← Späť na vyhľadávanie
Súdny dvor Európskej únie·27.11.2003

C-181/02

ECLI:EU:C:2003:645

Súd
Súdny dvor Európskej únie
IČS
62002CC0181

COMMISSION v KVAERNER WARNOW WERFT

OPINION OF ADVOCATE GENERAL LÉGER delivered on 27 November 2003 1

1. By two decisions adopted in 1999 and therefore held that the fact that KWW 2000, 2the Commission of the European produces more than 85 000 cgt per annum Communities requested that the Federal could not cause it to lose the aid, provided Republic of Germany recover part of the the shipyard complied with the technical State aid which it had paid to the shipyard restrictions imposed by the decisions Kvaerner Warnow Werft GmbH (herein- approving the aid. after 'KWW'). The Commission took the view that, for two consecutive years, KWW's actual production had exceeded the capacity restriction imposed in the decisions authorising the aid, namely 3. The Commission now asks that this 85 000 compensated gross tonnes (herein- judgment be set aside. It submits that the after 'cgt') per annum. findings of the Court of First Instance are based on an incorrect reading of the decisions authorising the aid.

2. On the application of KWW, the Court I — Legal background of First Instance of the European Commu- nities annulled the contested decisions on the ground that the capacity restriction did 4. Article 92(3)(e) of the EC Treaty (now, not apply to KWW's actual production but after amendment, Article 87(3)(e) EC) to the technical capacity of the shipyard provides: installations. 3The Court of First Instance

1 — Original language: French. 2 — Commission Decision 1999/675/EC of 8 July 1999 on State 'The following may be considered to be aid implemented by Germany in favour of Kvaerner Warnow Werft GmbH (OJ 1999 L 274, p. 23) and compatible with the common market: Commission Decision 2000/336/EC of 15 February 2000 on State aid implemented by Germany in favour of Kvaerner Warnow Werft GmbH (OJ 2000 L 120, p. 12), hereinafter collectively the 'recovery decisions' or the 'contested decisions'. 3 — Judgment of 28 February 2002 in Joined Cases T-227/99 a n d T-134/00 Kvaerner Warnow Werft v Commission [2002] ECR II-1205, hereinafter 'the contested judgment'.

I - 5705

OPINION OF MR LÉGER — CASE C-181/02 P

(e) such other categories of aid as may be 7. The preamble to Directive 92/68 states, specified by decision of the Council in this regard: acting by a qualified majority on a proposal from the Commission.'

'... the shipbuilding industry is important for the structural development of the coastal region of the territories of the 5. On the basis of this provision, the former German Democratic Republic; Council adopted, on 21 December 1990, Directive 90/684/EEC on aid to shipbuild- ing. 4 This provides for the possibility, subject to certain rules, of granting State aid to shipbuilding undertakings for oper- ating, investment, closure, and research and development. ... the shipbuilding industry, as it existed in those territories at the time of their incor- poration into the Community, requires urgent and comprehensive restructuring in order to become competitive ...;

6. Article 10a of Directive 90/684, as inserted by Directive 92/68/EEC, 5specifi- cally concerns aid granted to shipyards operating within the former German Demo- cratic Republic. Article 10a(2)(c) provides that operating aid for the shipbuilding and ... moreover, competition considerations ship conversion activities of yards operating dictate that the sector of the shipbuilding on 1 July 1990 within the former German industry of the territories in question should Democratic Republic may, until 31 Decem- contribute significantly to the reduction of ber 1993, be considered to be compatible the excess capacity which, worldwide, with the common market, provided that the continues to impede the restoration of Federal Republic of Germany agrees to normal market conditions for the shipbuild- carry out, before 31 December 1995, a ing industry; genuine and irreversible reduction in capa- city of 40% net of the capacity of 545 000 cgt existing on 1 July 1990.

4 — OJ 1990 L 380, p. 27. 5 — Council Directive of 20 July 1992, amending Directive 90/684 (OJ 1992 L 219, p. 54).

I - 5706

COMMISSION v KVAERNER WARNOW WERFT

I I— Facts and the proceedings before the question totalling DEM 1 246.9 million, on Court of First Instance condition that the capacity restriction of 85 000 cgt per year was complied with.

8. It is apparent from the contested judg- ment 6that in 1992 Warnow Werft, an East 10. In 1997 KWW's actual production was German shipyard, was sold by the Treu- 93 862 cgt. In 1998, its actual production handanstalt, the body with the task of reached 122 414 cgt. restructuring the undertakings of the for- mer German Democratic Republic, to the Norwegian industrial group Kvaerner. According to the sale contract sent by Germany to the Commission, Kvaerner undertook until 31 December 2005, with regard to the Warnow yard, not to exceed 11. Since the Commission took the view an annual shipbuilding capacity of that KWW had exceeded the capacity 85 000 cgt. This capacity was that allocated restriction of 85 000 cgt for 1998, it to KWW by the Federal Republic of adopted Decision 1999/675. In that deci- Germany in pursuance of Article 10a(2)(c) sion, it stated that the aid which Germany of Directive 90/684, as amended by Direc- had implemented in favour of KWW in an tive 92/68. 7 amount of EUR 41.5 million (DEM 83 million) was incompatible with the com- mon market and requested that Germany take the necessary measures to recover the aid from the recipient. 9

