the term 'cancellation' not only from Article 24(2) can also cover the entire Article 24(2) but also from the heading. amount of assistance concerned.

84. The following Article 24(3) is couched in general terms. It speaks only of the 82. Conserve Italia considers that the term obligation to repay any sum received 'cancellation' used in the heading must be unduly to the Commission. According to read in the context of Article 24(3). How- the wording thereof, this repayment is not ever, that provision governs only the restricted to a partial sum. The wording of recovery of sums unduly advanced. This is the provision also covers repayment of the also the consequence of a cancellation, as entire sum allocated. the Commission correctly points out, but it is not tantamount to an act of cancellation per se which goes hand in hand with the withdrawal of the administrative decision granting an advantage. Such withdrawal is tantamount to a cancellation or a reduction 85. The scheme of the provision set out and forms the basis for the obligation to above indicates that Article 24(2) must be repay laid down in Article 24(3). However, regarded as the legal basis for any recovery an obligation to repay is not a basis for by the Commission. This provision would enabling an administrative decision grant- be deprived of its 'effectiveness' (effet utile)

I-899

OPINION OF MR ALBER — CASE C-500/99 P

if it did not also cover the cancellation of a taken as a basis, then only 28% of the subsidy. Article 24(1) of the provision subsidy allocated would be affected and grants the Commission the right to conduct 72% of the monies which the Commission examinations where neither part nor the paid to Conserve Italia would be retained whole of the aid appears justified. It by that undertaking. However, the risk of involves the Member State in clarifying losing the entire subsidy as a consequence the situation by requiring it to submit of providing false data and documents is an comments. As the representative of the important deterrent in managing EAGGF Commission correctly emphasised at the resources. It contributes to the effective hearing, this is merely a procedural safe- management of public aid. As the Court guard which offers the Member State and noted in the contested judgment, in manag- the undertakings concerned an opportunity ing the Funds the Commission is reliant on to submit comments on the Commission's the applicants providing correct infor- findings. Article 24(2) deals with the poss- mation on the planned investments. ible measures the Commission may take on the basis of the results of the examination carried out. It would not be logical to be able to extend the examination provided for in Article 24(1) to the legality of the assistance as a whole but to seek to limit to part of the assistance the possible measures taken on the basis of the results of the examination. 22 Finally, Article 24(3) imposes a complementary obligation to repay on the beneficiary of the subsidy affected by the penalty, which can, nat- urally, cover the entire assistance. 87. This interpretation of Article 24(2) as a comprehensive rule for penalties resulting from irregularities found in the use of aid is supported by a comparison of the fore- runner of that provision. Article 19(2) of Regulation No 355/77 which, as stated above, was applicable to cases such as the present until October 1993, empowered the Commission to carry out checks (first paragraph) and to suspend, reduce or 86. If the scope of Article 24(2) were discontinue aid from the EAGGF (second limited to cases of reduction (in particular paragraph) and provided that the Commis- a pro rata reduction corresponding to the sion was to recover any sums the payment irregularities found, as proposed by Con- of which was not or was no longer justified serve Italia) and of suspension, the recipient (paragraph 3). Therefore, that provision of a subsidy who had acted unlawfully had the same structure as Article 24. It would still retain the part of the subsidy certainly made express provision for the which was not affected by the irregularity. possibility of cancelling the assistance com- If the figures given by Conserve Italia are pletely. Nevertheless, there are no indi- cations that the legislature intended to limit the Commission's power by the new word- 22 — See, to this effect, also Case T-143/99 Hortiplant v Commission [2001] ECR 11-1665, paragraph 39. ing in Article 24 of Regulation No 4253/88.

I - 900

CONSERVE ITALIA v COMMISSION

88. Finally, it should also be noted that the found in its judgment, the beneficiary had Commission was also able, on the basis of provided the Commission with incorrect general legal principles alone, to withdraw information as to the date on which the an administrative measure granting unlaw- Tetra Pak machine was installed on its ful advantage such as the grant of assist- premises. In that respect at least Conserve ance to Conserve Italia by the decision of Italia has no legitimate interests which 29 June 1990. This was done by the preclude recovery of the aid. adoption of the decision of 3 October 1996.

90. These considerations confirm the inter- pretation placed on Article 24(2) of Regu- lation No 4253/88 above as a sufficient basis for the adoption of the decision of 3 October 1996. Consequently, this ground of appeal must also be rejected. 89. As early as in its judgment in Algera and Others the Court ruled that any administrative measure granting unlawful advantage may in principle be withdrawn ex tunc. 23The authorities must certainly comply with the principle of legal cer- tainty 24 and in particular the principle of (4) The ground of appeal alleging infringe- the protection of legitimate expectations. 25 ment of the principles of proportionality As part of the balancing of interests which and non-discrimination has to be carried out by the institution concerned, regard must also be had to whether the beneficiary was aware of its unlawfulness 26 or whether he provided (a) Submissions of the parties incomplete or incorrect information.27 By virtue of this case-law the Commission had the power to recover the aid from Conserve Italia since, as the Court of First Instance