9. By five decisions communicated to the Federal Republic of Germany between 1993 and 1995, 8 the Commission authorised, in accordance with Directive 12. The Commission took the view that 90/684, planned aid from the Federal KWW had also exceeded the capacity Republic of Germany to the shipyard in restriction of 85 000 cgt in 1997 and therefore adopted Decision 2000/336. In that decision, it stated that the aid which Germany had implemented in favour of 6 — Paragraphs 4 to 14. 7 — Hereinafter 'Directive 90/684'. 8 — Letters SG (93) D/3421 of 3 March 1993 relating to State aid No N 692/D/91; SG (94) D/567 of 17 January 1994 relating to State aid No N 692/J/91; SG (95) D/1818 of 20 9 — It should be noted that the Commission calculated the February 1995 relating to State aid No N 1/95; amount of aid to be recovered on the basis of a 'combination SG (95) D/12821 of 18 October 1995 relating to State aid of the pure proportional approach and a supplementary part No N 637/95 and SG (95) D/15969 of 11 December 1995 which addresses the aggravated distortion of competition relating to State aid No N 797/95 (Annex K2 to the caused by the considerable amount of exceeding the annual application in Case T-134/00, hereinafter, collectively, 'the capacity limitation in this case' (recital 103 in me preamble authorising decisions' and, individually, the first, second, to Decision 1999/675). That method is also disputed in these third, fourth and fifth authorising decisions). proceedings (points 71 and 72 of this Opinion).

I - 5707

OPINION OF MR LÉGER — CASE C-181/02 P

KWW amounting to EUR 6.3 million III — The contested judgment (DEM 12.6 million) was incompatible with the common market and requested Ger- many to take the necessary measures to recover the aid from the recipient. 15. In support of its actions, KWW relied on eight pleas, two of which were based upon errors in applying Articles 87 EC and 88 EC and Directive 90/684.

13. Finally, on 29 March 2000, the Com- 16. KWW claimed that the concept of a mission adopted Decision 2000/416/EC on 'capacity restriction' as used in the author- State aid implemented by Germany in ising decisions did not impose a limit on favour of Kvaerner Warnow Werft GmbH actual production but simply required ( 1 9 9 9 ) and a m e n d i n g D e c i s i o n compliance with a series of technical 1999/675.10In this decision, the Commis- restrictions relating to the production sion stated that '[KWW] complied in 1999 installations. Thus, in stating that this with the capacity limitation, compliance concept had to be interpreted to mean that with which is, pursuant to the Decision on KWW's production could not exceed the State aid measure No N 325/99, notified by limit of 85 000 cgt per year fixed by the letter of 5 August 1999, a condition for the authorising decisions, the contested deci- compatibility of the aid with the common sions were vitiated by errors of fact and of market'. 11 The Commission therefore law. reduced, to EUR 41.1 million (DEM 82.2 million), the amount of aid declared incom- patible by Decision 1999/675.

17. The Court of First Instance upheld those pleas after reasoning as follows:

14. By applications lodged at the Registry '91 It must be observed at the outset that of the Court of First Instance on 11 October Directive 90/684, as amended by 1999 and 18 May 2000, KWW brought Directive 92/68, does not define the two actions seeking the annulment of the concept of capacity and that, conse- recovery decisions. quently, the Commission has a mea- sure of discretion when interpreting that concept... However, it should also 10 — OJ 2000 L 156, p. 39. be noted that the applicant, rather than 11 — Article 1 of the operative part. disputing the Commission's interpreta-

I - 5708

COMMISSION v KVAERNER WARNOW WERFT

tion within the scope of that discretion, 94 As regards, first, the legal framework complains principally that the Com- within which the authorising decisions mission failed to have regard in the were taken, it must be observed that contested decisions to the concept of the objective of the capacity reduction capacity as imposed by it previously in laid down by Article 10a(2)(c) of the authorising decisions ... Directive 90/684 ("the German Gov- ernment agrees to carry out ... a genuine and irreversible reduction of capacity of 40% net of the capacity of 545 000 cgt existing on 1 July 1990"), of which the capacity restriction of 85 000 cgt per annum imposed on the applicant forms part ..., is to restore a 92 Consequently, when ascertaining in the normal market situation within the present case whether there is a manifest shipbuilding sector and the competi- error of assessment in the contested tiveness of the shipyards of the former decisions, the Court must take into German Democratic Republic, while account the rule that the Community reducing excess capacity. institutions must comply with the principle that they may not alter measures which they have adopted, so that the legal certainty of the persons affected by those measures may be ensured ... It cannot be accepted that the Commission can require recovery of aid to the detriment 95 As the reason for inserting the new of a recipient of the aid who has Article 10a into Directive 90/684, the complied with the aid conditions laid Council stated in the third recital to down by the Commission in the Directive 92/68 that "competition con- authorising decisions. siderations dictate that the sector of the shipbuilding industry of the [former German Democratic Republic] should contribute significantly to the reduc- tion of the excess capacity which, worldwide, continues to impede the restoration of normal market condi- tions for the shipbuilding industry". 93 It is therefore first necessary to exam- ine the legal framework within which the authorising decisions were taken and then to analyse those decisions in order to ascertain whether in the contested decisions the Commission has applied an interpretation of the requirements for a capacity restriction which is different from, and more 96 The wording of Directive 90/684 also restrictive than, the definition applied reveals its objective of eliminating the in the authorising decisions. structural overcapacity of shipyards in

I - 5709

OPINION OF MR LÉGER — CASE C-I 81/02 P

the European Community in order to tion is in essence ensured by the fixing make them more efficient and compe- of technical restrictions, known as titive. That objective may be deduced, "technical bottlenecks". That emerges in particular, from Article 6 of Direc- clearly from the authorising decisions tive 90/684 ... and from the third, (see paragraph 5 above). sixth, eighth and ninth recitals in that directive. According to the third reci- tal, "although since 1989 there have been significant improvements in the world market for shipbuilding, a satis- factory equilibrium between supply and demand has still not been estab- lished and the price improvements which have taken place are still insuffi- cient in the overall context to restore a 98 First of all, in its letter of 3 March normal market situation within the 1993, which constitutes the first sector ...". According to the sixth authorising decision, the Commission recital, "[an agreement between the states that, "although the independent most important shipbuilding nations] expert's report ordered by the Com- must ensure fair competition at an mission has shown that the construc- international level among shipyards tion capacity [of the Warnow through a balanced and equitable shipyard] will hardly exceed 85 000 elimination of all existing impediments cgt — the quota granted to the to normal competition conditions ...". shipyard by the German Government The eighth recital states "a competitive out of the total of 327 000 cgt granted shipbuilding industry is of vital interest to the East German shipyards — to the Community ...". Lastly, accord- monitoring of the carrying out of the ing to the ninth recital, "a tight and investments is deemed necessary in selective aid policy should be contin- order to ensure that the capacities will ued in order to support the present actually be reduced. The reduction is trend in production towards more dependent upon the investments being technologically-advanced ships and in carried out according to the plans and order to ensure fair and uniform designs presented to the consultant. conditions for intra-Community com- Kvaerner acknowledged that the fol- petition". lowing restrictions would have to be placed on the yard:

— the new steel cutting shop to stay as 97 It must be observed, next, that the developed with no additions except for reduction of excess capacity through a mechanical edge preparation the introduction of a capacity restric- machine (milling machine type);

I - 5710

COMMISSION v KVAERNER WARNOW WERFT

— the number of work stations on the (two identified) to be of the jib type large panel line and the double bottom with a maximum lifting capacity of 50 line to be fixed at eight respectively six tonnes." as defined in the designs in the consultant's report EECLOOOIA;

— any increase in length of these lines should be allowed only if the commen- surate area is deducted from the 600 99 It is clear from that passage that the tonne super unit shop. The converse objective set out in it, namely an actual must also be applied, that is, any reduction of capacity, was to be reduction in large panel/double bottom achieved essentially through compli- line area could be accompanied by an ance with a series of technical restric- increase of the super unit shop area tions concerning the production plant equal to the reduction in the large of the shipyard. panel/double bottom line area;

— the number of work stations on the curved panel line to remain at six as defined in the consultant's report EEŒ0001A; 100 The Commission's letter of 17 January 1994, which comprises the second authorising decision, is to the same effect. The Commission states in it that "the capacity restriction depends on the investments being made in accor- — the number of work stations on the dance with the plans and designs small panel line to remain at a max- presented to the consultants, in parti- imum of three as defined in the cular with regard to the adherence to consultant's report EECI:0001A; the maximum steel consumption of 73 000 tonnes cgt and in accordance with the restrictions provided for in the consultant's report." The fact that the capacity restriction of 85 000 cgt was based on a body of specific technical restrictions is also corroborated by the — only one 600 tonne crane to be fitted explanation in the same letter that "in over the dock. The dockside cranes the event of a failure to comply with

I-5711

OPINION OF MR LÉGER — CASE C-181/02 P

the capacity restrictions, the Commis- of production and of production sion will be obliged to require all the itself"; "In the light of the two aid to be repaid" and in particular by production monitoring reports sent to the use of the plural ("capacity restric- the Commission to date, monitoring tions") in that sentence. clearly remains necessary in order to ensure compliance with the maximum capacity authorised in the framework of the planned production as in that of actual production"; "In accordance with the production monitoring reports sent to the Commission to 101 In that context it should be added that date, monitoring remains necessary in if the Commission had really wished to order to ensure compliance with the impose on the applicant, when it maximum capacity in the framework authorised the aid, an annual ceiling of actual production as in that of on actual production, it would have planned production". Those sentences sufficed for it to use the terms "pro- clearly indicate that the applicant duction limit" or to specify that the must, in the planning and actual capacity restriction referred, in the production phases, comply with the present case, to maximum production technical restrictions on capacity. If, in optimum conditions. In the absence for example, the applicant receives two of such explanations, the applicant orders which would lead it to produce cannot be criticised for having more than 85 000 cgt in one year, it is exceeded the capacity restriction of permissible for it to accept and per- 85 000 cgt per annum, since it is form those orders within that year if it common ground that it complied, is able to do so while complying at the throughout the period in question, same time with the technical restric- with all the technical restrictions. tions on capacity laid down (such as those set out in paragraph 98 above relating inter alia to the number of work stations on the curved panel line and to the presence of only one 600 tonne crane over the dock). 102 However, in the authorising decisions there is no explanation of that kind. In particular, interpretation of the capa- city restriction expressed in cgt per annum as being a restriction of actual production cannot be inferred from the following sentences in the letters of 20 February, 18 October and 11 Decem- ber 1995 (the third, fourth and fifth 103 Furthermore, in the same letters some authorising decisions respectively): sentences clearly indicate that compli- "Furthermore, the first production ance with the capacity restriction of monitoring report sent to the Commis- 85 000 cgt per annum is treated in the sion shows that it is also necessary to same way as compliance with the monitor compliance with the capacity technical restrictions on the installa- restrictions at the time of the planning tions. Thus in the letter of 20 February I - 5712

COMMISSION v KVAERNER WARNOW WERFT

1995 (third authorising decision) the the applicant relies ([Case T-266/94] Commission explains that "in carrying Skibsvaerftsforeningen and Others v out the investment plan it is appro- Commission [[1996] ECR II-1399], priate to monitor compliance with the paragraph 177), the capacity restric- capacity restriction applicable to ship- tion laid down in those authorising building. Such compliance is ensured decisions corresponded to the produc- only if the investment plan presented to tion achievable under favourable nor- the consultants is scrupulously mal conditions, given the facilities observed; that applies in particular available. When accepting and execut- with regard to the maximum permis- ing orders for the construction of ships, sible output of 73 000 tonnes of steel, the applicant therefore had to comply the double bottom line and the two with the technical restrictions on its panel lines. The German Government installations, restrictions which had has given an assurance that the ship- been calculated and laid down in such yard will comply with the capacity a way that under favourable normal restriction." In its letters of 18 October conditions it would not produce more and 11 December 1995 (the fourth and than 85 000 cgt per annum. However, fifth authorising decisions), the Com- the authorising decisions did not pro- mission observes, in almost identical hibit the applicant from producing, terms, that the double bottom assem- under exceptionally favourable condi- bly line and the large panel line limit tions such as those which might result the shipyard's capacity to transform from the receipt of orders which could steel and by that very fact restrict the be executed more quickly than normal, shipyard's production capacity to more than 85 000 cgt per annum, but 85 000 cgt per annum. The Commis- merely required compliance with the sion adds in those two letters that for technical restrictions set out in parti- the duration of that capacity restriction cular in the authorising decisions, such it is indispensable that the layout of the as those limiting the number of work shipyard should not be amended and stations on the curved panel line to six that the "optional" equipment which and the number of work stations on has not yet been installed should the small panel line to three. comply with the specifications which the shipyard submitted for an opinion by the consultant.