(i) Conserve Italia 23 — Joined Cases 7/56 and 3/57 to 7/57 Algeraand Others v Common Assembly [1957] ECR 39. Settled case-law, see Case C-90/95 P de Compte v Parliament [1997] ECR I-1999, paragraph 35, and the references contained therein; Case T-227/95 AssiDtmiän Kraft Products and Others v Commission |1997| ECR III 185, paragraph 90, and the references contained therein. 24 — Joined Cases 42/59 and 49/59 SNUPAT v High Authority 91. Conserve Italia complains firstly of a [1962] ECR 53; Case 14/61 Hoogovens v High Authority [1962] ECR 253. breach of the principle of proportionality. 25 —Case 111/63 Lemmerz-Werke v High Authority [1965] The infringements found (the date on ECR 677; de Compte v Parliament, cited in footnote 23, paragraph 35. which work began and the delivery of the 26 — Case 14/81 Alpha Steel v Commission [1982]ECR 749, Tetra Pak machine) are relatively insignifi- paragraph 10. 27 — SNUPAT v High Authority, cited in footnote 24; de cant and do not justify the withdrawal of Compte v Parliament, cited in footnote 23, paragraph 37. the entire assistance. Furthermore, they are

I -901

OPINION OF MR ALBER — CASE C-500/99 P

less serious than in other cases in which the They resulted in an artificial inflation of the Commission has recovered aid. Moreover, investments eligible for aid. Furthermore, the Commission has no measure of dis- the Commission has to take extensive cretion. Contrary to the assumption of the account of agricultural policy when taking Court of First Instance at paragraph 102 of decisions both to allocate and to recover the contested decision, Conserve Italia aid. Therefore, it enjoyed a wide measure considers that the present situation is not of discretion. The complete recovery of the comparable with the complex cases in subsidy was the only measure which which the case-law grants the Commission enabled the desired objective to be attained. a wide measure of discretion in formulating agricultural policy. What is involved is merely the proper application of rules which result from previous political decisions.

(b) Appraisal 92. Furthermore, the judgment in Cereol Italia28 cited at paragraph 103 of the contested judgment cannot, in the view of Conserve Italia, be taken as a precedent in respect of the present case. It relates to the application of a regulation which made express provision for the imposition of penalties. This was precisely not so in the case of Regulation No 4253/88. 94. In the contested judgment the Court of First Instance correctly rejected the com- plaint alleging that the recovery of the aid was disproportionate. The risk of losing, where irregularities are found, the entire aid, and not merely the part affected by the (ii) Commission irregularity on a pro rata basis, has a deterrent effect. This is not only an appro- priate means of safeguarding the effective management of EAGGF resources, but is also necessary and proportionate. As the Commission correctly observes, if a bene- ficiary of a subsidy who acts unlawfully merely ran the risk of losing the aid only in 93. By contrast, the Commission points to so far as it was based on his misconduct, the seriousness of the infringements found. that would constitute encouragement to commit abuse. Therefore, there is no less stringent means of achieving the desired 28 — Case C-104/94 Cereol Italia v Azienda Agricola Castello effective management of aid. [1995] ECR I-2983.

I-902

CONSERVE ITALIA v COMMISSION

95. In so far as Conserve Italia complains crimination where a case in which 28% of that the Court of First Instance was wrong the investment is affected by incorrect to rely on Cereol Italia, 29 it should be information is treated in exactly the same noted that in that judgment the Court of way as a case in which 100% is affected. Justice also considered the proportionality The risk of losing the aid in its entirety is an of a Commission measure, that is to say the important instrument in the effective man- compatibility of the adoption of a rule agement of resources. Therefore, the fourth relating to penalties pursuant to powers ground of appeal must also be rejected. granted in a Council regulation. It can therefore be held that the present case relates to a comparable situation. Here too the compatibility of a Commission measure — the recovery of aid — is being considered against the principle of propor- tionality. The Court of First Instance was therefore right to rely on this case-law in its judgment. 98. Consequently, it must be held that judgment of the Court of First Instance is not vitiated by any error in law. The appeal must be dismissed.

96. In light of the above findings, in the present case it is also irrelevant as to how far Regulation No 4253/88 grants the Commission a wide measure of discretion since a potentially complex situation has to be evaluated and political decisions have to be taken. The measure involving the com- VI — Costs plete recovery of the aid is proportionate and therefore it can also be held that the Commission did not exceed the powers granted to it.

99. Under Article 122 of the Rules of Procedure, read in conjunction with Articles 118 and 69(2) thereof, the unsuc- cessful party is be ordered to pay the costs 97. In light of the considerations relating to if they have been applied for in the success- proportionality, there is likewise no dis- ful party's pleadings. Since the Commission applied for Conserve Italia to be ordered to pay the costs of the proceedings and the 29 — Cereol Italiav Azienda Agricola Castello, cited in footnote appeal must be dismissed, Conserve Italia 28, paragraph 24. must bear the costs of the proceedings.

I-903

OPINION OF MR ALBER — CASE C-500/99 P

V I I— Conclusion

100. In light of the foregoing, I propose that the Court should rule as follows:

(1) The appeal is dismissed.

(2) Conserve Italia shall bear the costs of the proceedings.

I-904

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-500/99 – Súdny dvor Európskej únie | AI Pravnik