105 Moreover, it has already been held by the Court of Justice and the Court of 104 Directives 90/684 and 92/68 and the First Instance that although construc- authorising decisions are therefore tion capacity — in the present case consistent in showing that, in line with 85 000 cgt per annum — is by its the Commission's administrative prac- nature capacity for production pur- tice as shown by another case on which poses, that concept is not in itself the

I - 5713

OPINION OF MR LÉGER — CASE C-181/02 P

same as "actual production" ([Case sion's assertions, that finding is not 14/81] Alpha Steel v Commission incompatible with the objective of [[1982] ECR 749], paragraph 22; Directive 90/684. That objective, Joined Cases 311/81 and 30/82 Klòck- reduction in excess capacity, is ner-Werke v Commission [1983] ECR achieved by restricting the applicant's 1549, paragraph 23; Joined Cases capacity at the level of its assembly T-164/96 to T-167/96, T-122/97 and lines, which ensures that in normal T-130/97 Moccia Irme and Others v conditions 85 000 cgt per annum will Commission [1999] ECR II-1477, not be exceeded. paragraph 138) or "maximum produc- tion achievable under optimum condi- tions" (Skibsvaerftsforeningen and Others v Commission, paragraph 174).

107 Lastly, several documents submitted by the applicant confirm that the capacity restriction imposed on it relates to the production achievable under favour- able normal conditions, given the facilities available.

106 According to that case-law, a capacity restriction may, as is apparent in the present case from the wording of the authorising decisions, relate to "pro- duction achievable under favourable normal conditions, given the facilities 108 Thus, the minutes of a meeting held on available" and not express an actual 1 June 1993 concerning privatisation maximum production which may not of the shipyards in the former German be exceeded even under exceptionally Democratic Republic state as follows: favourable conditions. The Commis- sion cannot convincingly argue that the capacity restriction imposed on the applicant, even though relating to "the production achievable under favour- able normal conditions, given the facilities available", nevertheless indi- cates a maximum actual production "The Danish, Italian and the UK which may not be exceeded in any delegates were expressing their worry event (see paragraph 87 above). If the that the actual production would capacity restriction reflects production exceed the assigned capacity after the achievable under favourable normal investments would be implemented. conditions, that in itself implies that The Commission was confident that the figure indicated by that restriction future production would not exceed may be exceeded in periods of optimal the agreed capacity limits because of conditions. Contrary to the Commis- the technical bottlenecks in the invest-

I - 5714

COMMISSION v KVAERNER WARNOW WERFT

ment plans, because of the present and 109 Likewise, the Commission's report on future monitoring of the investment the monitoring of the privatisation of plans together with the contractual shipyards in the former German capacity limits in the privatisation Democratic Republic annexed to the contracts, because of the German letter of 6 May 1993 addressed to the Government's undertaking to respect Permanent Representative of the Fed- the limits and because all aid payments eral Republic of Germany states that, are conditional on respect of the in the Commission's view, the capacity capacity limits." restriction was constituted by the entirety of the technical restrictions imposed:

"... the significant technical restrictions contained in the investment plans ensure compliance with the capacity restrictions for each shipyard, even though it seems necessary to maintain detailed monitoring when the invest- ments are implemented. The main That discussion between the Danish, technical bottlenecks and conditions Italian and the UIC delegations, on the guarantee the capacity restriction ...". one hand, and the Commission, on the other, would be meaningless if the capacity restriction of 85 000 cgt were to be understood as an absolute limit on actual production. In such a case it would have sufficed for the Commis- sion to explain that the 85 000 cgt limit per annum was a ceiling on actual production and that the applicant was 110 It follows from the whole of the quite simply prohibited from produ- foregoing that the applicant has duly cing above that ceiling. The position proved that the Commission com- adopted by the Commission at that mitted a manifest error of appraisal in meeting indicates, on the contrary, that treating in the contested decisions, its confidence that production would contrary to its approach in the author- be lower or equal to 85 000 cgt was ising decisions, the concept of a capa- based simply on the calculation that city restriction as a limit on actual the technical restrictions on the appli- production. Since the Commission cant's installations would normally based the contested decisions on the prevent it from producing more than mere fact that the applicant's actual that tonnage per annum. production in 1997 and 1998 exceeded

I - 5715

OPINION OF MR LÉGER — CASE C-181/02 P

85 000 egt ..., the operative parts of and to refer the case back to the Court of those decisions are vitiated in their First Instance for judgment as provided for entirety by that error of appraisal. in Article 61 of the Statute of the Court of Justice.

111 It should be observed in that regard that the sole basis for the contested decisions is the simple fact that actual 20. In support of its appeal, the Commis- production exceeded 85 000 cgt per sion puts forward three pleas in law: annum. The Commission neither examined, nor alleged, that the excess production during the years in ques- tion is the result of a failure to comply with the restrictive conditions laid down in the authorising decisions.' — breach of Article 10a(2)(c) of Directive 90/684;

18. The Court of First Instance therefore annulled the contested decisions without considering the other pleas put forward by — breach of the authorising decisions; KWW. 12 and

— an error of law in the assessment of the IV — The appeal case-law and of the documents cited in paragraphs 105 to 109 of the contested judgment.

19. By application lodged at the Court Registry on 15 May 2002, the Commission brought the present appeal. It requests the Court to set aside the contested judgment 21. In my view, the first and third pleas must be rejected on identical grounds. I will therefore consider them together (A below) 12 — With the exception of the first plea, alleging irregularities in before examining the second plea (B the composition of the Commission (paragraphs 61 to 77 of the contested judgment). below).

I - 5716

COMMISSION v KVAERNER WARNOW WERFT

A — The first and third pleas double error in law. 14 Firstly, it misread the case-law cited in paragraph 105 of the contested judgment since, contrary to its finding in paragraph 106, it may not be inferred from that case-law that the capa­ city restriction related only to the technical 22. In its first plea, 13 the Commission installations of the shipyards. Secondly, the alleges that the Court of First Instance documents in the case referred to in wrongly defined the legal framework for paragraphs 107 to 109 of the contested the authorising decisions. It claims that the judgment were taken out of context and do Court of First Instance interpreted the not support the disputed interpretation concept of 'capacity restriction' solely in either. the light of one of the two aims of Directive 90/684, namely the reduction of excess capacity in the shipbuilding sector. The Commission points out that Directive 90/684 does, however, have another objec­ tive, which is to compensate for the 25. As I have stated, I consider that these distortion to competition caused by the two pleas must be rejected. grant of aid to the East German shipyards.

26. In accordance with settled case-law, 15 the Court rejects from the outset claims 23. Unlike the first objective, the second challenging grounds that constitute an can be achieved only by limiting the actual alternative or superfluous line of reasoning production of the shipyards. Therefore, if in the judgment of the Court of First the Court of First Instance had correctly Instance. The Court considers that, to the identified the aims of Directive 90/684, it extent that the operative part of the would have seen that the capacity restric­ judgment of the Court of First Instance is tion applied not only to the technical based on other, primary, grounds, such installations of the shipyards, but also to their actual production.

14 — Ibid, (paragraphs 35 to 44). 15 — See, inter aha, judgments in Case C-35/92 P Parliament v Frederiksen [1993] ECR I-991, paragraphs 25 and 26, Case C-244/91 P Pincherle v Commission [1993] ECR I- 6965, paragraph 31, Case C-326/91 P De Compie v Parliament [1994] ECR I-2091, paragraph 94, Case C-39/93 P SFEI and Others v Commission [1994] ECR I-2681, paragraph 23, Case C-264/95 P Commission v UIC [1997] ECR I-1287, paragraphs 48 to 51, Case C-362/95 P Blackspur DIY and Others v Council and 24. In its third plea, the Commission claims Commission [1997] ECR I-4775, paragraph 23, and Case that the Court of First Instance made a C-122/01 P T. Port v Commission [2003] ECR I-4261, paragraphs 16, 17 and 30 to 33, and orders i n Case C-137/95 P SPC) and Others vCommission [1996] ECR I- 1611, paragraphs 47 to 49, Case C-49/96 P Progoulis v Commission Į1996] LCR 1-6803, paragraph 27, and Case C-241/00 P Kish Class v Commission [2001] ECR I-7759, 13 — Appeal (paragraphs 6 to 111. paragraph 42.

I-5717

OPINION OF MR LÉGER — CASE C-181/02 P

claims cannot cause the contested judgment normal conditions, given the facilities avail- to be set aside and are, as a result, of no able' 16 and not to the maximum actual consequence. production.

27. In the present case, I consider that the 31. Finally, the third line of reasoning very purpose of the first and third pleas is to relates to case-law and to certain docu- contest reasoning which is superfluous in ments in the case. In paragraphs 105 and view of that set out in paragraphs 97 to 104 106 of the contested judgment, the Court of of the contested judgment. First Instance took as its basis a number of judgments of the Court of Justice and of the Court of First Instance in confirming that 'a capacity restriction may ... relate to "pro- duction achievable under favourable nor- mal conditions'". 17 Similarly, in para- 28. It can be seen from the contested graphs 107 to 109 of the contested judg- judgment that, in accepting the view put ment, the Court of First Instance found that forward by KWW, the Court of First certain documents produced by KWW Instance developed its reasoning along three 'confirm that the capacity restriction ... lines. relates to the production achievable under favourable normal conditions, given the facilities available'. 18

29. The first line of reasoning relates to the legal framework within which the authoris- ing decisions were taken. In paragraphs 94 32. However, only the second of these lines to 96 of the contested judgment, the Court of reasoning constitutes the principal rea- of First Instance stated that Article 10a(2) soning of the contested judgment. (c) of Directive 90/684 was intended to reduce excess capacity in the shipbuilding sector.

33. As can be seen from paragraph 91 of the contested judgment, the Court of First Instance noted at the outset that 'the 30. The second line of reasoning relates to applicant, rather than disputing the Com- the contents of the authorising decisions. In mission's interpretation [of the concept of paragraphs 97 to 104 of the contested judgment, the Court of First Instance held that the concept of 'capacity restriction' in 16 — Contested judgment (paragraph 104). the authorising decisions referred to 'the 17 — Ibid, (paragraph 106). production achievable under favourable 18 — Ibid, (paragraph 107).

I - 5718

COMMISSION v KVAERNER WARNOW WERFT

"capacity" as referred to in Directive 35. The first and third pleas are accord- 90/684], complains principally that the ingly of no consequence. Commission failed to have regard in the contested decisions to the concept of capacity as imposed ... in the authorising decisions'. The Court of First Instance therefore decided to examine the legality of the contested decisions in the light of 'the rule that the Community institutions must comply with the principle that they may not alter measures which they have adopted'. 19 The reason given by the Court of First Instance for its annulment of the recovery decisions is, furthermore, that 'the Commis- 36. These pleas cannot cause the contested sion committed a manifest error ... in judgment to be set aside since, even if they treating in the contested decisions, contrary are well founded (that is to say that the to its approach in the authorising decisions, Court of First Instance did make an error in the concept of a capacity restriction as a defining the objectives of Directive 90/684 limit on actual production'. 20 and in analysing the case-law and the documents in the case), the operative part of the judgment (namely the annulment of the contested decisions) would still be based upon the fact that, in the recovery decisions, the Commission applied the concept of 'capacity restriction' in a manner different 34. It follows that the principal reasoning from that in the authorising decisions. In underlying the contested judgment is that order to have the contested judgment set the Commission based the recovery deci- aside, the Commission must on any view sions on a concept of 'capacity restriction' show that the reasoning relating to the which differed from that stemming from the contents of the authorising decisions (para- authorising decisions. The reasoning relat- graphs 97 to 104 of the contested judg- ing to the objectives of Directive 90/684 ment) is incorrect, that is to say that the (paragraphs 94 to 96 of the contested concept of 'capacity restriction' as referred judgment) and that relating to the case- to in the authorising decisions relates to a law of the Court of Justice and of the Court limit on KWW's actual production. of First Instance (paragraphs 105 and 106 of the contested judgment) and to the documents produced by KWW (paragraphs 107 to 109 of the contested judgment) are therefore superfluous vis-à-vis the reason- ing relating to the concept of a 'capacity restriction' as referred to in the authorising decisions (paragraphs 97 to 104 of the contested judgment).

19 — Ibid, (paragraph 92). 37. As a result, I propose that the Court 20 — Ibid, (paragraph 110). should reject the first and third pleas.

I-5719

OPINION OF MR LÉGER — CASE C-181/02 P

B — The second plea Instance, that the Commission confined itself to interpreting the capacity restriction in the sense of a limit on the technical capacity of the installations. 38. The second plea put forward by the Commission has two parts, which I will examine jointly.

39. In the first part, 21 the Commission 42. In shipbuilding, unlike other sectors, complains that the Court of First Instance there is no 'single technical bottleneck has interpreted the concept of 'capacity applicable to the installations' allowing restriction' on the basis of the wording of production to be regulated by a simple the first and second authorising decisions reduction in capacity. This is why, in only. The Commission states that, read addition to the technical restrictions on the together, the five authorising decisions installations, it was necessary to impose a show that the concept of 'capacity restric- limit on actual production in the authoris- tion' refers to both a restriction on technical ing decisions. installations and a restriction on KWW's actual production.

40. The Commission concedes that the first and second authorising decisions set out in detail the technical restrictions on the 43. As to why the restriction on actual installations and that, unlike the other three production was expressly mentioned only authorising decisions, they contain no in the third, fourth and fifth authorising indications regarding production. decisions, the Commission draws a distinc- tion between an 'investment' phase and a 'production' phase. The first and second authorising decisions concern solely the investment phase, namely the phase of creation and extension of the shipyard installations: during this phase, determina- 41. However, according to the Commis- tion of and compliance with the technical sion, the efforts to ensure compliance with restrictions were what mattered above all to the capacity restriction by putting technical the Commission. By contrast, the other bottlenecks into place do not mean, con- authorising decisions, adopted in 1995, in trary to the findings of the Court of First essence relate to the production phase starting on 1 January 1996. It is therefore logical that they emphasise the restriction 21 — Appeal (paragraphs 16 to 24). on and monitoring of actual production.

I - 5720

COMMISSION v KVAERNER WARNOW WERFT

44. In the second part of the plea, 22 the 47. Thus, the first authorising decision Commission points out that the third, reads as follows: fourth and fifth authorising decisions all contain a monitoring clause, under which, despite the technical restrictions put into place by KWW, monitoring remained necessary 'in order to ensure compliance with the maximum capacity authorised in the framework of the planned production as in that of actual production'. 23 The 'Although the independent expert's report Commission submits that the Court of First ordered by the Commission has shown that Instance misunderstood the wording of this [KWW's] construction capacity will hardly clause by interpreting it to mean that the exceed 85 000 cgt — the quota granted to technical restrictions were also to be the shipyard by the German Government... observed during the production phase — monitoring of the carrying out of the (paragraph 102 of the contested judgment). investments is deemed necessary in order to It maintains that this interpretation renders ensure that the capacities will actually be the monitoring of production ordered in the reduced. The reduction is dependent upon authorising decisions entirely pointless. the investments being carried out according to the plans and designs presented to the consultant. Kvaerner acknowledged that the following restrictions would have to be placed on the yard, [relating to] the new steel cutting shop ..., the number of work stations on the large panel line and on the double bottom line ..., [the] lines [them- selves] ..., [the] work stations on the curved 45. Like the Commission, I consider that panel line ..., the number of work stations the Court of First Instance did misread the on the small panel line ... [and the] crane authorising decisions. [which may] be fitted over the dock [and] the dockside cranes ...'

48. In the same way, the second authoris- 46. It is true, as the Court of First Instance ing decision provides: found in paragraphs 97 to 100 and 103 of the contested judgment, that the authoris- ing decisions contain a large number of references to the technical restrictions on KWW's installations.

22 — Ibid, (paragraphs 25 to 34). 'Although the monitoring study, for which 23 — Ibid, (paragraph 25). the Commission instructed an independent

I - 5721

OPINION OF MR LÉGER — CASE C-181/02 P

consultant, has shown that [KWW's] con- 51. It follows that the payment of the struction capacity should probably not contested aid was indisputably made sub- exceed the 85 000 cgt allotted by the ject to the implementation by KWW of a German Government to the shipyard ..., it series of technical restrictions, as the Court remains necessary to continue monitoring of First Instance found in paragraphs 97 to during the distribution of the investment 100 and 103 of the contested judgment. moneys and the carrying out of the invest- ment programme to ensure compliance with the reduction in shipbuilding capacity. The capacity restriction depends on the investments being made in accordance with the plans and designs presented to the consultants, in particular with regard to the adherence to the maximum steel con- 52. However, contrary to the Court of First sumption of 73 000 tonnes cgt, and in Instance's findings in paragraphs 101 and accordance with the restrictions provided 102 of the contested judgment, the condi- for in the consultant's report. The German tion relating to a technical restriction on the Government has agreed that the shipyard installations is not the only condition will abide by these conditions.' imposed by the authorising decisions. The other three authorising decisions contain several elements which show that the capacity restriction also related to KWW's actual production.

49. Similar indications are also to be found in the third, fourth and fifth authorising decisions.

53. The third authorising decision states:

50. In all these decisions, the Commission states that KWW's shipbuilding capacity must be limited to 85 000 cgt per annum and that this restriction must be effective. 'According to the independent technical That means, for the Commission, that the monitoring study carried out at the request investments made in the context of the of the Commission, [KWW's] shipbuilding restructuring of the shipyard were to take capacity will not exceed 85 000 cgt ... place in accordance with the plans pre- Nevertheless, in carrying out the investment sented to the firm of consultants nominated plan it is appropriate to monitor compli- by the Commission. It can therefore be ance with the capacity restriction applicable assumed that the plans presented to this to shipbuilding. Such compliance is ensured firm already included all the technical only if the investment plan presented to the requirements to be complied with by consultants is scrupulously observed; that KWW. applies in particular with regard to the

I - 5722

COMMISSION v KVAERNER WARNOW WERFT

maximum permissible output of 73 000 as to check that the technical bottlenecks tonnes of steel, the double bottom line and are in fact put in place correctly. the two panel lines. The German Govern- ment has given an assurance that the shipyard will comply with the capacity restriction.

55. However, following this reminder, the Commission adds, in the second paragraph: 'Furthermore, the first production monitor- ing report sent to the Commission shows that it is also necessary to monitor com- pliance with the capacity restrictions at the time of the planning of production and of production itself'. 24

Furthermore, the first production monitor- ing report sent to the Commission shows that it is also necessary to monitor com- pliance with the capacity restrictions at the time of the planning of production and of production itself. 56. The words 'furthermore' and 'also' show that the Commission intended to establish (or confirm) monitoring arrange- ments in addition to those relating to the carrying out of the work and the putting into place of the technical bottlenecks. According to the wording of the clause in question, the subject of the additional monitoring is KWW's production. Further- more, the fact that this clause was expressly inserted (or confirmed) after transmission of the 'first production monitoring report' relating to KWW confirms that the Com- 54. I consider that this decision deals with mission's monitoring would be not merely two matters. In the first paragraph, the of building work but of production itself. Commission begins by reiterating that, in The Commission therefore wished to sub- order to ensure that the capacity restriction mit KWW's production to regular checks, is complied with, the work must be in which implies that, in the Commission's accordance with the investment plan and, in view, the quantities produced by KWW particular, with the technical requirements contained therein. In this regard, the Commission confirms that it will continue to monitor the work during its execution so 24 — Emphasis added.

I - 5723

OPINION OF MR LÉGER — CASE C-181/02 P

might pose a problem with regard to the The German Government has given an capacity restriction. assurance that the shipyard will comply with the capacity restriction.' 25

57. This element is confirmed by the other two authorising decisions. The fourth 58. The fifth authorising decision contains authorising decision provides: identical points, stating:

'In August 1995 the independent technical 'In August 1995 the independent technical consultant instructed by the Commission to consultant instructed by the Commission to conduct the monitoring carried out a conduct the monitoring carried out a further survey to check the progress of the further survey to check the progress of the work at the shipyard, in order to verify work at the shipyard, in order to verify whether the building work carried out whether the building work carried out corresponded to the agreed investment plan corresponded to the agreed investment plan and to gather other technical information. and to gather other technical information. He found that the work ... had meanwhile He essentially found that the work had largely been completed and complied with meanwhile largely been completed and the investment plan. In his view, the double complied with the investment plan. In his hull assembly section and the large panel view, the double hull assembly section and line limit the shipyard's steelworking capa- the large panel line limit the shipyard's city, thereby restricting its production steelworking capacity, thereby restricting its capacity to 85 000 cgt per annum. For the production capacity to 85 000 cgt per duration of the capacity restriction it is annum. For the duration of the capacity essential that the layout of the shipyard restriction it is essential that the layout of should remain unchanged and that the shipyard should remain unchanged ... "optional" equipment not yet installed In accordance with the production monitor- should comply with the specifications sub- ing reports sent to the Commission to date, mitted by the shipyard to the technical monitoring remains necessary in order to consultant for his opinion. In the light of the ensure compliance with the maximum two production monitoring reports sent to capacity in the framework of actual produc- the Commission to date, monitoring clearly tion as in that of planned production. The remains necessary in order to ensure com- German Government has given an assur- pliance with the maximum capacity authorised in the framework of the planned production as in that of actual production. 25 — Emphasis added.

I - 5724

COMMISSION v KVAERNER WARNOW WERFT

ance that the shipyard will comply with the pose a problem with regard to the capacity capacity restriction.' 26 restriction, that means that the capacity restriction also applied to KWW's actual production.

59. These decisions also deal with two matters. Firstly, the Commission states that 61. It accordingly seems to me that the its technical consultant carried out a check assessment made by the Court of First to verify that the work complied with the Instance that the capacity restriction investment plan. The consultant found that applied only to the technical restrictions KWW's installations did comply with the on KWW's installations (paragraphs 101 technical restrictions imposed, the effect of and 102 of the contested judgment) is which was to limit its production to 85 000 incompatible with the wording of the cgt per annum. Nevertheless, after this authorising decisions. Nor, in my view, finding, the Commission adds, on the basis does that interpretation appear to be of the reports on the monitoring of KWW's consistent with the broad logic of those production, that monitoring 'remains decisions. necessary' to ensure compliance with the limit of 85 000 cgt in respect of both actual production and planned production.

62. As the Commission has stated, 27 the assessment of the Court of First Instance renders pointless the monitoring ordered in 60. The words 'remains necessary' confirm the authorising decisions. If one supposes that the monitoring put in place by the that the authorising decisions impose Commission was not merely to oversee the merely a technical restriction on KWW's work carried out, but also to oversee installations, it is no longer possible to KWW's production. Furthermore, the fact understand why the Commission set up that it was decided to maintain the mon- monitoring of the shipyard's actual produc- itoring 'in the light of' or 'in accordance tion. By their nature, the technical char- with' the reports on the monitoring of acteristics of KWW's installations cannot KWW's production confirms that, for the vary according to the shipyard's production Commission, the amounts produced by (projected or actual). The sole reason why KWW were liable to pose a problem with the authorising decisions set up monitoring regard to the capacity restriction. Logically, of KWW's production is therefore that the if the amounts produced by KWW could capacity restriction of 85 000 cgt also

26 — Emphasis added. 27 — Appeal (paragraph 28).

I - 5725

OPINION OF MR LÉGER — CASE C-181/02 P

applied to the shipyard's actual production. decisions therefore clearly has the aim of The interpretation of the Court of First limiting KWW's production of ships and Instance in paragraph 102 of the contested ocean-going vessels. judgment thus seems to me to be difficult to reconcile with the rationale of the monitor- ing clause and with the very logic of the authorising decisions.

65. The interpretation adopted by the Court of First Instance does not permit this objective to be achieved. The facts of the case show, on the contrary, that despite the technical restrictions imposed on KWW, 63. Furthermore, the Commission's view the shipyard produced up to 44% more also seems to me to be the only one which than the authorised capacity restriction. accords with the objective of the authoris- The interpretation that the authorising ing decisions. decisions impose only a technical restriction on KWW's installations therefore also seems to me to be contrary to the very objective of the capacity restriction.

64. It is common ground that the objective of the capacity restriction laid down by the authorising decisions is to limit KWW's 66. In conclusion, I consider that the production. This objective is clear from the wording, broad logic and objectives of the third authorising decision where the Com- authorising decisions show that the capa- mission states that the technical restrictions city restriction of 85 000 cgt related not put in place by KWW are in accordance only to the technical restrictions on KWW's with the investment plan and 'by that very installations, but also to the shipyard's fact restrict the shipyard's production capa- actual production. city to 85 000 cgt per annum'. Further- more, this objective is in accordance with that of Directive 92/68, which is intended to allow the restructuring of East German shipyards whilst imposing on them a requirement to 'contribute significantly to the reduction of the excess capacity [in] the shipbuilding industry'. 28 The capacity 67. As a result, in adopting the disputed restriction imposed by the authorising interpretation, the Court of First Instance misread the authorising decisions. I there- fore propose that the Court of Justice should set aside the contested judgment on 28 — Third recital in the preamble to Directive 92/68. this point.

I - 5726

COMMISSION v KVAERNER WARNOW WERFT

V — Referral of the case back to the Court the aid to be recovered. KWW submitted of First Instance that, even if it had failed to comply with the capacity restriction laid down by the authorising decisions, the Commission, in any event, made an error in the calculation of the amount of aid to be repaid since it 68. The first paragraph of Article 61 of the based the amount on the aid authorised and Statute of the Court of Justice provides that, not on the aid actually granted by the if the appeal is well founded, the Court of Federal Republic of Germany. Justice is to quash the decision of the Court of First Instance. In this situation, the Court may itself give judgment in the matter, where the state of the proceedings so permits, or refer the case back to the Court of First Instance for judgment.

72. It is common ground that, so far as the second claim is concerned, the state of the proceedings does not permit the Court to 69. In the present case, I consider that the give final judgment. 30 In support of that state of the proceedings does not permit the claim, KWW made numerous offers of Court to give judgment in the matter. evidence to the Court of First Instance in order to establish that the alleged error was made. However, the Court of First Instance, because of the conclusion it reached on the principal claim, made no finding on the applicant's evidence in support. 70. Before the Court of First Instance, KWW made two separate claims for annulment. 29 The first, principal, claim sought annulment of the recovery decisions in their entirety. In this connection, KWW disputed the Commission's assessment that it had not complied with the capacity restriction laid down by the authorising decisions. 73. I accordingly consider that the Court should refer the case back to the Court of First Instance. It will be for the latter to assess the need to order measures of inquiry and the value to be attached to the evidence submitted. It will also be for the Court of 71. The second claim, put in the alterna- First Instance to rule on all the costs, tive, sought the annulment of the contested including the costs of this appeal. decisions only with regard to the amount of

30 — See also, to this effect, the appeal (paragraphs 48 to 50) 29 — Sec the applications in Cases T-227/99 (paragraph 267) and the response (introductory section, under the heading and T-134/00 (paragraph 381). 'Claims').

I - 5727

OPINION OF MR LÉGER — CASE C-181/02 P

VI — Conclusion

74. On the basis of all the above considerations, I therefore propose that the Court should:

(1) set aside the judgment of the Court of First Instance of the European Communities of 28 February 2002 in Joined Cases T-227/99 and T-134/00 Kvaerner Warnow Werft v Commission;

(2) refer the case back to the Court of First Instance; and

(3) order that the costs be reserved.

I - 5728

Text rozhodnutia bol prevzatý z verejne dostupných úradných zdrojov. Rozhodnutie je úradným dokumentom.
Navrhy_ga C-181/02 – Súdny dvor Európskej únie | AI Pravnik